Practical guide · Quality management

What is APQP? The five phases, the gates, and APQP vs PPAP

Short answer

APQP, advanced product quality planning, is the automotive method for planning a new part and the process that makes it in five phases, each closed by a gate review, so every customer requirement is met before production starts. PPAP is its approval step.

APQP stands for advanced product quality planning. It is a structured way to launch a new or changed part: a cross-functional team works through five phases (plan and define the program, product design and development, process design and development, product and process validation, then feedback, assessment and corrective action) and checks the deliverables of each at a gate before the next one is committed. The outputs are the documents and proofs a customer expects at launch: the FMEAs, the process flow, the control plan, gauge studies, capability studies and the PPAP submission. The method was written by Ford, General Motors and Chrysler and is published by AIAG; IATF 16949 expects a launch process like it, and aerospace has its own version in AS9145. APQP is the plan for the whole launch. PPAP, the production part approval process, is the step near the end of phase 4 where the supplier proves the plan worked and the customer approves the part.

Last reviewed:

What APQP means

APQP is short for advanced product quality planning. Advanced means early: the quality work is done while the part is still being designed and the line is still being built, not after the first bad batch. Product quality planning means the team decides up front what the customer needs, which features matter most, how each one will be made and checked, and what proof the customer will see before the first shipment.

Ford, General Motors and Chrysler wrote the method together in the late 1980s and early 1990s so that their suppliers would plan a launch one way instead of three. The Automotive Industry Action Group (AIAG) published it in 1994 as the Advanced Product Quality Planning and Control Plan reference manual. The 2008 second edition is the one most supplier manuals still cite. AIAG has revised it since, so ask which edition your customer works to.

APQP is a planning framework, not a certificate: there is no APQP certification for a plant the way there is for IATF 16949. What customers check is that each launch followed a documented plan and produced the required outputs. IATF 16949:2016, the automotive quality management standard, asks for a design and development process (clause 8.3), the customer's product approval process (clause 8.3.4.4) and a control plan (clause 8.5.1.1, with the contents in Annex A), which is why automotive suppliers run APQP whether or not the customer names it.

APQP and the other AIAG core tools
Core toolWhat it doesWhere it sits in APQPOur page
APQPPlans the whole launch in five phases with gate reviewsThe framework the others sit inAPQP checklist
FMEAFinds how the design or process could fail and ranks the risks before parts are madeDFMEA in phase 2, PFMEA in phase 3FMEA guide
MSAProves the gauges and test equipment give readings you can trust (gauge R&R, bias, stability)Planned in phase 3, results in phase 4MSA study workbook
SPCWatches each important characteristic with a control chart and works out capability (Cpk, Ppk)Capability study in phase 4, SPC in productionControl chart guide
PPAPProves to the customer that the production process makes good parts at the quoted rateEnd of phase 4PPAP checklist

The control plan is the sixth document people group with these. It is written in APQP phases 3 and 4 and is the link between the PFMEA and the checks the floor runs every shift.

The five phases of APQP

The AIAG manual splits a launch into five phases. The outputs of one phase are the inputs of the next, and the phases overlap: process design starts before the product design is fully frozen, because tooling and gauges take months to arrive. Each phase ends at a gate where the team and its managers decide, on evidence, whether to commit the money and time for the next one.

