Method guide · TPM and maintenance
Preventive maintenance: what it is, the types, a PM schedule example and PM compliance
Short answer
Preventive maintenance (PM) is planned work done on a machine at a set interval of time or use, before it fails: inspecting, cleaning, lubricating, adjusting and changing wear parts. The point is to catch wear while the fix is small and the stop can go on the plan.
A preventive maintenance task is triggered by the calendar (every week, every quarter) or by a meter (every 2,000 running hours, every 250,000 cycles), not by a breakdown or a sensor alarm. A PM program is the list of those tasks for every machine that matters, with who does each one, how long it takes and when it is next due. Plants judge it with PM compliance, the share of PMs due that were done on time, and with the breakdown trend on the machines it covers.
Last reviewed:
What is preventive maintenance?
Preventive maintenance means servicing equipment on a plan so it keeps running, instead of waiting for it to stop. Each PM is a defined job on one asset: change the inlet filter on compressor 2, check the oil and listen to the gearbox on conveyor 4, replace the vacuum cups on the case packer. The job has a trigger, an interval, a time estimate and a standard to check against.
Most PM work falls into five kinds of task. Inspect: look, listen, feel, and take a reading against a limit. Clean: remove the dirt, dust and product build-up that hide leaks and cause heat. Lubricate: the right grease or oil, in the right amount, at the right point. Adjust: belt tension, chain slack, guide clearances, sensor positions. Replace: filters, seals, belts and other parts that wear at a known rate.
Preventive and preventative mean the same thing. Preventive is the more common spelling in maintenance standards and job titles, and PM is the shorthand on the shop floor, as in "Line 3 is down for PM on Saturday".
| Equipment | Typical PM task | Usual trigger |
|---|---|---|
| Air compressor | Change the inlet filter, drain condensate, check belt tension | Running hours on the compressor's hour meter |
| Gearbox | Check the oil level and colour, look for leaks, feel for heat, listen for noise | Calendar, weekly or monthly |
| Conveyor | Check belt tracking and splices, lubricate bearings, clean the rollers | Calendar, weekly |
| Hydraulic press | Check hoses and fittings for weeping, change the return filter, test the guard interlocks | Calendar, monthly, plus filter change by hours |
| Forklift | Daily pre-use check by the driver, then a service by a technician | Shift start, then engine hours |
| Pick-and-place or case packer | Inspect and replace vacuum cups, check grippers and sensors | Cycle count |
The interval for each task starts from the maker's manual and is then adjusted from your own records. The free [preventive maintenance checklist](/templates/preventive-maintenance-checklist) has task rows with frequency, method, standard, reading and sign-off, and a schedule that works out the next due date.
Types of preventive maintenance
Preventive maintenance has two triggers, and the type is named after the trigger.
| Type | What starts the job | Fits when | Watch out for |
|---|---|---|---|
| Time-based (calendar) PM | A date: every shift, week, month, quarter or year | Wear tracks the calendar because the machine runs a steady pattern, or a rule sets the date, such as a yearly inspection | A machine that runs one shift some weeks and three shifts in others gets serviced too early or too late |
| Usage-based (meter) PM | A count: running hours, cycles, strokes, units made, kilometres | Wear tracks how hard the machine works and the run pattern changes | Someone has to read the meter, or the count has to be worked out from the production plan |
Some guides add condition-based and predictive maintenance as further types of PM. They are better treated as a different strategy, because the trigger is the state of the machine (a vibration reading, an oil sample, a temperature) rather than a fixed interval. A PM round can still collect those readings: the inspection task on the gearbox records the temperature, and a rising trend raises a job before the next PM is due. Preventive vs predictive maintenance compares the two side by side with reactive, planned and autonomous maintenance and TPM.
Who does the work is a separate choice from the trigger. Daily cleaning, inspection, lubrication and tightening often moves to the operator under autonomous maintenance, using a short CILR checklist at the start of the shift. Technicians keep the PMs that need tools, skills, lockout or parts. CILR in manufacturing covers the operator side.
