A SIPOC is a one-page, high-level map of a process in five columns, Suppliers, Inputs, Process, Outputs and Customers, used to agree where a process starts and ends before it is measured or mapped in detail.
A SIPOC diagram frames a process at a high level before anyone maps it in detail: who supplies what into it, the five to seven main steps, what comes out, and who receives it. It is the first hour of most process improvement projects, because it gets the team to agree where the process starts and ends.
When to use it
When to use the SIPOC board
- At the start of a value stream map, a DMAIC project or a kaizen event, to set the scope.
- When a process crosses departments and each one describes it differently.
- To brief a new team member or a sponsor on a process in one page.
- Before choosing metrics: outputs and customers say what should be measured.
What is on the board
- 1
Suppliers
Who or what provides the inputs, inside or outside the plant.
- 2
Inputs
Materials, information, people and equipment the process needs.
- 3
Process
Five to seven high-level steps from the trigger to the end.
- 4
Outputs
What the process produces: products, documents, decisions.
- 5
Customers
Who receives each output, internal or external.
Running it
How to run a SIPOC session
- 1Invite one person from each function the process passes through, plus someone who receives its output. Six to ten people, typically an hour.
- 2Name the process, its trigger and its end point on the board first: 'from schedule received to pallet in weld cell 3'. Half the value of a SIPOC is this sentence.
- 3Fill the Process column with five to seven stickies, verbs first: load, set, stamp, inspect, pack. If the team wants twelve, merge until seven remain.
- 4Work right: for each step, what comes out, and who receives it. Then left: what each step needs, and who provides it.
- 5Read each row back as a sentence, and draw an arrow on any input whose supplier is not obvious or whose quality is a known problem.
- 6Agree what the outputs should be measured on: on time, complete, right first time. Those become the project's metrics.
- 7Good output: one board a new team member can read in two minutes, a scope sentence everyone signed up to, and two or three metrics to baseline next.
Worked example · sample data
Worked example
The sample SIPOC frames a stamping process in five steps: load coil, set die, stamp, inspect, pack. Its inputs are 1.2 mm coil from the steel service centre, the weekly schedule from planning, and a die set and checked by the tool room. Its outputs are brackets at 400 per pallet and an inspection record, going to weld cell 3 and to quality. Laying it out surfaced two things the team had not agreed on: whether 'set die' started when the die left the tool room or when it reached the press, and that quality was a customer of the process as well as a step in it. The team fixed the scope at coil arrival to pallet in weld cell 3, and chose pallets delivered on time to weld cell 3 as the first metric to baseline.
The board shown at the top of this page, read through. Invented data, not a customer.
Common mistakes
- Too many process steps. A SIPOC with fifteen steps is a process map without the detail; keep it to seven.
- Filling in Suppliers first. Start with the process so the inputs are the ones the steps use.
- Leaving out internal customers. The next process is a customer, and usually the one with the complaints.
- Writing outputs as activities. 'Inspection done' is a step; 'an inspection record' is something a customer receives.
- Doing it alone at a desk. The point is agreement between functions.
- Never using it again. The SIPOC should sit at the top of the project board as the scope everyone agreed.
How it works in Lean Studio
- 1Start from the SIPOC template: five columns in order, with the process column in the middle.
- 2Fill the process column first with five to seven stickies, then work outwards to outputs and customers, then inputs and suppliers.
- 3Draw arrows between a supplier, its input and the step that uses it when the link is not obvious.
- 4Save the finished board to My templates so the next team starts from your version.
Lean Studio boards are drawn with stickies, text, shapes (rectangle, rounded rectangle, ellipse, diamond), arrows and charts, and any board can carry the 15 data widgets, from a scorecard to a kanban. See all widgets and boards.
Also in LeanSuite
Where it goes next in LeanSuite
LeanSuite's Vision AI builds a value stream map from a process video.
A SIPOC is the Define step of a DMAIC project; in Kaizen & Projects, DMAIC is a ready-made five-phase methodology with owners and due dates per phase. Kaizen & Projects
The outputs' measures become KPIs with a target and RAG ranges on the dashboard, rolled up through KPI trees. KPI Dashboards
When the team is ready for detail, Vision AI builds a current-state value stream map from a walk of the process filmed on a phone, with process times, wait times, inventory and information flow. AI Video Analysis
Open this board in LeanSuite
SIPOC is one of the 30 ready-made boards in Lean Studio, LeanSuite's whiteboard. Try the interactive demo in your browser with sample data, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.
What Lean Studio isRelated boards and templates
In the lean glossary
FAQ
SIPOC board: common questions
More process & flow boards
All 30 Lean Studio boards- Value Stream MapMap material and information flow across a process to expose waste and lead time.
- Swimlane Process MapMap a process left to right across role lanes to show who does each step.
- Kanban BoardVisualize work and limit work in progress across a simple four-stage flow.
- Yamazumi Operator BalanceVisualize operator cycle-time stacks against takt time to spot overload and imbalance.