Total productive maintenance (TPM): meaning, the 8 pillars, autonomous maintenance, OEE and a worked example
Short answer
Total productive maintenance (TPM) is a way of running a plant in which operators, maintenance and managers share the job of keeping machines in good condition, aiming for zero breakdowns, zero defects and zero accidents. Operators take on the daily cleaning, checks and lubrication of their own machines, and maintenance moves to planned work and to removing the causes of failure.
TPM stands for total productive maintenance. It grew up in Japanese plants and was set out by Seiichi Nakajima of the Japan Institute of Plant Maintenance (JIPM). It is organised as eight pillars on a 5S foundation: autonomous maintenance, planned maintenance, focused improvement, quality maintenance, early equipment management, training and education, safety, health and environment, and office TPM. Progress is measured with OEE (availability x performance x quality) and the six big losses it breaks into. Plants start TPM on one model machine, prove it there, then spread it.
Last reviewed:
What is TPM (total productive maintenance)?
TPM means total productive maintenance. Each word does work. Total: everyone who touches the machine has a part, from the operator on nights to the plant manager. Productive: the target is output, so a machine that runs all shift at two thirds of its rated speed is a TPM problem even though it never broke. Maintenance: the means is keeping equipment in the condition it was designed to run in.
The old split says operators run the machine and maintenance fixes it. TPM ends that split. The operator who stands at the filler for eight hours is the first to hear a new noise, see a drip or feel a guard working loose, so the operator does the basic care: clean, inspect, lubricate and tighten, and tag anything abnormal. The technicians, freed from small jobs, plan the bigger maintenance work and go after the reasons machines fail.
| Role | Before TPM | With TPM |
|---|---|---|
| Operator | Runs the machine and calls maintenance when it stops | Does the daily clean, inspection, lubrication and tightening, tags abnormalities, and makes the small fixes they are trained for |
| Maintenance technician | Spends most of the shift on breakdowns | Plans and does the preventive work, fixes the causes behind repeat failures, trains operators and works the maintenance tags |
| Engineering | Buys and installs new machines | Feeds what the plant learned about failures and cleaning into the design of the next machine |
| Plant and area managers | Judge maintenance on cost and response time | Give time for cleaning and training, own the pillar plans and review the losses each week |
TPM comes from Japan. Seiichi Nakajima of the Japan Institute of Plant Maintenance (JIPM) set it out in a short book, published in English as Introduction to TPM (Productivity Press, 1988). The first JIPM award for it is usually credited to Nippondenso, a Toyota parts supplier, in 1971. Our summary of Nakajima's book covers what it argues and where it has dated.
TPM has other meanings outside the plant. In computing it is a trusted platform module, a security chip in a PC. On the shop floor it always means total productive maintenance, and you will also see it written as total productivity maintenance or total product maintenance. Same idea.
The 8 pillars of TPM
TPM work is split into pillars, each with an owner, a plan and its own measures. Nakajima's book describes five core activities; the eight-pillar model most plants use today grew out of them later. The pillars stand on a foundation of 5S, because a machine you cannot see clearly cannot be inspected.
| Pillar | Also called | The job | First move on the floor | Free plan or template |
|---|---|---|---|---|
| Autonomous maintenance | Jishu hozen, AM | Operators keep their own machines at basic condition and spot abnormalities early | A first clean of one machine with the operators and a technician, tagging every abnormality | AM 90-day plan |
| Planned maintenance | Professional maintenance, PM pillar | Maintenance plans preventive and predictive work from the failure history and cuts breakdowns | List the failures on the model machine and write PM tasks with limits for the ones that repeat | Professional maintenance 90-day plan |
| Focused improvement | Kobetsu kaizen | Small cross-functional teams remove the biggest losses one at a time | Pick the largest loss on the loss map and run one improvement on it | Focused improvement 90-day plan |
| Quality maintenance | Hinshitsu hozen | Find the machine conditions that cause defects, then set and hold them | Link each defect type to the settings and parts that cause it | Quality control 90-day plan |
| Early equipment management | Early management | New machines and parts are designed to be easy to run, clean, inspect and change over | Write down what the current machine taught you before the next one is specified | Early equipment management 90-day plan |
| Training and education | People development | Operators and technicians get the skills the other pillars ask of them | A skills matrix for the model machine and one-point lessons for each new task | People development 90-day plan |
| Safety, health and environment | SHE | No accidents, no harm to health, no harm to the environment from the equipment or the work on it | Make every cleaning and inspection point safe to reach before operators are asked to use it | Safety pillar 90-day plan |
| Office TPM | TPM in administration | Planning, purchasing, stores and other support teams cut the losses that hold the line up | Count the hours lost waiting for parts, plans or approvals on the model machine | None yet; start from the loss list |
Pillar names vary a little between books and between plants; some split safety and environment, some add cost deployment. Our [model area guide](/learn/model-area) explains how each pillar starts in one area and then spreads, with all ten 90-day plans. [The 8 pillars of TPM explained](/blogs/eight-pillars-tpm-manufacturing-guide) covers each pillar in more depth.