Why preventive maintenance matters, and what it costs
A planned stop is cheaper than a breakdown. When a gearbox seizes in the middle of a run, the line stops without warning, the order is late, the technician starts by looking for the cause, and the part may not be on the shelf. When the same gearbox has its oil checked every week, the low level shows up on a Tuesday, the leak is fixed in a planned half hour, and the line keeps its plan.
PM has its own costs. Parts are sometimes changed with life left in them. The machine has to stop for most tasks, so PM is planned downtime the production schedule must allow for. Every PM takes technician hours, and a badly written PM can do harm: a bearing over-greased or a guard put back loose. The aim is not the most PM, it is the PM that prevents a failure you can see coming.
How to build a preventive maintenance program
A PM program is the full set of PM tasks for a plant, with the schedule and the records that show whether it is working. Build it one line at a time, not for the whole plant in one go.
Building a preventive maintenance program in six steps
- 1
List the assets
- 2
Rank them by criticality
- 3
Write the tasks, each with a limit
- 4
Set the trigger and interval
- 5
Build and level the schedule
- 6
Do, record and review
Then back to steps 3 and 4: change the tasks and intervals the records say are wrong
- 1
List the assets
Every machine and utility on the line with an asset number, a location and the maker's manual. Include the things that stop the line when they fail and are easy to forget: the compressor, the chiller, the dust extraction.
- 2
Rank them by criticality
Score each asset on what its failure does to safety, quality, output and cost. The equipment criticality analysis sorts assets into classes A, B and C. Start PM on the A class. Some C class items can run to failure on purpose, with a spare on the shelf.
- 3
Write the tasks
For each critical asset, take the maker's recommended tasks, then add what your own breakdown history shows. Write every task as an action and a limit: "Check belt deflection, 10 to 15 mm", not "Check belt". A task without a limit cannot be signed off honestly.
- 4
Set the trigger and interval
Choose calendar or meter for each task and set the interval. Convert meter intervals into weeks from the production plan so they can be scheduled, and round down, never up.
- 5
Build and level the schedule
Add up the hours per week by craft and spread the tasks so no week is overloaded. Agree the downtime windows with production and put them on the production plan. The weekly maintenance schedule loads next week's jobs against each craft's hours.
- 6
Do, record and review
Each PM is done from a checklist with readings, and anything found that cannot be fixed in the PM becomes a work order with a priority. Each month, measure PM compliance and look at the breakdowns on PM'd assets. Change the tasks and intervals the records say are wrong.
Step 6 never ends. A program that is set up once and never reviewed collects tasks nobody understands and misses the failures that changed since. The maintenance job plan template is useful for the larger PMs, where parts, permits and several crafts have to be ready before the machine stops.
A preventive maintenance schedule example, worked out in numbers
This example is illustrative. A packaging line runs two 8-hour shifts, 5 days a week, for 50 weeks a year: 80 running hours a week and 4,000 a year. The case packer makes 10 cycles a minute while the line runs, which is 600 cycles an hour and 48,000 a week. The compressor serves only this line and runs when it runs. The team has five PM tasks on the line's critical assets.
| Asset and task | Trigger and interval | Converted to weeks | PMs a year | Minutes each | Hours a year |
|---|---|---|---|---|---|
| Air compressor: change the inlet filter | Usage, every 2,000 running hours | 2,000 / 80 = every 25 weeks | 4,000 / 2,000 = 2 | 30 | 2 x 30 min = 1.0 |
| Conveyor gearbox: oil level, leaks, heat, noise | Time, weekly | Every week the line runs | 50 | 12 | 50 x 12 min = 10.0 |
| Case packer: inspect and replace vacuum cups | Usage, every 250,000 cycles | 250,000 / 48,000 = 5.2, so every 5 weeks | 50 / 5 = 10 | 45 | 10 x 45 min = 7.5 |
| Filler: valves, seals and lube points | Time, monthly | Every calendar month | 12 | 90 | 12 x 90 min = 18.0 |
| Stretch wrapper: drive chain lube and tension | Time, quarterly | Every 13 weeks | 4 | 60 | 4 x 60 min = 4.0 |
| Total | 78 | 40.5 |
Check the total the other way: 60 + 600 + 450 + 1,080 + 240 = 2,430 minutes, and 2,430 / 60 = 40.5 hours. The case packer interval is rounded down: every 5 weeks is 240,000 cycles, inside the 250,000 limit, while every 6 weeks would be 288,000 cycles, 15% past it.
