Example 1: Plant manager OKR example
DeliveryWhy this objective: The largest customer audits this plant twice a year because of late deliveries and two escapes. Earning the audit back to once a year is worth more than any single project.
Run a plant the customer stops checking up on
- On-time in-full delivery (OTIF)91% to 96%
- Unplanned downtime, Lines 1 to 462 hours a month to 40 hours a month
- Customer escapes2 a quarter to 0 a quarter
- PlantPlant manager
Run a plant the customer stops checking up on
- DepartmentProduction
Make the schedule every day on Line 2, the line behind most late shipments
- Schedule attainment, Line 2: 84% to 95%
- Unplanned downtime, Line 2: 24 hours a month to 14 hours a month
- PersonLine 2 supervisor
Owns these key results
- Shifts with the start-up readiness check done before the first part: 60% to 100%
- Minor stops escalated within the shift, not the next day: 50% to 100%