First pass yield (FPY) calculator
First pass yield (FPY) is the share of units that get through a process step right the first time, with no rework, repair or scrap. Rolled throughput yield (RTY) multiplies the FPY of every step together: the chance that a unit gets through the whole process without a single fix.
FPY (each step)equalsUnits passed first time divided by Units in × 100
RTYequalsFPY step 1 × FPY step 2 × … × FPY step n
Pre-filled with the worked example. Passed first time means no rework, repair or scrap at that step; a reworked unit that later passes does not count.
Rolled throughput yield
81.3%
Of every 100 units started, about 81.3 get through all 4 steps with no rework or scrap.
Lowest step
Step 2
90.0% first pass yield
Reworked or scrapped
200 units
Across all steps
First pass yield by step
Next step
Want to track this every week?
Bring this result to a 45-minute demo and we will show where it fits in LeanSuite's Quality Improvement.
How to calculate it
Count what went right the first time
For each step, count the units in, every unit that entered the step in the period, and the units passed first time, the ones that needed no rework, repair or scrap there. Their ratio is that step's first pass yield.
Multiply the step yields together for the rolled throughput yield. Steps that each look fine on their own can still leave a low RTY, because the losses compound: a unit has to survive every step.
The step with the lowest FPY is usually the place to start, and a root cause analysis there pays off fastest. To put a money value on the rework and scrap, use the cost of poor quality calculator.
Worked example
Illustrative numbers, not a benchmarkA four-step process handles 1,000 units at each step. First time through, 950 pass step 1, 900 pass step 2, 980 pass step 3 and 970 pass step 4.
- 1FPY step 1 = 950 ÷ 1,000 = 95%. Step 2 = 900 ÷ 1,000 = 90%.
- 2FPY step 3 = 980 ÷ 1,000 = 98%. Step 4 = 970 ÷ 1,000 = 97%.
- 3RTY = 0.95 × 0.90 × 0.98 × 0.97 = 0.8128 = 81.3%.
Embed this calculator
Teaching this, or writing about it? Paste this code into your site, course page or intranet and the calculator works right there. It is free, with no sign-up.
<iframe src="https://www.theleansuite.com/tools/first-pass-yield-calculator/embed" title="First pass yield (FPY) calculator by LeanSuite" width="100%" height="1580" style="border:0;max-width:1000px" loading="lazy" allow="clipboard-write"></iframe>
<p style="font:13px/1.4 sans-serif"><a href="https://www.theleansuite.com/tools/first-pass-yield-calculator">First pass yield (FPY) calculator</a> by LeanSuite</p>How LeanSuite helps
LeanSuite lets you log quality issues from the floor, trace each one to its root cause and follow the corrective action through to closure.
See Quality ImprovementRead more
- Free template: Defect catalogue template with boundary samples
- First pass yield (FPY) in the lean glossary
- First Pass Yield: Definition, Calculation, and Improvement
- How to reduce scrap and rework: a worked month
- First Pass Yield: Definition, Calculation, and Improvement
- Cost of poor quality (COPQ) in the lean glossary
- Poka-yoke in the lean glossary
FAQ
First pass yield (FPY) calculator: common questions
Divide the units that passed a step the first time, with no rework, repair or scrap, by the units that entered the step, and multiply by 100. For example, 900 units passing first time out of 1,000 entering is an FPY of 90%.
Rolled throughput yield is the chance that a unit gets through every step of a process without any rework or scrap. It is the first pass yields of all the steps multiplied together, so four steps at 95%, 90%, 98% and 97% give an RTY of about 81.3%.
Final yield counts every unit that eventually ships, including units that were reworked along the way. First pass yield counts only units that were right the first time. The gap between the two is the rework a plant does to fix its own defects, often called the hidden factory.
Because a unit has to get through every step. If step 1 passes 95% first time and step 2 passes 90% of what reaches it, only 95% × 90% = 85.5% get through both untouched. An average of 92.5% would hide the losses compounding from step to step.
