Model area: a 90-day plan for each pillar, then expansion

Short answer

A model area is one line, machine or zone where an improvement pillar first proves its method with the people who work there, before the method spreads across the plant. The area is chosen from loss data, the pillar runs a 90-day plan there with a clear done-when for every step, and a day-90 gate decides whether it is ready to copy. After that the method spreads in waves, coached by the model area team, with each new area measured against its own baseline.

Last reviewed:

What a model area is, and how to choose one

Pillars such as safety, quality and maintenance do not start everywhere at once. Each pillar picks one area, runs its method there until it works on the floor, writes the standard and only then spreads it. Starting everywhere at once spreads the pillar team thin and produces activity without results, which is why our TPM launch guide starts with a single pilot area. The glossary calls the same idea a model line.

Four things to score each candidate area on (1 weak, 2 fair, 3 strong, an example scale)
CriterionWhat to look forWhy it matters
Loss dataThe area's real losses for this pillar: incidents, defects, breakdowns, waste or energyResults on a real loss convince people; results on an easy area do not
VisibilityLeaders and visitors walk past it every dayPeople copy what they can see working
Team willingnessThe supervisor and team want to do it, not only accept itThe model area team becomes the coaches for the next areas
RepeatabilityThe same machines, process or hazards run elsewhereA standard that copies with little change spreads faster

Score loss data first. On a tie, the higher loss data score wins.

One model area on the floor, and what goes on its board

Illustrative example

Three candidates scored on the four criteria, out of 12

  • Press line 1
  • Press line 2Model areaScored 11
  • Press line 3

Main aisle

  • Weld cell AScored 9
  • Weld cell B
  • Tool room
  • Stores
  • Shipping dockScored 7

Team board at Press line 2

Safety cross: one box a day, filled in daily

KPI board: baseline, day-90 target, weekly actual (arrow: the way it should move)

  • Near misses and unsafe conditions reported(higher is better)
  • Safety actions closed on time(higher is better)
  • High risks still open(lower is better)
  • Tasks with a current risk assessment(higher is better)
  • First-aid and recordable cases(lower is better)
The safety plan's worked example: a metal stamping plant, made-up scores, layout drawn for this page. Press line 2 had the most first-aid cases and the highest-rated risks (pinch points at die change), sits on the main aisle, and its tasks repeat on two other press lines.

Starting in one area is also the first step of the 1-1-90 method: 1 area, 1 pain point, 90 days, then expand. It has a one-page worksheet for scoring areas and planning what comes after.

The 1-1-90 method, read as a model area plan

  1. 1area

    One line, one cell, one shift or one department.

    In a plan: One model area per pillar: a line, machine or zone, scored on the four criteria.

  2. 1pain point

    One problem, written as one sentence with a number.

    In a plan: The pillar's own loss in that area, such as incidents, defects, breakdowns or waste.

  3. 90days

    A fixed run with a decision at the end.

    In a plan: 13 weeks in three phases, ending with the day-90 gate.

  4. thenexpand

    Copy what worked to the next area, then to other plants.

    In a plan: Three waves in months 4 to 12, coached by the model area team.

The ten 90-day plans

Each plan has the same shape, so the pillar leads can review them side by side: a 13-week plan in three phases, a scoring table to choose the area, the team, a KPI board, a day-90 gate and an expansion plan for months 4 to 12. The method inside each one is the pillar's own.

What each pillar does in its model area in the first 90 days
  • Page 1 of the safety pillar 90-day model area plan: a 13-week Gantt chart in three phases with the owner, deliverable and done-when of each activity, from the incident pyramid to the day-90 gate.

    Safety

    Model area is usually: The area with the most incidents, near misses or highest-rated risks

    The 90 days cover: Incident pyramid, safety cross, near-miss reporting, hazard hunt, risk assessment, hierarchy of controls, standards, observations, audit

    Safety pillar 90-day plan, free PDF and Excel
  • Page 1 of the quality control pillar 90-day model area plan: a 13-week Gantt chart in three phases with the owner, deliverable and done-when of each activity, from the defect data to the day-90 gate.