The five phases of APQP

  1. 1Gate 1

    Plan and define the program

  2. 2Gate 2

    Product design and development

  3. 3Gate 3

    Process design and development

  4. 4Gate 4, PPAP

    Product and process validation

  5. 5Ongoing

    Feedback, assessment and corrective action

Lessons learned in phase 5 feed phase 1 of the next program

Phases overlap in time. Each of the first four ends at a gate review; PPAP is submitted and approved inside phase 4. Phase 5 runs for the life of the part.
The five APQP phases: inputs, outputs and who leads
PhaseWhat it starts fromWhat it must produceWho leads
1. Plan and define the programThe customer's request and drawings, its customer-specific requirements, warranty and complaint history on similar parts, the business case and the start of production dateDesign goals, reliability and quality targets, a first bill of materials, a first process flow, a first list of special characteristics, the product assurance plan and a timing plan worked back from start of productionProgram manager with sales, quality and engineering
2. Product design and developmentThe phase 1 goals and the first list of special characteristicsDesign FMEA, design reviews, design verification plan, released drawings and material specifications, the prototype control plan, the agreed special characteristics, the tooling, equipment and gauge needs, and a signed team feasibility commitmentThe design owner: your design team, or the customer for a build-to-print part
3. Process design and developmentThe released design, the special characteristics and the equipment and gauge needsProcess flow diagram, floor plan, characteristics matrix, process FMEA, the pre-launch control plan, work instructions, the MSA plan, the capability study plan and the packaging specificationProcess or manufacturing engineering with quality, production and maintenance
4. Product and process validationThe finished line, production tooling and gauges, trained operators and the pre-launch control planA significant production run, MSA results, initial process (capability) studies, production validation tests, the packaging evaluation, the production control plan, the PPAP submission and the quality planning sign-offQuality engineering with production
5. Feedback, assessment and corrective actionRunning production and the first customer feedbackReduced variation, launch problems closed through corrective action, delivery and customer satisfaction tracked, and lessons learned written down for the next programPlant quality and production, with the program team until the launch is stable

Phase 5 is sometimes called launch, feedback, assessment and corrective action. It does not end at a gate: it runs for the life of the part. The [APQP checklist](/templates/apqp-checklist) lists 43 deliverables across the five phases with an owner, a due date and a late flag for each.

A build-to-print supplier, one that makes a part to the customer's drawing, still runs phase 2. Its job there is to review the drawing for feasibility, agree the special characteristics, take part in the customer's DFMEA where asked, and order tooling and gauges. The design itself belongs to the customer.

APQP gates: what each review asks to see

A gate is a short, scheduled review at the end of a phase. The program team shows the evidence for each deliverable and a manager with the authority to spend money decides one of three things: pass, conditional pass with the open items named, each with an owner and a date, or fail and hold. The AIAG manual describes the phases and their outputs; the names and dates of the gates usually come from your customer's launch process or your own.

What each APQP gate checks
GateThe questionEvidence to put on the tableWhy it usually fails
End of phase 1Do we understand what the customer needs, and can we commit to the date?Requirements and customer-specific requirements read and listed, quality targets, first process flow and special characteristics, a timing plan back from start of production, the team namedCustomer-specific requirements never collected; the timing plan starts from today instead of from start of production
End of phase 2Is the design ready to cut tools for, and can we make it?DFMEA or the customer's released design, drawings and specifications released, special characteristics agreed, feasibility commitment signed, tooling and gauge orders placedThe drawing is still changing; feasibility was signed without the process engineer in the room
End of phase 3Is the process ready to run production parts?Process flow, floor plan, PFMEA, pre-launch control plan, work instructions, MSA and capability plans, packaging specification, tooling on site and tried outTooling or gauges late; the PFMEA was copied from a similar part and nobody walked the new line
End of phase 4Did a real production run prove the process, and has the customer approved the part?Significant production run results, MSA results, initial process studies, validation tests, production control plan, PPAP approval, quality planning sign-offCapability below the customer's target on a special characteristic; parts came from a hand-picked trial run
Phase 5 reviewIs the launch stable, and what do we carry into the next program?Launch containment results, scrap and rework, complaints, delivery, corrective actions closed, lessons learned recordedNever held: the team moves to the next launch and the lessons stay in people's heads

A gate that always passes teaches the team to stop reporting problems. A conditional pass with dated actions is an honest answer; a pass with open items nobody wrote down is not.

APQP vs PPAP

The difference between APQP and PPAP is scope. APQP is the plan for the whole launch, from the customer's request to stable production. PPAP is one deliverable inside it: the evidence package, submitted near the end of phase 4, that shows the customer the plan worked on real production parts. Most of what goes into a PPAP is made earlier in APQP, which is why a launch that skipped the planning finds its PPAP impossible to finish on time.

APQP vs PPAP side by side
APQPPPAP
Full nameAdvanced product quality planningProduction part approval process
What it isA planning framework for a launchAn approval package and the customer's decision on it
WhenFrom the sourcing decision to stable production, and through the life of the part in phase 5Near the end of phase 4, and again after significant changes
Who it is forThe supplier's own team, to launch on time without surprisesThe customer, to approve the part for production shipments
OutputThe FMEAs, control plans, studies and records of every phaseA part submission warrant (PSW) with the evidence the submission level asks for
ReferenceAIAG Advanced Product Quality Planning and Control Plan manualAIAG Production Part Approval Process manual (fourth edition, 2006)
The resultA launch plan and its recordsApproved, interim approval or rejected

The 18 PPAP elements and the APQP phase that makes each one

The AIAG PPAP manual lists 18 elements. The customer decides which are submitted and which are kept on file at your plant. The right-hand column is the useful part for planning: almost every element is made in APQP phases 2 to 4, so it needs an owner and a date long before the submission.

