Method guide · Quality management
What is a nonconformance? Meaning, types, examples and the NCR process
Short answer
A nonconformance (also spelled non-conformance or nonconformity) is any case where a product, material, process or system does not meet a stated requirement: a drawing tolerance, a specification, a procedure or a clause of a standard. A non-conformance report (NCR) records it, contains it and decides what happens to the parts.
A nonconformance is a failure to meet a requirement. The requirement can be a drawing tolerance, a specification, a customer contract, a written procedure or a clause of a standard such as ISO 9001, and the thing that fails can be a part, a batch of material, a process step or the management system itself. ISO standards spell it nonconformity; plants say non-conformance, nonconformance or NC. The record of one is a non-conformance report, or NCR: it says what was found and how much is affected, how it was contained and what was decided for the parts. Serious or repeated nonconformances then go to a corrective action to remove the cause. The NCR Corporation, which makes point-of-sale and ATM systems, is unrelated.
Last reviewed:
Nonconformance meaning
A nonconformance is any case where something that should meet a requirement does not. ISO 9000, the vocabulary standard behind ISO 9001, defines nonconformity as the non-fulfilment of a requirement, and that is the whole idea: there is a stated requirement, and the output, the process or the system does not satisfy it. The requirement can be a dimension on a drawing, a specification limit, a step in a procedure, a customer contract term, a legal rule or a clause of a management system standard.
The spelling varies and the meaning does not. ISO standards and certification auditors say nonconformity. Quality engineers and shop floors say nonconformance, non-conformance or non conformance, and shorten it to NC. A nonconforming part, lot or output is the thing that failed; the nonconformance is the fact that it failed. The record of that fact is the non-conformance report, covered below.
Conformance is not the same as compliance, although the words are often swapped. Conformance means meeting a requirement you have set or adopted: your drawing, your procedure, the standard you chose to certify to. Compliance means meeting a requirement imposed from outside, usually by law or a regulator. A part out of tolerance is a nonconformance. A missing guard that the law requires is a noncompliance, and very likely a nonconformance against your own safety procedure as well.
Types of nonconformance
| Type | What failed | Example (illustrative) |
|---|---|---|
| Product or output | A part, assembly, batch or service does not meet its specification. | A shaft diameter over the upper limit; a label with the wrong lot code. |
| Process | A process step was not done as the procedure says, whether or not the output was affected. | A torque check skipped; a cure time cut short. |
| Material or supplier | Bought-in material fails incoming inspection or the purchase specification. | Coating thickness below the minimum on five pallets. |
| System | The management system misses a requirement of the standard or of the company's own procedures. | Calibration records missing; an internal audit not done on schedule. |
| Documentation | Work done to an obsolete or unapproved document. | An old drawing revision still at the station. |
Common groupings. Standards and companies draw the lines differently.
Product and material nonconformances are found by inspection and usually raise an NCR about parts. Process, system and documentation nonconformances are found by internal audits, layered process audits and external audits, and the finding is written against the clause or the procedure rather than against a lot. Both kinds need the same three things afterwards: correct the instance, find the cause, stop the repeat.
Major vs minor nonconformance
Certification bodies grade the nonconformities they raise in an audit. A major nonconformance is a complete failure to meet a requirement of the standard, or a breakdown that puts in doubt whether the system can deliver what it is meant to, such as a required process missing altogether or a pattern of lapses. A minor nonconformance is a single lapse or an isolated gap that does not undermine the system. Auditors may also note an opportunity for improvement, which is a suggestion and not a finding. A major finding normally has to be corrected, with evidence, before a certificate is issued or renewed; a minor needs a credible corrective action plan. The grading rules and response times come from your certification body, so read its own guidance.
Inside the plant, product nonconformances are usually ranked by severity instead: critical, major and minor, by the effect on safety, function and the customer. The sections below cover that scheme and the NCR that records it.
NCR meaning: the non-conformance report
NCR is short for non-conformance report. Because the word is spelled several ways, you will also see nonconformance report, non conformance report, nonconformity report and the letters spaced out as n c r. In some plants a report about bought-in material is called an NCMR, a nonconforming material report. They all point at the same thing: a written record that something did not meet its requirement.
The NCR is how you capture the nonconformance before it gets lost in conversation. It names the requirement, what was found against it and how much is affected, and it carries the decisions that follow: containment, disposition and whether a corrective action is needed.
What an NCR is used for
- A quality record. It shows an auditor, a customer or a colleague that the problem was seen, written down and dealt with.
- Containment. It names the suspect parts, says where else to look and holds them back until someone with authority decides.
