What is lead time? Definition, formula and how to reduce it
Short answer
Lead time is the total time from a request or order until delivery. It includes every wait along the way, not only the time spent working, so it is almost always much longer than the work itself. It is measured from a start point to an end point you choose, such as order placed to goods delivered. Shorten it by cutting waiting, not by working faster.
Last updated:
What is lead time?
Lead time is how long it takes from the moment something is asked for until it arrives. For a customer it runs from placing the order to receiving the goods. For a purchaser it runs from placing a purchase order to the material arriving at the dock.
The key point is that it counts waiting. An order sits in an inbox, waits for material, waits in a pile before a machine, waits for a truck. The time spent actually working on it is usually a small part of the total.
In business, supply chain and inventory management the meaning is the same. What changes is where the clock starts and stops, so always say which lead time you mean. A number with no start and end point cannot be compared with another.
The lead time formula
There are two ways to calculate lead time. Use the first to measure one order, and the second to estimate an average for a process.
| Method | Formula | Use it when |
|---|---|---|
| From dates | Lead time = end date minus start date | You can track an order or batch from start to finish |
| Add the parts | Lead time = all the waiting time + all the processing time | You are mapping a process step by step |
| Little's Law | Lead time = work in process (WIP) divided by output per day | You can count WIP and know the average daily output |
Use the same units throughout, and the same start and end points. The [lead time calculator](/tools/lead-time-calculator) does the Little's Law sum for you.
Little's Law holds for averages in a steady process. It is a good check on the other two methods: if the dates say one thing and WIP divided by output says another, a pile has been missed.
The types of lead time
Which lead time you need depends on who is asking. A customer cares about one, a planner about another, a buyer about a third.
| Type | Clock starts | Clock stops | Who uses it |
|---|---|---|---|
| Customer lead time | The customer places the order | The goods reach the customer | Sales, customers |
| Production lead time | The order is released to production | The finished product is ready | Planners, production managers |
| Supplier lead time | You place the purchase order | The supplier's goods arrive | Buyers, planners |
| Material lead time | You decide the material is needed | The material is received and ready to use | Inventory and materials planners |
| Cumulative lead time | Nothing is in stock | The finished product is ready | Planners quoting a made-from-scratch order |
Names vary between companies. Our post on the [four types of lead time](/blogs/four-types-of-lead-time) uses material, customer, production and cumulative.
A worked example
This example is illustrative. A shop makes brackets to order. Follow one order from placement to delivery.
| Stage | Working days | What is happening |
|---|---|---|
| Order entry and checks | 1 | The order waits to be entered and approved |
| Waiting for material | 5 | Sheet metal is ordered after the order arrives (supplier lead time) |
| Queue before the first operation | 3 | The job waits behind other jobs |
| On the floor, all steps | 4 | Cutting, bending, welding and finishing, including waits between them |
| Shipping and transit | 2 | Packed, collected and delivered |
| Customer lead time | 15 | Sum of the stages above |
Production lead time here is the 4 days on the floor. The same figure falls out of Little's Law: if 120 jobs are in process and 30 leave each day, 120 divided by 30 is 4 days. If the job is worked on for about 6 hours in total, the other 3.5 days or so are waiting.
The lesson is where the days are. Machines were busy for hours, but the customer waited 15 days. Running the machines faster would barely move that number. Removing the 5 days waiting for material, or the 3-day queue, would.
To measure your own, use the free lead time worksheet. It turns the inventory at each step into days of demand and adds them up.
How lead time differs from cycle time
Cycle time is how often a step finishes a part. Lead time is how long the part takes to get through everything, waiting included. A step can have a cycle time of 80 seconds and a part can still take days to reach the end.
Throughput time sits between the two: first step to last step, waiting included, but not the order handling or the material waiting outside the floor. Cycle time vs lead time follows one part through all of these with a full set of numbers.
How to reduce lead time
Lead time falls when waiting falls. Five causes of waiting account for most of it. Start with the biggest block of days in your own table, like the one above.
| Cause | What it looks like | What to do |
|---|---|---|
| Queues | Piles of work in front of a step | Cap the pile at a marked limit, and release work only as the next step takes it |
| Batching | Parts wait for the rest of the batch to finish | Make the batch smaller, and move parts on in smaller groups |
| Handoffs | Work sits between people, teams or departments | Cut the number of handoffs, and make the next step visible to the one before |
| Changeovers | Long setups push people to run big batches | Shorten setups so smaller batches pay off |
| Waiting for material or information | A job stops because something has not arrived | Fix the shortage at its source, and agree what the next step needs before a job starts |
Our post on [how to reduce lead time in manufacturing](/blogs/how-to-reduce-lead-time-in-manufacturing) goes through each lever. Batch size is covered in [batch production](/blogs/batch-production) and setups in [reducing changeover time](/blogs/reduce-changeover-time-in-manufacturing).
