Skip to content
LeanSuite

Free template

Updated

Standard work combination table

A standard work combination table shows how one operator's work combines with the machines they run, element by element, on a time chart against takt. Manual work, walking and machine time are drawn in different lines, so it is clear when the operator is working, walking or waiting and when each machine is running on its own. The cycle time is the longer of the operator's loop (manual plus walk) and the longest machine cycle (load plus auto); when a machine needs longer than the loop, the operator waits for it. Page 1 of the PDF is the blank table with takt, operator time, the longest machine cycle and cycle time, a 70-box time chart and columns for manual, auto, walk and wait. Page 2 is a worked example drawn on the chart, a one-operator cell where the mill sets the cycle, with what to check before posting it. Page 3 is a process capacity sheet: how many pieces each machine can make in a shift, including tool changes. The Excel version works out takt, the machine cycles, operator time, cycle time and the wait, the start and end of every element, and draws the chart with machine time carrying past the cycle end, plus a process capacity sheet that finds the machine that limits the cell. The standard work sheet template pairs a simpler combination table with the station layout and standard WIP; this one adds the waits, the machine cycles and the capacity check.

Free to use: print it, copy it and edit it for your team. Enter your name and work email once to download.

Want this run for you? See how it works

Page 1 of the standard work combination tableFields for part, cell, operator, date and preparer, a row for available time, demand, takt, operator time, longest machine cycle and cycle time, a line key for manual, machine, walk, wait and takt, and a 13-row table with manual, auto, walk and wait columns beside a gridded time chart.
Takt timeManual, auto, walk, waitTime chartMachine cyclesCycle time vs taktWorked example drawnProcess capacity sheetExcel chart
Filled-in Standard work combination table: a one-operator machining cell
The same sheet filled in with the worked example (page 2 of the PDF, illustrative numbers). Open full size (opens the picture in a new tab)

When to use it

When to use a combination table

  • When one operator runs more than one machine, to see whether the machines are ready when the operator comes back.
  • When setting up a cell or rebalancing it after a takt change, to check the operator's loop fits inside takt.
  • To find waiting: an operator standing at a machine for its auto cycle to finish.
  • Alongside the standard work chart (the layout and path) and the job breakdown, as one of the three standard work documents.

How to fill it in

  1. 1

    Work out takt

    Available time per shift in seconds ÷ demand per shift. 27,000 seconds and 450 parts give a takt of 60 s.
  2. 2

    List the work elements in order

    One row per element as the operator does it, starting at the same point each cycle. Time each one on the floor several times and use a repeatable time, not the fastest.
  3. 3

    Split each element into manual, auto and walk

    Manual is the operator's hands-on time, auto is the machine running on its own after it is started, walk is the time to the next element.
  4. 4

    Draw the chart

    Each element starts where the one before it ends: manual as a solid line, walk as a wavy line after it, machine time as a dashed line from the end of the manual work. Draw takt as a red line.
  5. 5

    Check every machine is ready

    A machine's load plus auto time must fit inside the operator's loop. If it does not, its dashed line runs past the cycle end and the operator waits; write the wait in.
  6. 6

    Check machine capacity

    On the process capacity sheet, work out each machine's pieces per shift with its tool changes. A machine below demand cannot be fixed by moving operator work.

A filled-in example

Illustrative, not a benchmark

A one-operator machining cell (illustrative), the same numbers as on page 2 of the PDF and in the Excel worked example.

The example cell against takt

  1. Mill: 7 s load + 50 s auto57 ssets the cycle
  2. Operator: 38 s manual + 17 s walking55 s
  3. Lathe: 8 s load + 30 s auto38 s

Takt 60 seconds. Operator loop 55 seconds, lathe 38, mill 57. The mill sets the cycle time at 57 seconds, 3 under takt.

The mill, not the operator, sets the 57 s cycle: the operator waits 2 s at it every cycle. Shorten the mill's auto time or its tool change to gain time.
  • Takt: 27,000 seconds ÷ 450 parts = 60 s.
  • Operator time: 38 s of manual work plus 17 s of walking = 55 s.
  • Lathe: 8 s to unload and load + 30 s auto = 38 s, ready long before the operator comes back. Mill: 7 + 50 = 57 s, 2 s longer than the operator's loop, so the operator waits 2 s at the mill every cycle.
  • Process capacity: the mill's 57 s plus 240 s of tool change every 200 pieces is 58.2 s a piece, and 27,000 ÷ 58.2 = 463 pieces a shift, the lowest in the cell and close to the demand of 450.

Cycle time is 57 s, set by the mill, under the 60 s takt with 3 s to spare. Moving operator work will not shorten it; cutting the mill's auto time or its tool change time will.

To work out takt time from your shift length, breaks and demand, use the free Takt time calculator.

Common mistakes

  • Adding manual and machine time together

    Machine time runs while the operator does other work. Only the operator's manual and walk time make up the loop; machine time matters when it is longer than the loop.

  • Timing from the desk

    Use times measured on the floor, several cycles each. Times from routings or estimates leave out the small walks and waits that the chart is meant to show.

  • Hiding the wait

    Waiting for a machine is real time in the cycle. Leave it on the chart where everyone can see it, then work on the machine.

  • Filling every second up to takt

    A loop drawn at exactly takt has no room for a small problem. Leave a little space and use it to see when something goes wrong.

From this worksheet to a running system

LeanSuite takes the element times this table needs from a video and charts each operator's work as a Yamazumi against takt.

  • Each station's cycle time becomes a stacked bar of elements, split into value-added, semi-value-added and non-value-added time.
  • A takt line sits over every Yamazumi and recalculates when demand or shift pattern changes.
  • See each operator's utilization against takt, with bottlenecks and idle time in one view.
Illustration of a LeanSuite Yamazumi chart: five stations, each bar stacked by work element, with Station 3 over the takt line and marked as the bottleneck

Download the template

Free to use: print it, copy it and edit it for your team. Enter your name and work email once to download.

Run this template in LeanSuite

In LeanSuite the AI times each operator's work elements from one video of the line and charts every station against a takt line that recalculates when demand changes, and you drag elements between operators and save each scenario with the minutes and cost it saves.

See it in a 45-minute demo

FAQ

Standard work combination table: common questions

  1. A chart of one operator's work elements in order, with the manual, machine and walking time of each drawn on a time scale against takt. It shows how the operator's work and the machines' running time fit together, and where the operator waits.

  2. Add the operator's manual and walking time to get the operator's loop. Compare it with each machine's load plus auto time. The cycle time is the larger of the two; in the example the loop is 55 s but the mill needs 57 s, so the cycle is 57 s.

  3. The machine is still running when the next cycle starts. The dashed line carries on from the left of the chart; if it ends after the operator reaches that machine again, the operator waits.

  4. A table of how many pieces each machine can make in a shift: available time ÷ (manual time + auto time + tool change time per piece), rounded down. It is filled in before the combination table, because no operator layout can make a machine produce more than its capacity.

  5. The standard work sheet template pairs a simple combination table with the station layout, key points and standard WIP. This template is the combination table in full: waits, machine time that runs past the cycle end, the cycle set by the longest machine, a drawn example and a process capacity sheet.

More free templates

All templates
Browse all 278 templates

Can't find the template you need?

Tell us what you're looking for. We'll make it and send it to your inbox, free.

A shift handover sheet, a red tag log, a changeover checklist for one machine: if your team uses it on the floor, ask.

By sending this form you agree to our Terms of Service and Privacy Policy.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.