Comparison with a worked decision
RACI vs RASCI, DACI and RAPID: which one to use
Short answer
RACI and RASCI assign roles to the tasks of a project. DACI and RAPID assign roles to one decision. RASCI adds a Support role to RACI, DACI names a Driver and a single Approver, and RAPID, from Bain and Company, splits a decision into Recommend, Agree, Input, Decide and Perform.
Last updated:
RACI
- RResponsible
- AAccountable
- CConsulted
- IInformed
RASCI
- RResponsible
- AAccountable
- SSupport
- CConsulted
- IInformed
DACI
- DDriver
- AApprover
- CContributors
- IInformed
RAPID
- RRecommend
- AAgree
- PPerform
- IInput
- DDecide
- Owns the call or the result
- Does, drives or recommends
- Must agree before it moves
- Asked first
- Told after
In one table
How do RACI, RASCI, DACI and RAPID compare?
RACI says who does, owns, is asked and is told for each task. RASCI adds Support for people who help deliver. DACI is for one decision: a Driver runs it and one Approver makes the call. RAPID splits a decision into five roles, including Agree for those who must sign off before it moves, and one Decide.
| Aspect | Letters | Built for | The one rule | A good fit |
|---|---|---|---|---|
| RACI | Responsible, Accountable, Consulted, Informed | Tasks in a project or process | One Accountable per task, and at least one Responsible. | A kaizen event, a launch, a handover: any list of tasks with several people on it. |
| RASCI | Responsible, Accountable, Support, Consulted, Informed | Tasks, when helpers outside the core team matter | The same as RACI. Support is for helpers, not owners. | Work that could slip because a named person outside the core team does not show up. |
| DACI | Driver, Approver, Contributors, Informed | One decision with a date | Exactly one Approver, as the Atlassian play puts it. | A decision that keeps getting reopened, or that no one has been asked to drive. |
| RAPID | Recommend, Agree, Perform, Input, Decide | Decisions that cross functions | One Decide. Bain's line is that when one person has the D, bottlenecks go. | A decision that stalls between functions, or between a site and the center. |
Letter by letter
What do the letters mean in each?
RACI is Responsible, Accountable, Consulted, Informed. RASCI adds Support. DACI is Driver, Approver, Contributors, Informed. RAPID is Recommend, Agree, Perform, Input, Decide. Some letters repeat with different meanings: the A is Accountable in RACI, Approver in DACI and Agree in RAPID, and the I is Informed in three and Input in RAPID.
RACI
- RResponsibleDoes the work.
- AAccountableOwns the result and signs it off.
- CConsultedAsked for input before the work is done.
- IInformedKept up to date, often only when it is done.
RASCI
- RResponsibleDoes the work.
- AAccountableOwns the result and signs it off.
- SSupportActively helps deliver, without owning the result.
- CConsultedAsked for input before the work is done.
- IInformedTold once it is done.
DACI
- DDriverGathers people and facts, sets the scope and gets the decision made by the agreed date.
- AApproverThe one person who makes the decision.
- CContributorsExperts who recommend options. A voice but no vote.
- IInformedAffected by the decision. Told the outcome, with no vote or voice.
RAPID
- RRecommendProposes a course of action, with alternatives.
- AAgreeMust approve the recommendation before it moves. Some can veto, and must then offer an alternative or escalate.
- PPerformCarries out the decision.
- IInputSupplies facts. The recommender weighs them but is not bound by them.
- DDecideThe single point of accountability. Makes the final call.
- Owns the call or the result
- Does, drives or recommends
- Must agree before it moves
- Asked first
- Told after
Letters that look alike and are not
The A means three things
Accountable in RACI, Approver in DACI, Agree in RAPID. In RAPID the person who owns the call is the D, and A is a sign-off before it moves.
The I means two things
Informed in RACI and DACI, Input in RAPID. Input is asked before the call. Informed is told after.
RACI for a decision
RACI can say who is accountable for a decision, but it has no letter for who recommends it and no letter for who may block it. Decision frameworks such as DACI and RAPID add those letters.
Four frameworks in one plant
Pick one for tasks and one for decisions at most. Three letter systems in one building confuse people.
Choosing
Which one should you use?
Use RACI for the tasks of a project. Add Support when named helpers outside the core team must show up. Use DACI when one decision needs an answer by a date. Use RAPID when a decision stalls between functions or some people must sign off before it moves. For a small fix by one team, a name and a date are enough.
- RACI
You are dividing up the tasks of a project or a process
It answers who does, who owns, who is asked and who is told, one task at a time. The free template on this site is a RACI.
- RASCI
Named people outside the core team have to show up for the work
Mutomorro's test: could the work miss its date because a specific person outside the core team does not show up? If so, give them an S. If not, RACI is simpler.
