Free tool
SMED changeover calculator
SMED (single-minute exchange of die) shortens changeovers by moving work the crew can do while the machine is still running, external work, out of the stop. The changeover time that remains is the internal work: the steps that can only happen with the machine stopped.
New changeover timeequalsInternal work − Minutes moved to external
Time freed per weekequalsMinutes moved × Changeovers per week
Capacity freedequalsTime freed (seconds) divided by Cycle time (seconds)
Smaller batch sizeequalsBatch size × New changeover time divided by Changeover time today
Done with the machine stopped: today's changeover time
Already done while the machine runs
Fetching tools, preheating, presetting, paperwork
To turn freed time into units
Units made between changeovers
Pre-filled with the worked example. Changeover time runs from the last good part of one product to the first good part of the next.
New changeover time
60 min
Down from 90 min: 30 min (33.3%) saved on every changeover.
Machine time freed
3 h / week
180 min at 6 changeovers a week
Capacity freed
240 units
Per week, if batch sizes stay the same
Or a smaller batch
1,000 units
Up to 9 changeovers a week in today's 540 min
Internal share of the work
82% → 55%
Of 110 min of changeover work
How to calculate it
Split the work, then move it
Film or time one changeover and list every step. Mark each one internal (the machine must be stopped) or external (it could be done while the machine runs). Today's changeover time is the internal total.
Then find the internal steps that could be done before the stop or after the restart: fetching tools and material, preheating, presetting, paperwork. Those are the minutes you can make external. Steps you speed up without moving them, such as quick-release clamps, simply lower the internal time.
Changeovers count against availability in OEE, and shorter ones make smaller batches practical, the basis of just-in-time production. To see what the stop itself costs, use the downtime cost calculator.
Worked example
Illustrative numbers, not a benchmarkA press has 90 minutes of internal changeover work and 20 minutes of external work. The team finds 30 internal minutes it can move to external. It changes over 6 times a week, runs a 45-second cycle and makes batches of 1,500.
- 1New changeover time = 90 − 30 = 60 min, 33.3% shorter.
- 2Time freed = 30 × 6 = 180 min = 3 hours a week.
- 3Capacity freed = 180 × 60 ÷ 45 = 240 units a week.
- 4Or smaller batches: 1,500 × 60 ÷ 90 = 1,000 units, with 6 × 90 ÷ 60 = 9 changeovers fitting in today's 540 minutes a week.
- 5Internal share of the work: 90 of 110 minutes (82%) before, 60 of 110 (55%) after.
Embed this calculator
Teaching this, or writing about it? Paste this code into your site, course page or intranet and the calculator works right there. It is free, with no sign-up.
<iframe src="https://www.theleansuite.com/tools/smed-changeover-calculator/embed" title="SMED changeover calculator by LeanSuite" width="100%" height="1310" style="border:0;max-width:1000px" loading="lazy" allow="clipboard-write"></iframe>
<p style="font:13px/1.4 sans-serif"><a href="https://www.theleansuite.com/tools/smed-changeover-calculator">SMED changeover calculator</a> by LeanSuite</p>How LeanSuite helps
LeanSuite watches a video of your changeover, separates internal and external tasks and recommends a leaner sequence.
See SMEDFAQ
SMED changeover calculator: common questions
More free lean tools
All tools- OEE calculatorOverall equipment effectiveness from shift time, downtime, ideal cycle time and part counts.
- Downtime cost calculatorWhat an hour, an event and a year of unplanned downtime cost, from lost output, idle labour, scrap and overtime.
- Takt time calculatorThe pace a line must hit to meet customer demand, from shift time, breaks and daily demand.
- Cycle time calculatorCycle time against takt, units per hour, capacity per shift and the gap to daily demand.
- Line balancing calculatorLine efficiency, balance delay and the minimum number of stations from station times and takt.
- First pass yield (FPY) calculatorFirst pass yield at each step and rolled throughput yield (RTY) across the whole process.
- Cost of poor quality (COPQ) calculatorTotal COPQ and cost of quality, and each as a share of revenue, from the four quality cost categories.
- Process capability (Cp, Cpk) calculatorCp and Cpk against your specification limits, plus Pp and Ppk from pasted measurements, with a distribution chart.
- MTBF and MTTR calculatorMean time between failures, mean time to repair and availability from operating time, failures and repair time.
- Lead time calculatorManufacturing lead time from WIP and throughput (Little's Law), and the share of it that adds value.
- Manufacturing ROI calculatorAnswer a few questions about your shop floor, shifts and downtime to estimate your potential ROI with LeanSuite.