Practical guide · Lean manufacturing fundamentals
Lean manufacturing principles: the five, where they come from, and a worked example
Short answer
The five lean manufacturing principles are value, the value stream, flow, pull and perfection. James Womack and Daniel Jones set them out in the book Lean Thinking in 1996 as the order in which a company removes waste from the way it makes a product.
Start with value: what this customer will pay for in this product. Then follow the value stream, every step the product goes through, and mark the steps that add nothing. Make the steps that remain flow, one after another without queues. Let the customer pull, so nothing is made until the next step needs it. Then go round again, which is what perfection means here. The five are a sequence and you take them one product family at a time. They are not the same list as the 14 principles of The Toyota Way, which describe how Toyota manages, and they are not 5S, which is a method for organising a workplace.
Last reviewed:
What are the five principles of lean manufacturing?
The five principles of lean manufacturing are specify value, identify the value stream, make value flow, let the customer pull and pursue perfection. Womack and Jones set them out in Lean Thinking in 1996, and the Lean Enterprise Institute calls them a five-step thought process. You take them in that order, one product family at a time.
The five lean principles, in order
- 1
Value
- 2
Value stream
- 3
Flow
- 4
Pull
- 5
Perfection
Then back to value, for the same product family or the next one
- 1
Specify value
Define value from the standpoint of the end customer, for one product family at a time. Value is what that customer would pay for if they could watch the work.
- 2
Identify the value stream
List every step the product family goes through, from order to delivery, and remove the steps that create no value wherever you can.
- 3
Make value flow
Put the steps that remain in tight sequence so the product moves from one to the next without waiting in a queue.
- 4
Let the customer pull
Once the product flows, make only what the next step downstream asks for, when it asks for it.
- 5
Pursue perfection
Repeat the first four. Each pass exposes waste that the last one hid, so the work has no end point.
Two details get lost in the short list. The unit is the product family, not the plant, so a site with four families has four value streams. And pull comes after flow, because a pull signal sent into a process full of queues and breakdowns only starves the customer.
Where the five principles come from
The word lean came first. The Machine That Changed the World, published in 1990 by James Womack, Daniel Jones and Daniel Roos, reported five years of MIT-led research into how car makers build cars, and named what the researchers saw at Toyota lean production. It did not tell a manager in another industry what to do on Monday.
Lean Thinking, by Womack and Jones in 1996, was the answer. It boiled the practice down to the five steps above so that any company could follow them. The principles are therefore an outside reading of the Toyota Production System, written by researchers. Toyota does not describe its own system in these five words.
According to the Lean Enterprise Institute, Womack and Jones cut the five down in 2007 to three questions about purpose, process and people. The five are still the version most plants are taught.
What each principle looks like on the shop floor
A principle is only useful if you can tell, standing at the line, whether you are following it. The table gives one question to ask for each, what the answer looks like when the principle is missing, and the tool most plants pick up first.
| Principle | Question to ask | What you see when it is missing | First tool |
|---|---|---|---|
| Value | What would the customer pay for in this step? | Inspection, rework and paperwork that nobody outside the plant asked for | A walk for the 8 wastes |
| Value stream | What happens to the part between the dock doors? | Nobody can say how long an order takes or where it waits | A value stream map |
| Flow | Does the part move on as soon as it is done? | Pallets between every operation and batches sized to fill a shift | Cells, small lots and takt time |
| Pull | Who told this station to make this part now? | A schedule pushed to every station, plus expediting | Kanban and a supermarket |
| Perfection | What did we change this week? | A map on the wall from two years ago | Kaizen and a standard to hold the gain |
The tools are where plants usually start, not the only way to follow a principle.
The guide to lean tools goes deeper on each. To score a plant first, use the lean principles assessment.
A worked example: one bracket family through all five
Illustrative numbers. A fabrication shop makes a family of steel brackets in five steps. The customer orders them weekly and complains about delivery. The team times one bracket through the plant and writes down the work at each step and the wait in front of it.
| Step | Work (minutes) | Wait before it, today (hours) | Wait before it, after (hours) |
|---|---|---|---|
| Cut | 2 | 12 | 4 |
| Bend | 3 | 8 | 2 |
| Weld | 6 | 16 | 0 |
| Paint | 12 | 4 | 2 |
| Pack | 2 | 8 | 4 |
| Total | 25 | 48 | 12 |
Lead time today is 48 hours of waiting plus 25 minutes of work: 2,905 minutes. After, it is 12 hours plus 25 minutes: 745 minutes.