- Disposition. It records the decision on the parts: use as is, rework, repair, return to the supplier or scrap. When several functions need to agree, a material review board makes this decision.
- A link to corrective action. When the cause is systemic or the defect repeats, the NCR starts a CAPA so the cause is removed.
When to raise an NCR
Raise one whenever a part, material, product or process fails a requirement and you cannot simply fix it on the spot. Typical triggers are:
- At receiving: a delivery fails its incoming inspection.
- In process: an operator or an inspector finds a defect that cannot be corrected at the station.
- At final inspection: a finished lot fails the check before it ships.
- From a customer: a return or a complaint shows a product did not meet its requirement.
- From an audit: an internal or external audit finds a process step that does not follow the procedure.
- On a construction site: finished work does not match the specification or drawing.
Many plants set a rule for the small stuff. A defect found and fixed at the station, within the operator's authority, may only need a note on the check sheet. The NCR is for anything that needs containment, a decision or a cause.
What goes on an NCR
There is no universal standard form. The fields below are the ones on LeanSuite's own free NCR form template, which runs to two pages. Other forms group them differently.
| Field | What to write |
|---|---|
| Part, revision and lot | Part number and name, revision, lot or serial numbers. |
| Quantities | How many were checked and how many were bad. |
| Where found | Receiving, in process, final inspection, customer or audit. |
| Requirement | The drawing or specification, with the limit. |
| What was found | The measured value or the defect, with photos or readings. |
| Severity | Critical, major or minor, by your own definitions. |
| Containment | Where suspect parts were checked, how many were bad and how they were identified. |
| Disposition | Use as is, rework, scrap, return to the supplier or other, with the approvals. |
| Root cause | Why it happened and why it was not caught. |
| Corrective action | Whether a CAPA is needed, and its reference. |
| Cost | Optional: scrap, rework and other costs. |
| Closure | The date, the person, and the check that the parts were dealt with. |
Fields from the template at /templates/ncr-form-template, not a universal standard.
The most common weakness is a vague description. "Bad parts" tells nobody anything. Write the requirement, the measured value and how many, so a stranger could understand the problem without calling you.
Severity: critical, major and minor
Many quality systems rank each NCR so the serious ones get attention first. A common scheme has three classes. The definitions vary by company, product and standard, so use the table as a pattern and write your own.
A typical severity scheme
Critical
- Typical meaning
- Could affect safety, break a legal or regulatory requirement, or make the product unusable.
- Typical response
- Alert Quality and Engineering at once. Stop shipping and contain wide.
Major
- Typical meaning
- Likely to affect function or fail a customer requirement, but not a safety risk.
- Typical response
- Contain, decide disposition promptly and consider a corrective action.
Minor
- Typical meaning
- A departure that does not change function or a customer requirement.
- Typical response
- Record, decide disposition and watch for repeats.
The NCR process in six steps
The NCR process in six steps
- 1
Detect
- 2
Contain
- 3
Document
- 4
Decide the disposition
- 5
Find the root cause
- 6
Verify and close
- 1
Detect
Someone sees the problem. In most plants anyone can raise an NCR, because the person closest to the work usually sees it first.
- 2
Contain
Tag the suspect parts and move them to hold. Then look wider: stock, work in progress, parts in transit and anything already at the customer.
- 3
Document
Fill in the part, lot, quantities, requirement, what was found and the severity. Attach photos and readings.
- 4
Decide the disposition
Choose use as is, rework, repair, scrap or return, with the approvals your rules require. Use as is needs a recorded concession, and sometimes the customer's approval. The material review board guide explains who decides and how.
- 5
Find the root cause
Ask why it happened and why it was not caught. A one-off, contained problem can close with the NCR. A repeat or a systemic cause needs a corrective action. Root cause analysis covers the methods.
- 6
Verify and close
Close the NCR only when the parts are dealt with and the action is checked. Closing too early is how the same defect returns.
Nonconformance vs defect, noncompliance, deviation, CAPA, 8D and SCAR
| Term | What it is |
|---|---|
| Nonconformance | Any failure to meet a stated requirement, in a product, a process or the system. |
| Defect | A nonconformance that affects the product's intended use. Every defect is a nonconformance; a departure that does not affect use is a nonconformance but not a defect. |
| Noncompliance | Failure to meet a requirement imposed from outside, by law or a regulator, rather than one you set or adopted. |
| NCR | The record of the nonconformance and its containment, with a decision on the parts. |
| Deviation | Permission, given in advance, to depart from a requirement for a defined quantity or time. |
| Concession or waiver | Permission, given after the fact, to accept a specific nonconforming lot as it is. |
| CAPA | The work to find and remove the cause of a problem, so it does not happen again. |
| 8D | A structured, eight-step way to run a CAPA, from containment to prevention. |
| SCAR | A supplier corrective action request: a CAPA sent to a supplier whose material caused the problem. |
Plain-language summaries. Companies use the words slightly differently.
