Practical guide · Value stream mapping and flow
Cycle time, throughput time and lead time for one part, worked through
Short answer
Cycle time is how often one step finishes a part. Throughput time is how long a part takes from the first step to the last, waiting included. Lead time is longer again: dock to dock for production, or order to delivery for the customer. In the example below the slowest step finishes a shaft every 84 seconds and each shaft is worked on for 401 seconds in total, yet it spends 7.0 working days between the first and last step, 13.0 days from receiving to the truck, and the customer waits 14.0 days. Nearly all of that is waiting in piles, so lead time falls when the piles shrink, not when machines get faster.
The terms, as this page uses them
Plants use these words in different ways, so agree on the definitions before you compare numbers. This page follows the Lean Enterprise Institute's Lean Lexicon where it can and says where it does not.
| Term | What it measures | How to get it | In the example |
|---|---|---|---|
| Takt time | The pace demand sets: how often the line must finish one part | Available time per day ÷ parts the customer takes per day | 54,000 s ÷ 600 = 90 s |
| Cycle time (of a step) | How often a step finishes a part, timed on the floor | Time from one part leaving to the next; or time on one machine ÷ machines doing that step | 30 s to 84 s; the slowest step, 84 s, sets the line's |
| Processing time | How long a part is actually being worked on | Time on one machine for one part, loading and unloading included | 401 s over six steps |
| Value-added time | The part of processing time that changes the part in a way the customer pays for | Watch each step and keep only the seconds that change the part | 280 s |
| Throughput time | From the start of the first step to the end of the last, waiting included | Waits between steps + processing time | 7.0 working days |
| Production lead time | Dock to dock: from raw material arriving to the product leaving on the truck | Every pile ÷ daily output, + processing time; or WIP ÷ throughput (Little's Law) | 13.0 working days |
| Order lead time | What the customer waits, from sending the order to receiving the parts | Order handling + the order's time in production + shipping | 14.0 working days |
| Value-added ratio | The share of lead time that adds value | Value-added time ÷ production lead time, in the same units | 0.04% |
Illustrative numbers from the shaft example below, in working days of 15 available hours.
Cycle time has two common meanings. In lean and on value stream maps it is a step's rhythm: the time to make one part at a station, as measured, which is the Lean Lexicon's definition. In the Factory Physics textbook, and in some plants' reports, cycle time is the average time a job takes from release at the start of its routing to the end of it, which this page calls throughput time. For the same shaft the first meaning gives 84 seconds and the second gives 7.0 days, so ask which one a number is before you act on it. This page uses the first.
Throughput time varies too. The Lean Lexicon treats throughput time and production lead time as one measure, door to door. Many plants use throughput time for the shop floor only, first step to last, and production lead time for dock to dock. This page keeps them apart so you can see what waits outside the machines: raw material and packed parts. Throughput on its own is a rate, not a time: the parts a day that leave the process, 600 here.
The part and the raw numbers
A machine shop makes a steel drive shaft to order for one customer, who takes 600 a day. The shop runs two 8-hour shifts with 30 minutes of breaks in each, so 15 hours, or 54,000 seconds, are available per day. Every shaft goes through the same six steps. On one walk, a team timed each step and counted every pile of parts.
| Step | Machines | Time on one machine per shaft | Value-added part of it | Shafts waiting in front |
|---|---|---|---|---|
| 1. Saw to length | 1 | 30 s | 24 s | 3,000 (bar stock at receiving, counted in shaft lengths) |
| 2. CNC turn | 1 | 84 s | 66 s | 2,100 cut blanks |
| 3. Drill and tap | 1 | 52 s | 40 s | 300 |
| 4. Induction harden | 1 | 45 s | 30 s | 600 |
| 5. Grind | 2 | 150 s | 120 s | 900 |
| 6. Inspect and pack | 1 | 40 s | 0 s | 300 |
| After step 6 | 600 packed, waiting for the daily truck |
Value-added time leaves out loading, unloading and inspection. Order side: an order takes 1.5 working days to be entered and checked, the schedule goes to the floor once a week, and the truck takes 2 working days to reach the customer.
Takt time and cycle time: can the line keep up?
Takt time is 54,000 s ÷ 600 = 90 s: the line has to finish a shaft every 90 seconds on average. A step's cycle time is the time on one machine divided by the machines doing that step. Grinding takes 150 s per shaft, but two grinders work side by side, so the step finishes one every 75 s.
