Risk assessment: what it is, the six steps and a 5x5 worked example

Short answer

A risk assessment is a structured look at a task, machine or area to find what could hurt people, judge how likely and how bad that harm would be, and decide which controls bring the risk down to an acceptable level. The result is a written record of each hazard, its rating, the controls and who acts by when.

A hazard is something that can cause harm: a moving ram, a hot surface, a forklift aisle. Risk is the chance that the harm happens combined with how serious it would be. A risk assessment lists the hazards, decides who could be harmed and how, rates each risk with the controls in place today, usually as severity times likelihood on a risk matrix, and adds further controls in the order of the hierarchy of controls until the risk is acceptable. The findings are recorded with an owner and a date for each action, and the assessment is reviewed whenever the work changes or something goes wrong.

Last reviewed:

What is a risk assessment? Hazard vs risk

The two words get swapped, and the difference is the whole method. A hazard is the source of harm. Risk is how likely that harm is and how bad it would be, given the way the work is done today. A press brake ram is a hazard. The risk depends on who stands at it, how close their hands get, and what stops the ram.

Hazard and risk on one line
HazardWho could be harmed and howWhat sets the risk
Press brake ramThe operator: fingers crushed between punch and dieHow close hands get to the tooling, and whether a guard stops the ram
Welding fumeWelders and people at nearby benches: breathing it in over monthsHow much fume reaches the breathing zone, and for how long
Steel sheet on the shear tableThe shear operator and helper: back strain lifting itThe weight, how often, and how far from the body it is held
Offcuts and air hoses on the floorAnyone walking through the cell: trips and fallsHow often the floor is cleared and where the hoses run

Illustrative. The same hazard can carry a low risk in one cell and a high one in another, which is why the assessment looks at the work as it is really done.

ISO 31000:2018, the general risk management standard, splits risk assessment into three parts in clause 6.4: identifying risks, analysing them and evaluating them against criteria. Safety practice adds the controls and the record. Methods range from qualitative (words such as low and high), through semi-quantitative (a numbered matrix, the usual choice on a plant floor), to quantitative (probabilities and frequencies, used for process safety and fault trees).

When is a risk assessment required?

In the United States, no single OSHA general industry standard requires one written risk assessment for the whole workplace. Specific standards ask for hazard assessments of their own. 29 CFR 1910.132(d)(1) requires the employer to assess the workplace for hazards that call for personal protective equipment, and 1910.132(d)(2) requires a written certification of that assessment naming the workplace evaluated, the person certifying it and the date. Section 5(a)(1) of the OSH Act, the general duty clause, obliges employers to deal with recognized serious hazards even where no standard applies. OSHA's Recommended Practices for Safety and Health Programs make hazard identification and assessment one of the core elements of a program.

In Great Britain, regulation 3 of the Management of Health and Safety at Work Regulations 1999 requires every employer to make a suitable and sufficient assessment of the risks to employees and to others affected by the work, and where five or more people are employed the significant findings have to be written down. Sites certified to ISO 45001 need a documented process for it under clause 6.1.2. Customers and insurers often ask to see one too.

  • Before a new task, machine, material or layout goes live.
  • When a task, machine, material, shift pattern or crew changes.
  • After an injury, a near miss or a failed control, for the task involved.
  • When new information arrives: a noise survey, a new safety data sheet, a manufacturer's notice.
  • On a fixed review cycle that your own procedure sets, shorter for the higher bands.

How to do a risk assessment in six steps

The order below follows the classic five steps published by HSE, the British regulator, with control split out from evaluation so the hierarchy of controls gets its own step. HSE's current guidance, Managing risks and risk assessment at work, runs the same sequence: identify hazards, assess the risks, control them, record the findings, review the controls.

Risk assessment in six steps

  1. 1

    Identify the hazards

  2. 2

    Decide who could be harmed and how

  3. 3S x L

    Evaluate the risk with today's controls

  4. 4

    Decide further controls by the hierarchy

  5. 5

    Record the findings and assign the actions

  6. 6

    Review and update

Steps 3 and 4 repeat until every risk sits in a band your policy accepts. Step 6 starts the loop again when the work changes.
  1. 1

    Identify the hazards

    Walk the area while the work is running, with the people who do it. Read the near miss and injury records, the maintenance work orders, the safety data sheets and the machine manuals. Include the non-routine jobs: changeovers, cleaning, jam clearing, maintenance. A walk during normal running never shows them.

  2. 2

    Decide who could be harmed and how

    Operators first, then maintenance, cleaners, contractors, drivers and visitors. Think about new starters, young workers, pregnant workers, people working alone and the night shift. Write how the harm happens: caught between, struck by, breathed in, lifted, slipped.

