Method guide · TPM and maintenance
Model area: a 90-day plan for each pillar, then expansion
Short answer
A model area is one line, machine or zone where an improvement pillar first proves its method with the people who work there, before the method spreads across the plant. The area is chosen from loss data, the pillar runs a 90-day plan there with a clear done-when for every step, and a day-90 gate decides whether it is ready to copy. After that the method spreads in waves, coached by the model area team, with each new area measured against its own baseline.
Last reviewed:
What a model area is, and how to choose one
Pillars such as safety, quality and maintenance do not start everywhere at once. Each pillar picks one area, runs its method there until it works on the floor, writes the standard and only then spreads it. Starting everywhere at once spreads the pillar team thin and produces activity without results, which is why our TPM launch guide starts with a single pilot area. The glossary calls the same idea a model line.
| Criterion | What to look for | Why it matters |
|---|---|---|
| Loss data | The area's real losses for this pillar: incidents, defects, breakdowns, waste or energy | Results on a real loss convince people; results on an easy area do not |
| Visibility | Leaders and visitors walk past it every day | People copy what they can see working |
| Team willingness | The supervisor and team want to do it, not only accept it | The model area team becomes the coaches for the next areas |
| Repeatability | The same machines, process or hazards run elsewhere | A standard that copies with little change spreads faster |
Score loss data first. On a tie, the higher loss data score wins.
One model area on the floor, and what goes on its board
Illustrative exampleThree candidates scored on the four criteria, out of 12
- Press line 1
- Press line 2Model areaScored 11
- Press line 3
Main aisle
- Weld cell AScored 9
- Weld cell B
- Tool room
- Stores
- Shipping dockScored 7
Team board at Press line 2
Safety cross: one box a day, filled in daily
KPI board: baseline, day-90 target, weekly actual (arrow: the way it should move)
- Near misses and unsafe conditions reported(higher is better)
- Safety actions closed on time(higher is better)
- High risks still open(lower is better)
- Tasks with a current risk assessment(higher is better)
- First-aid and recordable cases(lower is better)
Starting in one area is also the first step of the 1-1-90 method: 1 area, 1 pain point, 90 days, then expand. It has a one-page worksheet for scoring areas and planning what comes after.
The 1-1-90 method, read as a model area plan
1area
One line, one cell, one shift or one department.
In a plan: One model area per pillar: a line, machine or zone, scored on the four criteria.
1pain point
One problem, written as one sentence with a number.
In a plan: The pillar's own loss in that area, such as incidents, defects, breakdowns or waste.
90days
A fixed run with a decision at the end.
In a plan: 13 weeks in three phases, ending with the day-90 gate.
thenexpand
Copy what worked to the next area, then to other plants.
In a plan: Three waves in months 4 to 12, coached by the model area team.
The ten 90-day plans
Each plan has the same shape, so the pillar leads can review them side by side: a 13-week plan in three phases, a scoring table to choose the area, the team, a KPI board, a day-90 gate and an expansion plan for months 4 to 12. The method inside each one is the pillar's own.

Safety
Model area is usually: The area with the most incidents, near misses or highest-rated risks
The 90 days cover: Incident pyramid, safety cross, near-miss reporting, hazard hunt, risk assessment, hierarchy of controls, standards, observations, audit
Safety pillar 90-day plan, free PDF and Excel
Quality control
Model area is usually: The line or cell with the most scrap, rework or complaints
The 90 days cover: QA matrix, containment, defect mode analysis, restore conditions, countermeasures, conditions for zero defects, QM matrix
Quality control pillar 90-day plan, free PDF and Excel
Autonomous maintenance
Model area is usually: One machine with high breakdowns or minor stops
The 90 days cover: Steps 0 to 3: preparation, initial cleaning and tagging, sources of contamination and hard-to-access areas, provisional standards
Autonomous maintenance 90-day plan, free PDF and Excel
Professional maintenance
Model area is usually: One machine with high downtime or repeat failures
The 90 days cover: Breakdown analysis, restoration, weak points, component ranking, PM tasks, spares, PM calendar
Professional maintenance 90-day plan, free PDF and Excel
Environment and energy
Model area is usually: The area with the biggest waste streams or energy use
The 90 days cover: Waste and energy maps, legal register, aspects, energy losses, waste hierarchy, segregation, standards
Environment pillar 90-day plan, free PDF and Excel
Focused improvement
Model area is usually: The line with the biggest OEE losses
The 90 days cover: OEE and the six big losses, loss themes run with PDCA, standardize, quick kaizen, savings confirmed by finance
Focused improvement 90-day plan, free PDF and Excel
Logistics and customer service
Model area is usually: The value stream with the most shortages or late deliveries
The 90 days cover: Value stream map, point-of-use material, supermarket, kanban loops, water spider route, FIFO, shortage escalation
Logistics pillar 90-day plan, free PDF and Excel
People development
Model area is usually: The area with the most errors from skill gaps or single points of failure
The 90 days cover: Skills matrix, skill gaps from losses, job instruction trainers, breakdown sheets, training and sign-off
People development 90-day plan, free PDF and Excel
Early equipment management
Model area is usually: One coming equipment project
The 90 days cover: Lessons from current machines, design checklist, reviews, risk assessment, acceptance tests, start-up
Early equipment management 90-day plan, free PDF and Excel
Cost deployment
Model area is usually: The area with the largest share of conversion cost
The 90 days cover: Loss map, causal and resultant losses, loss costing, ranked projects, savings followed up with finance
Cost deployment 90-day plan, free PDF and Excel
Each template is a PDF to print and an Excel version that works out the dates, status, scores and gap closed.