Each step's cycle time against takt
Example numbers| Step | Cycle time | Share of takt | Shafts a day it could make |
|---|---|---|---|
| 1. Saw to length | 30 s | 33% | 1,800 |
| 2. CNC turn | 84 s | 93% | 642 |
| 3. Drill and tap | 52 s | 58% | 1,038 |
| 4. Induction harden | 45 s | 50% | 1,200 |
| 5. Grind | 75 s (150 s ÷ 2 grinders) | 83% | 720 |
| 6. Inspect and pack | 40 s | 44% | 1,350 |
Shafts a day = 54,000 s ÷ cycle time, rounded down. Share of takt = cycle time ÷ 90 s.
- The lathe is the bottleneck. At 84 s it is the slowest step, so the line can make at most 642 shafts a day.
- Every step is under takt, so the line can meet demand, but only just at the lathe: 600 shafts take 600 × 84 = 50,400 s of its 54,000, which leaves 3,600 s, or 60 minutes a day. More than an hour of lathe stops in a day means a short day or overtime.
- Adding the step cycle times gives 326 s, and that sum means nothing. It is not how long a shaft is worked on (401 s, because each grinder spends 150 s on a shaft) and not how long a shaft takes to get through (days).
Follow one shaft: throughput time
Tag one shaft with a traveller card that gets the time written on it at each step, and follow it. In a steady line where each pile is worked first in, first out, a shaft that joins a pile of 2,100 drained at 600 a day waits 3.5 days.
One shaft, receiving to truck: 13.0 working days
Example numbers- Throughput time: 7.0 days
- Saw to packing bench (the yellow band): 7.0 days of waiting and 401 s of work.
- Production lead time: 13.0 days
- Receiving to truck: adds the 5.0 days of bar stock and the 1.0 day packed shafts wait for the truck.
- Order lead time: 14.0 days
- What the customer waits: 4.0 days of order handling and waiting for release, the 7.0 days on the floor, 1.0 day for the truck and 2.0 days in transit. The bar stock was already on the rack.
| Where the shaft is | Waiting | Being worked on | Clock so far |
|---|---|---|---|
| Saw to length | 30 s | 30 s | |
| Pile before the lathe (2,100) | 3.5 days | 3.5 days + 30 s | |
| CNC turn | 84 s | 3.5 days + 114 s | |
| Pile before drilling (300) | 0.5 days | 4.0 days + 114 s | |
| Drill and tap | 52 s | 4.0 days + 166 s | |
| Pile before hardening (600) | 1.0 day | 5.0 days + 166 s | |
| Induction harden | 45 s | 5.0 days + 211 s | |
| Pile before grinding (900) | 1.5 days | 6.5 days + 211 s | |
| Grind | 150 s | 6.5 days + 361 s | |
| Pile before inspection (300) | 0.5 days | 7.0 days + 361 s | |
| Inspect and pack | 40 s | 7.0 days + 401 s | |
| Throughput time | 7.0 days | 401 s | 7.007 working days |
Waiting days = shafts in the pile ÷ 600 a day. 401 s ÷ 54,000 s a day = 0.007 days.
Throughput time is 7.0 working days plus 401 seconds. The shaft was worked on for under 7 minutes and waited for the rest. This is cycle time in its second meaning, the Factory Physics one.
Production lead time and Little's Law
Production lead time adds the two piles outside the six steps: bar stock waiting at receiving and packed shafts waiting for the truck. A value stream map gets it the way Learning to See teaches: divide each pile by daily demand to turn it into days, add the days, then add the processing time.
| Pile | Shafts | Days (shafts ÷ 600 a day) |
|---|---|---|
| Bar stock at receiving | 3,000 | 5.0 |
| Before the lathe | 2,100 | 3.5 |
| Before drilling | 300 | 0.5 |
| Before hardening | 600 | 1.0 |
| Before grinding | 900 | 1.5 |
| Before inspection | 300 | 0.5 |
| Packed, waiting for the truck | 600 | 1.0 |
| All piles | 7,800 | 13.0 |
Plus 401 s of processing: production lead time = 13.0 days + 401 s = 13.007 working days.
Little's Law says that in a stable process, average work in process (WIP) = throughput × average time in the process, so lead time = WIP ÷ throughput. Count everything between the receiving dock and the truck: 7,800 shafts in piles, plus the shafts on machines. A machine holds a shaft only while it works on it, so on average 600 ÷ 54,000 × 401 = 4.5 shafts are on machines. WIP is 7,804.5 shafts, and 7,804.5 ÷ 600 a day = 13.007 days: the same as the waits and processing times added up for the tagged shaft. It has to be, because each pile's days are Little's Law applied to that pile.
That makes Little's Law a check on your own numbers. Count the WIP one morning and divide it by what you ship per day. If tagged parts take much longer or much less than that on average, a pile is growing or shrinking, the count missed something, or the WIP and the shipments were counted between different points.
- Use averages over several weeks. Little's Law is about averages, and one tagged shaft is one sample.