The short version: the NCR records and contains the nonconformance, and the CAPA removes the cause. See the CAPA, 8D and SCAR glossary entries, or the best CAPA software comparison if you are choosing a system.
NCR in construction
In construction, an NCR records work that does not match the specification, the drawings or the agreed method. A site inspector, a clerk of works or the client's representative usually raises it, and it is addressed to the contractor responsible, who is expected to respond with a correction. Typical examples are concrete that missed its strength requirement, a component installed in the wrong place and materials that were not the ones specified.
The core logic is the same as in a factory. The problem is recorded, the affected work is identified, a decision is made (accept with a concession, repair, redo) and the cause is addressed. What differs is who is involved: three parties, contractor, inspector and client, with the contract deciding who can approve a concession. The work is also fixed in place, so containment means stopping the next stage until the NCR is resolved. LeanSuite is built for manufacturing plants and does not offer a construction product. The form template is a starting point, not a construction standard.
Which standards ask for it
Most quality management standards expect a plant to identify and control nonconforming output so it is not used or delivered by mistake. ISO 9001, the general standard, has a requirement on the control of nonconforming outputs, clause 8.7 in the 2015 edition, and a separate requirement to react to each nonconformity, evaluate whether action is needed to remove its cause, and keep records of what was done, clause 10.2. Sector standards built on it, such as AS9100 for aerospace and ISO 13485 for medical devices, carry the same expectation with their own additions, and medical device manufacturers selling in the United States also deal with the FDA's Quality Management System Regulation, which has applied since February 2026 and builds on ISO 13485. This page names these standards without quoting them, because the exact wording and numbering depend on the edition, so check the current text of the standard that applies to you.
None of them prescribe a form. They expect that nonconforming output is identified, controlled, and dealt with in a documented way, with the records kept. An NCR is the usual way to meet that.
Nonconformance examples and two filled NCRs
Everything in this section is made up for this page and is illustrative, not from a real plant. First, six one-line nonconformances of different types; then two of them written up as full NCRs.
- Product: a machined shaft measures 25.08 mm against a limit of 25.05 mm.
- Product: a carton is labelled with last week's lot code.
- Process: the procedure calls for a torque check on every tenth part and the check sheet shows none for the shift.
- Material: a delivery of coated brackets measures below the minimum coating thickness.
- System: three gauges on the line have calibration stickers that expired last month.
- Documentation: the drawing at the station is revision C and the controlled copy is revision D.
Example 1: a stamped bracket at final inspection
- Requirement: a stamped bracket with a hole position within 0.30 mm of the drawing. Found: the hole 0.45 to 0.60 mm off on 12 of 30 brackets checked. Severity: major.
- Containment: the bracket bin at the press, the next two stations and the packed pallets were checked, and more were found off position. None had shipped. All were tagged and moved to the hold area.
- Disposition: scrap, because the hole cannot be moved. Engineering confirmed that a rework drill was not an approved repair. The count and the cost were logged on the NCR.
- Cause: a locating pin in the die had worn. A CAPA added the pin to the die's preventive maintenance list.
Example 2: a bought-in coating at receiving
- Requirement: coating thickness within the range on the purchase specification. Found: a sample from each of five pallets below the minimum. Severity: major.
- Containment: the delivery was held at receiving. The previous delivery was checked in stock, and the parts in production that used it were tagged.
- Disposition: return to the supplier. The supplier was sent a supplier corrective action request with the readings and photos.
- Cause: found in the supplier's response, a worn spray nozzle. The NCR closed when the replacement lot passed incoming inspection.
NCR tools: spreadsheet, form or software
A paper or spreadsheet NCR is enough at low volume. If a handful of people raise a few NCRs a month and one person tracks them, a form and a log work. The free NCR form template includes both, a two-page form and an Excel log with status, days open and counts by disposition.
Software starts to help when many people raise NCRs, when routing matters, when the cost has to be tracked and when the corrective action should not live in a separate email thread. Look for fast capture on the floor, routing by severity, containment tracking, a link to root cause work and a record an auditor can follow. The comparison of root cause analysis software and the CAPA software comparison list options.