The pillars depend on each other. Autonomous maintenance needs the training pillar, or operators are handed tasks they were never shown. Planned maintenance needs the tags operators raise, or it plans from guesswork. Focused improvement needs the loss data the first two produce. That is why most plants start with autonomous and planned maintenance on the same machine.
Autonomous maintenance: the 7 steps
Autonomous maintenance is the pillar most people picture when they hear TPM. Operators take over the basic care of their machine in seven steps, and a team moves to the next step only when the current one holds, usually checked by an audit.
The seven steps of autonomous maintenance
- 1Step 1
Initial cleaning and inspection
- 2Step 2
Remove contamination sources and hard-to-reach areas
- 3Step 3
Set cleaning, lubrication and inspection standards
- 4Step 4
General inspection
- 5Step 5
Autonomous inspection
- 6Step 6
Standardization
- 7Step 7
Autonomous management
- 1
Initial cleaning and inspection
Operators and a technician clean the machine down to bare metal, together. Cleaning is how they find things: every leak, loose bolt, crack, worn part and hard-to-reach point gets a tag and goes on the tag log.
- 2
Remove sources of contamination and hard-to-reach areas
Stop the dirt at its source (a split seal, a spill from the conveyor above, a missing cover), and make every point that has to be cleaned, checked or greased easy to reach.
- 3
Set cleaning, lubrication and inspection standards
Write down what is cleaned, lubricated and checked, how, with what, how often and in how many minutes. The first version is provisional; operators test the times on a real shift.
- 4
General inspection
Technicians teach operators how each main system works (drives, pneumatics, hydraulics, electrics, fasteners) and what failure looks like, often through one-point lessons. Operators then inspect each system as part of the daily check.
- 5
Autonomous inspection
Operators run the full inspection on their own, from a check sheet they helped write, and the cleaning and inspection standards are merged into one routine that fits the time available.
- 6
Standardization
The routine is extended to the area around the machine: tools, spare parts, materials and quality checks each get a standard place and a standard check.
- 7
Autonomous management
Operators run and improve their own standards, track their machine's losses and take part in improvement work, with maintenance as the support behind them.
The daily routine that comes out of steps 3 to 5 is usually called CILR or CILT (clean, inspect, lubricate, retighten or tighten). CILR in manufacturing shows a filled checklist, and the autonomous maintenance example walks one machine through the steps.
What a first clean turns up (illustrative)
A crew of three operators and one technician spends two hours on the first clean of a bottle filler. They hang 38 tags. Each tag is sorted by who can fix it: the operator, or maintenance.
| What was found | Tags | Operator can fix | Needs maintenance |
|---|---|---|---|
| Leaks (oil, air, product) | 7 | 3 | 4 |
| Loose or missing fasteners | 9 | 9 | 0 |
| Sources of contamination | 6 | 4 | 2 |
| Points hard to clean, inspect or lubricate | 8 | 6 | 2 |
| Worn or damaged parts | 5 | 1 | 4 |
| Safety hazards | 3 | 1 | 2 |
| Total | 38 | 24 | 14 |
Check the totals both ways: 7 + 9 + 6 + 8 + 5 + 3 = 38, and 24 + 14 = 38. Four weeks later all 24 operator tags and 9 of the 14 maintenance tags are closed, 33 of 38 or 86.8%. The other 5 wait for parts or a planned stop, and they stay open on the [TPM tag log](/templates/tpm-tag-log) until they are done.
