Root cause analysis tools: which tool, in what order
Short answer
Root cause analysis (RCA) is a structured way to find why a problem happens, down to the cause that, once fixed, stops it coming back. RCA tools are the charts and tables that do each part of that job: Pareto, is / is not, fishbone, 5 whys, fault tree, FMEA and scatter diagram.
Root cause analysis is a sequence, not one tool. Contain the problem, focus with a Pareto chart, describe it with 5W1H and an is / is not table, list what changed, widen the candidates with a fishbone, strike out every candidate the facts contradict, then dig into the survivor with 5 whys, or a fault tree when several failures combine. A cause is the root cause only when removing it stops the problem and restoring it brings the problem back, it explains every is and is not fact, and fixing it would have prevented the original event. An A3 or an 8D carries the work and the report.
Last reviewed:
Watch
A short story from the plant floor
· 4:33
Your Closed Maintenance Ticket Is Lying About Root Cause
A press leaks. Maintenance fixes it. The ticket closes. The press leaks again. This happens three times before anyone asks why. In this episode the crew chases one hose leak until the root cause is dead. They find what was rubbing the hose, find the other presses with the same edge, and make sure both shifts hear about the fix. A problem is not solved when…
Root cause analysis finds why a problem happens, not only where it shows up, and stops at a cause the plant can change. RCA tools, also called RCA techniques or root cause analysis methods, are the charts, tables and question sets a team uses to get there. No single tool finds a root cause on its own. Each does one job in the investigation: focus on the biggest loss, describe it, find what changed or rebuild the event, widen the list of possible causes, test them against data, and dig from a proven cause to the system behind it. The table groups 17 tools by that job.
Root cause analysis tools compared, grouped by the job each one does
Tool
Job
What it gives you
Use it when
Where to start
[Pareto chart](/learn/pareto-chart)
Focus
Categories ranked by count or cost, with a cumulative share
Many defect types, stop reasons or complaints compete and nobody agrees which to work on
Many symptoms traced back to a few core problems with if-then links
Problems in several departments look unrelated and you suspect one shared cause
No template of ours yet; see the sources at the end
Listed in the order an investigation usually meets them. The worked example further down uses eight of them on one problem: Pareto, 5W1H, is / is not, timeline, 5G walk, fishbone, fault tree and 5 whys.
A bar on a Pareto chart or a pattern on a scatter diagram points at a cause; it does not prove one. Two readings can move together because both follow a third thing, such as the time of day. Proof comes from the three tests in the verification section further down this page.
Cause-finding tools against problem solving methods
8D, A3, PDCA, DMAIC and Toyota's practical problem solving are not in the table because they are methods, not tools. A method carries a problem from containment to a fix that holds, and one of its steps is finding the cause; the tools above do the work inside that step. To choose the method, see problem solving methods compared. This page is about finding the cause.
Types of root cause analysis
RCA is split into types in three common ways. A plant needs all three views, because each one catches a different mistake.
By job: focus, describe, find what changed or rebuild the event, widen, test and dig, as in the table. A full investigation uses at least one tool for each job. Skipping a job is where most wrong answers come from.
By problem: event RCA is for one incident with a start time, such as an injury, a spill or a bad batch, and leans on the timeline, the events and causal factors chart, barrier analysis and the fault tree. Chronic RCA is for a loss that has run for months with no start date, such as scrap that never drops, and leans on the Pareto chart, stratification, the scatter diagram and the control chart, often inside a DMAIC project.
By the cause it reaches: a physical cause (the part or machine condition that failed), a human cause (what someone did or did not do) and a system cause (the procedure, training, design or check that let it happen). A finished RCA reaches the system cause. In the worked example the physical cause is a draft blowing the shielding gas away, and the system causes are a change log that skips the surroundings and a repair with no due date.
RCA software
Paper, a whiteboard and a spreadsheet can run every tool in the table. Software earns its place when the same problems come back across shifts and lines, because it keeps the problem statement, the evidence, the actions and the verification in one record the next team can search. LeanSuite's AI Root Cause Analysis asks questions about a problem you describe, then suggests likely root causes and an action plan. Treat those suggestions the way you treat fishbone votes: candidates to test against the is / is not facts, not answers. Other RCA software is compared on best root cause analysis software.
Which tool to start with
Pick the first tool from what the problem looks like and the data you already have. Most problems then pass through several of these tools in the order in the next section; this table only tells you where to enter.
