Method guide · Quality management
What is an NCR? Non-conformance report meaning, fields and process
Short answer
NCR stands for non-conformance report, also written nonconformance report or non-conformity report. It is a record that a product, material or process did not meet its requirement. It says what was found and how much is affected, how it was contained and what was decided for the parts. Serious or repeated problems then go to a corrective action to remove the cause. The NCR Corporation, which makes point-of-sale and ATM systems, is unrelated.
Last updated:
NCR meaning
NCR is short for non-conformance report. Because the word is spelled several ways, you will also see nonconformance report, non conformance report, nonconformity report and the letters spaced out as n c r. In some plants a report about bought-in material is called an NCMR, a nonconforming material report. They all point at the same thing: a written record that something did not meet its requirement.
"Conformance" means meeting a stated requirement, such as a drawing tolerance, a specification, a contract term or a written procedure. A non-conformance is any case where the product, the material or the process missed it. The NCR is how you capture that fact before it gets lost in conversation.
What an NCR is used for
- A quality record. It shows an auditor, a customer or a colleague that the problem was seen, written down and dealt with.
- Containment. It names the suspect parts, says where else to look and holds them back until someone with authority decides.
- Disposition. It records the decision on the parts: use as is, rework, repair, return to the supplier or scrap. When several functions need to agree, a material review board makes this decision.
- A link to corrective action. When the cause is systemic or the defect repeats, the NCR starts a CAPA so the cause is removed.
When to raise an NCR
Raise one whenever a part, material, product or process fails a requirement and you cannot simply fix it on the spot. Typical triggers are:
- At receiving: a delivery fails its incoming inspection.
- In process: an operator or an inspector finds a defect that cannot be corrected at the station.
- At final inspection: a finished lot fails the check before it ships.
- From a customer: a return or a complaint shows a product did not meet its requirement.
- From an audit: an internal or external audit finds a process step that does not follow the procedure.
- On a construction site: finished work does not match the specification or drawing.
Many plants set a rule for the small stuff. A defect found and fixed at the station, within the operator's authority, may only need a note on the check sheet. The NCR is for anything that needs containment, a decision or a cause.
What goes on an NCR
There is no universal standard form. The fields below are the ones on LeanSuite's own free NCR form template, which runs to two pages. Other forms group them differently.
| Field | What to write |
|---|---|
| Part, revision and lot | Part number and name, revision, lot or serial numbers. |
| Quantities | How many were checked and how many were bad. |
| Where found | Receiving, in process, final inspection, customer or audit. |
| Requirement | The drawing or specification, with the limit. |
| What was found | The measured value or the defect, with photos or readings. |
| Severity | Critical, major or minor, by your own definitions. |
| Containment | Where suspect parts were checked, how many were bad and how they were identified. |
| Disposition | Use as is, rework, scrap, return to the supplier or other, with the approvals. |
| Root cause | Why it happened and why it was not caught. |
| Corrective action | Whether a CAPA is needed, and its reference. |
| Cost | Optional: scrap, rework and other costs. |
| Closure | The date, the person, and the check that the parts were dealt with. |
Fields from the template at /templates/ncr-form-template, not a universal standard.
The most common weakness is a vague description. "Bad parts" tells nobody anything. Write the requirement, the measured value and how many, so a stranger could understand the problem without calling you.
Severity: critical, major and minor
Many quality systems rank each NCR so the serious ones get attention first. A common scheme has three classes. The definitions vary by company, product and standard, so use the table as a pattern and write your own.
| Class | Typical meaning | Typical response |
|---|---|---|
| Critical | Could affect safety, break a legal or regulatory requirement, or make the product unusable. | Alert Quality and Engineering at once. Stop shipping and contain wide. |
| Major | Likely to affect function or fail a customer requirement, but not a safety risk. | Contain, decide disposition promptly and consider a corrective action. |
| Minor | A departure that does not change function or a customer requirement. | Record, decide disposition and watch for repeats. |
A common three-class scheme. Your own definitions come first.
The NCR process in six steps
- 1
Detect
Someone sees the problem. In most plants anyone can raise an NCR, because the person closest to the work usually sees it first.
- 2
Contain
Tag the suspect parts and move them to hold. Then look wider: stock, work in progress, parts in transit and anything already at the customer.
- 3
Document
Fill in the part, lot, quantities, requirement, what was found and the severity. Attach photos and readings.
- 4
Decide the disposition
Choose use as is, rework, repair, scrap or return, with the approvals your rules require. Use as is needs a recorded concession, and sometimes the customer's approval. The material review board guide explains who decides and how.
- 5
Find the root cause
Ask why it happened and why it was not caught. A one-off, contained problem can close with the NCR. A repeat or a systemic cause needs a corrective action. Root cause analysis covers the methods.