- Divide by what actually leaves the process, not by a forecast. Learning to See divides by daily customer demand, which is the same number only when the line ships what the customer takes.
- Count WIP and throughput between the same two points. Bar stock counts in the dock-to-dock figure; it does not count in the saw-to-pack throughput time.
- It holds whatever order parts are taken in, first in first out or not. It tells you the average wait, not what any single part will wait.
Factory Physics adds a benchmark. Raw process time (401 s here) multiplied by the bottleneck rate (one shaft every 84 s) gives the critical WIP: the parts a line with no variation at all would need to run at full rate, 401 ÷ 84 = 4.8 shafts. A real line needs more, to ride through stops and changeovers, but 4,200 shafts between the saw and the packing bench is far more than that, so most of the WIP is there for other reasons, such as the saw cutting whole bar lots ahead.
Order to delivery: what the customer waits
The customer never sees the shop floor. Their clock starts when they send the order and stops when the shafts arrive. The Lean Lexicon calls this order lead time: production lead time plus the time spent handling the order and getting the product to the customer.
| Stage | Working days | Why |
|---|---|---|
| Order entry and checks | 1.5 | Orders sit in the inbox, then get entered and checked |
| Waiting for the weekly schedule | 2.5 | The schedule goes to the floor once a week, so an order waits half a week on average |
| Saw to packed (throughput time) | 7.0 | As traced above |
| Waiting for the truck | 1.0 | 600 packed shafts ÷ 600 a day |
| Transit | 2.0 | Carrier time to the customer |
| Order lead time | 14.0 | Almost three calendar weeks once weekends are added |
The 5.0 days of bar stock count in production lead time but not in this order's wait: the bar was already on the rack when the order was released. Bar stock ties up cash and floor space; it does not delay this order. If you make to stock instead, the customer waits only for order handling, picking and transit, and production lead time tells you how fast you can react when demand changes.
Value-added ratio
Value-added time is 280 s. Production lead time in seconds is 13.007 days × 54,000 = 702,401 s. The value-added ratio is 280 ÷ 702,401 = 0.04%. Counting every second of processing, 401 s, it is still only 0.06%. Both say what the timeline shows: the time is in the piles. Some plants divide by calendar time instead of working time, which makes the ratio smaller still, so say which you used.
What each number tells you to do
| Number | In the example | What it tells you | What to do |
|---|---|---|---|
| Takt time | 90 s | The pace demand sets | Staff and balance the line to it, and work it out again when demand or the shift pattern changes. |
| Step cycle times | 30 s to 84 s | Which step limits output: the lathe, with 60 minutes a day to spare | Protect the lathe: cover its breaks, fix its stops first, check parts before it so it never works on scrap. Do not speed up the saw. |
| Throughput time | 7.0 days | How long a shaft takes on the floor | Cap the piles between steps. At the same output it falls in proportion to the WIP. |
| Production lead time | 13.0 days | Cash tied up, and how fast the plant can react when demand changes | Smaller, more frequent bar deliveries and fewer packed shafts waiting. |
| Order lead time | 14.0 days | What the customer feels and what sales can promise | Look outside the floor as well: 4 of the 14 days are order handling and the weekly schedule. |
| Value-added ratio | 0.04% | Almost all of the lead time is waiting | Start with the piles and the release rules before buying faster machines. |
| Change | Throughput time | Production lead time | Order lead time | Line capacity |
|---|---|---|---|---|
| Today | 7.0 days | 13.0 days | 14.0 days | 642 a day |
| Cap the pile before the lathe at 300 shafts and release the schedule every day | 4.0 days | 10.0 days | 9.0 days | 642 a day |
| Instead, take 14 s of loading off the lathe (84 s to 70 s) | 7.0 days | 13.0 days | 14.0 days | 720 a day (grinding becomes the bottleneck) |
Same demand (600 a day) and the same other piles. The faster lathe shortens every lead time by 14 seconds.
Capping the pile before the lathe takes 1,800 shafts out of WIP and 3.0 days out of every lead time without touching a machine. Half a day of blanks (300) still sits in front of the lathe, so a saw stop does not starve it; size that buffer from the longest saw stop you have seen, not from habit. Releasing the schedule every day cuts the average wait for release from 2.5 days to 0.5. Together they bring the customer's wait from 14.0 to 9.0 days. The faster lathe adds 78 shafts a day of capacity, which is worth having only if demand grows.
Measure your own in one shift
- 1
Pick one part and the two ends
One part number or a family that shares the steps. Write down where the clock starts and stops, such as receiving to truck, or first step to last, and keep the same ends next time.
- 2
Work out takt
Available time per day after breaks, divided by the parts the customer takes per day. The takt time calculator does it from shift time, breaks and demand.