Which root cause analysis tool to start with
If the problem looks like this
And you have
Start with
Then
Many defect types, stop reasons or complaints, and no agreed priority
Chronic variation with many inputs and no start date
Process data over months
A DMAIC project
Statistical tools in place of a timeline
This table picks a tool inside one investigation. To choose between a quick fix, a kaizen event, an A3 and a DMAIC project, use the process improvement method selector.
The order, and what ends each step
Each step hands something specific to the next one and ends on evidence, not on the meeting running out of time. A skipped step usually shows up later as a fix that did not hold.
The nine steps on one page
Each step ends on evidence, not on time. A failed verification test sends you back to testing the candidates against the facts.
Root cause analysis in nine steps
Step
Tools
Hands on to the next step
The step ends when you have
1. Contain
Sort suspect stock, check every part, test the check itself
Time to investigate without risk to the customer
Suspect product found and sorted, and a check in place that you have proved catches the defect
A cause you can change, and the system condition that allowed it
A chain that reads back with "therefore" and ends at a process or system, not a person
8. Verify
Off and on test, fact check, prevention check
A verified root cause
All three tests passed; a failed test sends you back to step 6
9. Fix and hold
A3 or 8D, standard work, the change log, the PFMEA
A closed problem
The rate back at its normal level for a period agreed before the fix
The order is a default. If a Pareto shows one category is nearly everything, go straight to describing it; if the start date is sharp, the timeline can come before the fishbone. Two things should not move: candidates are tested against the facts before anyone digs into one, and a cause is verified before the fix is called done.
One problem worked through every tool
This example is illustrative: the plant, the dates and the numbers are made up, but they add up. A plant welds steel hydraulic oil tanks in two robot cells, cell 1 and cell 2, each making about 600 tanks a week, and every tank gets a leak test at the end of the line. In the eight weeks before 15 July, 77 of 9,600 tanks failed the test (0.8%). In the four weeks from 15 July, 221 of 4,800 failed (4.6%).
1. Contain, then focus with a Pareto chart
Every tank is already leak tested, so containment starts with whether the test can be trusted. The team runs a reference leak through the tester at the start of every shift, and it is caught every time, so leaking tanks are not getting out. Rejects are repaired and retested. With the customer protected, the team sorts the 221 rejects by where the leak was found.
Leak test rejects by leak location, four weeks (221 rejects)
Example numbers
CategoryCount (bar scale: 0 to 221)Cum.
Drain-boss weld18885%
Filler-neck weld1491%
Corner seams1196%
Return-port weld599%
Other3100%
2211110
80%
188
14
11
5
3
100%50%0%
Drain-boss weld85%
Filler-neck weld91%
Corner seams96%
Return-port weld99%
Other100%
Count, largest firstCumulative % (number under each name)
Drain-boss weld: 188, 85% of the total, cumulative 85%.
Filler-neck weld: 14, 6% of the total, cumulative 91%.
Corner seams: 11, 5% of the total, cumulative 96%.
Return-port weld: 5, 2% of the total, cumulative 99%.
Other: 3, 1% of the total, cumulative 100%.
Pareto chart: Drain-boss weld 188, Filler-neck weld 14, Corner seams 11, Return-port weld 5, Other 3. The drain-boss weld alone is 85.1% of the rejects.
One bar is the problem. The other locations run at the same rate as before, so they are left out of the investigation.
Leak test rejects by leak location, four weeks from 15 July
Leak location
Rejects
Share
Cumulative
Eight weeks before
Drain-boss weld
188
85.1%
85.1%
14
Filler-neck weld
14
6.3%
91.4%
27
Corner seams
11
5.0%
96.4%
21
Return-port weld
5
2.3%
98.6%
10
Other
3
1.4%
100%
5
Illustrative. 221 rejects in 4,800 tanks after, 77 in 9,600 tanks before.
One bar holds 85.1% of the rejects. The other locations add up to 33 rejects in 4,800 tanks (0.69%), the same rate as before (63 in 9,600, 0.66%), so they are the normal background and not part of this problem. From here on the investigation is about the drain-boss weld alone: 188 leaks in four weeks (3.9% of tanks) against 14 in the eight weeks before (0.15%).
2. Describe it: 5W1H, then is / is not
5W1H turns the reject reports into one statement with a number and no cause in it: "Since 15 July, 3.9% of hydraulic tanks leak at the drain-boss weld at the final leak test (188 of 4,800 in four weeks), against 0.15% in the eight weeks before." The why stays empty on purpose. The is / is not table then splits the same data by cell, shift and week, and writes down where the problem could be but is not. The 5W1H questions list has 48 questions to work through when the statement will not come together.