- 6
Verify and close
Close the NCR only when the parts are dealt with and the action is checked. Closing too early is how the same defect returns.
NCR, CAPA, 8D, deviation and SCAR
| Term | What it is |
|---|---|
| NCR | The record of the problem and its containment, with a decision on the parts. |
| CAPA | The work to find and remove the cause of a problem, so it does not happen again. |
| 8D | A structured, eight-step way to run a CAPA, from containment to prevention. |
| Deviation | Permission, given in advance, to depart from a requirement for a defined quantity or time. |
| SCAR | A supplier corrective action request: a CAPA sent to a supplier whose material caused the problem. |
Plain-language summaries. Companies use the words slightly differently.
The short version: the NCR records and contains the problem, and the CAPA removes the cause. See the CAPA, 8D and SCAR glossary entries, or the best CAPA software comparison if you are choosing a system.
NCR in construction
In construction, an NCR records work that does not match the specification, the drawings or the agreed method. A site inspector, a clerk of works or the client's representative usually raises it, and it is addressed to the contractor responsible, who is expected to respond with a correction. Typical examples are concrete that missed its strength requirement, a component installed in the wrong place and materials that were not the ones specified.
The core logic is the same as in a factory. The problem is recorded, the affected work is identified, a decision is made (accept with a concession, repair, redo) and the cause is addressed. What differs is who is involved: three parties, contractor, inspector and client, with the contract deciding who can approve a concession. The work is also fixed in place, so containment means stopping the next stage until the NCR is resolved. LeanSuite is built for manufacturing plants and does not offer a construction product. The form template is a starting point, not a construction standard.
Which standards ask for it
Most quality management standards expect a plant to identify and control nonconforming output so it is not used or delivered by mistake. ISO 9001, the general standard, has a requirement on the control of nonconforming outputs, clause 8.7 in the 2015 edition. Sector standards built on it, such as AS9100 for aerospace and ISO 13485 for medical devices, carry the same expectation with their own additions, and medical device manufacturers selling in the United States also deal with the FDA's quality system rules. This page names these standards without quoting them, because the exact wording and numbering depend on the edition, so check the current text of the standard that applies to you.
None of them prescribe a form. They expect that nonconforming output is identified, controlled, and dealt with in a documented way, with the records kept. An NCR is the usual way to meet that.
NCR examples
Both examples are made up for this page. They are illustrative, not from a real plant.
Example 1: a stamped bracket at final inspection
- Requirement: a stamped bracket with a hole position within 0.30 mm of the drawing. Found: the hole 0.45 to 0.60 mm off on 12 of 30 brackets checked. Severity: major.
- Containment: the bracket bin at the press, the next two stations and the packed pallets were checked, and more were found off position. None had shipped. All were tagged and moved to the hold area.
- Disposition: scrap, because the hole cannot be moved. Engineering confirmed that a rework drill was not an approved repair. The count and the cost were logged on the NCR.
- Cause: a locating pin in the die had worn. A CAPA added the pin to the die's preventive maintenance list.
Example 2: a bought-in coating at receiving
- Requirement: coating thickness within the range on the purchase specification. Found: a sample from each of five pallets below the minimum. Severity: major.
- Containment: the delivery was held at receiving. The previous delivery was checked in stock, and the parts in production that used it were tagged.
- Disposition: return to the supplier. The supplier was sent a supplier corrective action request with the readings and photos.
- Cause: found in the supplier's response, a worn spray nozzle. The NCR closed when the replacement lot passed incoming inspection.
NCR tools: spreadsheet, form or software
A paper or spreadsheet NCR is enough at low volume. If a handful of people raise a few NCRs a month and one person tracks them, a form and a log work. The free NCR form template includes both, a two-page form and an Excel log with status, days open and counts by disposition.
Software starts to help when many people raise NCRs, when routing matters, when the cost has to be tracked and when the corrective action should not live in a separate email thread. Look for fast capture on the floor, routing by severity, containment tracking, a link to root cause work and a record an auditor can follow. The comparison of root cause analysis software and the CAPA software comparison list options.
LeanSuite's non-conformance management works this way. An operator scans a QR code and the form opens with the machine, line and shift filled in. Critical NCRs alert Quality and Engineering at once. Containment is assigned and tracked, and supplier defects can start a supplier corrective action request with photo evidence. Escalation rules turn systemic NCRs into an 8D or DMAIC project, and scrap, rework and expedite costs are logged against each NCR. The fix goes out as a required one-point lesson, and the NCR cannot close until the training is acknowledged. If the same defect code returns, earlier closures are flagged. See also quality tags, the corrective action log, supplier quality and cost of poor quality, or book a demo.
LeanSuite can act as the shop-floor layer next to your quality system. It does not have to replace it.
Go deeper
This page is the short version. These guides cover each part in full.