The closing matters more than the hanging. Operators judge TPM by whether their tags get fixed. If the maintenance tags from the first clean are still open two months later, the second clean finds fewer tags because nobody bothers. The AM step audit checks whether a team has really finished a step before it moves on.
TPM and OEE: how TPM is measured
TPM is measured by what the machine produces, not by how busy maintenance is. The main measure is overall equipment effectiveness (OEE): OEE = availability x performance x quality. Availability is the share of planned time the machine ran. Performance is how fast it ran against its ideal rate. Quality is the share of output that was good first time. The OEE calculation guide works through the formula with three examples.
Nakajima split the lost time into six big losses, and each one has a pillar that goes after it. That map tells a plant which pillar to put effort into first: the one that owns the largest loss.
| Loss | OEE factor | Main pillar | Typical first countermeasure |
|---|---|---|---|
| Breakdowns (equipment failure) | Availability | Autonomous and planned maintenance | Restore basic conditions, then PM tasks with limits on the parts that fail |
| Setup and adjustment | Availability | Focused improvement | SMED: move setup work outside the stop and remove trial-and-error adjustment |
| Small stops and idling | Performance | Autonomous maintenance, focused improvement | Clean the sensors and fix the jam points the operators know about |
| Reduced speed | Performance | Focused improvement, planned maintenance | Find out why the machine is set below its ideal rate and remove that reason |
| Start-up rejects | Quality | Quality maintenance | A standard for settings at start-up and after each changeover |
| Production rejects | Quality | Quality maintenance | Tie each defect to a machine condition and add that condition to the daily check |
Small stops are the loss most often missed, because they are too short to be logged. The [six big losses worksheet](/templates/six-big-losses-worksheet) sorts a week of stops into the six, and [the six big losses in lean manufacturing](/blogs/six-big-losses-lean-manufacturing) explains each one.
Other measures sit beside OEE. Mean time between failures (MTBF) shows whether breakdowns are getting rarer, and mean time to repair (MTTR) whether they are getting shorter; the MTBF and MTTR calculator works both out from a downtime log. PM compliance shows whether the planned work happens on time (see preventive maintenance). Tags raised and closed, and the number of machines through each autonomous maintenance step, show whether the pillars are moving.
A TPM example, worked out in numbers
This example is illustrative. A bottle filler is the model machine. It is planned to run two shifts of 450 minutes, five days a week: 2 x 450 x 5 = 4,500 minutes a week. Its ideal cycle time is 0.5 minutes a case, so at full speed with no stops it would make 9,000 cases a week. The team logs one baseline week.
| Step | Calculation | Result |
|---|---|---|
| Planned production time | 2 shifts x 450 min x 5 days | 4,500 min |
| Breakdowns | 9 stops averaging 45 min | 405 min |
| Setup and adjustment | 5 changeovers x 45 min | 225 min |
| Run time | 4,500 - 405 - 225 | 3,870 min |
| Availability | 3,870 / 4,500 | 86.0% |
| Cases made | Counted | 6,966 |
| Performance | 6,966 x 0.5 min / 3,870 min = 3,483 / 3,870 | 90.0% |
| Good cases | 6,966 - 209 rejects | 6,757 |
| Quality | 6,757 / 6,966 | 97.0% |
| OEE | 86.0% x 90.0% x 97.0% | 75.1% |
Check it the other way: good cases x ideal cycle time / planned time = 6,757 x 0.5 / 4,500 = 3,378.5 / 4,500 = 75.1%.
Next, turn the lost 24.9% into minutes and give each loss an owner. This is the loss map the pillars work from.
| Loss | Minutes | Share of planned time | Pillar that owns it |
|---|---|---|---|
| Breakdowns | 405 | 9.0% | Autonomous and planned maintenance |
| Setup and adjustment | 225 | 5.0% | Focused improvement (SMED) |
| Small stops and reduced speed | 3,870 - 3,483 = 387 | 8.6% | Autonomous maintenance, focused improvement |
| Rejects | 209 x 0.5 = 104.5 | 2.3% | Quality maintenance |
| Total lost | 1,121.5 | 24.9% |
Check: 405 + 225 + 387 + 104.5 = 1,121.5 minutes, and 4,500 - 1,121.5 = 3,378.5 minutes of good output, the same 75.1% as above.
