Free tool
Bottleneck calculator
A bottleneck is the step in a process with the least capacity, so it sets the output of the whole line. Each step's capacity is the number of machines or operators × 3,600 ÷ its cycle time in seconds × its uptime. The lowest of those is the bottleneck and the most the line can make per hour.
Step capacity per hourequalsMachines × 3,600 divided by Cycle time (s) × Uptime
Line capacityequalsLowest step capacity (the bottleneck)
Utilization of a stepequalsLine capacity divided by Step capacity
After breaks
Leave blank to skip
Pre-filled with the worked example. Cycle time is what one machine or operator takes per unit; uptime is the share of the day the step can really run, after breakdowns, changeovers and waiting for material.
Bottleneck
Step 2
64.8 units an hour: the most the whole line can make.
Line capacity
64.8 / h
The bottleneck's capacity
Units per day
518
At 8 hours a day
Share of demand met
94.3%
32 units a day short
Cycle time step 2 needs
47.1 s
Down from 50 s, to meet demand
Capacity of each step, and how busy it is at the bottleneck's pace
Next step
Want to track this every week?
Bring this result to a 45-minute demo and we will show where it fits in LeanSuite's Line Balancing.
How to calculate it
Three numbers for each step
Cycle time is the time one machine or operator takes to finish one unit at that step. Time it on the floor rather than taking the standard from the routing; the two often differ.
Machines are the identical machines, booths or operators doing the same step side by side. Two welders working in parallel double the step's capacity.
Uptime is the share of the day the step can actually run after breakdowns, changeovers and waiting for material. This is where a step that looks fast on paper often turns out to be the real limit; the MTBF and MTTR calculator gives availability from breakdown data.
Add demand per day to see whether the line keeps up, and what cycle time the bottleneck would need. To spread work evenly across stations against takt time instead, use the line balancing calculator.
Worked example
Illustrative numbers, not a benchmarkA line with four steps runs 8 hours a day and needs to make 550 units: cutting (30 s, one machine, 100% uptime), welding (50 s, one welder, 90%), painting (90 s, two booths, 90%) and assembly (40 s, one operator, 100%).
Step 1
Cutting = 1 × 3,600 ÷ 30 × 1.0 = 120 units an hour.Step 2
Welding = 1 × 3,600 ÷ 50 × 0.9 = 64.8 units an hour.Step 3
Painting = 2 × 3,600 ÷ 90 × 0.9 = 72 units an hour. Assembly = 3,600 ÷ 40 = 90.Step 4
Bottleneck = welding at 64.8 an hour, so 64.8 × 8 = 518 units a day.Step 5
518.4 ÷ 550 = 94.3% of demand: 32 units a day short.
Embed this calculator
Teaching this, or writing about it? Paste this code into your site, course page or intranet and the calculator works right there. It is free, with no sign-up.
<iframe src="https://www.theleansuite.com/tools/bottleneck-calculator/embed" title="Bottleneck calculator by LeanSuite" width="100%" height="1460" style="border:0;max-width:1000px" loading="lazy" allow="clipboard-write"></iframe>
<p style="font:13px/1.4 sans-serif"><a href="https://www.theleansuite.com/tools/bottleneck-calculator">Bottleneck calculator</a> by LeanSuite</p>How LeanSuite helps
Drop in a video of your line and LeanSuite's Line Balancing produces a Yamazumi chart, a takt comparison and rebalancing recommendations.
See Line BalancingRead more
- Free template: Bottleneck analysis worksheet
- Bottleneck in the lean glossary
- Manufacturing Bottleneck Elimination: 5 Proven Strategies
- Theory of constraints in the lean glossary
- Throughput in the lean glossary
- The Theory of Constraints: A Framework for Operational Excellence
- Cycle time, throughput time and lead time for one part
FAQ
Bottleneck calculator: common questions
Work out how many units each step can make per hour and find the lowest: that step limits the whole line. On the floor it usually shows as a pile of work in front of one step while the steps after it wait. The calculation confirms what you see and tells you by how much the step falls short.
Capacity per hour = machines × 3,600 ÷ cycle time in seconds × uptime. A step with one machine, a 50 second cycle and 90% uptime makes 3,600 ÷ 50 × 0.9 = 64.8 units an hour. Multiply by the hours run per day for daily capacity.
No. A step with two machines in parallel can have the longest cycle time and still make more per hour than a single machine with a shorter one, and a step that is often down for breakdowns or changeovers loses capacity it would have on paper. That is why the calculator counts machines and uptime, not cycle time alone.
In the theory of constraints, a constraint is anything that limits how much the whole system can produce: a machine, a skill, a supplier, a policy or customer demand itself. A bottleneck is a constraint that is a resource on the floor, a step whose capacity is below what is asked of it. If every step can make more than customers order, the limit is demand, not a bottleneck.
Make sure it never waits: keep a small buffer of work in front of it, run it through breaks and changeovers where you can, and check quality before it so it never works on parts that will be scrapped. Pace the other steps to it rather than to their own speed. Only then add capacity, and recalculate, because the bottleneck moves once you fix it.