- 3
Time each step and find the bottleneck
Time at least ten parts at each step with a time study sheet, divide by the machines doing that step, and compare with takt in the cycle time calculator. The bottleneck calculator adds machine uptime.
- 4
Count every pile on one walk
Count the same morning, from the truck back to receiving, raw material and packed parts included, and divide each pile by daily output. The lead time worksheet does the sums and names the biggest pile.
- 5
Check it two ways
Divide total WIP by what you ship per day in the lead time calculator, then tag five parts over two weeks and add up their waits in the throughput time calculator. If the two disagree badly, recount.
- 6
Trace a few orders and draw the map
Take the dates from recent orders: received, released, started, packed, shipped, delivered. Then draw the flow on the value stream map template and plan the changes with the future state VSM worksheet.
Sources, and where definitions differ
- Lean Enterprise Institute, Lean Lexicon (lean.org): the entries for cycle time (with machine cycle time, processing time, production lead time, also called throughput time, and order lead time), takt time and value stream mapping.
- Mike Rother and John Shook, Learning to See (Lean Enterprise Institute, 1999): value stream mapping, with each pile of inventory turned into days of customer demand on the lead time line.
- John D. C. Little, A proof for the queuing formula L = λW, Operations Research 9(3), 1961, and Little's Law as Viewed on Its 50th Anniversary, Operations Research 59(3), 2011.
- Wallace Hopp and Mark Spearman, Factory Physics: Little's Law written as TH = WIP ÷ CT, with cycle time as the average time from release to the end of the routing, and raw process time, bottleneck rate and critical WIP.
These sources, and most companies, do not use exactly the same words for the same measures. When you share a number, say which definition and which two end points you used.
Go deeper
This page is the short version. These guides cover each part in full.
- What Are the Four Types of Lead Time?Material, customer, production and cumulative lead time, and why each matters.
- How to Improve Throughput Time in ManufacturingWhat throughput time includes, how it differs from cycle time and lead time, and ways to shorten it.
- How to Reduce Lead Time in ManufacturingThe levers on lead time beyond the shop floor, from suppliers to scheduling.
- The Three Elements of Standard Work: Takt Time, Work Sequence, Standard WIPHow takt time sets the pace for standard work and how much WIP a station should hold.
- Manufacturing Bottleneck Elimination: 5 Proven StrategiesWays to raise the capacity of the step that limits the line, once you have found it.
- Value Stream Mapping: A Beginner's Complete GuideHow to draw the current-state map where these numbers live, symbols included.
- Value-Added vs Non-Value-Added Time in ManufacturingHow to sort each second into value-added, necessary and pure waste.
All our articles on this subject are in the value stream mapping and flow topic.
Free templates and tools
- Value stream map templateA printable current-state and future-state map with data boxes, inventory triangles and the lead-time ladder; the Excel version works out takt, inventory days and processing time ÷ lead time.
- Lead time worksheetProduction lead time from the inventory waiting at each step, value-added time and process cycle efficiency, plus an order traced from order to delivery.
- Bottleneck analysis worksheetEffective capacity per station from cycle time, parallel units, availability and yield, the bottleneck, takt and utilization, a queue cross-check and the five focusing steps.
- Time study sheetTime each element over 10 cycles and work out the average, lowest repeatable and standard time. Excel does the sums.
- Process capacity sheet templateEach machine in a part's routing with manual, auto and tool change time, its capacity per shift, and the step that limits the cell against demand.
- Future state value stream map worksheetThe eight future-state questions worked through in order: takt, pitch, flow, supermarkets, the pacemaker and the mix, with an EPEI check and current against future lead time.
- Takt time calculatorThe pace a line must hit to meet customer demand, from shift time, breaks and daily demand.
- Cycle time calculatorCycle time against takt, units per hour, capacity per shift and the gap to daily demand.
- Bottleneck calculatorThe step that limits your line, from each step's cycle time, machines and uptime, with daily capacity and the gap to demand.
- Lead time calculatorManufacturing lead time from WIP and throughput (Little's Law), and the share of it that adds value.
- Throughput time calculatorThroughput time from process, inspection, move and wait time, the share of it that adds value, and units per hour.
- Line balancing calculatorLine efficiency, balance delay and the minimum number of stations from station times and takt.
- Time study sample size calculatorHow many cycles of an element to time, from your first readings, with the t formula, the ILO formula and the range method.
Doing this in LeanSuite
Value Stream Mapping
Turns video of each process step into a current-state value stream map with cycle times, inventory and lead time.
See Value Stream MappingLine Balancing
Drop in a video of your line and get a Yamazumi chart, a takt comparison and rebalancing recommendations.
See Line Balancing
See it on your own lines
Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.
FAQ
Questions about cycle time vs lead time, worked through
Rather see it on your own problem?
Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.

