Total productive maintenance (TPM): meaning, the 8 pillars, autonomous maintenance, OEE and a worked example

Short answer

Total productive maintenance (TPM) is a way of running a plant in which operators, maintenance and managers share the job of keeping machines in good condition, aiming for zero breakdowns, zero defects and zero accidents. Operators take on the daily cleaning, checks and lubrication of their own machines, and maintenance moves to planned work and to removing the causes of failure.

TPM stands for total productive maintenance. It grew up in Japanese plants and was set out by Seiichi Nakajima of the Japan Institute of Plant Maintenance (JIPM). It is organised as eight pillars on a 5S foundation: autonomous maintenance, planned maintenance, focused improvement, quality maintenance, early equipment management, training and education, safety, health and environment, and office TPM. Progress is measured with OEE (availability x performance x quality) and the six big losses it breaks into. Plants start TPM on one model machine, prove it there, then spread it.

Last reviewed:

What is TPM (total productive maintenance)?

TPM means total productive maintenance. Each word does work. Total: everyone who touches the machine has a part, from the operator on nights to the plant manager. Productive: the target is output, so a machine that runs all shift at two thirds of its rated speed is a TPM problem even though it never broke. Maintenance: the means is keeping equipment in the condition it was designed to run in.

The old split says operators run the machine and maintenance fixes it. TPM ends that split. The operator who stands at the filler for eight hours is the first to hear a new noise, see a drip or feel a guard working loose, so the operator does the basic care: clean, inspect, lubricate and tighten, and tag anything abnormal. The technicians, freed from small jobs, plan the bigger maintenance work and go after the reasons machines fail.

Who does what, before TPM and with it (illustrative)
RoleBefore TPMWith TPM
OperatorRuns the machine and calls maintenance when it stopsDoes the daily clean, inspection, lubrication and tightening, tags abnormalities, and makes the small fixes they are trained for
Maintenance technicianSpends most of the shift on breakdownsPlans and does the preventive work, fixes the causes behind repeat failures, trains operators and works the maintenance tags
EngineeringBuys and installs new machinesFeeds what the plant learned about failures and cleaning into the design of the next machine
Plant and area managersJudge maintenance on cost and response timeGive time for cleaning and training, own the pillar plans and review the losses each week

TPM comes from Japan. Seiichi Nakajima of the Japan Institute of Plant Maintenance (JIPM) set it out in a short book, published in English as Introduction to TPM (Productivity Press, 1988). The first JIPM award for it is usually credited to Nippondenso, a Toyota parts supplier, in 1971. Our summary of Nakajima's book covers what it argues and where it has dated.

TPM has other meanings outside the plant. In computing it is a trusted platform module, a security chip in a PC. On the shop floor it always means total productive maintenance, and you will also see it written as total productivity maintenance or total product maintenance. Same idea.

The 8 pillars of TPM

TPM work is split into pillars, each with an owner, a plan and its own measures. Nakajima's book describes five core activities; the eight-pillar model most plants use today grew out of them later. The pillars stand on a foundation of 5S, because a machine you cannot see clearly cannot be inspected.

The eight pillars of TPM, the job of each and where to start
PillarAlso calledThe jobFirst move on the floorFree plan or template
Autonomous maintenanceJishu hozen, AMOperators keep their own machines at basic condition and spot abnormalities earlyA first clean of one machine with the operators and a technician, tagging every abnormalityAM 90-day plan
Planned maintenanceProfessional maintenance, PM pillarMaintenance plans preventive and predictive work from the failure history and cuts breakdownsList the failures on the model machine and write PM tasks with limits for the ones that repeatProfessional maintenance 90-day plan
Focused improvementKobetsu kaizenSmall cross-functional teams remove the biggest losses one at a timePick the largest loss on the loss map and run one improvement on itFocused improvement 90-day plan
Quality maintenanceHinshitsu hozenFind the machine conditions that cause defects, then set and hold themLink each defect type to the settings and parts that cause itQuality control 90-day plan
Early equipment managementEarly managementNew machines and parts are designed to be easy to run, clean, inspect and change overWrite down what the current machine taught you before the next one is specifiedEarly equipment management 90-day plan
Training and educationPeople developmentOperators and technicians get the skills the other pillars ask of themA skills matrix for the model machine and one-point lessons for each new taskPeople development 90-day plan
Safety, health and environmentSHENo accidents, no harm to health, no harm to the environment from the equipment or the work on itMake every cleaning and inspection point safe to reach before operators are asked to use itSafety pillar 90-day plan
Office TPMTPM in administrationPlanning, purchasing, stores and other support teams cut the losses that hold the line upCount the hours lost waiting for parts, plans or approvals on the model machineNone yet; start from the loss list