Three things come out of the numbers. First, the technician load is small on average, 40.5 hours over 50 weeks is about 49 minutes a week, but it is lumpy. In a week where the gearbox check, the case packer, the filler and the wrapper all fall due, the line needs 12 + 45 + 90 + 60 = 207 minutes, almost 3.5 hours. Keeping the wrapper and the compressor filter out of the filler's week brings the worst week down to the filler, the case packer and the gearbox check: 90 + 45 + 12 = 147 minutes, under 2.5 hours.
Second, most of these PMs stop the line. The gearbox check is done running, at the start of the shift, but the other four need the machine stopped: 1.0 + 7.5 + 18.0 + 4.0 = 30.5 hours of planned downtime a year, which is 30.5 / 4,000 = 0.76% of the running time. Production needs those windows on its plan, and the OEE calculation needs a rule for whether they count against availability.
Third, the usage intervals depend on the plan. If the line goes to three shifts, 120 hours a week, the compressor filter falls due every 2,000 / 120 = 16.7 weeks and the case packer every 250,000 / 72,000 = 3.5 weeks, so every 3. A calendar schedule copied from a two-shift year is now late on both. Usage-based PMs should be re-worked whenever the shift pattern changes, or driven from the meter itself.
Fixed or floating due dates
When a PM is done late, the next due date can be set two ways. A fixed schedule keeps the original dates: the PM is always due in weeks 5, 10, 15 and so on, whenever the last one was done. A floating schedule counts from the date the work was actually done.
| Fixed schedule | Floating schedule | |
|---|---|---|
| PM due | Week 5 | Week 5 |
| PM done | Week 7 | Week 7 |
| Next PM due | Week 10 (5 + 5) | Week 12 (7 + 5) |
| Wear on the new cups at the next PM | 3 weeks, 144,000 cycles | 5 weeks, 240,000 cycles |
| Fits | Inspections tied to a date, such as a yearly statutory inspection, and PMs grouped into a shutdown | Wear parts, where the clock should restart when the part is changed |
Check the cycles: 3 weeks x 48,000 = 144,000 and 5 weeks x 48,000 = 240,000. Either way the week 7 PM counts as late in PM compliance. Floating dates must not be used to hide that.
PM compliance: how to measure a preventive maintenance program
PM compliance is the share of the PMs that fell due in a period which were done on time. PM compliance = PMs done on time / PMs due x 100. On time usually means inside a grace window the plant sets, such as 10% of the interval: a quarterly PM done 9 days late is still on time, a weekly PM done 2 days late is not.
This example is illustrative. In March a plant has 120 PMs due. 102 are done inside their window, 11 are done late, and 7 are not done at all.
PM compliance for one month
Example numbersPM compliance = PMs done on time ÷ PMs due
Check it the other way: 102 + 11 + 7 = 120. The two numbers answer different questions. Completion says the work got done in the end; compliance says it got done when the plan needed it. Report both, and keep the 7 open PMs on the list as overdue rather than closing them to tidy the number.