How the pillars usually start
- 1
Loss data first
Before any pillar picks its model area, pull the plant's losses by area: incidents, defects, breakdowns, waste and energy. Each pillar chooses from its own losses, so two pillars can start in different areas.
- 2
Safety from day one
Many plants start the safety pillar first, because no other pillar's work should add hazards and its routines, near-miss reporting and risk assessment, cost little to start. The 8 pillars of TPM guide puts safety, health and environment in one pillar; many plants run safety and environment separately, as these templates do.
- 3
Autonomous and professional maintenance early
Our TPM launch guide starts both maintenance pillars in the first quarter, because they build the operator skill and the equipment data the later pillars depend on. Run them on the same machine and split the checks between operators and maintenance.
- 4
Quality control once there is condition data
Quality control traces defects to machine and process conditions. It works best once the maintenance pillars have restored the machines and there is defect and condition history to analyse.
- 5
Cost deployment, focused improvement and people development as the data and the work grow
A costed loss map helps every pillar choose where to work, so it pays to start cost deployment early. Focused improvement needs enough loss data first; our TPM launch guide puts it in the third quarter. People development runs alongside every pillar, since each one needs trained people, and early equipment management starts when the next equipment project does.
- 6
Environment when its losses are large
Environment and energy can start whenever its loss data shows a big loss, such as waste to landfill or compressed air. It often shares the model area with safety, since both start from a walk of the area.
The 90 days in three phases
- Days 1 to 30 · weeks 1 to 4Set up, measure the baseline, see the real conditionEnds with: a team, a baseline on the KPI board and the area's real problems on paper
- Days 31 to 60 · weeks 5 to 9Find causes and fix themEnds with: the main causes found and countermeasures in place or scheduled
- Days 61 to 90 · weeks 10 to 13Write the standard, hold it, pass the gateEnds with: a standard the team follows without help, and the day-90 gate
Week by week: what each plan does in its 13 weeks
Choose the model area and form the team (Setup, week 1)
Draw the incident pyramid for the area (Reactive, weeks 1 to 2)
Start the safety cross (Reactive, weeks 2 to 3)
Launch near-miss reporting (Preventive, weeks 2 to 4)
Hazard hunt: walk the whole area (Preventive, weeks 3 to 5)
Risk assessment of every task in the area (Preventive, weeks 4 to 7)
Remove high risks by the hierarchy of controls (Preventive, weeks 5 to 9)
Investigate incidents and serious near misses (Reactive, weeks 6 to 9)
Write the safety standards for the area (Proactive, weeks 8 to 11)
Start safety observations (Proactive, weeks 9 to 12)
Safety audit of the area and close the gaps (Proactive, weeks 11 to 13)
Day-90 review and decision to expand (Gate, week 13)
The day-90 gate is a short checklist signed by the sponsor and the pillar lead: the method's own checks (for example, every task risk-assessed, or steps 1 to 3 passing the autonomous maintenance step audit), 13 weeks of KPI data against the baseline, and the standard and lessons written up so another team can copy them. If a check is not met, the team fixes it before any other area starts.
Press line 2 on day 1 and in week 13
Example numbersNear misses and unsafe conditions reported (higher is better)
- Day 1
- 2 a week
- Week 13
- 7 a week
Day-90 target 8 a week. 83% of the gap closed.
Safety actions closed on time (higher is better)
- Day 1
- 45%
- Week 13
- 85%
Day-90 target 90%. 89% of the gap closed.
High risks still open (lower is better)
- Day 1
- 6
- Week 13
- 1
Day-90 target 0. 83% of the gap closed.