Over the next twelve months the pillars work on the filler. The first clean and the tags close out leaks and loose guide rails; the operators' CILR routine and new PM tasks on the capper drive bring breakdowns down to 5 stops, 225 minutes. A SMED event cuts each changeover from 45 to 36 minutes, so 5 changeovers take 180. Cleaning the photo-eyes every shift and fixing the infeed jam point cut small stops and slow running to 300 minutes. A torque check on the capper at every changeover brings rejects down to 140 cases.
| Step | Calculation | Result |
|---|---|---|
| Run time | 4,500 - 225 - 180 | 4,095 min |
| Availability | 4,095 / 4,500 | 91.0% |
| Cases made | (4,095 - 300) / 0.5 = 3,795 / 0.5 | 7,590 |
| Performance | 3,795 / 4,095 | 92.7% |
| Good cases | 7,590 - 140 rejects | 7,450 |
| Quality | 7,450 / 7,590 | 98.2% |
| OEE | 91.0% x 92.7% x 98.2% | 82.8% |
Check it the other way: 7,450 x 0.5 / 4,500 = 3,725 / 4,500 = 82.8%. The gain is 7,450 - 6,757 = 693 more good cases a week from the same planned hours, which is 693 x 0.5 = 346.5 minutes, or 82.8% - 75.1% = 7.7 points of the 4,500.
Two things to take from the numbers. First, no single pillar did it. The breakdown work took 180 minutes a week off breakdowns (405 - 225), and the other changes took off another 166.5: 45 from setup, 87 from small stops and slow running, and 34.5 from rejects (69 fewer cases x 0.5). Together that is the 346.5 minutes of the gain. Second, the extra 693 cases are only worth money if they can be sold or let the line run fewer overtime shifts. Put the gain into the plan before claiming it. The OEE calculator and the downtime cost calculator turn your own figures into the same sums.
How to implement TPM: start on one machine
TPM is a change in who owns the machine, so it is rolled out the way a change in habits is: small, visible, then wider. Most plants follow a sequence like this one.
Starting TPM on one model machine
- 1
Decide and appoint
- 2
Measure the losses
- 3
Pick the model machine
- 4
Clean, tag and close
- 5
Set the standards, start the pillar work
- 6
Review weekly, then spread
Then the next machines, in waves: back to steps 2 to 6
- 1
Decide and appoint
The plant manager sponsors it, a TPM lead runs it, and the first two pillar owners (autonomous and planned maintenance) are named. Tell operators plainly why: fewer breakdowns and less firefighting, not fewer people.
- 2
Measure the losses
Log every stop on the candidate machines for a few weeks with a reason code, and work out OEE and the six big losses. The equipment downtime log and the downtime reason codes template give a standard way to record them.
- 3
Pick the model machine
Choose one that matters to output, loses a lot of time and has a crew willing to try. A machine that is easy but unimportant proves nothing to the rest of the plant.
- 4
Clean, tag and close
Run the first clean with the operators and a technician, tag everything, and close the operator tags within days and the maintenance tags as fast as parts allow.
- 5
Set the standards and start the pillar work
Write the CILR routine and the PM tasks for the machine, train the operators with one-point lessons, and put the first focused improvement on the biggest loss on the loss map.
- 6
Review weekly, then spread
Review OEE, the loss map and the open tags every week at the machine. When the model machine holds its gains, copy the method to the next machines in waves, with the model crew teaching.
How long it takes depends on the plant. Our pillar plans give the first model area 90 days; spreading TPM across a whole site takes years, not months. TPM launch: year one deployment sets out one way to sequence the pillars over the first year, and the model area guide covers the expansion waves.
