Method guide · TPM and maintenance
Reliability-centered maintenance (RCM): the 7 questions, failure patterns and a worked example
Short answer
Reliability-centered maintenance (RCM) is a method for deciding what maintenance each asset needs by working through what it must do, the ways it can fail and what each failure costs. For every failure mode the team picks one task that can really prevent or find it and is worth the effort, or decides on purpose to run it to failure.
An RCM analysis answers seven questions for one asset: its functions and the standard each must meet, how it can fail to meet them, what causes each failure, what happens when it occurs, why that matters, what task can predict or prevent it, and what to do if no task fits. The answers turn into a list of tasks, each tied to a failure mode: condition checks, scheduled replacements, failure-finding tests on protective devices, redesigns and planned run to failure. The method came from airline maintenance in the 1970s, and SAE JA1011 sets out what a process must include to be called RCM.
Last reviewed:
What is reliability-centered maintenance?
Reliability-centered maintenance starts from the failure, not from the machine's manual. Instead of asking "what PM does this conveyor need?", the team asks "what does this conveyor have to do, how can it stop doing that, and which of those failures is worth acting on?" Every task that comes out of the analysis names the failure mode it deals with. A task that cannot name one is dropped.
The result is a mix. Some failure modes get a condition check, because they give a warning you can measure. Some get a replacement at a fixed age, because they really do wear out on time. Protective devices get a test, because nobody notices when they fail. Some failures are designed out. And some are left to run to failure on purpose, with a spare ready, because no task would pay for itself. RCM is the method for deciding which is which, one failure mode at a time.
Reliability-centered and reliability-centred are the same thing, US and UK spelling. "Reliability maintenance" is often used loosely for the same idea, or for the wider job of a reliability engineer. RCM is the shorthand in both cases.
Where RCM came from
The method came out of airline maintenance. F. Stanley Nowlan and Howard F. Heap of United Airlines described it in Reliability-Centered Maintenance, their 1978 report for the US Department of Defense, which gave the method its name. Their data showed that many aircraft components did not wear out at a predictable age, so overhauling them on a timer did little for reliability. The airline industry's MSG-3 process for planning aircraft maintenance grew from the same work.
John Moubray carried the method into plants and utilities with his book Reliability-centred Maintenance (RCM II, 2nd edition 1997). In 1999 SAE International published SAE JA1011, Evaluation Criteria for Reliability-Centered Maintenance (RCM) Processes, which sets the minimum a process must do to be called RCM, followed in 2002 by SAE JA1012, a guide to applying it. Both are paid standards; this page names them and puts the questions in its own words.
The 7 questions of RCM
SAE JA1011 frames an RCM process as seven questions asked, in order, about the asset being analysed. Here they are in plain words, with what the team writes down for each and how they come out for the conveyor drive in the worked example further down.
The seven questions of an RCM analysis
- 1Functions
What must it do, and how well?
- 2Functional failures
How can it fail to do that?
- 3Failure modes
What causes each failure?
- 4Effects
What happens when it fails?
- 5Consequences
Why does it matter?
- 6Proactive task
What task can predict or prevent it?
- 7Default action
What if no task fits?
Then review: findings and new failures send the team back to questions 3 to 6
| Question | What the team writes down | On the conveyor drive (illustrative) |
|---|---|---|
| 1. What does the asset have to do, and how well? | Functions, each with a performance standard: a rate, a pressure, a temperature, a limit | Carry bottles to the filler at up to 300 a minute; slip before a jam can break the chain; keep gearbox oil off the floor |
| 2. In what ways can it fail to do that? | Functional failures: a total loss and each partial loss of every function | Stops; runs but skips and drops bottles; leaks oil; does not slip in a jam |
| 3. What causes each functional failure? | Failure modes: specific causes, from breakdown records and from the people who fix the machine | Bearing wear, seal leak, chain stretch, photo-eye fault, seized torque limiter |
| 4. What happens when each one occurs? | Failure effects: what anyone would see, what gets damaged, how long the stop lasts | The bearing seizes, the conveyor stops, and a breakdown change takes about 6 hours |
| 5. In what way does each failure matter? | Consequence class: hidden, safety or environment, operational, or non-operational | The oil leak puts oil on a walkway, so it has a safety consequence |
| 6. What can be done to predict or prevent each failure? | A proactive task and its interval, if one is both possible and worth doing | A vibration and temperature reading on the gearbox every 4 weeks |
| 7. What should be done if no proactive task fits? | A default action: a failure-finding test, a redesign or run to failure | The photo-eye runs to failure, with a spare kept at the line |
Questions 1 to 4 are the failure analysis, close to an FMEA. Questions 5 to 7 are the decision, and that is what makes it RCM. The free [RCM worksheet](/templates/rcm-worksheet) has a column for every answer and works out the failure-finding interval.