Tasks with a current risk assessment (higher is better)
- Day 1
- 20%
- Week 13
- 100%
Day-90 target 100%. 100% of the gap closed.
First-aid and recordable cases (lower is better)
- Day 1
- 3
- Week 13
- 1
Day-90 target 0. 67% of the gap closed.
How expansion works after day 90
Months 4 to 12: three waves of expansion
- Wave 1 · months 4 to 6The areas most like the model area: same machine type, process or hazardsCoached by: model area team members, one per new area
- Wave 2 · months 7 to 9The next areas by size of loss for this pillarCoached by: people trained in wave 1, checked by the pillar lead
- Wave 3 · months 10 to 12The remaining priority areas, including support areas such as stores, utilities and workshopsCoached by: coaches from waves 1 and 2
From one area to the plant in 12 months
Illustrative example- Press line 1Wave 1
- Press line 2Model area
- Press line 3Wave 1
Main aisle
- Weld cell AWave 2
- Weld cell BWave 2
- Tool roomWave 3
- StoresWave 3
- Shipping dockWave 3
- Model area, days 1 to 90: Press line 2The model area team proves the method
- Wave 1, months 4 to 6: Press line 1, Press line 3Model area team members, one per new area
- Wave 2, months 7 to 9: Weld cell A, Weld cell BPeople trained in wave 1, checked by the pillar lead
- Wave 3, months 10 to 12: Tool room, Stores, Shipping dockCoaches from waves 1 and 2
- Copy the method, not only the paperwork. Each new area runs its own 13 weeks against its own baseline, often faster with a coach who has done it. This is yokoten: someone owns the adaptation in each receiving area, and its results are measured and compared with the model area.
- The model area team trains the next area. A team member coaches each wave 1 area at the gemba, wave 1 people coach wave 2, and the pillar lead checks each new coach before they coach alone.
- Each wave has a gate: the new area passed the same day-90 gate, its KPIs are measured against its own baseline, the copy is recorded, the next coaches are named, and the model area still holds its standard. The yokoten tracker keeps the record of what was copied where.
- Agree the resources before each wave: coach hours each week, maintenance or engineering time, and a budget for the fixes the new areas will need.
Go deeper
This page is the short version. These guides cover each part in full.
- TPM Launch: Year One Deployment GuideChoosing and staffing the pilot, the quarter-by-quarter first year, and when to expand beyond the pilot.
- The 8 Pillars of TPM ExplainedWhat each pillar covers, how they depend on each other, and which to start with.
- 7 Steps of Autonomous Maintenance: The TPM Pillar ExplainedAll seven autonomous maintenance steps, including the four that come after the model area's first 90 days.
- Yokoten: Horizontal Deployment of Kaizen Best PracticesHow a proven practice is shared and adapted across areas and plants.
- Near Miss Reporting That Actually Prevents Future IncidentsThe near-miss routine the safety model area starts in its first month.
All our articles on this subject are in the tpm and maintenance topic.
Free templates and tools
- Safety pillar 90-day model area planThirteen weeks from the incident pyramid to safety standards on one model area, a KPI board, the day-90 gate and expansion waves.
- Quality control pillar 90-day model area planThirteen weeks from the QA matrix to the QM matrix on one model area, a KPI board, the day-90 gate and expansion waves.
- Autonomous maintenance 90-day model area planAM steps 0 to 3 on one model machine in 13 weeks, a KPI board, the day-90 gate and expansion waves for months 4 to 12.
- Professional maintenance (PM) 90-day model area planThirteen weeks from breakdown analysis to a running PM calendar on one model machine, a KPI board, the day-90 gate and expansion waves.
- Environment and energy pillar 90-day model area planThirteen weeks from waste and energy maps to area standards on one model area, a KPI board, the day-90 gate and expansion waves.
- Focused improvement 90-day model area planThirteen weeks from the loss Pareto to standardized fixes on one model line, a KPI board, the day-90 gate and expansion waves.
- Logistics and customer service pillar 90-day model area planThirteen weeks from the current-state map to pull on one model value stream, a KPI board, the day-90 gate and expansion waves.
- People development pillar 90-day model area planThirteen weeks from the skills matrix to trained cover on critical tasks in one model area, a KPI board, the day-90 gate and expansion waves.
- Early equipment management 90-day model area planThirteen weeks from lessons on current machines to a tracked start-up on one model equipment project, a KPI board, the day-90 gate and expansion waves.
- Cost deployment pillar 90-day model area planThirteen weeks from the loss map to costed, ranked projects in one model area, a KPI board, the day-90 gate and expansion waves.
- Yokoten tracker (horizontal deployment)Copy a proven improvement line by line: the source result, each candidate's own before and after, its share of the source's improvement and the standard updated.