Pillar names vary a little between books and between plants; some split safety and environment, some add cost deployment. Our [model area guide](/learn/model-area) explains how each pillar starts in one area and then spreads, with all ten 90-day plans. [The 8 pillars of TPM explained](/blogs/eight-pillars-tpm-manufacturing-guide) covers each pillar in more depth.

The pillars depend on each other. Autonomous maintenance needs the training pillar, or operators are handed tasks they were never shown. Planned maintenance needs the tags operators raise, or it plans from guesswork. Focused improvement needs the loss data the first two produce. That is why most plants start with autonomous and planned maintenance on the same machine.

Autonomous maintenance: the 7 steps

Autonomous maintenance is the pillar most people picture when they hear TPM. Operators take over the basic care of their machine in seven steps, and a team moves to the next step only when the current one holds, usually checked by an audit.

The seven steps of autonomous maintenance

  1. 1Step 1

    Initial cleaning and inspection

  2. 2Step 2

    Remove contamination sources and hard-to-reach areas

  3. 3Step 3

    Set cleaning, lubrication and inspection standards

  4. 4Step 4

    General inspection

  5. 5Step 5

    Autonomous inspection

  6. 6Step 6

    Standardization

  7. 7Step 7

    Autonomous management

Steps 1 to 3 restore and hold basic condition; steps 4 and 5 teach operators to inspect; steps 6 and 7 hand them the standards. A team moves on only when the current step holds.
  1. 1

    Initial cleaning and inspection

    Operators and a technician clean the machine down to bare metal, together. Cleaning is how they find things: every leak, loose bolt, crack, worn part and hard-to-reach point gets a tag and goes on the tag log.

  2. 2

    Remove sources of contamination and hard-to-reach areas

    Stop the dirt at its source (a split seal, a spill from the conveyor above, a missing cover), and make every point that has to be cleaned, checked or greased easy to reach.

  3. 3

    Set cleaning, lubrication and inspection standards

    Write down what is cleaned, lubricated and checked, how, with what, how often and in how many minutes. The first version is provisional; operators test the times on a real shift.

  4. 4

    General inspection

    Technicians teach operators how each main system works (drives, pneumatics, hydraulics, electrics, fasteners) and what failure looks like, often through one-point lessons. Operators then inspect each system as part of the daily check.

  5. 5

    Autonomous inspection

    Operators run the full inspection on their own, from a check sheet they helped write, and the cleaning and inspection standards are merged into one routine that fits the time available.

  6. 6

    Standardization

    The routine is extended to the area around the machine: tools, spare parts, materials and quality checks each get a standard place and a standard check.

  7. 7

    Autonomous management

    Operators run and improve their own standards, track their machine's losses and take part in improvement work, with maintenance as the support behind them.

The daily routine that comes out of steps 3 to 5 is usually called CILR or CILT (clean, inspect, lubricate, retighten or tighten). CILR in manufacturing shows a filled checklist, and the autonomous maintenance example walks one machine through the steps.

What a first clean turns up (illustrative)

A crew of three operators and one technician spends two hours on the first clean of a bottle filler. They hang 38 tags. Each tag is sorted by who can fix it: the operator, or maintenance.