Most of the effort goes into question 1. If the function says only "convey bottles", every later answer is vague. A function with a number in it, "up to 300 bottles a minute", lets the team say exactly when a partial failure starts, and so what counts as a failure worth preventing.
Failure consequences and the RCM task types
Question 5 sorts each failure mode into one of four classes, and the class sets what "worth doing" means for any task. Nowlan and Heap's decision diagram asks about consequences first for that reason.
| Class | What it means | A task is worth doing if |
|---|---|---|
| Hidden | Nobody doing normal work would know the function has failed. Typical of protective devices: relief valves, level switches, torque limiters, standby pumps. | It keeps the protective function available enough that the multiple failure (the protection failed and then needed) is as rare as the site accepts |
| Safety or environment | The failure could hurt someone or breach an environmental limit or a law | It brings the risk down to a level the site accepts, whatever it costs. If no task does, redesign. |
| Operational | The failure stops or slows output, or harms quality | It costs less over a year than the repairs plus the lost output it prevents |
| Non-operational | Evident, and costs only the repair | It costs less than the repairs it prevents. Often nothing passes, and run to failure is the answer. |
Question 6 then tries the proactive tasks in order. A condition-based task comes first, because it replaces a part only when the part needs it. A scheduled restoration or replacement comes next, and only fits a failure mode with a clear wear-out age that most parts reach. For a hidden failure where neither works, question 7 gives a failure-finding test. The other defaults are a redesign, which includes a change to how the machine is run or a procedure, and run to failure.
| Task | What it is | Fits when |
|---|---|---|
| Condition-based (on-condition) | Check for a warning sign and act when you find it: vibration, temperature, oil analysis, a measured wear gauge, a look and listen | A warning can be detected, the warning time is fairly consistent, and it lasts longer than the time you need to act |
| Scheduled restoration | Overhaul or rebuild at a set age in hours, cycles or time | Failures rise sharply after a known age and most parts reach it |
| Scheduled discard | Replace the part at a set age, whatever it looks like | The same as restoration, for parts that are cheaper to throw away than to rebuild |
| Failure-finding | Test a protective device to find out whether it has already failed | The failure is hidden and no condition or age-based task works |
| Redesign or one-time change | Change the equipment, the way it is run, or a procedure | Safety or environmental risk stays too high with any task, or an operational failure costs too much |
| Run to failure | No scheduled task; repair when it fails, with the spare and the procedure ready | The failure is evident, harms no one, and no task is cheaper than the failures it prevents |
The P-F interval sets how often to check
A condition check works inside the P-F interval: the time from the point P where a coming failure can first be detected to the point F where it fails. The ABS Guidance Notes on Reliability-Centered Maintenance (section 4) put the check interval at no more than half the P-F interval. Then test the worst case: a sign that appears just after a check is found one interval later, so the time left is the P-F interval minus the check interval, and it must be longer than the time you need to get the part and plan the stop. The maintenance strategy selector runs these questions for one failure mode and does both interval sums.
The six failure patterns behind RCM
The reason RCM does not simply replace parts on a timer is the shape of the failure curve. United Airlines plotted how the chance of failure changed with age for its aircraft components and found six shapes. Nowlan and Heap published them in 1978 (Exhibit 2.13 of their report), with the share of the items studied that followed each one.
| Pattern | Shape of the chance of failure against age | Share of items studied | What a timed replacement does |
|---|---|---|---|
| A. Bathtub | High when new, then low and flat, then a wear-out zone | 4% | Can help, if the age limit sits before the wear-out zone |
| B. Wear-out | Flat or slowly rising, then a clear wear-out zone | 2% | Can help, the classic case for a fixed life |
| C. Slowly rising | Rises steadily with age, no clear wear-out age | 5% | Little: there is no age at which the risk jumps |
| D. Low, then steady | Low when new or just repaired, then rises quickly to a flat level | 7% | Nothing after the first period |
| E. Random | The same chance of failure at every age | 14% | Nothing: a new part is as likely to fail as an old one |
| F. Early life | High when new or just repaired, then flat | 68% | Harm: each replacement starts a new high-risk period |
Check the shares: 4 + 2 + 5 + 7 + 14 + 68 = 100%. Patterns A, B and C together are 4 + 2 + 5 = 11%, which leaves 89% with no wear-out zone. These are one airline's aircraft parts, not plant equipment, and we know of no comparable published study for plants that we could check. What carries over is the test, not the percentages.