    Quality control

    Model area is usually: The line or cell with the most scrap, rework or complaints

    The 90 days cover: QA matrix, containment, defect mode analysis, restore conditions, countermeasures, conditions for zero defects, QM matrix

    Quality control pillar 90-day plan, free PDF and Excel
  • Page 1 of the autonomous maintenance 90-day model area plan: a 13-week Gantt chart in three phases with the owner, deliverable and done-when of each activity, from step 0 preparation to the day-90 gate.

    Autonomous maintenance

    Model area is usually: One machine with high breakdowns or minor stops

    The 90 days cover: Steps 0 to 3: preparation, initial cleaning and tagging, sources of contamination and hard-to-access areas, provisional standards

    Autonomous maintenance 90-day plan, free PDF and Excel
  • Page 1 of the professional maintenance 90-day model area plan: a 13-week Gantt chart in three phases with the owner, deliverable and done-when of each activity, from breakdown analysis to the day-90 gate.

    Professional maintenance

    Model area is usually: One machine with high downtime or repeat failures

    The 90 days cover: Breakdown analysis, restoration, weak points, component ranking, PM tasks, spares, PM calendar

    Professional maintenance 90-day plan, free PDF and Excel
  • Page 1 of the environment and energy pillar 90-day model area plan: a 13-week Gantt chart in three phases with the owner, deliverable and done-when of each activity, from the waste and energy maps to the day-90 gate.

    Environment and energy

    Model area is usually: The area with the biggest waste streams or energy use

    The 90 days cover: Waste and energy maps, legal register, aspects, energy losses, waste hierarchy, segregation, standards

    Environment pillar 90-day plan, free PDF and Excel
  • Page 1 of the focused improvement 90-day model area plan: a 13-week Gantt chart in three phases with the owner, deliverable and done-when of each activity, from measuring OEE and the six big losses to the day-90 gate.

    Focused improvement

    Model area is usually: The line with the biggest OEE losses

    The 90 days cover: OEE and the six big losses, loss themes run with PDCA, standardize, quick kaizen, savings confirmed by finance

    Focused improvement 90-day plan, free PDF and Excel
  • Page 1 of the logistics and customer service pillar 90-day model area plan: a 13-week Gantt chart in three phases with the owner, deliverable and done-when of each activity, from mapping the current state to the day-90 gate.

    Logistics and customer service

    Model area is usually: The value stream with the most shortages or late deliveries

    The 90 days cover: Value stream map, point-of-use material, supermarket, kanban loops, water spider route, FIFO, shortage escalation

    Logistics pillar 90-day plan, free PDF and Excel
  • Page 1 of the people development pillar 90-day model area plan: a 13-week Gantt chart in three phases with the owner, deliverable and done-when of each activity, from building the skills matrix to the day-90 gate.

    People development

    Model area is usually: The area with the most errors from skill gaps or single points of failure

    The 90 days cover: Skills matrix, skill gaps from losses, job instruction trainers, breakdown sheets, training and sign-off

    People development 90-day plan, free PDF and Excel
  • Page 1 of the early equipment management 90-day model area plan: a 13-week Gantt chart in three phases with the owner, deliverable and done-when of each activity, from collecting lessons from similar machines to the day-90 gate.

    Early equipment management

    Model area is usually: One coming equipment project

    The 90 days cover: Lessons from current machines, design checklist, reviews, risk assessment, acceptance tests, start-up

    Early equipment management 90-day plan, free PDF and Excel
  • Page 1 of the cost deployment 90-day model area plan: a 13-week Gantt chart in three phases with the owner, deliverable and done-when of each activity, from collecting the costs and loss data to the day-90 gate.