Tags from the first clean of one filler (illustrative)
What was foundTagsOperator can fixNeeds maintenance
Leaks (oil, air, product)734
Loose or missing fasteners990
Sources of contamination642
Points hard to clean, inspect or lubricate862
Worn or damaged parts514
Safety hazards312
Total382414

Check the totals both ways: 7 + 9 + 6 + 8 + 5 + 3 = 38, and 24 + 14 = 38. Four weeks later all 24 operator tags and 9 of the 14 maintenance tags are closed, 33 of 38 or 86.8%. The other 5 wait for parts or a planned stop, and they stay open on the [TPM tag log](/templates/tpm-tag-log) until they are done.

The closing matters more than the hanging. Operators judge TPM by whether their tags get fixed. If the maintenance tags from the first clean are still open two months later, the second clean finds fewer tags because nobody bothers. The AM step audit checks whether a team has really finished a step before it moves on.

TPM and OEE: how TPM is measured

TPM is measured by what the machine produces, not by how busy maintenance is. The main measure is overall equipment effectiveness (OEE): OEE = availability x performance x quality. Availability is the share of planned time the machine ran. Performance is how fast it ran against its ideal rate. Quality is the share of output that was good first time. The OEE calculation guide works through the formula with three examples.

Nakajima split the lost time into six big losses, and each one has a pillar that goes after it. That map tells a plant which pillar to put effort into first: the one that owns the largest loss.

The six big losses and the TPM pillar that removes each one
LossOEE factorMain pillarTypical first countermeasure
Breakdowns (equipment failure)AvailabilityAutonomous and planned maintenanceRestore basic conditions, then PM tasks with limits on the parts that fail
Setup and adjustmentAvailabilityFocused improvementSMED: move setup work outside the stop and remove trial-and-error adjustment
Small stops and idlingPerformanceAutonomous maintenance, focused improvementClean the sensors and fix the jam points the operators know about
Reduced speedPerformanceFocused improvement, planned maintenanceFind out why the machine is set below its ideal rate and remove that reason
Start-up rejectsQualityQuality maintenanceA standard for settings at start-up and after each changeover
Production rejectsQualityQuality maintenanceTie each defect to a machine condition and add that condition to the daily check

Small stops are the loss most often missed, because they are too short to be logged. The [six big losses worksheet](/templates/six-big-losses-worksheet) sorts a week of stops into the six, and [the six big losses in lean manufacturing](/blogs/six-big-losses-lean-manufacturing) explains each one.

Other measures sit beside OEE. Mean time between failures (MTBF) shows whether breakdowns are getting rarer, and mean time to repair (MTTR) whether they are getting shorter; the MTBF and MTTR calculator works both out from a downtime log. PM compliance shows whether the planned work happens on time (see preventive maintenance). Tags raised and closed, and the number of machines through each autonomous maintenance step, show whether the pillars are moving.

A TPM example, worked out in numbers

This example is illustrative. A bottle filler is the model machine. It is planned to run two shifts of 450 minutes, five days a week: 2 x 450 x 5 = 4,500 minutes a week. Its ideal cycle time is 0.5 minutes a case, so at full speed with no stops it would make 9,000 cases a week. The team logs one baseline week.

Filler baseline week: OEE before TPM (illustrative)
StepCalculationResult
Planned production time2 shifts x 450 min x 5 days4,500 min
Breakdowns9 stops averaging 45 min405 min
Setup and adjustment5 changeovers x 45 min225 min
Run time4,500 - 405 - 2253,870 min
Availability3,870 / 4,50086.0%
Cases madeCounted6,966
Performance6,966 x 0.5 min / 3,870 min = 3,483 / 3,87090.0%
Good cases6,966 - 209 rejects6,757
Quality6,757 / 6,96697.0%
OEE86.0% x 90.0% x 97.0%75.1%

Check it the other way: good cases x ideal cycle time / planned time = 6,757 x 0.5 / 4,500 = 3,378.5 / 4,500 = 75.1%.