Share of items in each failure pattern (Nowlan and Heap, 1978)
- A. Bathtub4%
- B. Wear-out2%
- C. Slowly rising5%
- D. Low, then steady7%
- E. Random14%
- F. Early life68%
On a line, the lesson is to look at your own work orders before setting a fixed life. If the failures of a part come at widely spread ages, a scheduled replacement will throw away good parts and still miss the early failures. Pattern F is also a warning about intrusive PM: every time a machine is opened up, the chance of a bad repair, a pinched seal or a misaligned coupling comes back. The four most common causes of equipment failure covers how failures start on the floor.
RCM example: a worked analysis of one conveyor drive
This example is illustrative, not data from a real machine. A bottling line runs two 8-hour shifts, 5 days a week. The infeed conveyor carries bottles from the depalletiser to the filler. It has a motor, a gearbox, a drive chain, a torque limiter that slips if bottles jam, and a photo-eye that tells the filler bottles are coming. The current PM has two lines: "replace gearbox bearings every 2 years" and "inspect conveyor monthly", with no limit given. The team is the line's lead operator, the maintenance technician who fixes it, the area supervisor and a facilitator.
Functions and functional failures (questions 1 and 2)
| Function, with its standard | Functional failures |
|---|---|
| 1. Carry bottles from the depalletiser to the filler at up to 300 a minute | 1A. Does not move at all. 1B. Moves, but skips and drops bottles below 300 a minute. |
| 2. Slip and stop the drive if bottles jam, before the chain or gearbox is damaged | 2A. Does not slip at its set torque. |
| 3. Keep gearbox oil inside the gearbox | 3A. Leaks oil onto the floor. |
The RCM worksheet (questions 3 to 7)
| Failure mode | Effect: what happens | Consequence | Task chosen | Interval and owner |
|---|---|---|---|---|
| 1A. Gearbox output bearing wears | Noise, vibration and heat rise for weeks, then the bearing seizes and the conveyor stops. About 6 hours to change it as a breakdown. | Evident, operational | Condition-based: vibration and temperature reading on the gearbox, plan the change when it passes the alert limit | Every 4 weeks, technician on the route |
| 1B. Drive chain stretches with wear | The chain rides up the sprocket teeth, then skips. Bottles fall and jam at the filler. | Evident, operational | Condition-based: measure elongation with a chain wear gauge, replace at the maker's limit | Every 13 weeks, technician |
| 1A. Infeed photo-eye fails | The filler sees no bottles and stops. About 20 minutes to swap the sensor with a spare. | Evident, operational, small | Run to failure: electronics fail at random and there is no warning to check for. One spare photo-eye kept at the line. | No scheduled task |
| 2A. Torque limiter seizes and will not slip | Nothing shows in normal running. At the next jam the chain snaps or the gearbox shaft breaks. | Hidden; the multiple failure is operational | Failure-finding: slip test at the set torque, then reset | Every 26 weeks, technician |
| 3A. Gearbox output seal leaks | Oil drips onto the walkway and the oil level falls. Left alone, the gearbox runs dry and the bearing fails. | Safety (slip) and operational | Condition-based: look at the sight glass and the floor at shift start. One-time change: fit a drip tray under the gearbox. | Every shift, operator, on the CILR checklist |
Failure modes are numbered by the functional failure they cause. The oil leak is a safety failure because of the slip, so cost does not decide: the daily check finds the leak early and the drip tray keeps oil off the walkway in the time between.