Hours a bracket waits in front of each step, before and after
- Cut: 12 hours before, 4 after
- Bend: 8 hours before, 2 after
- Weld: 16 hours before, 0 after
- Paint: 4 hours before, 2 after
- Pack: 8 hours before, 4 after
Waiting in front of each step before and after: cut 12 to 4 hours, bend 8 to 2, weld 16 to 0, paint 4 to 2, pack 8 to 4.
- Value: the customer pays for a cut, bent, welded, painted bracket that arrives in the week it was ordered. The 25 minutes of work is the value.
- Value stream: the bracket spends 2,905 minutes in the plant and is worked on for 25 of them, which is 0.9% of the time. The rest is waiting.
- Flow: bend and weld move next to each other, so a bent bracket goes straight to the welder and the 16 hour queue in front of weld disappears. Cut runs smaller lots.
- Pull: paint and pack take from a small marked stock and cut replaces only what was taken. Waiting falls from 48 hours to 12.
- Perfection: lead time is now 745 minutes, 74% shorter, and work is 3.4% of it. Nearly all the time is still waiting, so the team maps again.
Nobody worked faster: the 25 minutes of work is the same before and after. The gain came from taking out waiting. See what lead time is for the measures.
The five lean principles and the 14 principles of The Toyota Way
Search for lean principles and you will find lists of 5 and lists of 14. They come from different books and answer different questions. The five, from Lean Thinking, say how to improve a value stream. The 14, from Jeffrey Liker's The Toyota Way in 2004, describe how Toyota runs a company, and Liker groups them under four headings: long-term philosophy, the right process, developing people and partners, and solving root problems.
| Lean principle | Closest of the 14 | What the 14 add around it |
|---|---|---|
| Value | None of its own | Principle 1 asks for decisions based on a long-term philosophy, even at short-term cost |
| Value stream | None of its own | Principle 12, go and see for yourself, is how Toyota expects you to learn the stream |
| Flow | Principle 2, continuous flow to bring problems to the surface | Principles 4 to 8: level the workload, stop to fix problems, standardize tasks, use visual control and proven technology |
| Pull | Principle 3, pull systems to avoid overproduction | Principle 11, on respecting and helping suppliers, extends pull beyond your own walls |
| Perfection | Principle 14, a learning organization through reflection and kaizen | Principles 9, 10 and 13: leaders who know the work, developed teams, and slow decisions by consensus |
The pairing is our reading. Liker does not map his list to Womack and Jones.
The 14 Toyota Way principles, and the three the lean five also name
Long-term philosophy
- 1Decide for the long term
The right process
- 2Continuous flowLean: Flow
- 3Pull systemsLean: Pull
- 4Level the workload
- 5Stop to fix problems
- 6Standardized tasks
- 7Visual control
- 8Proven technology
People and partners
- 9Grow leaders
- 10Develop people and teams
- 11Help partners and suppliers
Solving root problems
- 12Go and see
- 13Decide slowly, act fast
- 14Reflect and improveLean: Perfection
Liker's 14 principles in four groups: long-term philosophy (1), the right process (2 to 8), people and partners (9 to 11) and solving root problems (12 to 14). Principle 2 matches flow, principle 3 matches pull and principle 14 matches perfection.
Read down the right-hand column and the difference is plain. Most of the 14 sit outside the process heading, on leaders, teams, suppliers, decisions and learning, and the five say almost nothing on those. A plant that follows the five, cuts its lead time and drifts back has often changed the process and not the management.
Toyota's own 2001 Toyota Way has two pillars, continuous improvement and respect for people. Liker's 14 are his account of how they show up in practice.
The 14 principles of The Toyota Way, in order
Paraphrased from Liker's book, under his four headings.
- 1
Long-term philosophy
Decide for the long term, even when it costs money now.
- 2
The right process
Create continuous flow so problems show up.
- 3
The right process
Use pull to avoid overproduction.