    Cost deployment

    Model area is usually: The area with the largest share of conversion cost

    The 90 days cover: Loss map, causal and resultant losses, loss costing, ranked projects, savings followed up with finance

    Cost deployment 90-day plan, free PDF and Excel

Each template is a PDF to print and an Excel version that works out the dates, status, scores and gap closed.

How the pillars usually start

  1. 1

    Loss data first

    Before any pillar picks its model area, pull the plant's losses by area: incidents, defects, breakdowns, waste and energy. Each pillar chooses from its own losses, so two pillars can start in different areas.

  2. 2

    Safety from day one

    Many plants start the safety pillar first, because no other pillar's work should add hazards and its routines, near-miss reporting and risk assessment, cost little to start. The 8 pillars of TPM guide puts safety, health and environment in one pillar; many plants run safety and environment separately, as these templates do.

  3. 3

    Autonomous and professional maintenance early

    Our TPM launch guide starts both maintenance pillars in the first quarter, because they build the operator skill and the equipment data the later pillars depend on. Run them on the same machine and split the checks between operators and maintenance.

  4. 4

    Quality control once there is condition data

    Quality control traces defects to machine and process conditions. It works best once the maintenance pillars have restored the machines and there is defect and condition history to analyse.

  5. 5

    Cost deployment, focused improvement and people development as the data and the work grow

    A costed loss map helps every pillar choose where to work, so it pays to start cost deployment early. Focused improvement needs enough loss data first; our TPM launch guide puts it in the third quarter. People development runs alongside every pillar, since each one needs trained people, and early equipment management starts when the next equipment project does.

  6. 6

    Environment when its losses are large

    Environment and energy can start whenever its loss data shows a big loss, such as waste to landfill or compressed air. It often shares the model area with safety, since both start from a walk of the area.

The 90 days in three phases

  1. Days 1 to 30 · weeks 1 to 4Set up, measure the baseline, see the real conditionEnds with: a team, a baseline on the KPI board and the area's real problems on paper
  2. Days 31 to 60 · weeks 5 to 9Find causes and fix themEnds with: the main causes found and countermeasures in place or scheduled
  3. Days 61 to 90 · weeks 10 to 13Write the standard, hold it, pass the gateEnds with: a standard the team follows without help, and the day-90 gate
Week 13 ends on day 91; the phase limits are rounded to whole weeks.

Week by week: what each plan does in its 13 weeks

  1. Choose the model area and form the team (Setup, week 1)

  2. Draw the incident pyramid for the area (Reactive, weeks 1 to 2)

  3. Start the safety cross (Reactive, weeks 2 to 3)

  4. Launch near-miss reporting (Preventive, weeks 2 to 4)

  5. Hazard hunt: walk the whole area (Preventive, weeks 3 to 5)

  6. Risk assessment of every task in the area (Preventive, weeks 4 to 7)

  7. Remove high risks by the hierarchy of controls (Preventive, weeks 5 to 9)

  8. Investigate incidents and serious near misses (Reactive, weeks 6 to 9)

  9. Write the safety standards for the area (Proactive, weeks 8 to 11)

  10. Start safety observations (Proactive, weeks 9 to 12)

  11. Safety audit of the area and close the gaps (Proactive, weeks 11 to 13)

  12. Day-90 review and decision to expand (Gate, week 13)

The standard plan printed on page 1 of each PDF. Every plan has 12 activities, and the last one is the day-90 gate in week 13 (in yellow). Move the weeks to fit your area.

The day-90 gate is a short checklist signed by the sponsor and the pillar lead: the method's own checks (for example, every task risk-assessed, or steps 1 to 3 passing the autonomous maintenance step audit), 13 weeks of KPI data against the baseline, and the standard and lessons written up so another team can copy them. If a check is not met, the team fixes it before any other area starts.

Press line 2 on day 1 and in week 13

Example numbers
  • Near misses and unsafe conditions reported (higher is better)

    Day 1
    2 a week
    Week 13
    7 a week

    Day-90 target 8 a week. 83% of the gap closed.