The 18 PPAP elements mapped to APQP phases
#PPAP elementIn plain wordsMade in APQP phase
1Design recordsThe released drawing and specifications the part is made to2
2Authorized engineering change documentsApproved changes not yet shown on the drawing2, and at every change
3Customer engineering approvalThe customer's engineering sign-off, where it asks for one2 to 4
4Design FMEAThe design owner's FMEA2
5Process flow diagramEvery step from material in to part out1 (first version), 3
6Process FMEAHow each step could fail and what prevents or detects it3
7Control planWhat is checked at each step, how, how often and what to do if it fails3 (pre-launch), 4 (production)
8Measurement system analysis studiesGauge R&R and the other MSA studies on the gauges in the control plan3 (plan), 4 (results)
9Dimensional resultsEvery dimension on the drawing measured on sample parts4
10Records of material and performance test resultsMaterial certificates and the design validation tests4
11Initial process studiesCapability (Ppk) on the special characteristics from the production run4
12Qualified laboratory documentationProof the labs that did the tests are qualified for them4
13Appearance approval reportColour, grain and finish approval, for appearance parts only4
14Sample production partsParts from the production run, sent to the customer4
15Master sampleA signed, retained part kept for reference and training4
16Checking aidsFixtures and special gauges used to check the part3 (design), 4 (proved)
17Customer-specific requirementsRecords that the customer's own extra requirements were metAll phases
18Part submission warrant (PSW)The signed summary that declares the submission and asks for approvalEnd of 4

The element names are the standard ones from the AIAG PPAP manual; the descriptions and the phase mapping are ours. Track them with the free [PPAP checklist](/templates/ppap-checklist).

PPAP submission levels

The five PPAP submission levels
LevelWhat is sent to the customer
Level 1The warrant only (plus an appearance approval report for appearance parts)
Level 2The warrant with sample parts and limited supporting data
Level 3The warrant with sample parts and the complete supporting data. The default when the customer does not say
Level 4The warrant and whatever else the customer defines
Level 5The warrant with sample parts and complete data, reviewed at the supplier's plant

At every level the full set of records is kept at the plant. The level only changes what is sent.

Two defaults in the PPAP manual shape the end of phase 4, and your customer can override both. The parts must come from a significant production run: one to eight hours of production on production tooling, gauges, process, materials and people, at least 300 consecutive parts. And the initial process study on each special characteristic is read against Ppk: above 1.67 meets the acceptance criteria, 1.33 to 1.67 may be acceptable after talking to the customer, below 1.33 does not. The process capability calculator works out Cp, Cpk, Pp and Ppk from your readings.

The control plan in APQP

The control plan is the document APQP leaves on the shop floor. For every step in the process flow it lists the product and process characteristics that matter, how each one is measured, how many parts and how often, how the result is recorded, and the reaction plan when a check fails. It is built from the PFMEA: every prevention and detection control the PFMEA relies on must appear on the control plan, or the PFMEA's ratings are wishful.

APQP produces it three times. The prototype control plan covers the checks on prototype builds in phase 2. The pre-launch control plan, in phase 3, adds extra checks for the first weeks of production, while the process is still unproven. The production control plan, in phase 4, is the long-term version, revised whenever the PFMEA changes.

Illustrative control plan rows: operation 30, projection weld of an M8 nut to a bracket
CharacteristicProduct or processClassSpecificationMethodSample and frequencyReaction plan
Nut present and seatedProductNut on every bracket, flush to the faceProximity sensor in the weld fixtureEvery partMachine will not cycle; operator loads the nut and restarts
Nut push-out forceProductSpecialAt least 2.5 kN (illustrative)Push-out tester3 parts at start of shift, after each tip dress and after any stop over 30 minutesStop the cell, hold every part since the last good check, call the shift quality technician
Weld currentProcess9.5 to 10.5 kA (illustrative)Weld controller monitorEvery weldController rejects the part to the red bin; two faults in a row, call maintenance

The numbers are illustrative, not a weld specification. The class column carries the special characteristics agreed in phase 2, so the floor knows which checks it can never skip.