Next, turn the lost 24.9% into minutes and give each loss an owner. This is the loss map the pillars work from.

Filler loss map for the baseline week, by pillar (illustrative)
LossMinutesShare of planned timePillar that owns it
Breakdowns4059.0%Autonomous and planned maintenance
Setup and adjustment2255.0%Focused improvement (SMED)
Small stops and reduced speed3,870 - 3,483 = 3878.6%Autonomous maintenance, focused improvement
Rejects209 x 0.5 = 104.52.3%Quality maintenance
Total lost1,121.524.9%

Check: 405 + 225 + 387 + 104.5 = 1,121.5 minutes, and 4,500 - 1,121.5 = 3,378.5 minutes of good output, the same 75.1% as above.

Over the next twelve months the pillars work on the filler. The first clean and the tags close out leaks and loose guide rails; the operators' CILR routine and new PM tasks on the capper drive bring breakdowns down to 5 stops, 225 minutes. A SMED event cuts each changeover from 45 to 36 minutes, so 5 changeovers take 180. Cleaning the photo-eyes every shift and fixing the infeed jam point cut small stops and slow running to 300 minutes. A torque check on the capper at every changeover brings rejects down to 140 cases.

Filler OEE after twelve months of TPM, same planned time (illustrative)
StepCalculationResult
Run time4,500 - 225 - 1804,095 min
Availability4,095 / 4,50091.0%
Cases made(4,095 - 300) / 0.5 = 3,795 / 0.57,590
Performance3,795 / 4,09592.7%
Good cases7,590 - 140 rejects7,450
Quality7,450 / 7,59098.2%
OEE91.0% x 92.7% x 98.2%82.8%

Check it the other way: 7,450 x 0.5 / 4,500 = 3,725 / 4,500 = 82.8%. The gain is 7,450 - 6,757 = 693 more good cases a week from the same planned hours, which is 693 x 0.5 = 346.5 minutes, or 82.8% - 75.1% = 7.7 points of the 4,500.

Two things to take from the numbers. First, no single pillar did it. The breakdown work took 180 minutes a week off breakdowns (405 - 225), and the other changes took off another 166.5: 45 from setup, 87 from small stops and slow running, and 34.5 from rejects (69 fewer cases x 0.5). Together that is the 346.5 minutes of the gain. Second, the extra 693 cases are only worth money if they can be sold or let the line run fewer overtime shifts. Put the gain into the plan before claiming it. The OEE calculator and the downtime cost calculator turn your own figures into the same sums.

How to implement TPM: start on one machine

TPM is a change in who owns the machine, so it is rolled out the way a change in habits is: small, visible, then wider. Most plants follow a sequence like this one.

Starting TPM on one model machine

  1. 1

    Decide and appoint

  2. 2

    Measure the losses

  3. 3

    Pick the model machine

  4. 4

    Clean, tag and close

  5. 5

    Set the standards, start the pillar work

  6. 6

    Review weekly, then spread

Then the next machines, in waves: back to steps 2 to 6

Once the model machine holds its gains, steps 2 to 6 repeat on the next machines, with the model crew teaching.
  1. 1

    Decide and appoint

    The plant manager sponsors it, a TPM lead runs it, and the first two pillar owners (autonomous and planned maintenance) are named. Tell operators plainly why: fewer breakdowns and less firefighting, not fewer people.

  2. 2

    Measure the losses

    Log every stop on the candidate machines for a few weeks with a reason code, and work out OEE and the six big losses. The equipment downtime log and the downtime reason codes template give a standard way to record them.

  3. 3

    Pick the model machine

    Choose one that matters to output, loses a lot of time and has a crew willing to try. A machine that is easy but unimportant proves nothing to the rest of the plant.

  4. 4

    Clean, tag and close

    Run the first clean with the operators and a technician, tag everything, and close the operator tags within days and the maintenance tags as fast as parts allow.

