Throughput time calculator
Throughput time is the total time one unit takes to get through a production process, from the start of the first step to a finished unit. It is the sum of process time, inspection time, move time and wait time. Only the process time changes the product, so process time ÷ throughput time shows how much of the journey adds value.
Throughput timeequalsProcess time + Inspection time + Move time + Wait time
Process cycle efficiencyequalsProcess time divided by Throughput time
ThroughputequalsUnits finished divided by Time
Time spent working on the unit
Checks and tests
Transport between steps
Queues before each step
Pre-filled with the worked example. Use averages for one unit (or one batch) through the whole process. Clear both rate fields to skip the rate.
Throughput time
18 h
Process + inspection + move + wait, start to finish.
Process cycle efficiency
55.6%
Process time ÷ throughput time
Non-value-added time
8 h
Inspection + move + wait
Throughput rate
2 / h
Units finished ÷ hours
Where the time goes
How to calculate it
Follow one unit through the process
Process time is the time someone or something is working on the unit: machining, assembly, painting. If it differs from unit to unit, use the average.
Inspection time is the time spent checking it, and move time is the time spent carrying it between steps, including the forklift or the walk.
Wait time is the time it sits in a queue, waiting for the next step, a batch to fill or a machine to be free. It is usually the largest part and the hardest to see, so walk the process and count the units waiting in front of each step. Little's Law turns that count into time: the lead time calculator does it from WIP and throughput.
Process cycle efficiency treats all process time as value-added. If part of the processing does not change the product (rework, for example), count only the value-added time for a stricter figure. The optional rate fields give throughput in units per hour from the units finished in a period.
Worked example
Illustrative numbers, not a benchmarkA car plant (the example from our throughput time guide): 10 hours to assemble a car, 1 hour of quality inspection, 2 hours moving it between stations and 5 hours waiting for the next process to start. The plant finished 120 cars in 60 working hours.
- 1Throughput time = 10 + 1 + 2 + 5 = 18 h.
- 2Non-value-added time = 1 + 2 + 5 = 8 h.
- 3Process cycle efficiency = 10 ÷ 18 = 55.6%.
- 4Throughput = 120 cars ÷ 60 h = 2 cars per hour.
Throughput time, cycle time and lead time
| Measure | What it times | Includes waiting? |
|---|---|---|
| Cycle time | One step finishing one unit, or the gap between finished units | No |
| Throughput time | One unit through the whole production process | Yes, between steps |
| Lead time | Customer order to delivery | Yes, before, during and after production |
To compare cycle time with customer demand, use the cycle time calculator; to find the step that limits throughput, use the bottleneck calculator.
Embed this calculator
Teaching this, or writing about it? Paste this code into your site, course page or intranet and the calculator works right there. It is free, with no sign-up.
<iframe src="https://www.theleansuite.com/tools/throughput-time-calculator/embed" title="Throughput time calculator by LeanSuite" width="100%" height="1390" style="border:0;max-width:1000px" loading="lazy" allow="clipboard-write"></iframe>
<p style="font:13px/1.4 sans-serif"><a href="https://www.theleansuite.com/tools/throughput-time-calculator">Throughput time calculator</a> by LeanSuite</p>How LeanSuite helps
LeanSuite's Value Stream Mapping turns video of each process step into a current-state map with cycle times, inventory and lead time, and converts the inventory it counts between steps into days of WIP.
See Value Stream MappingRead more
FAQ
Throughput time calculator: common questions
More free lean tools
All tools- OEE calculatorOverall equipment effectiveness from shift time, downtime, ideal cycle time and part counts.
- Downtime cost calculatorWhat an hour, an event and a year of unplanned downtime cost, from lost output, idle labour, scrap and overtime.
- SMED changeover calculatorTime saved by moving changeover steps from internal to external, capacity freed per week and the smaller batch it allows.
- Takt time calculatorThe pace a line must hit to meet customer demand, from shift time, breaks and daily demand.
- Cycle time calculatorCycle time against takt, units per hour, capacity per shift and the gap to daily demand.
- Line balancing calculatorLine efficiency, balance delay and the minimum number of stations from station times and takt.
- Bottleneck calculatorThe step that limits your line, from each step's cycle time, machines and uptime, with daily capacity and the gap to demand.
- First pass yield (FPY) calculatorFirst pass yield at each step and rolled throughput yield (RTY) across the whole process.
- Cost of poor quality (COPQ) calculatorTotal COPQ and cost of quality, and each as a share of revenue, from the four quality cost categories.
- Process capability (Cp, Cpk) calculatorCp and Cpk against your specification limits, plus Pp and Ppk from pasted measurements, with a distribution chart.
- DPMO and sigma level calculatorDPMO, defects per unit, yield and sigma level from the defects found, units checked and opportunities per unit.
- MTBF and MTTR calculatorMean time between failures, mean time to repair and availability from operating time, failures and repair time.
- Lead time calculatorManufacturing lead time from WIP and throughput (Little's Law), and the share of it that adds value.
- Kaizen savings calculatorYearly savings, payback in months and first-year ROI of an improvement, from time saved, scrap avoided and its costs.
- Lean maturity self-assessmentScore 24 statements across eight dimensions and get a result band for each, an overall band and where to start.
- Manufacturing ROI calculatorAnswer a few questions about your shop floor, shifts and downtime to estimate your potential ROI with LeanSuite.