Is / is not for the drain-boss weld leaks
Question
Is
Is not, but could be
What is different about the is side
What
Leaks at the drain-boss weld: 188 (3.9% of tanks)
Leaks at the other welds: 33 (0.69%), the same rate as before
One weld changed, the rest did not
Where
Cell 2: 181 of 2,400 tanks (7.5%)
Cell 1: 7 of 2,400 (0.29%)
Something about cell 2
Where on the part
The drain boss, welded at the end of the fixture nearest the cell door
The welds on the faces of the tank turned away from the door
Its position in the cell
When
From 15 July, every week: 44, 47, 46 and 44 in cell 2
Before 15 July: 14 in eight weeks across both cells
Something started just before 15 July
When in the day
Afternoon shift 104 of 800 (13.0%), day shift 52 of 800 (6.5%)
Night shift: 25 of 800 (3.1%)
Worst in the hottest hours
Who
All three cell 2 crews
Any one person: operators rotate weekly between the cells, and the same people run at 0.29% in cell 1
It follows the cell, not the people
Extent
Steady at about 45 a week in cell 2
Growing week by week
A step change, not gradual wear
Illustrative. Each cell made 2,400 tanks in the four weeks, 800 on each shift.
3. Find what changed: records, then a walk of the cell
The team lists every change in the month before 15 July from purchasing, receiving, the maintenance log and the change log, then walks cell 2 with the people who run it, using the 5G sheet. The walk finds a change that no record shows.
Changes in the month before the start date
Date
Change
Found in
Cell 1, cell 2 or both
1 July
New lot of drain bosses
Receiving records
Both
7 July
Welding wire from a second supplier
Purchasing
Both
10 July
Torch neck replaced on the cell 2 robot
Maintenance log
Cell 2
11 July
Roof extraction fan over the cell 2 bay failed; repair waiting for parts
Maintenance log
Cell 2 bay
14 July
Pedestal fan placed at the cell 2 door to cool the operators
No record: seen on the walk
Cell 2
21 July
New leak test operator on nights
Training matrix
Both, and after the start
Illustrative.
Change analysis keeps a change only if it is on the is side alone and came before the start. Three are left: the torch neck, the failed roof fan and the pedestal fan. The wire and the boss lot went into both cells, and the new leak test operator started six days after the leaks did.
4. Widen with a fishbone, then test every candidate against the facts
So that the list is not limited to recent changes, the team runs a 6M fishbone. It gives 16 causes. Two came up in the first five minutes and took most of the votes: the supervisor's view that new operators on cell 2 were not wiping the bosses before loading, and the quality engineer's view that the new wire was to blame. The votes only set the order of the checks; the is / is not table does the checking.
Testing the candidate causes against the is / is not facts
Candidate cause
Drain boss only?
Cell 2 only?
From 15 July, worst in the afternoon?
Verdict
Operators not wiping the boss
No reason it would be
No: the same people run cell 1 at 0.29%
No
Struck out
New wire supplier
No
No: the same wire runs in cell 1
No: in use from 7 July
Struck out
Oily lot of drain bosses
Yes
No: the same lot runs in cell 1
No: in use from 1 July
Struck out
New leak test operator
No
No: one tester for both cells
No: started 21 July
Struck out
Gas leak at the new torch neck
No: it would hit every cell 2 weld
Yes
Partly: fitted 10 July, no afternoon pattern
Check
Low gas flow in cell 2
No: it would hit every cell 2 weld
Yes
No afternoon pattern
Check
Heat in the bay after the roof fan failed
No: the heat reaches every weld
Yes
Yes
Check
Draft from the pedestal fan
Yes: the boss is welded nearest the door
Yes
Yes: there from 14 July, run on high in the afternoons
Survives
Illustrative. Eight of the 16 fishbone causes shown.
Only the fan explains every row without an extra assumption. The three marked Check each fail at least one fact but are cheap to rule out, so the team checks them before acting: no leak at the new torch neck, gas flow at the nozzle matches the welding procedure in both cells, and heat alone does not explain why only one weld leaks.
5. Dig: a fault tree for the mechanism, 5 whys for the system
Ten rejected tanks are cut through the drain-boss weld, and all ten show gas porosity: pinholes running through the weld. Porosity has several known mechanisms, so the team draws a small fault tree with porosity as the top event and closes every branch with evidence before trusting the fan.
The fault tree, drawn
Illustrative. Circles are basic events. Every branch is closed with evidence: one confirmed, six ruled out. The table below gives the evidence for each.
