Free tool
TEEP calculator
Total effective equipment performance (TEEP) is the share of all calendar time that a machine spends making good parts at full speed. It is OEE multiplied by utilization, where utilization is planned production time divided by all the time in the period. OEE judges the hours you scheduled; TEEP judges every hour, so it shows how much capacity sits in unscheduled shifts.
TEEPequalsOEE × Utilization
UtilizationequalsPlanned production time divided by Calendar time
OEEequalsAvailability × Performance × Quality
All hours in the period: a week is 168
Hours scheduled to run, after planned stops
From your OEE: run time ÷ planned time
From your OEE: speed against ideal
From your OEE: good ÷ total
Pre-filled with the worked example. Use one machine or line and one period. Do not count planned stops against availability: they are already out of the planned time.
TEEP
39.9%
67 h of good output at full speed from 168 calendar hours.
OEE
83.8%
Availability × performance × quality
Utilization
47.6%
Planned time ÷ calendar time
Not scheduled
88 h
Calendar hours with no production planned
Next step
Want to track this every week?
Bring this result to a 45-minute demo and we will show where it fits in LeanSuite's KPI Dashboards.
How to calculate it
Five numbers: two for time, three from your OEE
Calendar time is every hour in the period: 168 for a week, 720 for a 30-day month. It does not matter whether the plant is open.
Planned production time is the hours you scheduled the machine to make product, after breaks and other planned stops. It is the same base your OEE uses.
Availability, performance and quality come from your OEE for the same period. If you only have the OEE figure, enter it as the performance and put 100 for the other two; the product is the same.
TEEP does not replace OEE. Read the two together: a low OEE means the scheduled hours are being lost, and a low utilization means the hours are not being scheduled. Only the first is a loss to fix on the line; the second is a business decision about capacity.
Worked example
Illustrative numbers, not a benchmarkA line in a week of 168 hours, scheduled for 80 hours of production. In those hours its availability was 90%, its performance 95% and its quality 98%.
Step 1
OEE = 0.90 × 0.95 × 0.98 = 83.79%.Step 2
Utilization = 80 ÷ 168 = 47.62%.Step 3
TEEP = 83.79% × 47.62% = 39.9%.Step 4
Good output at full speed = 39.9% × 168 h = 67.0 hours' worth.
Embed this calculator
Teaching this, or writing about it? Paste this code into your site, course page or intranet and the calculator works right there. It is free, with no sign-up.
<iframe src="https://www.theleansuite.com/tools/teep-calculator/embed" title="TEEP calculator by LeanSuite" width="100%" height="1000" style="border:0;max-width:1000px" loading="lazy" allow="clipboard-write"></iframe>
<p style="font:13px/1.4 sans-serif"><a href="https://www.theleansuite.com/tools/teep-calculator">TEEP calculator</a> by LeanSuite</p>How LeanSuite helps
LeanSuite's KPI Dashboards track OEE, downtime and production counts live, so you can see the availability, performance and quality behind the OEE half of TEEP.
See KPI DashboardsRead more
- Free template: OEE tracking sheet
- Free template: Six big losses worksheet
- Total effective equipment performance (TEEP) in the lean glossary
- OEE calculator
- OEE in the lean glossary
- Planned downtime in the lean glossary
- Overall Equipment Effectiveness (OEE): What is it?
- What is TPM? Total productive maintenance
- Reducing machine downtime: a worked month from one downtime log
- How to calculate OEE, and how TEEP differs
FAQ
TEEP calculator: common questions
Multiply OEE by utilization. Utilization is planned production time divided by all calendar time in the period, and OEE is availability × performance × quality. A line planned for 80 of 168 hours in a week (47.6% utilization) with an OEE of 83.8% has a TEEP of 39.9%.
OEE only looks at the time you planned to run, so a plant that runs one shift can show a high OEE. TEEP measures against every hour in the period, so it also shows the capacity in the shifts, nights and weekends you do not schedule. OEE tells you how well the scheduled time is used; TEEP tells you how much of the machine's full-time potential you are using.
There is no fixed benchmark, because TEEP depends on how many hours you choose to schedule. A plant that runs 24 hours a day, 7 days a week has a TEEP equal to its OEE. A plant that runs one 8-hour shift, 5 days a week can never get above 23.8% (40 of 168 hours), however well it runs. Compare a line with its own TEEP over time, not with another plant's.
Planned stops are taken out of the planned production time, so they lower utilization and therefore TEEP, but they are not counted as a loss inside OEE. The calculator's planned production time should be the hours you scheduled the machine to produce, after breaks and planned maintenance.
Use it before buying capacity. If TEEP is low because the machine is not scheduled, adding a shift may be cheaper than buying another machine. If TEEP is low because OEE is low, fixing availability, performance or quality on the hours you already run comes first.
More free lean tools
All tools- OEE calculatorOverall equipment effectiveness from shift time, downtime, ideal cycle time and part counts.