  3. 3

    Evaluate the risk with today's controls

    Rate the severity of the worst credible outcome and the likelihood of that outcome with the controls already in place. Multiply them on a risk matrix and read off the band. Score as a group, against a written scale.

  4. 4

    Decide further controls by the hierarchy

    For every risk above your accept band, choose controls from the top of the hierarchy of controls down: eliminate, substitute, engineer, then administrative controls and PPE. Score the hazard again with the further controls and check it moves down a band.

  5. 5

    Record the findings and assign the actions

    Write each hazard, who is at risk, the controls in place, the scores before and after, the further action, its owner and its due date. Share it with the crew that does the work, at the huddle or a toolbox talk.

  6. 6

    Review and update

    Check the actions were done and work. Review the assessment when the work changes, after an incident or near miss, and on the cycle your procedure sets. An assessment nobody has opened since it was signed is a record of what the area used to be.

Scoring risk with a 5x5 risk matrix

Most plants score risk as severity times likelihood on a matrix, the consequence and likelihood matrix that IEC 31010:2019 lists among risk assessment techniques. On a 5x5 grid each rating runs from 1 to 5 and the score from 1 to 25. The band the score falls in decides the action. No standard fixes the scales or the bands, so write yours down and use the same ones in every area.

A 5x5 banding and what to do at each band
BandScoresCells of the 25What to do
Low1 to 48Accept with the controls in place. Review when the task changes.
Medium5 to 97Reduce where you reasonably can. The supervisor agrees the controls and a date.
High10 to 167Reduce before the work goes on, or with temporary controls and a manager's approval.
Very high20 to 253Stop. Do not start or carry on until the risk is reduced.

The banding the free [risk assessment matrix template](/templates/risk-assessment-matrix) prints. Scores of 17 to 19 cannot occur on a 5x5 grid. Check the cell count both ways: 8 + 7 + 7 + 3 = 25 cells, and 5 x 5 = 25.

Severity is the worst credible outcome, not the worst imaginable: a 5 is a fatality or permanent disability, a 1 is first aid at most. Likelihood is how likely that outcome is with today's controls, from 1, not expected in the life of the task, to 5, happens regularly. The risk matrix calculator does the multiplication on a 3x3, 4x4 or 5x5 grid, shows the band, and lets you change the banding to your own policy.

Read the severity as well as the score. Severity 5 with likelihood 1 scores 5, the same band as a 2 x 3 hand cut. Consider a rule in your risk policy that sends any hazard at the top severity to a manager whatever its score. L. A. Cox Jr. set out the wider limits of risk matrices in What's Wrong with Risk Matrices? (Risk Analysis, 2008): ties between very different hazards, coarse cells, and scale words that people read differently.

Choosing controls: the hierarchy of controls

NIOSH ranks the ways of controlling a hazard from most to least effective: elimination, substitution, engineering controls, administrative controls, and personal protective equipment. ISO 45001:2018 sets the same order in clause 8.1.2. The higher the level, the less the control depends on someone remembering to do the right thing every shift.

The hierarchy of controls with examples from a fabrication cell
Level (NIOSH order)What it doesExample on the floor
1. EliminationRemoves the hazardBuy sheet cut to size so the shear job goes; run air hoses overhead so nothing lies on the floor
2. SubstitutionReplaces it with something less hazardousA water-based degreaser in place of a solvent; lower-noise grinding discs
3. Engineering controlsSeparates people from the hazardA light curtain on the press brake; on-torch fume extraction; a vacuum lifter for sheets
4. Administrative controlsChanges the way people workA written procedure, training, job rotation, a lockout, a permit, signs
5. PPEProtects the person when the hazard is still thereCut-resistant gloves, respirators, hearing protection, safety glasses

Most assessments end with a mix: an engineering control for the main hazard, a procedure to keep it working, and PPE for what is left.

A control lowers the score only by what it really changes. A guard that keeps hands out of the tool lowers the likelihood a lot. A sign lowers it very little. Severity rarely moves, because the hazard is still there if the control fails; it drops only when the control changes the hazard itself, such as less energy, a lower working height or a smaller quantity. For energy during servicing the control is a lockout: see the lockout tagout guide.

Risk assessment example: a fabrication cell scored on a 5x5 matrix

This example is illustrative. A fabrication cell has a press brake, a guillotine shear, a welding bay and a grinding bench, worked by four people on two shifts. The supervisor, two operators and the maintenance technician walk the cell for an hour, read the last year of near misses, and score five hazards on the 5x5 matrix with the banding above.

