Free tool
OEE calculator
Overall equipment effectiveness (OEE) measures how much of a machine's planned production time is truly productive. It is availability × performance × quality: the share of planned time the machine runs, how fast it runs against its ideal rate, and the share of parts that are good.
OEE formula
OEEequalsAvailability × Performance × Quality
AvailabilityequalsRun time divided by Planned production time
PerformanceequalsIdeal cycle time × Total count divided by Run time
QualityequalsGood count divided by Total count
Breaks, meetings, no orders
Breakdowns, changeovers, waiting
Fastest possible time for one unit
Good and bad units
Scrapped or reworked
Pre-filled with the worked example. Replace the numbers with your own shift; results update as you type.
OEE
72.9%
486 good units in 400 minutes of planned production time.
Availability
90.0%
360 of 400 min running
Performance
90.0%
Actual speed vs ideal
Quality
90.0%
486 of 540 good
Prefer a spreadsheet? Download the Excel version: the free OEE tracking sheet works out availability, performance, quality and OEE for each of 21 shifts and charts the weekly trend.
Next step
Want to track this every week?
Bring this result to a 45-minute demo and we will show where it fits in LeanSuite's KPI Dashboards.
How to calculate it
How to calculate OEE: six numbers from one shift
Shift length and planned stops give planned production time, the time the machine was meant to run. Breaks and meetings are not losses, so they are taken out first.
Unplanned downtime is every minute the machine should have run but did not: breakdowns, changeovers, waiting for material. It sets availability.
Ideal cycle time and total count set performance: how many units the run time could have made at full speed, against how many were made.
Rejects set quality. Count anything scrapped or reworked, since a reworked part was not good the first time.
Each factor points at a different kind of loss. The six big losses sort them into equipment failures and setups (availability), minor stops and slow running (performance), and defects and startup losses (quality).
OEE calculation example
Illustrative numbers, not a benchmarkA 450-minute shift with 50 minutes of planned breaks and 40 minutes of unplanned downtime. The ideal cycle time is 36 seconds, 540 units were made and 54 were rejected.
Step 1
Planned production time = 450 − 50 = 400 min. Run time = 400 − 40 = 360 min.Step 2
Availability = 360 ÷ 400 = 90%.Step 3
Performance = (36 s × 540) ÷ (360 min × 60) = 19,440 ÷ 21,600 = 90%.Step 4
Quality = (540 − 54) ÷ 540 = 486 ÷ 540 = 90%.
A note on the 85% “world-class” figure
The 85% OEE figure often called world-class is usually attributed to Seiichi Nakajima, who set out Total Productive Maintenance in Introduction to TPM (Productivity Press, 1988). Treat it as a reference point, not a target for every process: the Wikipedia article on OEE lists situations where it does not fit. Your own line's OEE, tracked shift by shift, is the comparison that shows whether improvements are working.
Embed this calculator
Teaching this, or writing about it? Paste this code into your site, course page or intranet and the calculator works right there. It is free, with no sign-up.
<iframe src="https://www.theleansuite.com/tools/oee-calculator/embed" title="OEE calculator by LeanSuite" width="100%" height="1000" style="border:0;max-width:1000px" loading="lazy" allow="clipboard-write"></iframe>
<p style="font:13px/1.4 sans-serif"><a href="https://www.theleansuite.com/tools/oee-calculator">OEE calculator</a> by LeanSuite</p>How LeanSuite helps
LeanSuite's KPI Dashboards track OEE, downtime and production counts live, so you can clear bottlenecks early and keep production on schedule.
See KPI DashboardsRead more
- Free template: OEE tracking sheet
- Free template: Six big losses worksheet
- Free template: Downtime reason codes template
- Overall equipment effectiveness (OEE) in the lean glossary
- Overall Equipment Effectiveness (OEE): What is it?
- Reducing machine downtime: a worked month from one downtime log
- Best OEE software: a buyer's guide to eight tools
- How to calculate OEE by hand, with a worked example
FAQ
OEE calculator: common questions
Multiply availability by performance by quality. Availability is run time divided by planned production time, performance is ideal cycle time times total count divided by run time, and quality is good count divided by total count. The same result comes from one shortcut: good count times ideal cycle time, divided by planned production time.
Planned stops are time the machine was never meant to run, such as breaks, team meetings or no orders; they are taken out before OEE is measured. Downtime is time the machine was meant to run but did not, such as breakdowns, changeovers and waiting for material; it lowers availability.
Ideal cycle time is the fastest time the machine or line can make one unit under ideal conditions, often the nameplate or design rate. Using a slower 'typical' time makes performance look better than it is, and can push it above 100%.
Performance above 100% means more units were counted than the ideal cycle time allows in the run time. The ideal cycle time is usually set too slow, or the counts or run time are wrong. Set the ideal cycle time to the fastest the equipment can run.
100% OEE means only good parts, made as fast as possible, with no stop time. The 85% figure often called world-class is usually attributed to Seiichi Nakajima's work on Total Productive Maintenance (TPM). It is a reference point rather than a target for every process; the most useful comparison is your own line's OEE over time.
