Lead time calculator

Manufacturing lead time is how long a unit takes to get through the process, from the first step to the last, including all the time it waits. Little's Law gives it from two numbers most plants already have: lead time = work in process ÷ throughput. Comparing it with the value-added time shows how much of that lead time is spent actually working on the product.

Lead timeequalsWork in process (WIP) divided by Throughput

Value-added ratioequalsValue-added time divided by Lead time

WIP is every unit between the first step and the last. Throughput is the average number of units that leave the process per day. Lead time comes out in the same time unit as throughput; convert it to minutes before dividing value-added minutes by it.

Every unit between the first step and the last

Average units finished per working day

Turns days into hours and minutes

Work that changes the product, all steps

Pre-filled with the worked example. Lead time comes out in working days because throughput is per working day.

Lead time

6 days

48 working hours, or 2,880 minutes, for a unit to get through.

Value-added ratio

1.25%

Value-added time ÷ lead time

Non-value-added time

2,844 min

Waiting, moving, inspecting

Share of lead time

Value-added1.25%
Non-value-added98.75%

Email me my results

Optional. Get these inputs and results in your inbox, with a link back to this calculator.

We may follow up about LeanSuite. See our Privacy Notice.

How to calculate it

Count the WIP, measure what leaves

Work in process is every unit that has started but not finished: in queues, on machines, in transit and waiting for inspection. A walk along the process with a count sheet gives a good snapshot, the same count a value stream map records between process boxes.

Throughput is the average number of finished units leaving the end of the process per working day. Take it over a few weeks, not one good day.

Working hours per day turn days into hours and minutes, so the lead time can be compared with the value-added time: the minutes of work on one unit, across every step, that change it in a way the customer pays for.

Worked example

Illustrative numbers, not a benchmark

A process with 1,200 units of work in process that finishes 200 units a day, running one 8-hour shift. Adding up every step that changes the product gives 36 minutes of value-added time per unit.

  1. 1Lead time = 1,200 units ÷ 200 units a day = 6 working days.
  2. 2In working time: 6 days × 8 h = 48 h = 2,880 minutes.
  3. 3Value-added ratio = 36 ÷ 2,880 = 1.25%.
  4. 4Non-value-added time = 2,880 − 36 = 2,844 minutes.
Lead time 6 days, value-added ratio 1.25%. A unit spends 36 minutes being worked on and the rest of its 6 days waiting. Cutting WIP to 600 units at the same throughput would halve lead time to 3 days and double the ratio to 2.5%.

Embed this calculator

Teaching this, or writing about it? Paste this code into your site, course page or intranet and the calculator works right there. It is free, with no sign-up.

<iframe src="https://www.theleansuite.com/tools/lead-time-calculator/embed" title="Lead time calculator by LeanSuite" width="100%" height="1020" style="border:0;max-width:1000px" loading="lazy" allow="clipboard-write"></iframe>
<p style="font:13px/1.4 sans-serif"><a href="https://www.theleansuite.com/tools/lead-time-calculator">Lead time calculator</a> by LeanSuite</p>

FAQ

Lead time calculator: common questions