The fabrication cell on the 5 x 5 matrix

Example numbers
  • Low (1 to 4)
  • Medium (5 to 9)
  • High (10 to 16)
  • Very high (20 to 25)
  • Press brake, fingers at the tooling. Before controls 5 × 3 = 15 (high), after 5 × 1 = 5 (medium).
  • Welding fume. Before controls 4 × 4 = 16 (high), after 4 × 2 = 8 (medium).
  • Lifting sheet onto the shear. Before controls 3 × 4 = 12 (high), after 3 × 2 = 6 (medium).
  • Trips on offcuts and hoses. Before controls 2 × 4 = 8 (medium), after 2 × 2 = 4 (low).
  • Noise from the shear and grinding. Before controls 4 × 4 = 16 (high), after 4 × 3 = 12 (high).
Outlined markers are the scores with today's controls, filled markers the scores after the further controls. Four of the five hazards move down at least one band; the noise hazard stays high.
Illustrative risk assessment of a fabrication cell, before and after further controls
Hazard and who is at riskToday's controlsBefore: S x LFurther controls (hierarchy level)After: S x L
1. Press brake: operator's fingers crushed at the toolingFoot pedal, written rule to keep fingers clear5 x 3 = 15, highLight curtain that stops the ram (engineering); check it at the start of each shift (administrative)5 x 1 = 5, medium
2. Welding fume: two welders and the fitter at the next benchGeneral ventilation, disposable masks4 x 4 = 16, highOn-torch fume extraction (engineering); fitted respirators with a fit check (PPE)4 x 2 = 8, medium
3. Lifting steel sheet onto the shear: operator and helper, back strainTwo-person lift3 x 4 = 12, highVacuum lifter on the jib crane (engineering)3 x 2 = 6, medium
4. Trips on offcuts and air hoses: anyone in the cellSweep at the end of the shift2 x 4 = 8, mediumHoses on overhead reels (elimination); offcut bin at each machine emptied at every break (administrative)2 x 2 = 4, low
5. Noise from the shear and grinding: everyone in the cellEarplugs at the cell entrance4 x 4 = 16, highLower-noise discs (substitution); hearing protection enforced and a noise dose survey (administrative and PPE)4 x 3 = 12, high

S is severity and L is likelihood, both 1 to 5. Hazard 5 stays high because nothing yet separates people from the noise at its source; an acoustic screen around the grinding bench goes on the plan for the next quarter, with the survey from the [noise dose calculator](/tools/noise-dose-calculator) as its input. For hazard 3, the [NIOSH lifting equation calculator](/tools/niosh-lifting-equation-calculator) checks the lift before and after.

Count the bands before: four high (15, 16, 12, 16) and one medium (8), so 4 + 1 = 5 hazards. After: one high (12), three medium (5, 8, 6) and one low (4), so 1 + 3 + 1 = 5. Four of the five moved down at least one band. The highest score fell from 16 to 12, and the only hazard still high is the one where the further controls sit at the bottom of the hierarchy.

Read hazard 1 the way a manager should. It scores 5 after the light curtain, a medium, but its severity is still 5. That is why the daily check of the curtain is written into the start-up routine and the press brake stays on the review list. Each action goes on the plan with an owner and a due date, and the assessment is reviewed once the actions are in.

Risk assessment vs JHA, FMEA and a risk register

A risk assessment looks at an area, a machine or an activity as a whole. A job hazard analysis takes one task and breaks it into steps, finding the hazards at each. The two work together: the area assessment tells you which tasks carry the highest risk, and those tasks get a JHA.

Which method for which question
MethodLooks atOutputUse it when
Risk assessmentAn area, machine or activityHazards rated before and after, controls, owners and datesSetting up or reviewing the safety of a cell, line or job family
Job hazard analysis (JHA or JSA)One task, step by stepHazards and controls for each step, often ratedA task that has hurt or nearly hurt someone, or is new or non-routine
FMEAHow a process or design can failFailure modes ranked by severity, occurrence and detectionQuality and reliability risk in a process or product
Preliminary hazard analysisA design or change before it is builtHazards to design out earlyNew equipment, a new line or a layout change
Risk registerEvery open risk in one listOwner, rating, next review dateTracking all assessments and actions across the site

The [FMEA guide](/learn/fmea) covers severity, occurrence and detection for failure modes. The [risk register template](/templates/risk-register-template) holds the risks from every assessment in one list.

What ISO 45001 clause 6.1 asks for

ISO 45001:2018 is the international standard for occupational health and safety management systems. Clause 6.1, actions to address risks and opportunities, is where risk assessment sits. The summary below is in our own words; read the standard itself for the exact requirements.