The intervals, worked out
Gearbox bearing. The technician's vibration readings on similar gearboxes show a bearing defect about 8 weeks before it seizes, so the P-F interval is 8 weeks. Getting the bearing and a weekend stop takes 2 weeks. The check interval is the smaller of 8 / 2 = 4 weeks and 8 - 2 = 6 weeks, so every 4 weeks. Worst case: a defect that starts just after a reading is found 4 weeks later, which leaves 8 - 4 = 4 weeks, more than the 2 weeks needed.
Drive chain. From the alert limit on the wear gauge to the chain skipping takes about 26 weeks of running, and a new chain is on the shelf in 1 week. The interval is the smaller of 26 / 2 = 13 weeks and 26 - 1 = 25 weeks, so every 13 weeks. Worst case left: 26 - 13 = 13 weeks, against 1 week needed.
Torque limiter. It fails at random, with an MTBF of 25 years, and the site wants it working 99% of the time. The failure-finding interval is 2 x (1 - availability) x MTBF (ABS Guidance Notes, section 5) = 2 x 0.01 x 25 = 0.5 years, which is 26 weeks. Check it another way: an unavailability of 0.01 gives an interval of 2% of the MTBF, and 2% of 25 years is 0.5 years, or 0.5 x 52 = 26 weeks. The formula holds while the interval is under a tenth of the MTBF: 0.5 / 25 = 0.02, well under 0.1.
| Task | Interval | Times a year | Minutes each | Minutes a year |
|---|---|---|---|---|
| Gearbox vibration and temperature | 4 weeks | 52 / 4 = 13 | 10 | 130 |
| Chain elongation check | 13 weeks | 52 / 13 = 4 | 30 | 120 |
| Torque limiter slip test | 26 weeks | 52 / 26 = 2 | 45 | 90 |
| Technician total | 19 | 340 | ||
| Sight glass and floor check | Every shift | 2 shifts x 5 days x 50 weeks = 500 | 1 | 500 |
Check the technician total: 130 + 120 + 90 = 340 minutes, and 340 / 60 = 5 hours 40 minutes a year, with the conveyor running for the vibration reading and stopped for the other two. The operator check is 500 minutes, 8 hours 20 minutes a year, spread a minute at a time inside the start-of-shift CILR round.
What changed in the PM list
The two-yearly bearing change is dropped. The last four bearing failures on these gearboxes came at 9, 31, 14 and 26 months: an average of (9 + 31 + 14 + 26) / 4 = 20 months, but spread so widely that a change every 24 months would have come too late for two of them (9 and 14) and thrown away two bearings that had months left (26 and 31). That spread looks like a random pattern, not a wear-out age, so a condition check fits and a fixed life does not. It also takes away a 6-hour planned stop every two years, and the risk of a bad reassembly each time.
"Inspect conveyor monthly" is replaced by three tasks that each name a failure mode and a limit. The torque limiter, which nobody had tested before, gets a test twice a year. The photo-eye gets a spare instead of a task. The new tasks go into the CMMS as PMs with these intervals, and the operator check goes onto the line's CILR checklist.
How to run an RCM analysis, step by step
An RCM analysis is a team exercise on one asset or system at a time. It needs the people who run the machine and the people who fix it in the room, because each knows failures the other does not.
- 1
Pick the asset
Start with one where failures hurt and the PM is not working: a line constraint, a utility the whole plant depends on, a machine with a safety history. The equipment criticality analysis ranks the candidates.
- 2
Set the boundary and the team
Write down where the system starts and stops (motor to discharge flange, depalletiser to filler infeed) and what is outside it. The team is an operator, a technician, someone who can speak for production and a facilitator who knows the method.
- 3
Write the functions and functional failures
Questions 1 and 2. Include protective functions, containment and anything a regulation requires, not only the main job. Put a number in every standard you can.
- 4
List failure modes and effects
Questions 3 and 4. Use work orders, downtime logs and the technicians' memory. Name causes at the level where a task can act on them: "output bearing wears", not "gearbox fails".
- 5
Class each failure mode and choose a task
Questions 5 to 7, in the order of the decision diagram. Write down the evidence for each answer, such as the warning time, the failure ages and the MTBF, and mark a guess as a guess.
- 6
Load the tasks and review them
Put each task into the CMMS or the CILR checklist with its interval and owner. Look at the analysis again after the first failures and at least once a year, and change any interval the findings say is wrong.