Yes. Units that were scrapped and units that were reworked or repaired both failed the first pass. Count them in the units that entered the step, and leave them out of the units that passed first time.
Every unit that misses the first pass costs something to rework or scrap, and those costs are internal failure costs in the cost of poor quality. First pass yield shows where units fail; putting a money value on the failures shows which step to fix first.
More free lean tools
All tools- OEE calculatorOverall equipment effectiveness from shift time, downtime, ideal cycle time and part counts.
- Downtime cost calculatorWhat an hour, an event and a year of unplanned downtime cost, from lost output, idle labour, scrap and overtime.
- SMED changeover calculatorTime saved by moving changeover steps from internal to external, capacity freed per week and the smaller batch it allows.
- Takt time calculatorThe pace a line must hit to meet customer demand, from shift time, breaks and daily demand.
- Cycle time calculatorCycle time against takt, units per hour, capacity per shift and the gap to daily demand.
- Line balancing calculatorLine efficiency, balance delay and the minimum number of stations from station times and takt.
- Bottleneck calculatorThe step that limits your line, from each step's cycle time, machines and uptime, with daily capacity and the gap to demand.
- Cost of poor quality (COPQ) calculatorTotal COPQ and cost of quality, and each as a share of revenue, from the four quality cost categories.
- Process capability (Cp, Cpk) calculatorCp and Cpk against your specification limits, plus Pp and Ppk from pasted measurements, with a distribution chart.
- DPMO and sigma level calculatorDPMO, defects per unit, yield and sigma level from the defects found, units checked and opportunities per unit.
- MTBF and MTTR calculatorMean time between failures, mean time to repair and availability from operating time, failures and repair time.
- Lead time calculatorManufacturing lead time from WIP and throughput (Little's Law), and the share of it that adds value.
- Throughput time calculatorThroughput time from process, inspection, move and wait time, the share of it that adds value, and units per hour.
- Kaizen savings calculatorYearly savings, payback in months and first-year ROI of an improvement, from time saved, scrap avoided and its costs.
- TEEP calculatorTotal effective equipment performance: OEE multiplied by how much of all calendar time you plan to run.
- Overall labor effectiveness (OLE) calculatorHow well paid labor hours turn into good output: availability, performance and quality of the crew.
- Inventory turnover and days on hand calculatorHow many times stock turns over in a period and how many days of it you hold, from COGS and average inventory.
- Safety stock calculatorSafety stock and reorder point from the service level you want, average demand and lead time, and how much each varies.
- Scrap rate calculatorScrap rate, the cost of scrap per period and per year, and what reaching a target rate would save.
- TRIR and DART rate calculatorOSHA recordable and DART incident rates from your 300A case counts and hours, and what one more case does to them.
- NIOSH lifting equation calculatorRecommended weight limit and lifting index for a two-handed lift, with every multiplier shown so you can see what to redesign.
- Time study sample size calculatorHow many cycles of an element to time, from your first readings, with the t formula, the ILO formula and the range method.
- Maintenance strategy selectorAnswer the RCM questions for one failure mode and get the maintenance strategy, the reasoning and the check or test interval.
- Noise dose and TWA calculatorDose and 8-hour TWA for a shift of noise levels under OSHA and NIOSH, which limits are reached and how much loud time to cut.
- Repair or replace calculatorEquivalent annual cost of keeping and repairing an old machine against buying a new one, with each one's economic life and the break-even figures.
- Compressed air leak cost calculatorAir lost, kW and cost a year for each tagged leak from its size and the pressure, ranked so the biggest gets fixed first.
- Machine hour rate calculatorWhat one productive hour of a machine costs, with and without the operator, the cost per part and how utilisation moves the rate.
- Acceptance sampling calculatorRead the OC curve and the real risks of a sampling plan, find the plan for your AQL and LTPD, or size a zero-defect test.
- Lean maturity self-assessmentScore 24 statements across eight dimensions and get a result band for each, an overall band and where to start.
- Manufacturing ROI calculatorAnswer a few questions about your shop floor, shifts and downtime to estimate your potential ROI with LeanSuite.