- Downtime cost calculatorWhat an hour, an event and a year of unplanned downtime cost, from lost output, idle labour, scrap and overtime.
- SMED changeover calculatorTime saved by moving changeover steps from internal to external, capacity freed per week and the smaller batch it allows.
- Takt time calculatorThe pace a line must hit to meet customer demand, from shift time, breaks and daily demand.
- Cycle time calculatorCycle time against takt, units per hour, capacity per shift and the gap to daily demand.
- Line balancing calculatorLine efficiency, balance delay and the minimum number of stations from station times and takt.
- Bottleneck calculatorThe step that limits your line, from each step's cycle time, machines and uptime, with daily capacity and the gap to demand.
- First pass yield (FPY) calculatorFirst pass yield at each step and rolled throughput yield (RTY) across the whole process.
- Cost of poor quality (COPQ) calculatorTotal COPQ and cost of quality, and each as a share of revenue, from the four quality cost categories.
- Process capability (Cp, Cpk) calculatorCp and Cpk against your specification limits, plus Pp and Ppk from pasted measurements, with a distribution chart.
- DPMO and sigma level calculatorDPMO, defects per unit, yield and sigma level from the defects found, units checked and opportunities per unit.
- MTBF and MTTR calculatorMean time between failures, mean time to repair and availability from operating time, failures and repair time.
- Lead time calculatorManufacturing lead time from WIP and throughput (Little's Law), and the share of it that adds value.
- Throughput time calculatorThroughput time from process, inspection, move and wait time, the share of it that adds value, and units per hour.
- Kaizen savings calculatorYearly savings, payback in months and first-year ROI of an improvement, from time saved, scrap avoided and its costs.
- Overall labor effectiveness (OLE) calculatorHow well paid labor hours turn into good output: availability, performance and quality of the crew.
- Inventory turnover and days on hand calculatorHow many times stock turns over in a period and how many days of it you hold, from COGS and average inventory.
- Safety stock calculatorSafety stock and reorder point from the service level you want, average demand and lead time, and how much each varies.
- Scrap rate calculatorScrap rate, the cost of scrap per period and per year, and what reaching a target rate would save.
- TRIR and DART rate calculatorOSHA recordable and DART incident rates from your 300A case counts and hours, and what one more case does to them.
- NIOSH lifting equation calculatorRecommended weight limit and lifting index for a two-handed lift, with every multiplier shown so you can see what to redesign.
- Time study sample size calculatorHow many cycles of an element to time, from your first readings, with the t formula, the ILO formula and the range method.
- Maintenance strategy selectorAnswer the RCM questions for one failure mode and get the maintenance strategy, the reasoning and the check or test interval.
- Noise dose and TWA calculatorDose and 8-hour TWA for a shift of noise levels under OSHA and NIOSH, which limits are reached and how much loud time to cut.
- Risk matrix calculatorSeverity times likelihood on a 3 x 3, 4 x 4 or 5 x 5 risk matrix, the band and its action, editable banding, and the score after further controls.
- Repair or replace calculatorEquivalent annual cost of keeping and repairing an old machine against buying a new one, with each one's economic life and the break-even figures.
- Compressed air leak cost calculatorAir lost, kW and cost a year for each tagged leak from its size and the pressure, ranked so the biggest gets fixed first.
- Machine hour rate calculatorWhat one productive hour of a machine costs, with and without the operator, the cost per part and how utilisation moves the rate.
- Total manufacturing cost calculatorTotal manufacturing cost, cost of goods manufactured, cost per unit and the overhead rate from materials, labor and overhead.
- Acceptance sampling calculatorRead the OC curve and the real risks of a sampling plan, find the plan for your AQL and LTPD, or size a zero-defect test.
- Shift schedule plannerTen shift patterns on real dates: calendar for each crew, hours a week, weekends off, coverage and the weeks over 40 hours.
- Pareto chart makerPaste categories and counts: sorted bars, cumulative percentage line and the vital few at the 80% line, as a PNG or SVG.
- Histogram makerPaste measurements: the histogram with automatic or chosen bins, plus mean, median and standard deviation, as a PNG or SVG.
- Box plot makerPaste one or more groups of numbers: box plots with quartiles, IQR, whiskers and outliers by the 1.5 IQR rule, as a PNG or SVG.
- Fishbone diagram makerName the problem, list causes under the 6M bones, and download the Ishikawa diagram as a PNG or SVG.
- 5 Whys canvasWrite the problem, answer up to five whys, state the root cause and countermeasure, then print the one-page canvas.
- Lean maturity self-assessmentScore 27 statements across nine dimensions and get a band for each, an overall band, where to start and the guides to read.
- Lean method navigatorSix questions about one problem, then the lean method to start with, the two that follow, why each fits, five steps for Monday and what it will not solve.
- Manufacturing ROI calculatorAnswer a few questions about your shop floor, shifts and downtime to estimate your potential ROI with LeanSuite.