TPM vs RCM vs preventive maintenance, and TPM vs TQM
These terms get mixed up because they overlap. Preventive maintenance is a kind of task. Reliability-centred maintenance (RCM) is a method for choosing tasks. TPM is a way of organising the whole plant around its equipment, and it uses both.
| Preventive maintenance (PM) | Total productive maintenance (TPM) | Reliability-centred maintenance (RCM) | |
|---|---|---|---|
| What it is | Planned work at a set interval of time or use, before failure | A plant-wide system in which operators, maintenance and managers share care of the equipment | A structured analysis that decides, failure mode by failure mode, which maintenance task each asset should get |
| Question it answers | When is this task due? | How do we stop losing output to the machines? | What is the right task for this failure, if any? |
| Who drives it | The maintenance team | Everyone, with operators doing the daily care | Reliability engineers with maintenance and operators in the analysis |
| Unit of work | One task on one asset | One machine or area at a time, across eight pillars | One failure mode on one critical asset |
| Main output | A PM schedule and PM compliance | Higher OEE, fewer breakdowns, operators who own their machines | A maintenance plan per asset: PM, condition check, redesign or run to failure |
| Where it comes from | Long-standing maintenance practice | Seiichi Nakajima and JIPM, Japan | F. Stanley Nowlan and Howard Heap, Reliability-Centered Maintenance (1978), from the US airlines; SAE JA1011 sets the criteria an RCM process must meet |
In practice they fit together. The planned maintenance pillar of TPM runs the PM schedule, and many plants use RCM to choose the tasks on their most critical machines. [Preventive maintenance](/learn/preventive-maintenance) works a PM schedule out in numbers, and [reliability-centred maintenance](/learn/reliability-centered-maintenance) covers the seven RCM questions.
TPM vs TQM. Total quality management aims at quality across the whole company, from design to service, and is run through the management system. TPM aims at the equipment and is run through the pillars at the machine. They share the habits of everyone taking part and of working on causes, and the quality maintenance pillar is where they meet: the machine conditions that make defects are found and held.
TPM in lean manufacturing. Lean cuts inventory between processes, and with little stock to cover a stop, a machine that breaks down stops the next process within minutes. TPM is the part of lean that makes machines dependable enough for just-in-time flow. The lean tools hub shows where TPM and OEE sit beside 5S, SMED, kanban and the rest.
TPM and predictive maintenance. A predictive task (vibration, oil analysis, thermography) is triggered by a measured condition rather than by the calendar. It belongs inside the planned maintenance pillar. Preventive vs predictive maintenance compares the trigger types.
Running TPM day to day: paper, CMMS and software
TPM has two record-keeping halves. The maintenance side (the asset register, PM work orders, parts and repair history) usually lives in a computerized maintenance management system (CMMS). The operator side (CILR checks, abnormality tags, small stops, one-point lessons, improvement actions) often lives on paper at the machine, which works until tags go missing and nobody can tell which checks were skipped.
LeanSuite handles the operator side and works alongside your CMMS; it is not a CMMS. Operators run visual CILR checklists on a tablet, with photos where a step requires one. An abnormality found during the check becomes an autonomous maintenance tag, routed to maintenance and tracked until the fix is done. Operators log micro-stops in one tap with a reason. LeanSuite does not connect to machines, so stop and OEE figures are what operators enter. A recurring issue can be turned into a kaizen. TPM software sets out, pillar by pillar, what a tool should do and where a CMMS ends.
Common TPM mistakes
- Calling it a maintenance program. If production managers do not give operators time for the daily care, TPM is a maintenance initiative with a new name, and it stalls.
- Starting everywhere at once. A plant-wide launch spreads the TPM lead and the technicians thin. One model machine that clearly works convinces more people than twenty half-done ones.
- Hanging tags and not closing them. Operators stop raising tags they never see fixed. Track open tags by age and review them at the machine every week.
- Handing over tasks without training. An operator asked to check chain tension needs to be shown what correct looks like, with a limit and a one-point lesson, and checked on the skills matrix.
- Using OEE to rank crews. OEE is for finding losses on one machine. Comparing it between machines or shifts that log stops differently starts arguments about the number instead of work on the losses.
- Counting activity instead of losses. Audits done and tags hung show effort. Breakdown minutes, small stops and rejects on the loss map show results.
- Using TPM to cut maintenance headcount. If technicians expect TPM to cost them their jobs, they will not train operators. Move freed hours to planned work and improvement.
- Skipping 5S. Cleaning and inspection standards cannot hold on a machine buried in clutter, with tools and parts that have no home.
TPM software
Run operator-side TPM in LeanSuite
Visual CILR routines on a tablet, abnormality tags routed to maintenance, and a skills matrix that keeps uncertified operators off critical tasks.
Go deeper
This page is the short version. These guides cover each part in full.
