Maintenance is essential for any business or organization that relies on equipment and machinery. Without proper maintenance, machines can break down unexpectedly, causing costly downtime and repairs. However, not all maintenance processes are the same. Planned and scheduled maintenance are two terms are often used interchangeably. While they go hand in hand with one another, they are not the same. In this blog post, we explore the difference between planned and scheduled maintenance.
What is planned maintenance?
Planned maintenance is a maintenance process that identifies the resources needed to address a specific equipment malfunction. In other words, the aim is to determine what specific tasks should be performed and how they should be carried out. What’s more, planned maintenance involves identifying potential equipment issues, determining the necessary steps for upkeep, and procuring the required tools and parts for execution. To achieve this, the planning process consists of equipment inspections, process descriptions, ordering replacement parts, and prioritizing work. A maintenance planner is responsible for overseeing these tasks to ensure that everything runs smoothly.
An example of planned maintenance
A HVAC manager assesses the various routine maintenance activities needed to help you breathe safer and healthier air, and be comfortable indoors, and creates standard operating procedures (SOPs) for HVAC technicians to follow according to standards.
What is scheduled maintenance?
Scheduled maintenance is a process that outlines who will perform maintenance tasks and when they will be performed. Essentially, the primary focus is on the timing of planned maintenance tasks and who will be responsible for them. The goal of scheduled maintenance is to ensure that all maintenance activities are carried out within a specified timeframe.
Work orders can be scheduled through paper, spreadsheets or Computerized Maintenance Management System (CMMS) software. Scheduled maintenance involves following a predetermined maintenance schedule that is based on the manufacturer’s recommendations or industry standards.
An example of scheduled maintenance
The HVAC manager arranges recurring work orders based on a combination of time and usage intervals. For example, each Spring and Fall of every year, or at least once a year HVAC systems should be serviced.
What's the difference between planned maintenance and scheduled maintenance?
Although they may sound similar, planned maintenance and scheduled maintenance have some fundamental differences. Basically, the main difference between planned maintenance and scheduled maintenance is that planned maintenance determines how and what work will be performed, while scheduled maintenance determines who performs the work and when.
There is a symbiotic relationship between planned and scheduled maintenance. Without maintenance planning, there can be a shortage of proper materials, tools, and process documentation when performing a job. Without maintenance scheduling, there can be confusion among employees regarding their job assignments, wrong employees can be assigned, and the work may not be completed in a timely manner.
However, when both maintenance planning and scheduling are executed efficiently, maintenance technicians and contractors can perform their work seamlessly without any organizational issues.
- 1What and how
Plan
Inspect equipment, describe the process, order parts, prioritize work. - 2Who and when
Schedule
Assign people and dates through work orders: paper, spreadsheet or CMMS. - 3
Work gets done
Without planning: missing parts, tools or documents. Without scheduling: unclear assignments and late work.
Planned vs. scheduled maintenance
The table below compares the difference between planned and scheduled maintenance:

Frequently Asked Questions
Is planned maintenance the same as scheduled maintenance?
No. Planned maintenance works out what needs doing on a piece of equipment and how: the tasks, the steps, the parts and tools. Scheduled maintenance works out who does that work and when. The two are often used as one term, and they depend on each other, but planning answers what and how while scheduling answers who and when.
Who is responsible for planned maintenance?
A maintenance planner. The planner inspects equipment, writes up the process for each job, orders replacement parts and sets the priority of the work so that when a technician picks up the job, the tools, parts and instructions are already there. The planner does not decide who performs the work or on what day. That belongs to scheduling.
What goes wrong if maintenance is scheduled but not planned?
The technician shows up without the right materials, tools or process documentation, because nobody worked out what the job needed. The reverse failure also happens: work that is planned but not scheduled leads to confusion over who owns the job, the wrong people being assigned and work finishing late. Both halves have to be done well for technicians and contractors to work without organizational hold-ups.
How are maintenance work orders scheduled?
On paper, in spreadsheets or in a CMMS, a computerized maintenance management system. Whatever the tool, the schedule follows a set pattern based on the equipment manufacturer's recommendations or industry standards, and it fixes two things for every work order: the person or team responsible and the time window in which the work has to be done.
What is an example of planned versus scheduled maintenance?
Take an HVAC system. Planning is the HVAC manager working out which routine tasks keep the air safe and the building comfortable, then writing standard operating procedures for the technicians to follow. Scheduling is the same manager setting up recurring work orders on time and usage intervals, for example a service every spring and fall, or at least once a year. The first decides the work, the second puts it on the calendar.
What is the goal of scheduled maintenance?
To get every maintenance task done within a set time window by a named person. Scheduling takes the jobs that planning has defined and gives each one an owner and a date, usually on recurring intervals based on time or usage and on the manufacturer's recommendations or industry standards. When scheduling is done well, nobody is confused about their assignments, the right people get the right jobs and the work does not slip.
Managing equipment maintenance is easy with LeanSuite
LeanSuite’s maintenance management system is an incredibly useful tool for anyone looking to streamline their maintenance processes. One of the main benefits of this system is its easy-to-use interface, which makes it simple for anyone to navigate and use effectively. By using this system, you can save time and improve efficiency by automating many of the tasks associated with maintenance management. For example, creating and tracking work orders, scheduling maintenance activities, and tracking maintenance history. Additionally, the system provides real-time data and analytics, allowing you to make informed decisions about maintenance activities and identify opportunities for improvement.
Free for this topic: Professional maintenance (PM) 90-day model area plan, Autonomous maintenance (CILR) checklist, OEE calculator
Want our lean manufacturing guides first in Google? Add us as a preferred source.
Add LeanSuite as a preferred source on Google (opens in a new tab)