- PMs due in March =From the schedule= 120
- PM compliance =102 on time / 120 due= 85.0%
- PM completion (done at all) =(102 + 11) / 120= 94.2%
- PMs still open at month end =120 - 102 - 11= 7, carried into April as overdue
PM compliance shows whether the plan is being followed. It does not show whether the plan is any good. For that, watch the breakdowns on the assets the PMs cover: if MTBF on those assets is not rising, the tasks or intervals are wrong, however high the compliance. The MTBF and MTTR calculator works out both from a downtime log, and the maintenance KPI tracker keeps MTBF, MTTR, availability and PM compliance per asset by month.
| Measure | Formula | What it tells you |
|---|---|---|
| PM compliance | PMs done on time / PMs due | Is preventive work happening when it should? |
| Schedule compliance | Jobs done as scheduled / jobs scheduled for the week | Is the weekly maintenance schedule holding, for all planned work, not only PM? |
| Planned maintenance percentage | Planned maintenance hours / total maintenance hours | How much of the crew's time goes on planned work rather than breakdowns? |
| MTBF | Running time / number of failures | Are the machines failing less often? |
A falling PM compliance is often the first sign that breakdown work is crowding out planned work. [Maintenance KPIs](/blogs/top-maintenance-kpis-to-track-for-optimal-performance) covers the wider set.
When preventive maintenance does not help
A scheduled replacement only prevents failures that get more likely as a part ages: wear, fatigue, corrosion, a filter loading up. Many failures do not behave that way. Some are random, as likely in the first week of a part's life as in the fiftieth; electronics often fail like this. Others come from a bad repair and are most likely just after the work is done. The airline studies that led to reliability-centred maintenance (F. Stanley Nowlan and Howard Heap, Reliability-Centered Maintenance, 1978) made this point, and it is why changing a part on a timer does nothing for some failures except add the risk of a bad reassembly.
For those failures, an inspection that spots the early warning, a predictive reading, or a spare on the shelf with a fast changeover does more than a time-based replacement. The maintenance strategy selector asks how an asset fails and what failure costs, and suggests which strategy fits. Reliability-centered maintenance goes through the full method with a worked example.
Two signs that a PM is in the wrong place: the technician finds nothing to fix at PM after PM, so the interval can be stretched, or the machine still breaks down between PMs with the same failure, so the task is the wrong one or the interval is too long.
Where the PM schedule lives: CMMS, spreadsheet or paper
Most plants with more than a few dozen PMs keep them in a computerized maintenance management system (CMMS). It holds the asset register, generates each PM as a work order when it falls due, records the parts and hours, and keeps the history that MTBF and PM compliance are worked out from. Smaller sites run PM from a spreadsheet with due dates and paper checklists, which works until PMs are missed because nobody opened the file.
LeanSuite is not a CMMS and does not replace one. It handles the operator side of maintenance and works alongside your CMMS: when a scheduled PM comes due or an operator tags an abnormality, it creates the work order and routes it to the maintenance team, and CILR checklists can be assigned to an asset with a repeat rule, with missed checks shown in red. See autonomous maintenance and professional maintenance tags. Why digitize equipment maintenance covers moving off paper.
Common preventive maintenance mistakes
- PM on everything. Putting every asset on PM spreads the crew thin. Rank by criticality and let cheap, non-critical items run to failure with a spare ready.
- Tasks without a limit. "Inspect motor" gets a tick whatever the motor looks like. Write what to check and the value that is out of limit.
- Ticks without readings. A tick says the task was done; a reading shows the trend that warns of the next failure.
- Rounding usage intervals up. Converting 5.2 weeks to 6 runs the part past the maker's interval every time.
- Skipping PMs when production is busy. A skipped PM is a late PM until it is done. Move it to the next window, agree that window with production, and keep it on the overdue list.
- Findings that go nowhere. A leak or a worn coupling found during a PM and not fixed needs its own work order and priority, or it waits for the breakdown.
- Never reviewing intervals. Intervals copied from the manual and never changed are too short for some machines and too long for others. Your own breakdown and reading history should move them.