- 4
The right process
Level the workload (heijunka).
- 5
The right process
Stop to fix problems and get quality right first time.
- 6
The right process
Standardize tasks as the base for improvement.
- 7
The right process
Use visual control so nothing hides.
- 8
The right process
Use only reliable, tested technology that serves people.
- 9
People and partners
Grow leaders who know the work and teach it.
- 10
People and partners
Develop exceptional people and teams.
- 11
People and partners
Respect suppliers by challenging and helping them.
- 12
Solving root problems
Go and see for yourself (genchi genbutsu).
- 13
Solving root problems
Decide slowly by consensus, then act fast.
- 14
Solving root problems
Learn through reflection and kaizen.
Which principle should you work on first?
Match the symptom you see to the principle behind it.
Which principle to work on first
What you see
Customers complain and nobody agrees what good is
Work on
Value
Write what one customer values as a number
What you see
Nobody can say how long an order takes
Work on
Value stream
Time one part from dock to dock
What you see
Parts sit in queues between steps
Work on
Flow
Move two steps together, shrink the lot
What you see
Stock builds in front of some steps while others starve
Work on
Pull
Add a small marked stock and replace only what is used
What you see
Gains fade after a few months
Work on
Perfection
Set a date for the next map and name an owner
How to apply the five principles in a plant
- 1
Pick one product family
Choose one with a real customer complaint and enough volume to see a change inside a few weeks. Leave the rest of the plant alone.
- 2
Ask the customer what they value
Delivery in the week ordered, a defect rate, a lot size. Write it as a number someone can check.
- 3
Walk the stream and time it
Follow one part from receiving to shipping. Record the work and the wait at every step, as in the example. The value stream plan holds the result.
- 4
Fix flow where the wait is longest
Take the biggest queue first. Move the two steps together, cut the lot size, or shorten the changeover that forces the batch.
- 5
Add pull where flow has to stop
Where steps cannot sit side by side, put a small marked stock between them and replace only what is used.
- 6
Measure, then go round again
Compare lead time with the customer's number, write the new standard down and map the family again.
One line or cell run this way is a model area: a place where the five can be seen working first.
Common mistakes with the lean principles
- Starting with tools. A plant runs 5S and kanban everywhere without having asked what the customer values, and tidies steps that should not exist.
- Defining value from inside. Value is set by the customer of that product family, not by what the plant is proud of or what the cost system rewards.
- Pull before flow. Kanban cards on a process with long changeovers and unreliable machines produce shortages, and the cards get the blame.
- Mixing the lists up. The five principles, the 14 of The Toyota Way, 5S and the 8 wastes are four different things.
Go deeper
This page is the short version. These guides cover each part in full.
- The Principles of Lean: What Are They?A longer read on each principle, with the measures a plant can track against them.
- Value Stream Mapping: A Beginner's Complete GuideHow to draw the map the second principle asks for: material flow, information flow and lead time.
- Pull Systems in Lean ManufacturingSupermarkets, kanban loops and the conditions pull needs before it works.
- History of Lean Manufacturing: From Ford to Toyota to TodayHow the ideas travelled from the car plants to the books that named them.
All our articles on this subject are in the lean manufacturing fundamentals topic.
Free templates and tools
- Value stream map templateA current-state frame for the map the second principle asks for.
- Lean principles assessment templateThe five lean principles as 25 things you can see on one value stream, answered yes, partly or no on a walk, with a score per principle, the next step and a trend over walks.
- Value stream plan (VSM action plan)The future-state map cut into loops, each with an objective and a measurable goal, and its kaizen bursts turned into owned, dated projects on a 12-month timeline.
- Waste walk checklist (TIMWOODS)32 things to look for across the eight wastes, with where and how much, and a findings log with dot votes, owners and dates.
- Takt time calculatorThe pace a line must hit to meet customer demand, from shift time, breaks and daily demand.
- Lean maturity self-assessmentScore 27 statements across nine dimensions and get a band for each, an overall band, where to start and the guides to read.
Doing this in LeanSuite
Value Stream Mapping
Turns video of each process step into a current-state value stream map with cycle times, inventory and lead time.
See Value Stream MappingKaizen & Projects
Manage every improvement project in one visual hub, from a small kaizen event to a full DMAIC project, and track each one through to results.