- The 8 Pillars of TPM ExplainedEach of the eight pillars on its own, and which order of pillars works best.
- 7 Steps of Autonomous Maintenance: The TPM Pillar ExplainedEach autonomous maintenance step in detail, with what the audit at the end of each step checks.
- TPM Launch: Year One Deployment GuideA quarter-by-quarter plan for the first year of TPM, pillar by pillar.
- CILR: Clean Inspect Lubricate Retighten in ManufacturingThe daily operator routine that autonomous maintenance produces, with a worked checklist.
- The Six Big Losses in Lean ManufacturingEach of the six losses explained, with how to spot it on the floor.
All our articles on this subject are in the tpm and maintenance topic.
Free templates and tools
- Autonomous maintenance (CILR) checklist20 clean, inspect, lubricate and retighten checks with a box per day, an abnormality log and sign-off.
- TPM tag logEvery abnormality tag with type, who fixes it, priority and dates, with days open and counts by type and week.
- Autonomous maintenance step auditCriteria for each of the seven autonomous maintenance steps, scored 0 to 2, with the step result and the decision to move on.
- Six big losses worksheetWhere a machine's planned time goes: the six big losses in minutes, ranked, with A, P, Q and OEE worked out.
- OEE tracking sheetOne row per shift for a week. The Excel version works out availability, performance, quality and OEE and charts the week.
- Autonomous maintenance 90-day model area planAM steps 0 to 3 on one model machine in 13 weeks, a KPI board, the day-90 gate and expansion waves for months 4 to 12.
- Professional maintenance (PM) 90-day model area planThirteen weeks from breakdown analysis to a running PM calendar on one model machine, a KPI board, the day-90 gate and expansion waves.
- Focused improvement 90-day model area planThirteen weeks from the loss Pareto to standardized fixes on one model line, a KPI board, the day-90 gate and expansion waves.
- SMED changeover worksheetChangeover steps with times, internal or external, what can move, ideas and before/after totals.
- One point lesson (OPL) templateOne topic on one page: wrong way and right way pictures, checkable key points, the standard it belongs to and a sign-off record.
- Equipment downtime log (MTTR and MTBF)A breakdown and downtime log, with MTTR, MTBF and downtime by machine and cause worked out in Excel.
- Preventive maintenance checklist templateA PM checklist per machine with readings and sign-off, and a PM schedule that works out the next due date.
- OEE calculatorOverall equipment effectiveness from shift time, downtime, ideal cycle time and part counts.
- MTBF and MTTR calculatorMean time between failures, mean time to repair and availability from operating time, failures and repair time.
- SMED changeover calculatorTime saved by moving changeover steps from internal to external, capacity freed per week and the smaller batch it allows.
- Downtime cost calculatorWhat an hour, an event and a year of unplanned downtime cost, from lost output, idle labour, scrap and overtime.
- Maintenance strategy selectorAnswer the RCM questions for one failure mode and get the maintenance strategy, the reasoning and the check or test interval.
Key terms
- Total productive maintenance (TPM)
- Eight pillars of TPM
- Autonomous maintenance
- CILR (clean, inspect, lubricate, retighten)
- F-tag
- Zero breakdowns (five countermeasures)
- Overall equipment effectiveness (OEE)
- Six big losses
- Single-minute exchange of die (SMED)
- Planned maintenance
- Preventive maintenance (PM)
- Reliability-centered maintenance (RCM)
- Mean time between failures (MTBF)
- Mean time to repair (MTTR)
Doing this in LeanSuite
Autonomous Maintenance
Rolls out visual CILR (clean, inspect, lube, retighten) checklists so operators catch small abnormalities before they cause downtime.
See Autonomous MaintenanceCILR Checklists
Build visual CILR checklists so operators clean, inspect, lubricate and re-tighten on schedule and catch problems before they become breakdowns.
See CILR ChecklistsAutonomous maintenance tags
Autonomous maintenance tags in LeanSuite let operators flag abnormalities on their own equipment during daily CILR checks, and every tag is tracked until the fix is done.
See Autonomous maintenance tagsMicro-stops
Log the brief jams your ERP and MES never report, and see which micro-stops cost the most so you can win back OEE.
See Micro-stops
See it on your own lines
Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.