- DACI
One decision needs an answer by a date, and people keep reopening it
It names a Driver to get it done and one Approver to make the call, and it leaves Contributors with a voice but no vote.
- RAPID
A decision stalls between functions, or some people must sign off before it moves
The Harvard Business Review article says decisions stall between function and function, center and business unit, global and local, and inside and outside partners. Agree gives sign-off its own role.
- None of them
A small fix by one team
A name and a date is enough. A chart for a five-minute fix costs more than the fix.
A worked decision
What does the same decision look like under each?
Take one decision: whether to buy a second set of quick-change dies for Press 2. Under RACI it becomes a purchase task with one owner. Under RASCI the tool room supports. Under DACI one supervisor drives and the plant manager approves. Under RAPID, finance must agree and the plant manager decides. Same decision, different questions answered.
The decision: Buy a second set of quick-change dies for Press 2.
RACI
A task: get the dies bought and fitted.
- APlant manager
- RMaintenance lead
- CProduction supervisor
- CFinance partner
- IOperators
RASCI
The same task, with the tool room named as a helper.
- APlant manager
- RMaintenance lead
- STool room
- CProduction supervisor
- CFinance partner
- IOperators
DACI
A decision: yes or no, by the end of the month.
- DProduction supervisor
- APlant manager
- CMaintenance lead
- CQuality manager
- CFinance partner
- IOperators
RAPID
A decision where the budget has to be agreed first.
- RProduction supervisor
- AFinance partner
- IQuality manager
- IOperators
- DPlant manager
- PPurchasing
- PMaintenance lead
- Under RACI and RASCI the decision is already made and the question is who gets it done. Nothing says who recommends or who may veto.
- Under DACI the supervisor drives, the plant manager approves, and the people with a view are Contributors: they speak, they do not vote.
- Under RAPID finance has to agree before the plant manager decides. In RAPID the letter I means Input, not Informed: Quality and the operators supply facts.
Where they come from
Where does each one come from?
Only RAPID has a named origin in the pages read: Paul Rogers and Marcia Blenko of Bain and Company, in a Harvard Business Review article in January 2006. The pages read for RACI, RASCI and DACI do not say who created them, so this page does not name anyone. Atlassian publishes DACI as a Team Playbook play.
RACI
The pages read give no author or date for RACI. They treat it as practice that grew over time.
RASCI
A RACI variant. Wikipedia lists it with RACIS, RASIC and RASI. The pages read name no author or date.
DACI
Atlassian publishes it as a Team Playbook play. That page does not say who created it, so this page names no origin.
RAPID
Paul Rogers and Marcia Blenko of Bain and Company, in Who Has the D? in Harvard Business Review, January 2006.
Read more on RACI and ownership
- RACI chart: what it is, how to build one, with an exampleThe RACI guide, with a ten-task sample and a six-step build.
- RACI matrix template for kaizenA free Excel and PDF grid with a check for one accountable per task.
- RACI Matrix in Lean Manufacturing: Roles, Accountability, and ClarityThe longer article on RACI in a lean plant.
- Strategy deployment softwareWho owns each goal.
- Cascading goals and goal alignmentA goal with an owner at every level.
- Kaizen event charter templateThe charter a RACI chart is attached to.
- Glossary: RACI matrixThe short definition.
FAQ
Questions about RACI, RASCI, DACI and RAPID
RASCI adds an S for Support: a person who actively helps deliver a task without owning the result. Everything else is the same. Add the S when the work could slip because a named person outside the core team does not show up. Otherwise RACI is simpler and an S column would sit empty.
RACI assigns the tasks of a project. DACI assigns one decision. DACI names a Driver to get the decision made by a date, and exactly one Approver to make it. Contributors give input but have no vote, and Informed people are told the outcome.
Recommend, Agree, Perform, Input and Decide. Recommend proposes a course of action. Agree must approve it before it moves. Input supplies facts. Decide makes the final call. Perform carries it out. The framework comes from Paul Rogers and Marcia Blenko of Bain and Company.
Paul Rogers and Marcia Blenko of Bain and Company described RAPID in the article Who Has the D? in Harvard Business Review in January 2006. Bain's own page says the point of the framework is that one person holds the D, the single point of accountability for the decision.
Driver, Approver, Contributors and Informed. Atlassian publishes it in its Team Playbook with exactly one Approver. The Atlassian page does not say who created it, and the other pages read for this guide do not either, so this site does not name an origin.
This site's advice: use a RACI chart for the tasks of the event, and DACI or RAPID only for a single big decision inside it, such as buying equipment. The free RACI template is set up for a kaizen event. A quick fix by one team needs only an owner and a date.
Yes. The free RACI matrix template on this site has 17 kaizen project tasks by ten roles, R, A, C, I drop-downs and a check that flags any task with no accountable person or more than one. It comes as an Excel file and a one-page PDF.