Lead time calculator
Manufacturing lead time is how long a unit takes to get through the process, from the first step to the last, including all the time it waits. Little's Law gives it from two numbers most plants already have: lead time = work in process ÷ throughput. Comparing it with the value-added time shows how much of that lead time is spent actually working on the product.
Lead timeequalsWork in process (WIP) divided by Throughput
Value-added ratioequalsValue-added time divided by Lead time
Every unit between the first step and the last
Average units finished per working day
Turns days into hours and minutes
Work that changes the product, all steps
Pre-filled with the worked example. Lead time comes out in working days because throughput is per working day.
Lead time
6 days
48 working hours, or 2,880 minutes, for a unit to get through.
Value-added ratio
1.25%
Value-added time ÷ lead time
Non-value-added time
2,844 min
Waiting, moving, inspecting
Share of lead time
How to calculate it
Count the WIP, measure what leaves
Work in process is every unit that has started but not finished: in queues, on machines, in transit and waiting for inspection. A walk along the process with a count sheet gives a good snapshot, the same count a value stream map records between process boxes.
Throughput is the average number of finished units leaving the end of the process per working day. Take it over a few weeks, not one good day.
Working hours per day turn days into hours and minutes, so the lead time can be compared with the value-added time: the minutes of work on one unit, across every step, that change it in a way the customer pays for.
Worked example
Illustrative numbers, not a benchmarkA process with 1,200 units of work in process that finishes 200 units a day, running one 8-hour shift. Adding up every step that changes the product gives 36 minutes of value-added time per unit.
- 1Lead time = 1,200 units ÷ 200 units a day = 6 working days.
- 2In working time: 6 days × 8 h = 48 h = 2,880 minutes.
- 3Value-added ratio = 36 ÷ 2,880 = 1.25%.
- 4Non-value-added time = 2,880 − 36 = 2,844 minutes.
Embed this calculator
Teaching this, or writing about it? Paste this code into your site, course page or intranet and the calculator works right there. It is free, with no sign-up.
<iframe src="https://www.theleansuite.com/tools/lead-time-calculator/embed" title="Lead time calculator by LeanSuite" width="100%" height="1020" style="border:0;max-width:1000px" loading="lazy" allow="clipboard-write"></iframe>
<p style="font:13px/1.4 sans-serif"><a href="https://www.theleansuite.com/tools/lead-time-calculator">Lead time calculator</a> by LeanSuite</p>How LeanSuite helps
LeanSuite's Value Stream Mapping turns video of each process step into a current-state map with cycle times, inventory and lead time, and converts the inventory it counts between steps into days of WIP.
See Value Stream MappingRead more
- Lead time in the lean glossary
- What Are the Four Types of Lead Time?
- Value-added time in the lean glossary
- Value stream mapping in the lean glossary
- How to Reduce Lead Time in Manufacturing
- Value-Added vs Non-Value-Added Time in Manufacturing
- How to Improve Throughput Time in Manufacturing
- Current State vs Future State Value Stream Mapping
FAQ
Lead time calculator: common questions
More free lean tools
All tools- OEE calculatorOverall equipment effectiveness from shift time, downtime, ideal cycle time and part counts.
- Downtime cost calculatorWhat an hour, an event and a year of unplanned downtime cost, from lost output, idle labour, scrap and overtime.
- SMED changeover calculatorTime saved by moving changeover steps from internal to external, capacity freed per week and the smaller batch it allows.
- Takt time calculatorThe pace a line must hit to meet customer demand, from shift time, breaks and daily demand.
- Cycle time calculatorCycle time against takt, units per hour, capacity per shift and the gap to daily demand.
- Line balancing calculatorLine efficiency, balance delay and the minimum number of stations from station times and takt.
- First pass yield (FPY) calculatorFirst pass yield at each step and rolled throughput yield (RTY) across the whole process.
- Cost of poor quality (COPQ) calculatorTotal COPQ and cost of quality, and each as a share of revenue, from the four quality cost categories.
- Process capability (Cp, Cpk) calculatorCp and Cpk against your specification limits, plus Pp and Ppk from pasted measurements, with a distribution chart.
- MTBF and MTTR calculatorMean time between failures, mean time to repair and availability from operating time, failures and repair time.
- Manufacturing ROI calculatorAnswer a few questions about your shop floor, shifts and downtime to estimate your potential ROI with LeanSuite.