Our control plan template has these columns ready to fill in, and the PFMEA template feeds it. How the PFMEA ranks the risks that the control plan then covers is in the FMEA guide.

An APQP timeline example, worked back from start of production

This example is illustrative. A supplier wins a stamped and welded seat bracket, built to the customer's drawing. The award arrives at the start of week 1 and the customer's start of production (SOP) is the start of week 41. Production tooling has a quoted lead time of 14 weeks, and the customer takes three weeks to review a PPAP submission.

Illustrative APQP timeline for a 40-week launch
PhaseWeeksLengthWhat fixes the datesGate
1. Plan and define1 to 44 weeksRequirements review, timing plan back from SOPEnd of week 4
2. Product design and development3 to 1210 weeksFeasibility signed and tooling ordered by the end of week 11End of week 12
3. Process design and development9 to 2618 weeksTooling arrives at the end of week 25, tryout in week 26End of week 26
4. Product and process validation27 to 3812 weeksProduction run in week 32, submission at the end of week 35, approval at the end of week 38End of week 38
Buffer39 to 402 weeksKept empty on purpose
5. Feedback, assessment and corrective action41 to 5212 weeksLaunch containment for six weeks, lessons learned review in week 52Week 52 review

Forward check: phases 1 to 4 add up to 4 + 10 + 18 + 12 = 44 weeks. Phases 1 and 2 overlap in weeks 3 and 4 (2 weeks) and phases 2 and 3 overlap in weeks 9 to 12 (4 weeks), so the span is 44 - 2 - 4 = 38 weeks, which is weeks 1 to 38.

The 40-week launch as a timeline

Example numbers
  1. Weeks 1 to 41. Plan and define4 weeks. Gate: End of week 4.
  2. Weeks 3 to 122. Product design and development10 weeks. Gate: End of week 12.
  3. Weeks 9 to 263. Process design and development18 weeks. Gate: End of week 26.
  4. Weeks 27 to 384. Product and process validation12 weeks. Gate: End of week 38.
  5. Weeks 39 to 40Buffer2 weeks. Kept empty on purpose.
  6. Weeks 41 to 525. Feedback, assessment and corrective action12 weeks. Gate: Week 52 review.
Phases overlap on purpose: product design starts in week 3, before planning ends, and process design starts in week 9. The two empty weeks before production protect the date.

Backward check, the way the plan should be built: SOP is the start of week 41. Keep two weeks of buffer, so approval is needed by the end of week 38. The customer needs three weeks to review, so the submission goes in at the end of week 35. Measuring every dimension, testing and putting the package together takes three weeks (weeks 33 to 35), so the production run is in week 32. Phase 4 starts in week 27, after tooling tryout in week 26. Tooling must arrive by the end of week 25, and with a 14-week lead time it must be ordered by the end of week 11: 25 - 14 = 11. Both directions give the same dates.

Now the order goes out four weeks late, at the end of week 15, because the drawing was still moving. Tooling arrives at the end of week 29 (15 + 14), tryout is week 30 and phase 4 starts in week 31. The production run moves to week 36 (31 + 5), the submission to the end of week 39 (36 + 3) and approval to the end of week 42 (39 + 3). The latest approval that still meets SOP is the end of week 40, so the launch is two weeks late: the buffer absorbed two of the four weeks and nothing else could. The lesson is the usual one. In most launches the long-lead tooling and gauges are the critical path, so phase 2 exists to get them ordered on a stable design, not to fill in forms.

APQP outside automotive

The phases are not specific to cars. Aerospace has its own standard for the same idea, AS9145, published by SAE for the aerospace supply chain, which pairs advanced product quality planning with a production part approval step. Medical device makers cover the same ground through design and development controls, such as ISO 13485 clause 7.3. Plants outside regulated supply chains use a lighter version: the five phases, a short gate review at the end of each, and only the deliverables that fit the risk of the part.

If you are scaling it down, keep three things: a timing plan worked back from the launch date, a PFMEA with a control plan that matches the floor, and one proof run at rate before the first shipment. Those catch most launch problems at a fraction of the paperwork.