  5. 5

    Set the standards and start the pillar work

    Write the CILR routine and the PM tasks for the machine, train the operators with one-point lessons, and put the first focused improvement on the biggest loss on the loss map.

  6. 6

    Review weekly, then spread

    Review OEE, the loss map and the open tags every week at the machine. When the model machine holds its gains, copy the method to the next machines in waves, with the model crew teaching.

How long it takes depends on the plant. Our pillar plans give the first model area 90 days; spreading TPM across a whole site takes years, not months. TPM launch: year one deployment sets out one way to sequence the pillars over the first year, and the model area guide covers the expansion waves.

TPM vs RCM vs preventive maintenance, and TPM vs TQM

These terms get mixed up because they overlap. Preventive maintenance is a kind of task. Reliability-centred maintenance (RCM) is a method for choosing tasks. TPM is a way of organising the whole plant around its equipment, and it uses both.

Preventive maintenance, TPM and reliability-centred maintenance compared
Preventive maintenance (PM)Total productive maintenance (TPM)Reliability-centred maintenance (RCM)
What it isPlanned work at a set interval of time or use, before failureA plant-wide system in which operators, maintenance and managers share care of the equipmentA structured analysis that decides, failure mode by failure mode, which maintenance task each asset should get
Question it answersWhen is this task due?How do we stop losing output to the machines?What is the right task for this failure, if any?
Who drives itThe maintenance teamEveryone, with operators doing the daily careReliability engineers with maintenance and operators in the analysis
Unit of workOne task on one assetOne machine or area at a time, across eight pillarsOne failure mode on one critical asset
Main outputA PM schedule and PM complianceHigher OEE, fewer breakdowns, operators who own their machinesA maintenance plan per asset: PM, condition check, redesign or run to failure
Where it comes fromLong-standing maintenance practiceSeiichi Nakajima and JIPM, JapanF. Stanley Nowlan and Howard Heap, Reliability-Centered Maintenance (1978), from the US airlines; SAE JA1011 sets the criteria an RCM process must meet

In practice they fit together. The planned maintenance pillar of TPM runs the PM schedule, and many plants use RCM to choose the tasks on their most critical machines. [Preventive maintenance](/learn/preventive-maintenance) works a PM schedule out in numbers, and [reliability-centred maintenance](/learn/reliability-centered-maintenance) covers the seven RCM questions.

TPM vs TQM. Total quality management aims at quality across the whole company, from design to service, and is run through the management system. TPM aims at the equipment and is run through the pillars at the machine. They share the habits of everyone taking part and of working on causes, and the quality maintenance pillar is where they meet: the machine conditions that make defects are found and held.

TPM in lean manufacturing. Lean cuts inventory between processes, and with little stock to cover a stop, a machine that breaks down stops the next process within minutes. TPM is the part of lean that makes machines dependable enough for just-in-time flow. The lean tools hub shows where TPM and OEE sit beside 5S, SMED, kanban and the rest.

TPM and predictive maintenance. A predictive task (vibration, oil analysis, thermography) is triggered by a measured condition rather than by the calendar. It belongs inside the planned maintenance pillar. Preventive vs predictive maintenance compares the trigger types.

Running TPM day to day: paper, CMMS and software

TPM has two record-keeping halves. The maintenance side (the asset register, PM work orders, parts and repair history) usually lives in a computerized maintenance management system (CMMS). The operator side (CILR checks, abnormality tags, small stops, one-point lessons, improvement actions) often lives on paper at the machine, which works until tags go missing and nobody can tell which checks were skipped.

LeanSuite handles the operator side and works alongside your CMMS; it is not a CMMS. Operators run visual CILR checklists on a tablet, with photos where a step requires one. An abnormality found during the check becomes an autonomous maintenance tag, routed to maintenance and tracked until the fix is done. Operators log micro-stops in one tap with a reason. LeanSuite does not connect to machines, so stop and OEE figures are what operators enter. A recurring issue can be turned into a kaizen. TPM software sets out, pillar by pillar, what a tool should do and where a CMMS ends.