See Kaizen & ProjectsLean Studio
LeanSuite's whiteboard for lean teams, with 30 ready-made boards including the fishbone, 5 Whys, A3 and 8D.
See Lean Studio
See it on your own lines
Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.
FAQ
Questions about lean manufacturing principles
Specify value from the customer's point of view, identify the value stream for each product family, make the value-creating steps flow, let the customer pull, and pursue perfection by repeating the cycle. They are taken in that order, one product family at a time.
James Womack and Daniel Jones, in the book Lean Thinking, first published in 1996. They based the five on their study of Toyota, which they and Daniel Roos had reported in The Machine That Changed the World in 1990.
The five come from Lean Thinking and describe how to improve a value stream: value, value stream, flow, pull, perfection. The 14 come from Jeffrey Liker's The Toyota Way and describe how Toyota manages, including long-term philosophy, leaders, people, suppliers and decision making. Flow and pull appear in both lists.
Lean production is the name the MIT researchers behind The Machine That Changed the World gave in 1990 to what they saw at Toyota. The Lean Enterprise Institute describes the practice as a way of delivering what the customer values with less waste. It is Toyota's system described for other companies.
Kaizen is the Japanese word for continuous improvement. In lean it means small changes made by the people who do the work, checked, and then written into the standard. It is the fifth principle, perfection, in daily practice, and the third foundation of the TPS house.
Continuous improvement is the habit of making the work a little better every day instead of waiting for a large project. Each change is tried, checked against the result and, if it works, becomes the new standard. In the five principles it is perfection: go round again.
Related guides and tools
- Toyota Production System: the house, the two pillars and where the five principles were drawn from
- Lean principles assessment: score a plant against each of the five
- Lean tools: which tool serves which principle
- Lean Thinking by Womack and Jones: what the book covers and who should read it
- Just-in-time manufacturing: flow and pull in more depth
- Continuous improvement: how the fifth principle, perfection, runs day to day
- Standard work: how a stable process is written down
- Takt time: the pace the customer sets, worked on one line
More method guides
- The 6 Ms of production
- Poka-yoke
- Model area 90-day plans
- Moving from Excel to one system
- Reducing machine downtime: a worked month
- Andon
- Cycle time vs lead time, worked through
- Root cause analysis
- How many operators a line needs
- Reducing scrap and rework: a worked month
- Unsafe acts and unsafe conditions
- Just culture
- Stop-work authority
- Material review board (MRB)
- Nonconformance and NCRs
- Problem solving methods
- Quad chart
- OEE calculation
- Quality assurance vs quality control
- SOP meaning and format
- Job hazard analysis
- Near miss reporting
- Fishbone diagram
- Pareto chart
- Histogram
- Control chart
- What is a gemba walk
- What is lead time
- What is operational excellence
- How to improve product quality
- Preventive vs predictive maintenance
- Kanban
- FMEA
- PDSA cycle
- Safety moments
- Just-in-time manufacturing
- Kaizen
- 5S
- Total quality management (TQM)
- CAPA (corrective and preventive action)
- Layered process audit (LPA)
- Lean tools
- Lockout tagout (LOTO)
- A3 problem solving
- Preventive maintenance
- APQP
- High reliability organization (HRO)
- Manufacturing KPIs
- Quality metrics
- Practical problem solving
- CMMS
- Risk assessment
- Production efficiency
- Total productive maintenance (TPM)
- Reliability-centered maintenance (RCM)
- Hierarchy of controls
- Personal protective equipment (PPE)
- Emergency action plan
- Safety signs
- Warehouse safety
- ISO 9001
- SIPOC diagram
- Rolling action item list (RAIL)
- Pugh matrix
- Flowchart
- Project charter
- ISO 9001:2026
- Fleet maintenance
- IATF 16949
- AS9100
- ISO 14001
- ISO 45001
- One point lesson
- Standard work
- Toyota Production System
- 5W1H
- 5 Whys
- Continuous improvement
- Takt time
- DMAIC
- PDCA
- 8D problem solving
- Prioritization matrix
- Gemba walk questions
- 5W1H questions
- Layered process audit questions
- 5S audit questions