  • Safety actions closed on time (higher is better)

    Day 1
    45%
    Week 13
    85%

    Day-90 target 90%. 89% of the gap closed.

  • High risks still open (lower is better)

    Day 1
    6
    Week 13
    1

    Day-90 target 0. 83% of the gap closed.

  • Tasks with a current risk assessment (higher is better)

    Day 1
    20%
    Week 13
    100%

    Day-90 target 100%. 100% of the gap closed.

  • First-aid and recordable cases (lower is better)

    Day 1
    3
    Week 13
    1

    Day-90 target 0. 67% of the gap closed.

The safety plan's worked example (page 4 of its PDF), made-up numbers, not a benchmark. Gap closed: how far week 13 moved from the baseline toward the target.

How expansion works after day 90

Months 4 to 12: three waves of expansion

  1. Wave 1 · months 4 to 6The areas most like the model area: same machine type, process or hazardsCoached by: model area team members, one per new area
  2. Wave 2 · months 7 to 9The next areas by size of loss for this pillarCoached by: people trained in wave 1, checked by the pillar lead
  3. Wave 3 · months 10 to 12The remaining priority areas, including support areas such as stores, utilities and workshopsCoached by: coaches from waves 1 and 2

From one area to the plant in 12 months

Illustrative example
  • Press line 1Wave 1
  • Press line 2Model area
  • Press line 3Wave 1

Main aisle

  • Weld cell AWave 2
  • Weld cell BWave 2
  • Tool roomWave 3
  • StoresWave 3
  • Shipping dockWave 3
  1. Model area, days 1 to 90: Press line 2The model area team proves the method
  2. Wave 1, months 4 to 6: Press line 1, Press line 3Model area team members, one per new area
  3. Wave 2, months 7 to 9: Weld cell A, Weld cell BPeople trained in wave 1, checked by the pillar lead
  4. Wave 3, months 10 to 12: Tool room, Stores, Shipping dockCoaches from waves 1 and 2
The safety example's waves. Each new area runs its own 13 weeks against its own baseline and passes the same day-90 gate.
  • Copy the method, not only the paperwork. Each new area runs its own 13 weeks against its own baseline, often faster with a coach who has done it. This is yokoten: someone owns the adaptation in each receiving area, and its results are measured and compared with the model area.
  • The model area team trains the next area. A team member coaches each wave 1 area at the gemba, wave 1 people coach wave 2, and the pillar lead checks each new coach before they coach alone.
  • Each wave has a gate: the new area passed the same day-90 gate, its KPIs are measured against its own baseline, the copy is recorded, the next coaches are named, and the model area still holds its standard. The yokoten tracker keeps the record of what was copied where.
  • Agree the resources before each wave: coach hours each week, maintenance or engineering time, and a budget for the fixes the new areas will need.

Free templates and tools

FAQ

Questions about model area 90-day plans

  1. A model area is one line, machine or zone where a pillar first runs its method with the people who work there and proves it gives results, before the method spreads to the rest of the plant. It is chosen to represent real production conditions, not the easiest or best-kept area, so the results are believed elsewhere.

  2. Start from loss data for the pillar, then look at visibility to leaders, whether the supervisor and team want to do it, and whether the same machines, process or hazards run elsewhere. Avoid the area that is already in good shape: results there do not transfer credibly to harder areas.

  3. Autonomous maintenance and planned (professional) maintenance usually start in the first quarter, because they build the operator skill and equipment data that later pillars such as quality maintenance and focused improvement depend on. Many plants run safety from day one alongside them.

  4. Only after the model area has shown sustained results against its original baseline. Each new area then follows the same sequence with its own baseline and staffing, often faster with a coach from the model area, rather than skipping steps to move faster.

  5. Yokoten (horizontal deployment) is the structured practice of taking an improvement that has been proven in one area and deliberately copying it to other lines, shifts or plants that run the same or a similar process. The improvement is written up well enough to copy, someone owns the adaptation in each receiving area, and the results there are measured and compared with the original.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.