A full analysis of one system often takes the team several sessions, which is why most plants keep full RCM for their critical assets. Shorter methods that skip or combine questions are common and usually called streamlined or RCM-based. They can be sensible on less critical assets, but they do not meet SAE JA1011, so call them what they are. The fault tree analysis template helps where one functional failure has several causes that combine.
RCM vs preventive maintenance, predictive maintenance, TPM and FMEA
RCM is not another kind of maintenance next to PM and predictive maintenance. It is the method that decides where each of those kinds goes. TPM works on who does the maintenance and how the plant is organised around it. They fit together rather than compete.
| Approach | What it is | What decides the task | How it relates to RCM |
|---|---|---|---|
| Reactive (run to failure) | Repair after the failure | Nothing; the failure arrives | RCM picks it on purpose for some failure modes, with spares ready |
| Preventive maintenance (PM) | Planned work at a set interval of time or use | The calendar or a meter, usually from the maker's manual | RCM keeps a timed task only where a failure mode has a wear-out age |
| Predictive or condition-based maintenance (PdM) | Act on a measured warning sign | A reading passing a limit | RCM's first choice whenever a warning can be detected in time |
| Reliability-centered maintenance (RCM) | A method for choosing the task for each failure mode | The function, the failure mode and its consequence | The decision method itself |
| Total productive maintenance (TPM) | A plant-wide program in which operators and maintenance share care of the equipment, organised in pillars | Pillar activities: autonomous maintenance, planned maintenance and the rest | RCM can set the tasks the planned maintenance pillar runs, and operators take the simple checks under autonomous maintenance |
| FMEA | A structured review of failure modes, effects and causes, ranked for risk | A severity, occurrence and detection rating or action priority | RCM questions 3 and 4 are an FMEA; RCM then adds the consequence class and task selection |
Preventive maintenance covers the PM program, the schedule and PM compliance in numbers. Preventive vs predictive maintenance compares the two side by side. FMEA covers the ratings, RPN against action priority and DFMEA against PFMEA. Total productive maintenance covers the eight pillars and autonomous maintenance, and the TPM and maintenance hub lists the rest.
Benefits and limits of reliability-centered maintenance
- Every task has a reason. Each line in the PM list names the failure mode it deals with, so a task that does nothing can be found and dropped.
- Less intrusive work. Timed overhauls of parts that fail at random are replaced by checks, which cuts planned stops and the failures a bad reassembly causes.
- Hidden failures get found. Relief valves, level switches, interlocks and standby units get a test at a worked-out interval instead of being assumed to work.
- Safety decisions are written down. A failure that could hurt someone is never left to a cost argument, and the record shows what was decided and why.
- Operators and technicians share what they know. The sessions put the people who see the first signs next to the people who know what the parts do.
The limits are real too. A full analysis takes team time, so it is not worth doing on every asset. It needs failure records that many plants do not have yet, and early answers are often estimates that have to be revised. It also decays: a study done once and filed while the process, the product or the equipment changes soon describes a different machine. Plants that get the most from RCM treat it as a living record they review, not a project they finish.
Where RCM results live: the CMMS, the CILR checklist and the work order
An RCM analysis ends as tasks, and the tasks have to land somewhere people will do them. Technician tasks go into the CMMS as preventive maintenance with their intervals, where each one comes due as a work order and the history builds the evidence for the next review. Short operator checks go onto the line's CILR checklist. Findings from either become work orders with a priority.
LeanSuite is not a CMMS and does not replace one. It handles the operator side of maintenance and works alongside your CMMS: when a scheduled PM comes due or an operator tags an abnormality, it creates the work order and routes it to the maintenance team, and CILR checklists can be assigned to an asset with a repeat rule, with missed checks shown in red. See autonomous maintenance and professional maintenance tags.
Common RCM mistakes
- Starting from the old PM list. Asking "which of these tasks do we keep?" skips the functions and the failure modes, and misses failures the old list never covered.
- Functions without a standard. "Pump water" cannot tell a partial failure from normal running; "pump at least 40 cubic metres an hour" can.
- Failure modes at the wrong level. "Gearbox fails" is too broad to choose a task for; "output bearing wears" is not.
- Treating a hidden function as evident. A torque limiter or relief valve that has seized gives no sign until the day it is needed. Ask question 5 about every protective device.
- Choosing a timed replacement without failure ages. A fixed life only helps a failure mode with a wear-out age. Look at when the part actually failed before you set one.
