Model area: a 90-day plan for each pillar, then expansion

Short answer

A model area is one line, machine or zone where an improvement pillar first proves its method with the people who work there, before the method spreads across the plant. The area is chosen from loss data, the pillar runs a 90-day plan there with a clear done-when for every step, and a day-90 gate decides whether it is ready to copy. After that the method spreads in waves, coached by the model area team, with each new area measured against its own baseline.

What a model area is, and how to choose one

Pillars such as safety, quality and maintenance do not start everywhere at once. Each pillar picks one area, runs its method there until it works on the floor, writes the standard and only then spreads it. Starting everywhere at once spreads the pillar team thin and produces activity without results, which is why our TPM launch guide starts with a single pilot area. The glossary calls the same idea a model line.

Four things to score each candidate area on (1 weak, 2 fair, 3 strong, an example scale)
CriterionWhat to look forWhy it matters
Loss dataThe area's real losses for this pillar: incidents, defects, breakdowns, waste or energyResults on a real loss convince people; results on an easy area do not
VisibilityLeaders and visitors walk past it every dayPeople copy what they can see working
Team willingnessThe supervisor and team want to do it, not only accept itThe model area team becomes the coaches for the next areas
RepeatabilityThe same machines, process or hazards run elsewhereA standard that copies with little change spreads faster

Score loss data first. On a tie, the higher loss data score wins.

The ten 90-day plans

Each plan has the same shape, so the pillar leads can review them side by side: a 13-week plan in three phases, a scoring table to choose the area, the team, a KPI board, a day-90 gate and an expansion plan for months 4 to 12. The method inside each one is the pillar's own.

What each pillar does in its model area in the first 90 days
PillarModel area is usuallyThe 90 days coverFree template
SafetyThe area with the most incidents, near misses or highest-rated risksIncident pyramid, safety cross, near-miss reporting, hazard hunt, risk assessment, hierarchy of controls, standards, observations, auditSafety pillar 90-day plan
Quality controlThe line or cell with the most scrap, rework or complaintsQA matrix, containment, defect mode analysis, restore conditions, countermeasures, conditions for zero defects, QM matrixQuality control pillar 90-day plan
Autonomous maintenanceOne machine with high breakdowns or minor stopsSteps 0 to 3: preparation, initial cleaning and tagging, sources of contamination and hard-to-access areas, provisional standardsAutonomous maintenance 90-day plan
Professional maintenanceOne machine with high downtime or repeat failuresBreakdown analysis, restoration, weak points, component ranking, PM tasks, spares, PM calendarProfessional maintenance 90-day plan
Environment and energyThe area with the biggest waste streams or energy useWaste and energy maps, legal register, aspects, energy losses, waste hierarchy, segregation, standardsEnvironment pillar 90-day plan
Focused improvementThe line with the biggest OEE lossesOEE and the six big losses, loss themes run with PDCA, standardize, quick kaizen, savings confirmed by financeFocused improvement 90-day plan
Logistics and customer serviceThe value stream with the most shortages or late deliveriesValue stream map, point-of-use material, supermarket, kanban loops, water spider route, FIFO, shortage escalationLogistics pillar 90-day plan
People developmentThe area with the most errors from skill gaps or single points of failureSkills matrix, skill gaps from losses, job instruction trainers, breakdown sheets, training and sign-offPeople development 90-day plan
Early equipment managementOne coming equipment projectLessons from current machines, design checklist, reviews, risk assessment, acceptance tests, start-upEarly equipment management 90-day plan
Cost deploymentThe area with the largest share of conversion costLoss map, causal and resultant losses, loss costing, ranked projects, savings followed up with financeCost deployment 90-day plan

Each template is a PDF to print and an Excel version that works out the dates, status, scores and gap closed.

How the pillars usually start

  1. 1

    Loss data first

    Before any pillar picks its model area, pull the plant's losses by area: incidents, defects, breakdowns, waste and energy. Each pillar chooses from its own losses, so two pillars can start in different areas.

  2. 2

    Safety from day one

    Many plants start the safety pillar first, because no other pillar's work should add hazards and its routines, near-miss reporting and risk assessment, cost little to start. The 8 pillars of TPM guide puts safety, health and environment in one pillar; many plants run safety and environment separately, as these templates do.

  3. 3

    Autonomous and professional maintenance early

    Our TPM launch guide starts both maintenance pillars in the first quarter, because they build the operator skill and the equipment data the later pillars depend on. Run them on the same machine and split the checks between operators and maintenance.

  4. 4

    Quality control once there is condition data

    Quality control traces defects to machine and process conditions. It works best once the maintenance pillars have restored the machines and there is defect and condition history to analyse.

  5. 5

    Cost deployment, focused improvement and people development as the data and the work grow

    A costed loss map helps every pillar choose where to work, so it pays to start cost deployment early. Focused improvement needs enough loss data first; our TPM launch guide puts it in the third quarter. People development runs alongside every pillar, since each one needs trained people, and early equipment management starts when the next equipment project does.

  6. 6

    Environment when its losses are large

    Environment and energy can start whenever its loss data shows a big loss, such as waste to landfill or compressed air. It often shares the model area with safety, since both start from a walk of the area.

The 90 days in three phases

The phases every plan follows
PhaseWeeksAimEnds with
Days 1 to 301 to 4Set up, measure the baseline, see the real conditionA team, a baseline on the KPI board and the area's real problems on paper
Days 31 to 605 to 9Find causes and fix themThe main causes found and countermeasures in place or scheduled
Days 61 to 9010 to 13Write the standard, hold it, pass the gateA standard the team follows without help, and the day-90 gate

Week 13 ends on day 91; the phase limits are rounded to whole weeks.

The day-90 gate is a short checklist signed by the sponsor and the pillar lead: the method's own checks (for example, every task risk-assessed, or steps 1 to 3 passing the autonomous maintenance step audit), 13 weeks of KPI data against the baseline, and the standard and lessons written up so another team can copy them. If a check is not met, the team fixes it before any other area starts.

How expansion works after day 90

Horizontal expansion in three waves, months 4 to 12
WaveMonthsWhich areasWho coaches
Wave 14 to 6The areas most like the model area: same machine type, process or hazardsModel area team members, one per new area
Wave 27 to 9The next areas by size of loss for this pillarPeople trained in wave 1, checked by the pillar lead
Wave 310 to 12The remaining priority areas, including support areas such as stores, utilities and workshopsCoaches from waves 1 and 2
  • Copy the method, not only the paperwork. Each new area runs its own 13 weeks against its own baseline, often faster with a coach who has done it. This is yokoten: someone owns the adaptation in each receiving area, and its results are measured and compared with the model area.
  • The model area team trains the next area. A team member coaches each wave 1 area at the gemba, wave 1 people coach wave 2, and the pillar lead checks each new coach before they coach alone.
  • Each wave has a gate: the new area passed the same day-90 gate, its KPIs are measured against its own baseline, the copy is recorded, the next coaches are named, and the model area still holds its standard. The yokoten tracker keeps the record of what was copied where.
  • Agree the resources before each wave: coach hours each week, maintenance or engineering time, and a budget for the fixes the new areas will need.

Free templates and tools

FAQ

Questions about model area 90-day plans

Or browse the topics, the full library and the lean glossary.