No. Utilization usually compares run time with all available time, and efficiency often compares output with a target. OEE combines three losses in one number: stops (availability), slow running (performance) and defects (quality), all measured against planned production time.
More free lean tools
All tools- Downtime cost calculatorWhat an hour, an event and a year of unplanned downtime cost, from lost output, idle labour, scrap and overtime.
- SMED changeover calculatorTime saved by moving changeover steps from internal to external, capacity freed per week and the smaller batch it allows.
- Takt time calculatorThe pace a line must hit to meet customer demand, from shift time, breaks and daily demand.
- Cycle time calculatorCycle time against takt, units per hour, capacity per shift and the gap to daily demand.
- Line balancing calculatorLine efficiency, balance delay and the minimum number of stations from station times and takt.
- Bottleneck calculatorThe step that limits your line, from each step's cycle time, machines and uptime, with daily capacity and the gap to demand.
- First pass yield (FPY) calculatorFirst pass yield at each step and rolled throughput yield (RTY) across the whole process.
- Cost of poor quality (COPQ) calculatorTotal COPQ and cost of quality, and each as a share of revenue, from the four quality cost categories.
- Process capability (Cp, Cpk) calculatorCp and Cpk against your specification limits, plus Pp and Ppk from pasted measurements, with a distribution chart.
- DPMO and sigma level calculatorDPMO, defects per unit, yield and sigma level from the defects found, units checked and opportunities per unit.
- MTBF and MTTR calculatorMean time between failures, mean time to repair and availability from operating time, failures and repair time.
- Lead time calculatorManufacturing lead time from WIP and throughput (Little's Law), and the share of it that adds value.
- Throughput time calculatorThroughput time from process, inspection, move and wait time, the share of it that adds value, and units per hour.
- Kaizen savings calculatorYearly savings, payback in months and first-year ROI of an improvement, from time saved, scrap avoided and its costs.
- TEEP calculatorTotal effective equipment performance: OEE multiplied by how much of all calendar time you plan to run.
- Overall labor effectiveness (OLE) calculatorHow well paid labor hours turn into good output: availability, performance and quality of the crew.
- Inventory turnover and days on hand calculatorHow many times stock turns over in a period and how many days of it you hold, from COGS and average inventory.
- Safety stock calculatorSafety stock and reorder point from the service level you want, average demand and lead time, and how much each varies.
- Scrap rate calculatorScrap rate, the cost of scrap per period and per year, and what reaching a target rate would save.
- TRIR and DART rate calculatorOSHA recordable and DART incident rates from your 300A case counts and hours, and what one more case does to them.
- NIOSH lifting equation calculatorRecommended weight limit and lifting index for a two-handed lift, with every multiplier shown so you can see what to redesign.
- Time study sample size calculatorHow many cycles of an element to time, from your first readings, with the t formula, the ILO formula and the range method.
- Maintenance strategy selectorAnswer the RCM questions for one failure mode and get the maintenance strategy, the reasoning and the check or test interval.
- Noise dose and TWA calculatorDose and 8-hour TWA for a shift of noise levels under OSHA and NIOSH, which limits are reached and how much loud time to cut.
- Risk matrix calculatorSeverity times likelihood on a 3 x 3, 4 x 4 or 5 x 5 risk matrix, the band and its action, editable banding, and the score after further controls.
- Repair or replace calculatorEquivalent annual cost of keeping and repairing an old machine against buying a new one, with each one's economic life and the break-even figures.
- Compressed air leak cost calculatorAir lost, kW and cost a year for each tagged leak from its size and the pressure, ranked so the biggest gets fixed first.
- Machine hour rate calculatorWhat one productive hour of a machine costs, with and without the operator, the cost per part and how utilisation moves the rate.
- Total manufacturing cost calculatorTotal manufacturing cost, cost of goods manufactured, cost per unit and the overhead rate from materials, labor and overhead.
- Acceptance sampling calculatorRead the OC curve and the real risks of a sampling plan, find the plan for your AQL and LTPD, or size a zero-defect test.
- Shift schedule plannerTen shift patterns on real dates: calendar for each crew, hours a week, weekends off, coverage and the weeks over 40 hours.
- Pareto chart makerPaste categories and counts: sorted bars, cumulative percentage line and the vital few at the 80% line, as a PNG or SVG.
- Histogram makerPaste measurements: the histogram with automatic or chosen bins, plus mean, median and standard deviation, as a PNG or SVG.
- Box plot makerPaste one or more groups of numbers: box plots with quartiles, IQR, whiskers and outliers by the 1.5 IQR rule, as a PNG or SVG.
- Fishbone diagram makerName the problem, list causes under the 6M bones, and download the Ishikawa diagram as a PNG or SVG.
- 5 Whys canvasWrite the problem, answer up to five whys, state the root cause and countermeasure, then print the one-page canvas.
- Lean maturity self-assessmentScore 27 statements across nine dimensions and get a band for each, an overall band, where to start and the guides to read.
- Lean method navigatorSix questions about one problem, then the lean method to start with, the two that follow, why each fits, five steps for Monday and what it will not solve.
- Manufacturing ROI calculatorAnswer a few questions about your shop floor, shifts and downtime to estimate your potential ROI with LeanSuite.