- Doing it at a desk. An analysis written by one engineer without the operator and the technician misses the failure modes they know about and gets little support on the floor.
- Never coming back to it. Intervals set from guesses must move when findings come in: a defect found late means a shorter interval; flat readings over many checks allow a longer one.
Go deeper
This page is the short version. These guides cover each part in full.
- What are Five Types of Maintenance Strategies?Reactive, preventive, corrective, predictive and reliability-centred maintenance, each described in turn.
- Four Most Common Causes of Equipment FailureHow failures start on the floor, the raw material for RCM question 3.
- FMEA in Manufacturing: Failure Mode and Effects Analysis Complete GuideThe failure mode and effects analysis that RCM questions 3 and 4 build on.
- The 8 Pillars of TPM: A Manufacturing GuideWhere the planned maintenance pillar, and the tasks RCM sets, sit in a TPM program.
- Root Cause Analysis for Equipment Failures: Methods and FrameworkWhat to do when a failure happens anyway: finding the cause so the RCM analysis can be corrected.
All our articles on this subject are in the tpm and maintenance topic.
Free templates and tools
- RCM worksheet (failure mode and task selection)Failure modes classed as hidden, safety, operational or non-operational, then a task chosen for each: condition-based, discard, failure-finding, redesign or run to failure.
- Equipment criticality analysisAssets scored 1 to 5 on six criteria with your own weights, ranked and sorted into classes A, B and C with a safety override and a suggested maintenance strategy.
- Condition monitoring route sheetA route of measuring points with baselines, alert and alarm limits, a check interval from the P-F interval, readings with rising and overdue flags, and an exceptions list worst first.
- Preventive maintenance checklist templateA PM checklist per machine with readings and sign-off, and a PM schedule that works out the next due date.
- Critical spare parts list and stocking levelsAssets ranked by consequence, each part classed and given a stocking policy, and min and max worked out from usage and lead time, with the downtime each stock-out would cost.
- Fault tree analysis templateA drawing area with the FTA symbols, an event table with probabilities and minimal cut sets, and the gates worked out bottom-up in Excel.
- PFMEA template (process FMEA)Failure modes, effects and causes rated for severity, occurrence and detection, with RPN before and after action.
- Maintenance KPI trackerMTBF, MTTR, availability and PM compliance per asset and month, plant figures from the totals, planned maintenance % and backlog in weeks.
- Maintenance strategy selectorAnswer the RCM questions for one failure mode and get the maintenance strategy, the reasoning and the check or test interval.
- MTBF and MTTR calculatorMean time between failures, mean time to repair and availability from operating time, failures and repair time.
- Downtime cost calculatorWhat an hour, an event and a year of unplanned downtime cost, from lost output, idle labour, scrap and overtime.
Key terms
- Reliability-centered maintenance (RCM)
- Failure-finding task
- P-F interval
- Condition-based maintenance (CBM)
- Predictive maintenance (PdM)
- Preventive maintenance (PM)
- Reactive maintenance
- Equipment criticality analysis
- Failure mode and effects analysis (FMEA)
- Total productive maintenance (TPM)
- Mean time between failures (MTBF)
- Computerized maintenance management system (CMMS)
Doing this in LeanSuite
Professional maintenance tags
Professional maintenance tags in LeanSuite turn radio calls and firefighting into work orders every technician can see, own and close out.
See Professional maintenance tagsCILR Checklists
Build visual CILR checklists so operators clean, inspect, lubricate and re-tighten on schedule and catch problems before they become breakdowns.
See CILR ChecklistsAutonomous Maintenance
Rolls out visual CILR (clean, inspect, lube, retighten) checklists so operators catch small abnormalities before they cause downtime.
See Autonomous Maintenance
See it on your own lines
Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.
FAQ
Questions about reliability-centered maintenance (RCM)
Reliability-centered maintenance (RCM) is a method for deciding what maintenance each asset needs by working through its functions, the ways it can fail and what each failure costs. For every failure mode the team picks a task that can really prevent or find it and is worth doing: a condition check, a scheduled replacement, a failure-finding test, a redesign, or run to failure on purpose.
SAE JA1011 frames RCM as seven questions about an asset: what it must do and how well, how it can fail to do that, what causes each failure, what happens when each occurs, why each failure matters, what task can predict or prevent it, and what to do if no task fits. The first four are the failure analysis; the last three are the maintenance decision.
