Takt time calculator
Takt time is the rate at which products must be finished to meet customer demand. It is the available production time divided by customer demand for the same period, and it sets the pace that every station on the line is balanced against.
Takt timeequalsAvailable production time divided by Customer demand
Available production timeequals(Shift length − Planned breaks) × Shifts
Breaks, meetings, planned cleaning
Pre-filled with the worked example. Use the same period for time and demand: here, one day.
Takt time
30 s
One unit must be finished this often to meet demand.
Per unit, in minutes
0.5 min
Output needed
120 / hour
Available time
450 min
27,000 seconds a day
How to calculate it
Available time over demand
Available production time is the time the line is scheduled to run: shift length minus planned breaks, meetings and planned cleaning, times the number of shifts.
Customer demand is how many units customers need in that same period, from orders or the forecast.
Divide one by the other and you have the heartbeat of the line. Compare each station's cycle time with it: a station slower than takt is a bottleneck, and one much faster has spare capacity. The line balancing calculator takes it from there.
Worked example
Illustrative numbers, not a benchmarkOne 480-minute shift a day with 30 minutes of planned breaks, and customer demand of 900 units a day.
- 1Available time = 480 − 30 = 450 min × 60 = 27,000 s.
- 2Takt time = 27,000 s ÷ 900 units = 30 s per unit.
- 3Output needed = 3,600 s ÷ 30 s = 120 units an hour.
Embed this calculator
Teaching this, or writing about it? Paste this code into your site, course page or intranet and the calculator works right there. It is free, with no sign-up.
<iframe src="https://www.theleansuite.com/tools/takt-time-calculator/embed" title="Takt time calculator by LeanSuite" width="100%" height="840" style="border:0;max-width:1000px" loading="lazy" allow="clipboard-write"></iframe>
<p style="font:13px/1.4 sans-serif"><a href="https://www.theleansuite.com/tools/takt-time-calculator">Takt time calculator</a> by LeanSuite</p>How LeanSuite helps
Drop in a video of your line and LeanSuite's Line Balancing produces a Yamazumi chart, a takt comparison and rebalancing recommendations.
See Line BalancingFAQ
Takt time calculator: common questions
More free lean tools
All tools- OEE calculatorOverall equipment effectiveness from shift time, downtime, ideal cycle time and part counts.
- Downtime cost calculatorWhat an hour, an event and a year of unplanned downtime cost, from lost output, idle labour, scrap and overtime.
- SMED changeover calculatorTime saved by moving changeover steps from internal to external, capacity freed per week and the smaller batch it allows.
- Cycle time calculatorCycle time against takt, units per hour, capacity per shift and the gap to daily demand.
- Line balancing calculatorLine efficiency, balance delay and the minimum number of stations from station times and takt.
- First pass yield (FPY) calculatorFirst pass yield at each step and rolled throughput yield (RTY) across the whole process.
- Cost of poor quality (COPQ) calculatorTotal COPQ and cost of quality, and each as a share of revenue, from the four quality cost categories.
- Process capability (Cp, Cpk) calculatorCp and Cpk against your specification limits, plus Pp and Ppk from pasted measurements, with a distribution chart.
- MTBF and MTTR calculatorMean time between failures, mean time to repair and availability from operating time, failures and repair time.
- Lead time calculatorManufacturing lead time from WIP and throughput (Little's Law), and the share of it that adds value.
- Manufacturing ROI calculatorAnswer a few questions about your shop floor, shifts and downtime to estimate your potential ROI with LeanSuite.