Measure first, then change one thing, then measure again. Run the lead time calculator before and after, so you know whether a change shortened the whole lead time or only moved the queue to another step.
Common mistakes
- Comparing numbers with different start and end points. Check where each clock starts and stops.
- Using the supplier's quoted lead time as the real one. Measure how long orders actually take, from your own records.
- Counting only time on the machines. Most of the lead time is waiting, so it is missed.
- Speeding up one step. If the bottleneck is elsewhere, the lead time does not change.
Go deeper
This page is the short version. These guides cover each part in full.
- Lead Time: 4 Types, How to Calculate It and How to Cut ItEach type of lead time in more depth, with the calculations and ways to shorten each.
- How to Reduce Lead Time in ManufacturingThe levers on manufacturing lead time and how to choose where to start.
- Throughput Time: How to Calculate and Improve ItThe shop floor part of lead time, and how to calculate and shorten it.
- How to Reduce Changeover Time: SMED and Standard WorkHow shorter setups make small batches practical and cut the waiting that batching causes.
- Pull System in Lean: Push vs Pull and the 3 Types of PullHow pull systems cap work in process and shorten queues.
All our articles on this subject are in the value stream mapping and flow topic.
Free templates and tools
- Lead time worksheetProduction lead time from the inventory waiting at each step, value-added time and process cycle efficiency, plus an order traced from order to delivery.
- Bottleneck analysis worksheetEffective capacity per station from cycle time, parallel units, availability and yield, the bottleneck, takt and utilization, a queue cross-check and the five focusing steps.
- SMED changeover worksheetChangeover steps with times, internal or external, what can move, ideas and before/after totals.
- Lead time calculatorManufacturing lead time from WIP and throughput (Little's Law), and the share of it that adds value.
- Throughput time calculatorThroughput time from process, inspection, move and wait time, the share of it that adds value, and units per hour.
Doing this in LeanSuite
Value Stream Mapping
Turns video of each process step into a current-state value stream map with cycle times, inventory and lead time.
See Value Stream MappingLine Balancing
Drop in a video of your line and get a Yamazumi chart, a takt comparison and rebalancing recommendations.
See Line BalancingKaizen & Projects
Manage every improvement project in one visual hub, from a small kaizen event to a full DMAIC project, and track each one through to results.
See Kaizen & Projects
See it on your own lines
Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.
FAQ
Questions about what is lead time
Lead time is the total time from a request or order until delivery, waiting included. For a customer it runs from placing the order to receiving the goods. It is usually much longer than the time spent working on the product, because most of it is waiting.
In business, lead time is how long a customer or buyer waits between asking for something and getting it. Sales uses it to quote delivery dates, planners use it to schedule work, and buyers use it to decide when to order material. State the start and end points whenever you quote one.
Subtract the start date from the end date for one order. For a process, add all the waiting time and processing time, or divide work in process by output per day (Little's Law). Use the same units and the same start and end points each time.
Common types are customer lead time (order to delivery), production lead time (order released to product finished), supplier lead time (purchase order to goods received), material lead time (material needed to material ready) and cumulative lead time (the whole chain from nothing in stock).
Cycle time is how often a step finishes a part. Lead time is how long a part takes to get through the whole process, waiting included. A step can run fast and the lead time can still be days, because the part waits between steps.
Cut the waiting, which is most of lead time. Cap queues in front of steps, make batches smaller, reduce handoffs, shorten changeovers so small batches pay off, and fix shortages of material or information. Measure before and after to confirm the whole lead time fell.
Delivery time is usually only the last part: shipping and transit once the goods are ready. Lead time starts earlier, when the order is placed, and includes order handling, waiting for material, production and delivery. Check which one a quoted number means.
Related guides and tools
More method guides
- The 6 Ms of production
- Poka-yoke
- Model area 90-day plans
- Moving from Excel to one system
- Reducing machine downtime: a worked month
- Andon and jidoka
- Cycle time vs lead time, worked through
- Root cause analysis
- How many operators a line needs
- Reducing scrap and rework: a worked month
- Unsafe acts and unsafe conditions
- Just culture
- Stop-work authority
- Material review board (MRB)
- What is an NCR?
- Problem solving methods
- Quad chart
- OEE calculation
- Quality assurance vs quality control
- SOP meaning and format
- Job hazard analysis
- Near miss reporting
- Fishbone diagram
- Pareto chart
- Histogram
- Control chart
- What is a gemba walk
- What is operational excellence
- How to improve product quality
- Preventive vs predictive maintenance
Or browse the topics, the full library and the lean glossary.