- Non-Conformance Reports: Managing Quality Deviations in ManufacturingThe NCR process in more depth, with the common mistakes.
- CAPA Systems in Manufacturing: Corrective and Preventive ActionWhat the corrective action behind a systemic NCR involves.
- Cost of Poor Quality: Calculation and Reduction FrameworkPutting a cost on the scrap, rework and returns an NCR records.
- Manufacturing Defects: Types, Root Causes, and PreventionThe kinds of defect that lead to an NCR, and their usual causes.
- 5 Whys: Root Cause Analysis Method for ManufacturingA simple method for the root cause step.
All our articles on this subject are in the quality management topic.
Free templates and tools
- Non-conformance report (NCR) formA two-page NCR from the requirement against what was found to disposition and closure, and an Excel NCR log.
- 8D report templateD0 to D8 with targets, containment counts, occurrence, escape and systemic causes, verified actions and a worked example.
- CAPA log templateAn Excel CAPA tracker with status, days open, late flags and counts by source, plus a printable log and monthly review.
- Supplier corrective action request (SCAR) formA SCAR from the problem and containment asked for to the supplier's 8D-style response, verification and closure.
- Defect check sheetTally defects by type and day, with units inspected, defect rates, a location sheet and the week's Pareto.
- Incoming inspection checklistReceiving inspection checks from paperwork to sample, the sampling plan, the decision, and an Excel log by supplier.
- Cost of poor quality (COPQ) calculatorTotal COPQ and cost of quality, and each as a share of revenue, from the four quality cost categories.
- First pass yield (FPY) calculatorFirst pass yield at each step and rolled throughput yield (RTY) across the whole process.
- Scrap rate calculatorScrap rate, the cost of scrap per period and per year, and what reaching a target rate would save.
- Acceptance sampling calculatorRead the OC curve and the real risks of a sampling plan, find the plan for your AQL and LTPD, or size a zero-defect test.
Doing this in LeanSuite
Non-Conformance (NCR)
Moves non-conformance reports into an automated workflow and links each defect report to root-cause problem solving.
See Non-Conformance (NCR)Corrective action log
One list of the problems a site has found and what is being done about each, with an owner and a due date.
See Corrective action logSupplier Quality
Digitizes inbound inspections, flags non-conformances with photo proof and builds supplier scorecards.
See Supplier QualityCost of Poor Quality
Pulls your scrap, rework and return data together, puts a dollar cost on each defect and shows engineering what to fix first.
See Cost of Poor Quality
See it on your own lines
Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.
FAQ
Questions about what is an NCR?
NCR stands for non-conformance report, also written nonconformance report or non-conformity report. It is a record that a product, material or process did not meet its requirement. The NCR Corporation, which makes point-of-sale and ATM systems, is an unrelated company.
An NCR records and contains the problem and decides what happens to the parts. A CAPA, a corrective and preventive action, removes the cause so the problem does not return. A one-off, contained problem can close with its NCR. A systemic or repeated one escalates to a CAPA.
In most plants anyone who finds the problem can raise one, since the person closest to the work usually sees it first. Approving the disposition is normally limited to authorized roles such as quality and engineering. This is common practice, and your own procedure sets the rule.
The part, revision and lot, the quantities checked and bad, the requirement next to what was found, the severity, the containment, the disposition with approvals, the root cause, the corrective action and the closure. Photos or readings should be attached. A free NCR form template with these fields is available on this site.
Only after the parts are dealt with and the action is verified. Closing early is how the same defect returns. In LeanSuite the NCR cannot close until the operators confirm they have read and acknowledged the training that goes with the fix.
NCMR stands for nonconforming material report. It is the name some plants use for an NCR about material, usually bought-in material that failed incoming inspection. It follows the same steps as an NCR: containment, disposition, and a supplier corrective action when the supplier is responsible.
Related guides and tools
- Material review board: who decides the disposition of a nonconforming lot
- Pareto chart: rank your NCRs by defect type to pick the first fix
- Free CAPA log for tracking the corrective actions an NCR starts
- CAPA software compared for teams that raise NCRs on the floor
- CAPA effectiveness check: confirming the fix held
More method guides
- The 6 Ms of production
- Poka-yoke
- Model area 90-day plans
- Moving from Excel to one system
- Reducing machine downtime: a worked month
- Andon and jidoka
- Cycle time vs lead time, worked through
- Root cause analysis
- How many operators a line needs
- Reducing scrap and rework: a worked month
- Unsafe acts and unsafe conditions
- Just culture
- Stop-work authority
- Material review board (MRB)
- Problem solving methods
- Quad chart
- OEE calculation
- Quality assurance vs quality control
- SOP meaning and format
- Job hazard analysis
- Near miss reporting
- Fishbone diagram
- Pareto chart
- Histogram
- Control chart