LeanSuite's non-conformance management works this way. An operator scans a QR code and the form opens with the machine, line and shift filled in. Critical NCRs alert Quality and Engineering at once. Containment is assigned and tracked, and supplier defects can start a supplier corrective action request with photo evidence. Escalation rules turn systemic NCRs into an 8D or DMAIC project, and scrap, rework and expedite costs are logged against each NCR. The fix goes out as a required one-point lesson, and the NCR cannot close until the training is acknowledged. If the same defect code returns, earlier closures are flagged. See also quality tags, the corrective action log, supplier quality and cost of poor quality, or book a demo.
LeanSuite can act as the shop-floor layer next to your quality system. It does not have to replace it.
Non-Conformance Management
Run NCRs in LeanSuite
Non-conformance management that fixes the cause, not just the part: capture each NCR at the line and link it to a CAPA with root cause analysis.
Go deeper
This page is the short version. These guides cover each part in full.
- Non-Conformance Reports: Managing Quality Deviations in ManufacturingThe NCR process in more depth, with the common mistakes.
- Cost of Poor Quality: Calculation and Reduction FrameworkPutting a cost on the scrap, rework and returns an NCR records.
- Manufacturing Defects: Types, Root Causes, and PreventionThe kinds of defect that lead to an NCR, and their usual causes.
- 5 Whys: Root Cause Analysis Method for ManufacturingA simple method for the root cause step.
All our articles on this subject are in the quality management topic.
Free templates and tools
- Non-conformance report (NCR) formA two-page NCR from the requirement against what was found to disposition and closure, and an Excel NCR log.
- 8D report templateD0 to D8 with targets, containment counts, occurrence, escape and systemic causes, verified actions and a worked example.
- CAPA log templateAn Excel CAPA tracker with status, days open, late flags and counts by source, plus a printable log and monthly review.
- Supplier corrective action request (SCAR) formA SCAR from the problem and containment asked for to the supplier's 8D-style response, verification and closure, with a filled-in example.
- Defect check sheetTally defects by type and day, with units inspected, defect rates, a location sheet and the week's Pareto.
- Incoming inspection checklistReceiving inspection checks from paperwork to sample, the sampling plan, the decision, and an Excel log by supplier.
- Incoming quality control stage sheetA register that shows how much control each purchased part has and plans the move from your dock to the supplier's process.
- Approved supplier list templateThe list of suppliers you may buy from, with the evidence behind each, certificate expiry alerts and re-evaluation dates.
- Cost of poor quality (COPQ) calculatorTotal COPQ and cost of quality, and each as a share of revenue, from the four quality cost categories.
- First pass yield (FPY) calculatorFirst pass yield at each step and rolled throughput yield (RTY) across the whole process.
- Scrap rate calculatorScrap rate, the cost of scrap per period and per year, and what reaching a target rate would save.
- Acceptance sampling calculatorRead the OC curve and the real risks of a sampling plan, find the plan for your AQL and LTPD, or size a zero-defect test.
Doing this in LeanSuite
Non-Conformance (NCR)
Moves non-conformance reports into an automated workflow and links each defect report to root-cause problem solving.
See Non-Conformance (NCR)Corrective action log
One list of the problems a site has found and what is being done about each, with an owner and a due date.
See Corrective action logSupplier Quality
Digitizes inbound inspections, flags non-conformances with photo proof and builds supplier scorecards.
See Supplier QualityCost of Poor Quality
Pulls your scrap, rework and return data together, puts a dollar cost on each defect and shows engineering what to fix first.
See Cost of Poor Quality
See it on your own lines
Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.
FAQ
Questions about nonconformance and NCRs
NCR stands for non-conformance report, also written nonconformance report or non-conformity report. It is a record that a product, material or process did not meet its requirement. The NCR Corporation, which makes point-of-sale and ATM systems, is an unrelated company.
An NCR records and contains the problem and decides what happens to the parts. A CAPA, a corrective and preventive action, removes the cause so the problem does not return. A one-off, contained problem can close with its NCR. A systemic or repeated one escalates to a CAPA.
In most plants anyone who finds the problem can raise one, since the person closest to the work usually sees it first. Approving the disposition is normally limited to authorized roles such as quality and engineering. This is common practice, and your own procedure sets the rule.
The part, revision and lot, the quantities checked and bad, the requirement next to what was found, the severity, the containment, the disposition with approvals, the root cause, the corrective action and the closure. Photos or readings should be attached. A free NCR form template with these fields is available on this site.
Only after the parts are dealt with and the action is verified. Closing early is how the same defect returns. In LeanSuite the NCR cannot close until the operators confirm they have read and acknowledged the training that goes with the fix.