Digital CILR Checklists
Run daily CILR checks in LeanSuite
Digital CILR checklists put each machine's clean, inspect, lubricate and retighten routine on the operator's Daily Standard Work in LeanSuite, so small problems are caught before they become breakdowns.
Go deeper
This page is the short version. These guides cover each part in full.
- What are Five Types of Maintenance Strategies?Reactive, preventive, corrective, predictive and reliability-centred maintenance, each described in turn.
- The Difference Between Planned and Scheduled MaintenanceHow planning a job differs from scheduling it, and why PM needs both.
- Maintenance KPIs: What to Measure and WhyMTBF, MTTR, planned maintenance percentage and the other maintenance measures beside PM compliance.
- CILR: Clean Inspect Lubricate Retighten in ManufacturingThe daily operator routine that takes the simplest PM tasks off the technicians.
All our articles on this subject are in the tpm and maintenance topic.
Free templates and tools
- Preventive maintenance checklist templateA PM checklist per machine with readings and sign-off, and a PM schedule that works out the next due date.
- Weekly maintenance schedule templateNext week's maintenance jobs, scheduled only when ready, loaded against each craft's hours by day, with schedule compliance and break-ins at week end.
- Maintenance KPI trackerMTBF, MTTR, availability and PM compliance per asset and month, plant figures from the totals, planned maintenance % and backlog in weeks.
- Lubrication schedule templateEvery lube point with lubricant, method, amount, frequency and who, with next due dates and a monthly sign-off record.
- Equipment criticality analysisAssets scored 1 to 5 on six criteria with your own weights, ranked and sorted into classes A, B and C with a safety override and a suggested maintenance strategy.
- Maintenance job plan templateOne job planned on one sheet: steps and craft hours, parts checked against stock, tools, lockout and permits, documents, a ready check for the schedule, and technician feedback.
- Work order template for maintenanceA work order template for maintenance: one form per job from request to handback, and a log of response, completion and backlog by priority.
- Critical spare parts list and stocking levelsAssets ranked by consequence, each part classed and given a stocking policy, and min and max worked out from usage and lead time, with the downtime each stock-out would cost.
- MTBF and MTTR calculatorMean time between failures, mean time to repair and availability from operating time, failures and repair time.
- Maintenance strategy selectorAnswer the RCM questions for one failure mode and get the maintenance strategy, the reasoning and the check or test interval.
- Downtime cost calculatorWhat an hour, an event and a year of unplanned downtime cost, from lost output, idle labour, scrap and overtime.
Key terms
- Preventive maintenance (PM)
- PM compliance
- Schedule compliance (maintenance)
- Planned maintenance percentage (PMP)
- Maintenance backlog
- Planned maintenance
- Predictive maintenance (PdM)
- Condition-based maintenance (CBM)
- Computerized maintenance management system (CMMS)
- Mean time between failures (MTBF)
- CILR (clean, inspect, lubricate, retighten)
Doing this in LeanSuite
Autonomous Maintenance
Rolls out visual CILR (clean, inspect, lube, retighten) checklists so operators catch small abnormalities before they cause downtime.
See Autonomous MaintenanceCILR Checklists
Build visual CILR checklists so operators clean, inspect, lubricate and re-tighten on schedule and catch problems before they become breakdowns.
See CILR ChecklistsProfessional maintenance tags
Professional maintenance tags in LeanSuite turn radio calls and firefighting into work orders every technician can see, own and close out.
See Professional maintenance tags
See it on your own lines
Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.
FAQ
Questions about preventive maintenance
Preventive maintenance (PM) is planned work done on equipment at a set interval of time or use, before it fails. Typical PM tasks are inspecting against a limit, cleaning, lubricating, adjusting and replacing wear parts such as filters, belts and seals. The aim is to find wear while the repair is small and the stop can be scheduled.
There are two triggers. Time-based PM is due on a date: every week, month, quarter or year. Usage-based PM is due on a count: running hours, cycles, strokes or units made. Condition-based and predictive maintenance are sometimes listed as types of PM, but their trigger is the measured state of the machine rather than a fixed interval, so they are usually treated as a separate strategy.