Fault tree for porosity in the drain-boss weld
Basic event
Branch
Evidence
Result
Gas flow low at the nozzle
Shielding gas lost
Flow at the nozzle matches the welding procedure in both cells
Ruled out
Gas leaking from the hose or torch
Shielding gas lost
Leak check of the hose, fittings and new torch neck: no leak
Ruled out
Spatter blocking the nozzle
Shielding gas lost
Nozzle clean at 10 random checks
Ruled out
Draft blowing the gas away
Shielding gas lost
Air at the drain boss 2.1 m/s with the fan on, 0.2 m/s with it off; 0.4 m/s or less at the other welds
Confirmed
Oil or rust preventive on the boss
Contamination in the arc
Same boss lot in cell 1; 10 wipe tests clean
Ruled out
Moisture in the gas
Contamination in the arc
One bulk gas supply feeds both cells
Ruled out
Wrong or faulty filler wire
Filler wire
Same wire lot in both cells
Ruled out
Illustrative.
Every gate in this tree is an OR gate: any one branch can cause porosity on its own, so every branch has to be closed. In a safety event you will usually meet AND gates too, such as a hazard present and a guard bypassed, and the fix can then target whichever input is easiest to remove for good. The fault tree template has the symbols and the arithmetic.
With the physical cause found, the 5 whys ask why the system let it happen. Each answer rests on a fact the team checked.
5 whys from the confirmed physical cause
Why?
Answer
Evidence
1. Why do tanks leak at the drain boss?
Gas porosity runs through the drain-boss weld
10 of 10 sectioned rejects
2. Why is there porosity?
Air moving across the torch blows the shielding gas off the weld pool
2.1 m/s at the drain boss with the fan on, 0.2 m/s with it off
3. Why is air moving there?
A pedestal fan at the cell 2 door blows into the cell, and the drain boss is welded at the end nearest the door
Seen on the walk; the fan has stood there since 14 July
4. Why is the fan there?
The roof extraction fan failed on 11 July, the bay got hot, and the shift brought in a fan to keep working
Maintenance log; the operators
5. Why did nobody see the risk?
The cell's change log covers people, machines, materials and methods but not the surroundings, so no welding engineer reviewed the fan; and the roof fan repair had no due date
The change log; the open repair order
Illustrative.
A team that stops at the fourth why blames the shift for the fan. The shift solved a real heat problem with what it had, and nothing in the system would have caught the side effect. The two root causes are system conditions the plant can change: changes to the surroundings of a weld cell go unreviewed, and a failed extraction fan can wait indefinitely.
6. Verify before fixing
Three tests of the root cause
Test
What the team did
Result
Off and on
Welded 20 drain bosses on scrapped tank bodies with the fan on and 20 with it off, then leak tested and sectioned them
Fan on: 7 of 20 leaked (35%). Fan off: 0 of 20
Explains every fact
Went down the is / is not table row by row
Drain boss only (welded nearest the door), cell 2 only (no fan at cell 1), from 15 July (fan from 14 July), worst in the afternoon (fan on high), every crew (it follows the cell)
Would have prevented it
Asked whether the fixes, in place on 13 July, would have stopped the leaks
Yes: with the surroundings on the change log, the fan is reviewed before its first shift, and with extraction repairs given a due date there is no reason to bring one in
Illustrative.
7. Fix, hold and report
The pedestal fan went and a draft screen was fitted at the cell 2 door on day 1; the roof extraction fan was repaired on day 3. Changes to the surroundings of the weld cells, such as fans, open doors and heaters, now go on the change log the cells already use (see the 4M change sheet), with the welding engineer as reviewer, and extraction and cooling repairs get a due date. In the first week after the fan went, cell 2 had 2 drain-boss leaks in 600 tanks (0.33%). Over the next four weeks both cells had 6 in 4,800 (0.13%), and all leak test rejects were 39 in 4,800 (0.81%), back at the old 0.8%.
The leaks were caught inside the plant, so the team wrote the work up on an A3: the Pareto and the problem statement as the current condition, the is / is not, timeline, fault tree and 5 whys as the cause analysis, and the three tests and the hold as the check (three worked A3s show the format). Had a leaking tank reached a customer, the same work would go into an 8D report, with containment in D3 and a second cause in D4: why the leak test let it out.
How to verify a root cause
A cause is a hypothesis until it passes three tests. Fishbone votes, a convincing story and a fix that seemed to work for a week are not tests.