More free lean tools
All tools- OEE calculatorOverall equipment effectiveness from shift time, downtime, ideal cycle time and part counts.
- Downtime cost calculatorWhat an hour, an event and a year of unplanned downtime cost, from lost output, idle labour, scrap and overtime.
- SMED changeover calculatorTime saved by moving changeover steps from internal to external, capacity freed per week and the smaller batch it allows.
- Takt time calculatorThe pace a line must hit to meet customer demand, from shift time, breaks and daily demand.
- Cycle time calculatorCycle time against takt, units per hour, capacity per shift and the gap to daily demand.
- Line balancing calculatorLine efficiency, balance delay and the minimum number of stations from station times and takt.
- First pass yield (FPY) calculatorFirst pass yield at each step and rolled throughput yield (RTY) across the whole process.
- Cost of poor quality (COPQ) calculatorTotal COPQ and cost of quality, and each as a share of revenue, from the four quality cost categories.
- Process capability (Cp, Cpk) calculatorCp and Cpk against your specification limits, plus Pp and Ppk from pasted measurements, with a distribution chart.
- DPMO and sigma level calculatorDPMO, defects per unit, yield and sigma level from the defects found, units checked and opportunities per unit.
- MTBF and MTTR calculatorMean time between failures, mean time to repair and availability from operating time, failures and repair time.
- Lead time calculatorManufacturing lead time from WIP and throughput (Little's Law), and the share of it that adds value.
- Throughput time calculatorThroughput time from process, inspection, move and wait time, the share of it that adds value, and units per hour.
- Kaizen savings calculatorYearly savings, payback in months and first-year ROI of an improvement, from time saved, scrap avoided and its costs.
- TEEP calculatorTotal effective equipment performance: OEE multiplied by how much of all calendar time you plan to run.
- Overall labor effectiveness (OLE) calculatorHow well paid labor hours turn into good output: availability, performance and quality of the crew.
- Inventory turnover and days on hand calculatorHow many times stock turns over in a period and how many days of it you hold, from COGS and average inventory.
- Safety stock calculatorSafety stock and reorder point from the service level you want, average demand and lead time, and how much each varies.
- Scrap rate calculatorScrap rate, the cost of scrap per period and per year, and what reaching a target rate would save.
- TRIR and DART rate calculatorOSHA recordable and DART incident rates from your 300A case counts and hours, and what one more case does to them.
- NIOSH lifting equation calculatorRecommended weight limit and lifting index for a two-handed lift, with every multiplier shown so you can see what to redesign.
- Time study sample size calculatorHow many cycles of an element to time, from your first readings, with the t formula, the ILO formula and the range method.
- Maintenance strategy selectorAnswer the RCM questions for one failure mode and get the maintenance strategy, the reasoning and the check or test interval.
- Noise dose and TWA calculatorDose and 8-hour TWA for a shift of noise levels under OSHA and NIOSH, which limits are reached and how much loud time to cut.
- Risk matrix calculatorSeverity times likelihood on a 3 x 3, 4 x 4 or 5 x 5 risk matrix, the band and its action, editable banding, and the score after further controls.
- Repair or replace calculatorEquivalent annual cost of keeping and repairing an old machine against buying a new one, with each one's economic life and the break-even figures.
- Compressed air leak cost calculatorAir lost, kW and cost a year for each tagged leak from its size and the pressure, ranked so the biggest gets fixed first.
- Machine hour rate calculatorWhat one productive hour of a machine costs, with and without the operator, the cost per part and how utilisation moves the rate.
- Total manufacturing cost calculatorTotal manufacturing cost, cost of goods manufactured, cost per unit and the overhead rate from materials, labor and overhead.
- Acceptance sampling calculatorRead the OC curve and the real risks of a sampling plan, find the plan for your AQL and LTPD, or size a zero-defect test.
- Shift schedule plannerTen shift patterns on real dates: calendar for each crew, hours a week, weekends off, coverage and the weeks over 40 hours.
- Pareto chart makerPaste categories and counts: sorted bars, cumulative percentage line and the vital few at the 80% line, as a PNG or SVG.
- Histogram makerPaste measurements: the histogram with automatic or chosen bins, plus mean, median and standard deviation, as a PNG or SVG.
- Box plot makerPaste one or more groups of numbers: box plots with quartiles, IQR, whiskers and outliers by the 1.5 IQR rule, as a PNG or SVG.
- Fishbone diagram makerName the problem, list causes under the 6M bones, and download the Ishikawa diagram as a PNG or SVG.
- 5 Whys canvasWrite the problem, answer up to five whys, state the root cause and countermeasure, then print the one-page canvas.
- Lean maturity self-assessmentScore 27 statements across nine dimensions and get a band for each, an overall band, where to start and the guides to read.
- Lean method navigatorSix questions about one problem, then the lean method to start with, the two that follow, why each fits, five steps for Monday and what it will not solve.
- Manufacturing ROI calculatorAnswer a few questions about your shop floor, shifts and downtime to estimate your potential ROI with LeanSuite.