FAQ
Questions about total productive maintenance (TPM)
TPM stands for total productive maintenance. It is a way of running a plant in which operators, maintenance and managers share responsibility for keeping equipment in good condition, aiming for zero breakdowns, zero defects and zero accidents. In computing TPM means a trusted platform module, which is unrelated.
Operators look after their own machines every day by cleaning, inspecting, lubricating and tightening them and tagging anything abnormal, while maintenance plans the bigger work and fixes the causes of repeat failures. Everyone works from the same list of losses, measured with OEE, so the machine breaks down less and makes more good parts.
Autonomous maintenance, planned maintenance, focused improvement, quality maintenance, early equipment management, training and education, safety, health and environment, and office TPM. They stand on a 5S foundation. Seiichi Nakajima's book describes five core activities; the eight-pillar model grew out of them later, and names vary a little between plants.
Initial cleaning and inspection; removing sources of contamination and hard-to-reach areas; setting cleaning, lubrication and inspection standards; general inspection; autonomous inspection; standardization; and autonomous management. A team moves to the next step only when the current one holds, usually confirmed by a step audit.
OEE is the main measure of TPM. OEE = availability x performance x quality, and the time lost is split into the six big losses: breakdowns, setup and adjustment, small stops, reduced speed, start-up rejects and production rejects. Each loss has a TPM pillar that goes after it, so the loss map shows which pillar to work on first.
Preventive maintenance is a kind of task: planned work at a set interval of time or use, done mostly by maintenance. TPM is a plant-wide system in which operators do the daily care and maintenance, engineering and management each have a part. Preventive maintenance is one of the tools inside TPM's planned maintenance pillar.
Reliability-centred maintenance (RCM) is an analysis that decides, failure mode by failure mode, which maintenance task each critical asset should get. It was described by Nowlan and Heap in 1978 for the airlines. TPM organises the whole plant, operators included, around equipment care and losses. Many plants use RCM inside TPM's planned maintenance pillar for their most critical machines.
Total quality management (TQM) aims at quality across the whole company and runs through the management system. TPM aims at equipment and runs through pillars at the machine. They share company-wide involvement and work on causes, and TPM's quality maintenance pillar is where they meet, by finding and holding the machine conditions that prevent defects.
On one model machine, not everywhere at once. Appoint a sponsor and a TPM lead, log the machine's stops to work out OEE and the six big losses, run a first clean with the operators and a technician, tag every abnormality and close the tags fast, write the CILR routine and PM tasks, then review the losses weekly. Spread to the next machines only when the first one holds.
Related guides and tools
- TPM and maintenance: every guide, template and calculator on keeping equipment running
- Preventive maintenance: the types, a PM schedule worked out in numbers and PM compliance
- What a CMMS is and how maintenance and CI teams use one alongside TPM
- TPM 8 pillars poster: free printable for the line or the TPM board
- TPM software: what to look for across the 8 pillars, and where a CMMS ends
- Skills gap analysis software: who is trained on which task
More method guides
- The 6 Ms of production
- Poka-yoke
- Model area 90-day plans
- Moving from Excel to one system
- Reducing machine downtime: a worked month
- Andon
- Cycle time vs lead time, worked through
- Root cause analysis
- How many operators a line needs
- Reducing scrap and rework: a worked month
- Unsafe acts and unsafe conditions
- Just culture
- Stop-work authority
- Material review board (MRB)
- Nonconformance and NCRs
- Problem solving methods
- Quad chart
- OEE calculation
- Quality assurance vs quality control
- SOP meaning and format
- Job hazard analysis
- Near miss reporting
- Fishbone diagram
- Pareto chart
- Histogram
- Control chart
- What is a gemba walk
- What is lead time
- What is operational excellence
- How to improve product quality
- Preventive vs predictive maintenance
- Kanban
- FMEA
- PDSA cycle
- Safety moments
- Just-in-time manufacturing
- Kaizen
- 5S
- Total quality management (TQM)
- CAPA (corrective and preventive action)
- Layered process audit (LPA)
- Lean tools
- Lockout tagout (LOTO)
- A3 problem solving
- Preventive maintenance
- APQP
- High reliability organization (HRO)
- Manufacturing KPIs
- Quality metrics
- Practical problem solving
- CMMS
- Risk assessment
- Production efficiency
- Reliability-centered maintenance (RCM)