Changing the inlet filter on an air compressor every 2,000 running hours, checking the oil level and listening to a conveyor gearbox every week, and replacing the vacuum cups on a case packer every 250,000 cycles. Each task has a trigger, an interval, a time estimate and a standard to check against.
Start from the maker's recommended interval for each task, then adjust it from your own records. If the technician finds nothing worn at PM after PM, the interval can be stretched. If the same failure happens between PMs, shorten the interval or change the task. For usage-based tasks, convert the interval to weeks from the production plan and round down, and redo the sum when the shift pattern changes.
PM compliance = PMs done on time / PMs due in the period x 100. On time usually means inside a grace window the plant sets, such as 10% of the interval. With 120 PMs due in a month and 102 done on time, compliance is 102 / 120 = 85.0%. If 11 more were done late, completion is 113 / 120 = 94.2%, but compliance stays at 85.0%.
A preventive maintenance program is the full set of PM tasks for a plant with the schedule and records that show whether it works. It is built in six steps: list the assets, rank them by criticality, write the tasks with limits, set the trigger and interval, build and level the schedule, then do the work, record readings and review the intervals every month.
Not quite. Preventive maintenance is work triggered by time or usage to stop a failure. Planned maintenance is any maintenance job prepared before it starts, with the steps, parts, tools and time worked out. Most PM is planned, but planned maintenance also covers repairs and predictive tasks that were prepared in advance.
Both spellings mean the same thing. Preventive is the more common form in maintenance standards, job titles and software, and PM is the usual shorthand on the shop floor.
Not to start. A small site can run PM from a spreadsheet with due dates and paper checklists. Once there are more PMs than one person can track, a computerized maintenance management system (CMMS) generates each PM as a work order when it falls due and keeps the history. LeanSuite is not a CMMS; it works alongside one on the operator side, creating the work order when a scheduled PM comes due or an operator tags an abnormality.
Related guides and tools
- Preventive vs predictive maintenance: the two compared with reactive, planned, autonomous and TPM, and how to choose per machine
- Preventive maintenance checklist: PM tasks with limits, readings and sign-off, and a schedule that works out the next due date
- Weekly maintenance schedule: next week's PM and repair jobs loaded against each craft's hours
- Total productive maintenance: where PM sits among the 8 TPM pillars, and TPM vs RCM vs PM
- MaintainX alternatives: CMMS tools and where LeanSuite fits
More method guides
- The 6 Ms of production
- Poka-yoke
- Model area 90-day plans
- Moving from Excel to one system
- Reducing machine downtime: a worked month
- Andon
- Cycle time vs lead time, worked through
- Root cause analysis
- How many operators a line needs
- Reducing scrap and rework: a worked month
- Unsafe acts and unsafe conditions
- Just culture
- Stop-work authority
- Material review board (MRB)
- Nonconformance and NCRs
- Problem solving methods
- Quad chart
- OEE calculation
- Quality assurance vs quality control
- SOP meaning and format
- Job hazard analysis
- Near miss reporting
- Fishbone diagram
- Pareto chart
- Histogram
- Control chart
- What is a gemba walk
- What is lead time
- What is operational excellence
- How to improve product quality
- Preventive vs predictive maintenance
- Kanban
- FMEA
- PDSA cycle
- Safety moments
- Just-in-time manufacturing
- Kaizen
- 5S
- Total quality management (TQM)
- CAPA (corrective and preventive action)
- Layered process audit (LPA)
- Lean tools
- Lockout tagout (LOTO)
- A3 problem solving
- APQP
- High reliability organization (HRO)
- Manufacturing KPIs
- Quality metrics
- Practical problem solving
- CMMS
- Risk assessment
- Production efficiency
- Total productive maintenance (TPM)
- Reliability-centered maintenance (RCM)