1
Turn the problem off and on with it
Remove the cause and the problem stops; restore it and the problem comes back. Restore it only where that is cheap and safe, on scrap parts, in a short trial or on a test rig, and never by bringing back a hazard. If you cannot restore it, show at least that the problem stopped when the cause went and stayed stopped long enough to rule out chance.
2
Explain every is and every is not
Go down the is / is not table and check that the cause explains each fact, including why the problem is absent where it could be. A cause that would also produce failures on the is not side is wrong, or only part of the story. This is the test at the heart of Kepner-Tregoe problem analysis.
3
Check the fix would have prevented the original event
Imagine the fix in place the day before the problem started. If the problem would still have happened, you have found a contributing cause and need to keep going. The US Department of Energy's root cause guidance defines the root cause the same way: the cause that, once corrected, stops this event and similar ones from happening again.
Then hold. Agree before the fix which number counts as fixed and for how long, and check it at the end of that period. The DOE guidance makes follow-up a phase of its own, and D6 of an 8D asks for the same evidence.
Where teams usually go wrong
Stopping at a person. "Operators not wiping the boss" sounded like an answer, but the rate followed the cell, not the people. When the answer is a person, ask what made the error possible or likely, as the 5 Whys template does.
Taking the first plausible cause. The new wire was a real change close to the start date, and it took the most votes. In the example above, one row of the is / is not table, cell 1 running the same wire at 0.29%, struck it out before anyone changed supplier.
A thin is not column. Without the cell 1 and night shift facts, the wire, the boss lot and the operators all stay possible. Fill in the is not side from data or a visit, not from memory.
A timeline built from records alone. The fan was in no log. Walk the area with the people who run it before you call the change list complete.
Treating fishbone votes as proof. Votes set the order of the checks. Several of the fishbone examples show the most-voted cause ruled out.
One chain, one cause. A single line of whys tends to find a single cause, a limit Alan Card describes in his 2017 critique of the 5 whys. Go wide first with a fishbone or fault tree, then deep, and expect more than one root cause: the example has two.
Closing the problem on the day of the fix. Without a number and a hold period, a fix that only coincided with a good week looks the same as one that worked.
How much analysis is enough
Match the effort to the problem. The DOE guidance asks for a formal, documented analysis for the most serious events and accepts a lighter one for minor ones, as long as it explains why the event happened and how to stop it happening again. A one-off minor stop may need only a clear problem statement and a short 5 whys. A repeat problem, a customer complaint or anything with a safety consequence gets the full sequence.
Some problems have no single cause to find. Chronic variation with many inputs and no start date is better handled with data over time, such as a capability study or a DMAIC project, than with a timeline. In complex processes Card's point applies: one tidy causal chain can hide how the process really fails, so map the branches and fix the system conditions, not only the last link.
Root cause analysis on its own fixes nothing. ASQ makes the point that it has to sit inside a wider problem-solving effort, with an owner who can make the change and a check that the change held.
Sources
ASQ, "What is root cause analysis?" (quality resources): the definition of a root cause and the main approaches, including events and causal factors, change analysis, barrier analysis and Kepner-Tregoe.
US Department of Energy, DOE-NE-STD-1004-92, Root Cause Analysis Guidance Document (February 1992): the five phases from data collection to follow-up, events and causal factors charting, barrier analysis, change analysis (Appendix E), the definition of a root cause and effort matched to significance.
Kaoru Ishikawa, Guide to Quality Control (Asian Productivity Organization): the basic quality tools, including the check sheet, Pareto diagram, cause and effect diagram, histogram, scatter diagram, stratification and control chart.
AIAG and VDA, FMEA Handbook (2019): design and process FMEA.
Eliyahu M. Goldratt, It's Not Luck (North River Press, 1994): the current reality tree, one of the Theory of Constraints thinking processes.
W. E. Vesely and others, Fault Tree Handbook, NUREG-0492, US Nuclear Regulatory Commission (1981): fault tree analysis as a deductive method, the top event, OR and AND gates, and minimal cut sets.
Kepner-Tregoe problem analysis (is and is not, distinctions, changes, testing causes against every fact), as described by Kepner-Tregoe (B. Prigge, "8D: IS or IS NOT", 2022) and in AHRQ's Kepner-Tregoe matrix tool.
Taiichi Ohno, Toyota Production System (Productivity Press, 1988), the origin of the five whys, as summarised in the Lean Enterprise Institute's Lean Lexicon.