Common TPM mistakes

  • Calling it a maintenance program. If production managers do not give operators time for the daily care, TPM is a maintenance initiative with a new name, and it stalls.
  • Starting everywhere at once. A plant-wide launch spreads the TPM lead and the technicians thin. One model machine that clearly works convinces more people than twenty half-done ones.
  • Hanging tags and not closing them. Operators stop raising tags they never see fixed. Track open tags by age and review them at the machine every week.
  • Handing over tasks without training. An operator asked to check chain tension needs to be shown what correct looks like, with a limit and a one-point lesson, and checked on the skills matrix.
  • Using OEE to rank crews. OEE is for finding losses on one machine. Comparing it between machines or shifts that log stops differently starts arguments about the number instead of work on the losses.
  • Counting activity instead of losses. Audits done and tags hung show effort. Breakdown minutes, small stops and rejects on the loss map show results.
  • Using TPM to cut maintenance headcount. If technicians expect TPM to cost them their jobs, they will not train operators. Move freed hours to planned work and improvement.
  • Skipping 5S. Cleaning and inspection standards cannot hold on a machine buried in clutter, with tools and parts that have no home.

TPM software

Run operator-side TPM in LeanSuite

Visual CILR routines on a tablet, abnormality tags routed to maintenance, and a skills matrix that keeps uncertified operators off critical tasks.

Free templates and tools

FAQ

Questions about total productive maintenance (TPM)

  1. TPM stands for total productive maintenance. It is a way of running a plant in which operators, maintenance and managers share responsibility for keeping equipment in good condition, aiming for zero breakdowns, zero defects and zero accidents. In computing TPM means a trusted platform module, which is unrelated.

  2. Operators look after their own machines every day by cleaning, inspecting, lubricating and tightening them and tagging anything abnormal, while maintenance plans the bigger work and fixes the causes of repeat failures. Everyone works from the same list of losses, measured with OEE, so the machine breaks down less and makes more good parts.

  3. Autonomous maintenance, planned maintenance, focused improvement, quality maintenance, early equipment management, training and education, safety, health and environment, and office TPM. They stand on a 5S foundation. Seiichi Nakajima's book describes five core activities; the eight-pillar model grew out of them later, and names vary a little between plants.

  4. Initial cleaning and inspection; removing sources of contamination and hard-to-reach areas; setting cleaning, lubrication and inspection standards; general inspection; autonomous inspection; standardization; and autonomous management. A team moves to the next step only when the current one holds, usually confirmed by a step audit.

  5. OEE is the main measure of TPM. OEE = availability x performance x quality, and the time lost is split into the six big losses: breakdowns, setup and adjustment, small stops, reduced speed, start-up rejects and production rejects. Each loss has a TPM pillar that goes after it, so the loss map shows which pillar to work on first.

  6. Preventive maintenance is a kind of task: planned work at a set interval of time or use, done mostly by maintenance. TPM is a plant-wide system in which operators do the daily care and maintenance, engineering and management each have a part. Preventive maintenance is one of the tools inside TPM's planned maintenance pillar.

  7. Reliability-centred maintenance (RCM) is an analysis that decides, failure mode by failure mode, which maintenance task each critical asset should get. It was described by Nowlan and Heap in 1978 for the airlines. TPM organises the whole plant, operators included, around equipment care and losses. Many plants use RCM inside TPM's planned maintenance pillar for their most critical machines.

  8. Total quality management (TQM) aims at quality across the whole company and runs through the management system. TPM aims at equipment and runs through pillars at the machine. They share company-wide involvement and work on causes, and TPM's quality maintenance pillar is where they meet, by finding and holding the machine conditions that prevent defects.

  9. On one model machine, not everywhere at once. Appoint a sponsor and a TPM lead, log the machine's stops to work out OEE and the six big losses, run a first clean with the operators and a technician, tag every abnormality and close the tags fast, write the CILR routine and PM tasks, then review the losses weekly. Spread to the next machines only when the first one holds.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.