- Autonomous maintenance step auditCriteria for each of the seven autonomous maintenance steps, scored 0 to 2, with the step result and the decision to move on.
- OEE calculatorOverall equipment effectiveness from shift time, downtime, ideal cycle time and part counts.
- MTBF and MTTR calculatorMean time between failures, mean time to repair and availability from operating time, failures and repair time.
Doing this in LeanSuite
Autonomous Maintenance
Rolls out visual CILR (clean, inspect, lube, retighten) checklists so operators catch small abnormalities before they cause downtime.
See Autonomous MaintenanceYokoten software
Captures local improvement wins and turns them into standards across every plant in your network.
See Yokoten softwareKPI Dashboards
Turns raw shop floor data into dashboards anyone can read, so everyone from operators to the plant manager can act on performance.
See KPI DashboardsSafety Improvement
Keeps employees alert to hazards and gives leaders the visibility to drive safety improvements.
See Safety Improvement
See it on your own lines
Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.
FAQ
Questions about model area 90-day plans
A model area is one line, machine or zone where a pillar first runs its method with the people who work there and proves it gives results, before the method spreads to the rest of the plant. It is chosen to represent real production conditions, not the easiest or best-kept area, so the results are believed elsewhere.
Start from loss data for the pillar, then look at visibility to leaders, whether the supervisor and team want to do it, and whether the same machines, process or hazards run elsewhere. Avoid the area that is already in good shape: results there do not transfer credibly to harder areas.
Autonomous maintenance and planned (professional) maintenance usually start in the first quarter, because they build the operator skill and equipment data that later pillars such as quality maintenance and focused improvement depend on. Many plants run safety from day one alongside them.
Only after the model area has shown sustained results against its original baseline. Each new area then follows the same sequence with its own baseline and staffing, often faster with a coach from the model area, rather than skipping steps to move faster.
Yokoten (horizontal deployment) is the structured practice of taking an improvement that has been proven in one area and deliberately copying it to other lines, shifts or plants that run the same or a similar process. The improvement is written up well enough to copy, someone owns the adaptation in each receiving area, and the results there are measured and compared with the original.
Related guides and tools
- Lean in 7 days, day 1: what lean is, before you pick a model area
- Lean in 7 days, day 3: 5S, the first thing most model areas do
- Lean in 7 days, day 2: gemba walks in your model area
- Kaizen cost savings tracking for the model area's results
- Free e-book, readable online: why CI programs stall, and why to start with one area and one pain point
More method guides
- The 6 Ms of production
- Poka-yoke
- Moving from Excel to one system
- Reducing machine downtime: a worked month
- Andon
- Cycle time vs lead time, worked through
- Root cause analysis
- How many operators a line needs
- Reducing scrap and rework: a worked month
- Unsafe acts and unsafe conditions
- Just culture
- Stop-work authority
- Material review board (MRB)
- Nonconformance and NCRs
- Problem solving methods
- Quad chart
- OEE calculation
- Quality assurance vs quality control
- SOP meaning and format
- Job hazard analysis
- Near miss reporting
- Fishbone diagram
- Pareto chart
- Histogram
- Control chart
- What is a gemba walk
- What is lead time
- What is operational excellence
- How to improve product quality
- Preventive vs predictive maintenance
- Kanban
- FMEA
- PDSA cycle
- Safety moments
- Just-in-time manufacturing
- Kaizen
- 5S
- Total quality management (TQM)
- CAPA (corrective and preventive action)
- Layered process audit (LPA)
- Lean tools
- Lockout tagout (LOTO)
- A3 problem solving
- Preventive maintenance
- APQP
- High reliability organization (HRO)
- Manufacturing KPIs
- Quality metrics
- Practical problem solving
- CMMS
- Risk assessment
- Production efficiency
- Total productive maintenance (TPM)
- Reliability-centered maintenance (RCM)
- Hierarchy of controls
- Personal protective equipment (PPE)
- Emergency action plan
- Safety signs
- Warehouse safety
- ISO 9001
- SIPOC diagram
- Rolling action item list (RAIL)
- Pugh matrix
- Flowchart
- Project charter
- ISO 9001:2026
- Fleet maintenance
- IATF 16949
- AS9100
- ISO 14001
- ISO 45001
- One point lesson
- Standard work
- Lean manufacturing principles
- Toyota Production System
- 5W1H
- 5 Whys
- Continuous improvement
- Takt time
- DMAIC
- PDCA
- 8D problem solving
- Prioritization matrix
- Gemba walk questions
- 5W1H questions
- Layered process audit questions
- 5S audit questions
Or browse the topics, the full library and the lean glossary.