A. J. Card, "The problem with '5 whys'", BMJ Quality and Safety 26(8), 2017, pages 671 to 677.
Miller Electric, "Tips for troubleshooting common MIG weld defects" (2024): drafts, low gas flow, leaks and spatter as causes of porosity, used for the example's mechanism.
AI Root Cause Analysis
Run root cause analysis in LeanSuite
AI root cause analysis in every Kaizen and EWO: the RCA Agent drafts a 5 Whys, 4M1D and fishbone from the problem, your attached manuals and SOPs, and your plant’s past problems.
The fishbone (Ishikawa) board is one of the 30 ready-made boards in Lean Studio, LeanSuite's whiteboard. Try the interactive demo in your browser with sample data, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.
They are the charts, tables and question sets a team uses to find why a problem happens. Each does one job: a Pareto chart or check sheet focuses on the biggest loss, 5W1H and is / is not describe it, a timeline finds what changed, a fishbone or FMEA widens the list of causes, a scatter diagram tests one you can measure, and 5 whys or a fault tree dig from a proven cause to the system behind it.
There is no official set of five. Lists of five usually name the Pareto chart, 5 whys, fishbone diagram, scatter diagram and FMEA. For a plant chasing a problem that has already happened, a more useful five are the Pareto chart, is / is not, fishbone, 5 whys and fault tree, because together they focus, describe, widen, test and dig.
RCA is usually split three ways. By the job a tool does: focus, describe, find what changed, widen, test and dig. By the problem: event RCA for one incident with a start time, and chronic RCA for a loss that has run for months. By the cause it reaches: physical, human and system. A finished RCA reaches a system cause the plant can change.
Partly. FMEA looks forward: it lists how a design or process could fail before it does, so it prevents causes rather than finding the cause of a failure that already happened. It helps RCA in two ways. Its lists of failure modes and causes are a ready-made set of candidates, and once an RCA finds a new failure mode, adding it to the PFMEA spreads the control to every line that runs the process.
Contain it, focus on the biggest category with a Pareto chart, describe it with 5W1H and is / is not, list what changed before it started, widen the candidates with a fishbone, strike out every candidate the facts contradict, then dig into the survivor with 5 whys or a fault tree. Call it the root cause only when it passes three tests: off and on, explains every fact, and would have prevented the event.
It is the step where a candidate cause is proved to be the root cause instead of assumed. A cause is determined when removing it stops the problem and restoring it brings the problem back, when it explains every is and is not fact, and when fixing it would have prevented the original event. Until then it is a hypothesis, however many votes it got.
No. A clear pattern shows that two readings move together, not that one causes the other: both can follow a third factor, such as the time of day. Use the scatter diagram to pick which cause to test first, then confirm it with an off and on trial, as the worked example does with the fan.
Protect the customer first: find and sort suspect product and put a check in place that you have proved works. Then define the problem precisely, with what, where, when and how much, and no cause in the statement, and collect evidence early, before conditions change and memories fade.
It depends on the problem and your data. With counts across many categories, start with a Pareto chart. With one vaguely described problem, write a 5W1H statement. If it happens in some places or times and not others, use is / is not. If it started on a date, list what changed. If the team has no lead, run a fishbone. Use the 5 whys once you have a confirmed cause, and a fault tree when several failures must combine.
Use three tests. Removing the cause stops the problem, and restoring it, on scrap parts or in a trial, brings the problem back. The cause explains every fact in the is / is not table, including where the problem is absent. And the fix, had it been in place before the problem started, would have prevented it. Then check that the problem stays fixed over a period agreed in advance.
Rarely. It is usually an intermediate cause with system conditions under it, such as an unclear procedure, missing training, a design that makes the error easy or staffing pressure. Ask what made the error possible and keep going until you reach a condition the plant can change. If the same error happens with different people, the cause is in the system.
Stop when you reach a condition the plant can change that, once fixed, would prevent this problem and similar ones, and when the chain reads back as a sequence of checked facts. Five is a rule of thumb: some chains end at three whys and others need seven. If the problem comes back after a fix that was made properly, the chain stopped too early.
5W1H gathers the full description of a problem: what, where, when, who, how and how much. Is / is not asks the same questions and adds, for each one, the closest place, time or product where the problem could be but is not. That contrast is what rules causes out, so use 5W1H to describe the problem and is / is not to narrow it.
Use a fishbone to collect possible causes across every area when you do not yet know where to look. Use a fault tree when you know the failure and need every path to it, especially when several conditions must happen together, as in safety events and failures of complex equipment. A fault tree joins causes with AND and OR gates, so it shows which combinations cause the event.
We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.