Common APQP mistakes

  • Treating APQP as the paperwork for the PPAP. The documents get written in the last month to fill a submission, and the problems they would have found are found by the customer instead.
  • Planning forward from kick-off. Dates set forward leave no room before SOP. Work back from SOP, as in the example above, and let the early phases absorb the slack.
  • Ordering tooling and gauges late. Gauge studies need the real gauges, and capability studies need the real tools. Both have long lead times, so they belong in phase 2 and 3 plans, not in phase 4.
  • Copying the PFMEA and control plan from a similar part. The failure modes of the new line, its new fixture and its new operators never make it onto the sheet.
  • A control plan that does not match the floor. If the operator's check sheet and the control plan disagree, the customer's auditor will find it before you do. Walk the line with the control plan in hand.
  • PPAP parts from a hand-built run. Parts made slowly by the best operator on a good day prove nothing about production at rate.
  • One quality engineer doing APQP alone. It needs process engineering, production, maintenance, purchasing and logistics in the room, or the feasibility commitment is a guess.
  • Skipping phase 5. Launch problems get fixed one by one and never reach the lessons learned list, so the next program repeats them.

FAQ

Questions about aPQP

  1. APQP, advanced product quality planning, is a structured method for launching a new or changed part. A cross-functional team plans the product and its production process in five phases, each ending at a gate review, so that every customer requirement is met and proved before production starts. It was written by Ford, General Motors and Chrysler and is published by AIAG.

  2. The five phases are: 1, plan and define the program; 2, product design and development; 3, process design and development; 4, product and process validation; and 5, feedback, assessment and corrective action. The first four each end at a gate review. Phase 5 runs for the life of the part and feeds lessons learned into the next program.

  3. APQP is the plan for the whole launch, from the customer's request to stable production. PPAP, the production part approval process, is one step inside it, near the end of phase 4: the evidence package and signed part submission warrant that show the customer the production process makes good parts at the quoted rate. Most PPAP elements are made earlier in APQP.

  4. The AIAG PPAP manual lists: design records, authorized engineering change documents, customer engineering approval, design FMEA, process flow diagram, process FMEA, control plan, measurement system analysis studies, dimensional results, material and performance test results, initial process studies, qualified laboratory documentation, appearance approval report, sample production parts, master sample, checking aids, customer-specific requirements records, and the part submission warrant.

  5. There are five. Level 1 sends the warrant only. Level 2 sends the warrant with sample parts and limited data. Level 3 sends the warrant with sample parts and complete data, and is the default. Level 4 is the warrant plus whatever the customer defines. Level 5 is complete data reviewed at the supplier's plant. At every level the full records are kept on file.

  6. IATF 16949:2016 requires what APQP delivers: a design and development process (clause 8.3), the customer's product approval process (clause 8.3.4.4) and control plans (clause 8.5.1.1 and Annex A). Most automotive customers also require APQP by name in their supplier manuals, so in practice automotive suppliers run it.

  7. The five AIAG core tools are APQP (planning the launch), PPAP (getting the part approved), FMEA (ranking how the design or process could fail), MSA (proving the gauges can be trusted) and SPC (watching the process with control charts and capability). The control plan is usually grouped with them. Each has its own AIAG reference manual.

  8. A control plan lists, for every process step, the characteristics that matter, how each is measured, the sample size and frequency, how results are recorded and what to do when a check fails. APQP produces three versions: prototype in phase 2, pre-launch with extra checks in phase 3, and production in phase 4. It is built from the PFMEA.

  9. It is the run the PPAP parts come from. By the PPAP manual's default it lasts one to eight hours and gives at least 300 consecutive parts, made on production tooling, gauges, process, materials and operators at the production rate. Your customer can set a different quantity. Parts from a prototype or hand-built trial run do not count.

  10. As long as the gap between the sourcing decision and the customer's start of production, which the customer sets. The plan is built backwards from that date: customer review time, the production run, tooling tryout and the tooling lead time. Long-lead tooling and gauges are usually the critical path, so they are ordered in phase 2 on a stable design.

  11. A program manager who owns the timing, plus design engineering (or the customer's design contact for a build-to-print part), process engineering, quality, production, maintenance or tooling, purchasing and supplier quality, and logistics for packaging. Sales or the account manager carries customer requirements in. Key sub-suppliers join for their parts.

  12. Yes. Aerospace has its own version, the SAE standard AS9145, which combines advanced product quality planning with a production part approval step. Medical device makers cover the same ground through design and development controls such as ISO 13485 clause 7.3. Other plants use a lighter version: five phases, short gate reviews and only the deliverables the risk calls for.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.