On a bottling line conveyor, an RCM team found five failure modes. The gearbox bearing got a vibration check every 4 weeks because it gives about 8 weeks of warning. The chain got a wear-gauge check every 13 weeks. The torque limiter, which nobody notices has seized until a jam, got a slip test every 26 weeks. The oil leak got a daily operator check and a drip tray. The photo-eye runs to failure with a spare. The figures are illustrative.
Every maintenance task names the failure it deals with, so tasks that do nothing are dropped. Timed overhauls of parts that fail at random are replaced by checks, which cuts planned stops and repair-induced failures. Hidden failures in protective devices get tested at a worked-out interval. Safety failures are decided on risk, not cost. The limits: it takes team time, needs failure records, and must be reviewed as the equipment changes.
Preventive maintenance is a type of task: planned work at a set interval of time or use. RCM is the method that decides, failure mode by failure mode, whether a preventive task is the right answer at all. It keeps a timed task only where failures rise after a known age, and otherwise chooses a condition check, a failure-finding test, a redesign or run to failure.
The P-F interval is the time from the point where a coming failure can first be detected, P, to the point where it fails, F. A condition check has to happen more often than that: the ABS Guidance Notes on RCM say at no more than half of it. A bearing that shows a vibration defect 8 weeks before it seizes is checked every 4 weeks, which still leaves 4 weeks to act in the worst case.
No, but they overlap. An FMEA lists failure modes, their effects and causes and ranks them for risk, often to change a design or a process. RCM uses the same failure mode analysis for its questions 3 and 4, then adds the consequence class and a rule for choosing a maintenance task for each failure mode. You can think of RCM as an FMEA with a maintenance decision on every row.
SAE JA1011, Evaluation Criteria for Reliability-Centered Maintenance (RCM) Processes, is a standard published by SAE International in 1999. It sets the minimum a process has to do to be called RCM, framed as seven questions. SAE JA1012, published in 2002, is a guide to applying it. Shorter methods that skip or combine questions are often called streamlined or RCM-based.
RCM is an analysis method that decides which maintenance task each failure mode gets. TPM, total productive maintenance, is a plant-wide program in which operators and maintenance share care of the equipment, organised in pillars such as autonomous maintenance and planned maintenance. They work together: RCM can set the tasks the planned maintenance pillar runs, and the simple checks move to operators under autonomous maintenance.
Related guides and tools
- Preventive maintenance: the types, a PM schedule worked out in numbers and PM compliance
- FMEA: ratings, RPN against action priority, DFMEA against PFMEA and a worked example
- What is a CMMS: where the RCM tasks are scheduled as PM work orders
- Maintenance strategy selector: the RCM task questions for one failure mode, with the P-F and failure-finding intervals
- RCM worksheet: failure modes, consequence class and the task for each, in Excel and PDF
More method guides
- The 6 Ms of production
- Poka-yoke
- Model area 90-day plans
- Moving from Excel to one system
- Reducing machine downtime: a worked month
- Andon
- Cycle time vs lead time, worked through
- Root cause analysis
- How many operators a line needs
- Reducing scrap and rework: a worked month
- Unsafe acts and unsafe conditions
- Just culture
- Stop-work authority
- Material review board (MRB)
- Nonconformance and NCRs
- Problem solving methods
- Quad chart
- OEE calculation
- Quality assurance vs quality control
- SOP meaning and format
- Job hazard analysis
- Near miss reporting
- Fishbone diagram
- Pareto chart
- Histogram
- Control chart
- What is a gemba walk
- What is lead time
- What is operational excellence
- How to improve product quality
- Preventive vs predictive maintenance
- Kanban
- FMEA
- PDSA cycle
- Safety moments
- Just-in-time manufacturing
- Kaizen
- 5S
- Total quality management (TQM)
- CAPA (corrective and preventive action)
- Layered process audit (LPA)
- Lean tools
- Lockout tagout (LOTO)
- A3 problem solving
- Preventive maintenance
- APQP
- High reliability organization (HRO)
- Manufacturing KPIs
- Quality metrics
- Practical problem solving
- CMMS
- Risk assessment
- Production efficiency
- Total productive maintenance (TPM)
Or browse the topics, the full library and the lean glossary.