ISO 45001:2018 clause 6.1 by subclause, in plain terms
ClauseTopicIn practice on a plant
6.1.1GeneralPlan for the risks and opportunities that affect the safety system and its results
6.1.2.1Hazard identificationAn ongoing, proactive process covering routine and non-routine work, past incidents, everyone in the workplace including contractors and visitors, and changes
6.1.2.2Assessment of risksDefined methods and criteria for rating risk, applied before harm happens rather than after, with records kept
6.1.2.3Assessment of opportunitiesWays to improve safety performance, such as adapting work to people
6.1.3Legal and other requirementsKnow which laws and customer requirements apply and how they affect the assessment
6.1.4Planning actionPlan the actions from the assessment, fit them into the system and check they work, using the hierarchy of controls

Clause 8.1.2 sets the hierarchy of controls, and clause 5.4 asks for workers to take part in identifying hazards and assessing risks. An auditor will ask to see your method, your criteria and a sample of assessments with their actions closed.

Common risk assessment mistakes

  • Writing it at a desk. The hazards that hurt people are in the non-routine work you only see on the floor: changeovers, cleaning, jam clearing.
  • Scoring with the new control already counted. Score today's controls first, then the further control, or there is no before.
  • Every control is PPE or a sign. They sit at the bottom of the hierarchy and barely move the likelihood.
  • Everything is a 5. Score the worst credible outcome, or nothing stands out and the list cannot be ranked.
  • Lowering the severity because a guard is fitted. If the guard fails, the harm is the same.
  • Different scales in every area. A 12 must mean the same thing on every line.
  • Actions with no owner or date. A rating without an action is only a description.
  • Never reviewing it. A new machine, a new material or a near miss makes the old scores wrong.

Safety Improvement

Report and control hazards in LeanSuite

Workplace safety in manufacturing, run from one platform: report hazards in seconds, fix them with tracked actions, train people and see safety KPIs on your tier boards.

Free templates and tools

FAQ

Questions about risk assessment

  1. A risk assessment is a structured review of a task, machine or area that finds the hazards, decides who could be harmed and how, rates each risk by severity and likelihood, and sets the controls that bring it down to an acceptable level. The findings are recorded with an owner and a date for every action.

  2. The classic five steps published by HSE are: identify the hazards, decide who might be harmed and how, evaluate the risks and decide on precautions, record the findings, and review and update. This guide splits evaluating from choosing controls, which gives six steps with the same content.

  3. A hazard is anything that can cause harm, such as a moving ram, a hot surface or a chemical. Risk is the combination of how likely the harm is and how serious it would be, given the way the work is done now. The same hazard can carry a low risk in one place and a high risk in another.

  4. Rate the severity of the worst credible outcome and its likelihood with today's controls, usually each from 1 to 5, and multiply them. Severity 5 and likelihood 3 give 15 out of 25, which falls in the high band of a common 5x5 banding. Score again after the further controls.

  5. By method: qualitative, which rates risk in words; semi-quantitative, which uses a numbered risk matrix and is usual on a plant floor; and quantitative, which uses probabilities and is used for process safety. By scope: area or activity assessments, task assessments such as a job hazard analysis, and quick pre-task checks done on the spot.

  6. The common ones are a risk matrix for rating, a job hazard analysis for single tasks, checklists for walking an area, FMEA for process and design failure modes, and fault trees, bow ties or HAZOP for process safety. A risk register keeps the results and actions in one list.

  7. In Great Britain, yes: regulation 3 of the Management of Health and Safety at Work Regulations 1999 requires one, written down where there are five or more employees. In the United States, OSHA has no single general requirement, but specific standards do, such as the certified PPE hazard assessment in 29 CFR 1910.132(d).

  8. A risk assessment covers an area, machine or activity as a whole. A job hazard analysis takes one task, breaks it into steps and finds the hazards at each step. The area assessment points to the riskiest tasks, and those get a JHA.

  9. A small group: the supervisor who owns the area, the people who do the work, and someone with safety or maintenance knowledge. The people who do the task know the shortcuts and the non-routine jobs. ISO 45001 clause 5.4 expects workers to take part in identifying hazards and assessing risks.

  10. Whenever the task, equipment, material, layout or crew changes, after an injury or near miss, when a control is found not working, and on a fixed cycle that your own procedure sets, shorter for higher risks. Check any interval your regulator or customer sets.

  11. Clause 6.1 covers it. 6.1.2.1 asks for ongoing hazard identification, including non-routine work, contractors and visitors. 6.1.2.2 asks for defined methods and criteria for assessing risk, with records kept. 6.1.4 asks for planned action, and clause 8.1.2 sets the hierarchy of controls.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.