NCMR stands for nonconforming material report. It is the name some plants use for an NCR about material, usually bought-in material that failed incoming inspection. It follows the same steps as an NCR: containment, disposition, and a supplier corrective action when the supplier is responsible.
A nonconformance is any failure to meet a stated requirement: a drawing tolerance, a specification, a procedure, a contract term or a clause of a standard. It can be a part, a batch of material, a process step or the management system itself. ISO standards spell it nonconformity. The record of one is a non-conformance report, or NCR.
A machined shaft measured over its diameter limit, a carton labelled with the wrong lot code, a torque check the procedure requires but the operator skipped, a delivery of coated parts below the minimum coating thickness, and a calibration record an audit finds missing. Each fails a stated requirement, so each is a nonconformance, even where the part still works.
Nonconformance is a failure to meet a requirement you set or adopted, such as your own drawing, procedure or the standard you certify to. Noncompliance is a failure to meet a requirement imposed from outside, usually by law or a regulator. A part out of tolerance is a nonconformance; a missing guard the law requires is a noncompliance, and usually a nonconformance against your own procedure as well.
In a certification audit, a major nonconformance is a complete failure to meet a requirement of the standard, or a breakdown that puts the whole system in doubt, such as a required process missing or a pattern of repeated lapses. A minor is a single, isolated lapse. Majors normally have to be corrected with evidence before a certificate is issued or renewed. Your certification body sets the exact rules.
Not quite. A defect is a nonconformance that affects the product's intended use. Every defect is a nonconformance, but a departure from a requirement that does not affect use, such as a cosmetic mark outside the customer's view, is a nonconformance without being a defect. Both still get recorded and dispositioned.
ISO 9001 uses the spelling nonconformity for any failure to meet a requirement. The 2015 edition asks organisations to identify and control nonconforming outputs so they are not used or delivered by mistake (clause 8.7), and to react to each nonconformity, evaluate whether action is needed to remove its cause, and keep records (clause 10.2). It prescribes no form. An NCR and a corrective action record are the usual way to show both.
Related guides and tools
- Material review board: who decides the disposition of a nonconforming lot
- Quality assurance vs quality control: who finds nonconformances and who prevents them
- ISO 9001 internal audit checklist: find system nonconformances before the external auditor does
- Quality alert form: tell the floor about a nonconformance the same shift
- SOP meaning and format: the procedure a process nonconformance is written against
- Pareto chart: rank your NCRs by defect type to pick the first fix
- Free CAPA log for tracking the corrective actions an NCR starts
- CAPA software compared for teams that raise NCRs on the floor
- CAPA effectiveness check: confirming the fix held
More method guides
- The 6 Ms of production
- Poka-yoke
- Model area 90-day plans
- Moving from Excel to one system
- Reducing machine downtime: a worked month
- Andon
- Cycle time vs lead time, worked through
- Root cause analysis
- How many operators a line needs
- Reducing scrap and rework: a worked month
- Unsafe acts and unsafe conditions
- Just culture
- Stop-work authority
- Material review board (MRB)
- Problem solving methods
- Quad chart
- OEE calculation
- Quality assurance vs quality control
- SOP meaning and format
- Job hazard analysis
- Near miss reporting
- Fishbone diagram
- Pareto chart
- Histogram
- Control chart
- What is a gemba walk
- What is lead time
- What is operational excellence
- How to improve product quality
- Preventive vs predictive maintenance
- Kanban
- FMEA
- PDSA cycle
- Safety moments
- Just-in-time manufacturing
- Kaizen
- 5S
- Total quality management (TQM)
- CAPA (corrective and preventive action)
- Layered process audit (LPA)
- Lean tools
- Lockout tagout (LOTO)
- A3 problem solving
- Preventive maintenance
- APQP
- High reliability organization (HRO)
- Manufacturing KPIs
- Quality metrics
- Practical problem solving
- CMMS
- Risk assessment
- Production efficiency
- Total productive maintenance (TPM)
- Reliability-centered maintenance (RCM)
- Hierarchy of controls
- Personal protective equipment (PPE)
- Emergency action plan
- Safety signs
- Warehouse safety
- ISO 9001
- SIPOC diagram
- Rolling action item list (RAIL)
- Pugh matrix
- Flowchart
- Project charter
- ISO 9001:2026
- Fleet maintenance
- IATF 16949
- AS9100
- ISO 14001
- ISO 45001
Or browse the topics, the full library and the lean glossary.
Rather see it on your own problem?
Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.

