Meeting cadence: how to set one, with example schedules for a plant

Short answer

A meeting cadence is the fixed rhythm of a team's recurring meetings: which meetings happen, how often, how long they last, who attends and in what order. In a plant it usually runs from a short daily huddle on each line up to a weekly plant review and a monthly business review, each one feeding the next.

A good cadence gives every level one meeting, at a fixed time and place, with a fixed agenda and the few KPIs that level can act on. The meetings are staggered so a problem raised on the line at 7:00 reaches the area review by 9:00 and the plant review the same week. Every meeting ends with decisions and actions on record, and what a level cannot settle goes up to the next meeting with its history.

Last reviewed:

What is a meeting cadence?

Cadence means rhythm. A meeting cadence is the rhythm of a team's recurring meetings: the daily, weekly, monthly and quarterly meetings, how long each one runs, who is in it, and how they connect. It answers one question for everyone in the building: when, and where, does this kind of problem get decided?

In manufacturing the cadence is usually built on tiered meetings. Tier 1 is the team on the line, tier 2 the area or department, tier 3 the plant, and tier 4 the business. Each tier meets on its own rhythm, looks at its own numbers and passes up what it cannot fix. Together with leader standard work and gemba walks, the cadence is the backbone of a plant's management operating system.

A cadence is not the same as a calendar full of meetings. The test is whether each meeting has a decision it exists to make. A meeting with no decision to make is a report, and a report can be read.

An example meeting cadence for a manufacturing plant

This is a common shape for a single plant running two or three shifts. The names, times and lengths are an example. What matters is that every level has one meeting, and that each meeting knows what it decides.

Example meeting cadence for one plant
MeetingWhoHow oftenLengthWhat it decides
Shift handoverOutgoing and incoming team leadersEvery shift change5 to 10 minWhat the next shift must know: open problems, machines down, material short
Tier 1 huddleTeam leader and the lineDaily, start of shift10 to 15 minToday's plan, yesterday's safety, quality, delivery and cost results, actions the team can take today
Tier 2 area reviewSupervisors, area manager, maintenance, qualityDaily, after the tier 1 huddles20 to 30 minBlockers the lines cannot remove, help across shifts, what goes to the plant
Tier 3 plant reviewPlant manager and department headsWeekly (some plants daily)45 to 60 minPriorities and resources, repeat problems that need a project, answers sent back down
Monthly business reviewPlant or site leadership, financeMonthly60 to 90 minResults against plan for the month and the year, projects started or stopped
Quarterly strategy reviewSite and business leadersQuarterlyHalf a dayThe year's goals and how they cascade to each plant and area

Lengths are typical, not rules. A huddle that runs past 15 minutes has usually turned into problem solving, which belongs in its own session.

A daily timetable: how to stagger the meetings

The order matters more than the times. Each meeting should start after the one below it has finished, so the numbers and escalations are fresh. An example for a plant whose day shift starts at 6:00:

Example daily timetable, day shift starting at 6:00
TimeMeetingFeeds
5:50Shift handover at each lineThe tier 1 huddle
6:30Tier 1 huddles, one per line or cellThe tier 2 area review
8:00Tier 2 area reviews, one per areaThe tier 3 plant review
9:00 (Monday)Tier 3 plant reviewThe monthly business review and the answers back to tier 2

Leave at least an hour between tier 1 and tier 2 on a plant with many lines, so supervisors can walk the huddles before their own meeting.

Keep the times fixed. When a meeting moves around the calendar, people stop preparing for it and start attending it, and the meeting turns into reading the numbers for the first time.

How the cadence changes with shifts and sites

Meeting cadence by type of operation
OperationWhat changes
One shift, one plantTier 1 and tier 2 can run back to back in the first hour. Tier 3 often runs weekly, with a short daily stand-up for the plant manager's staff.
Two or three shiftsEvery shift gets its own tier 1 huddle and a handover. Tier 2 runs once a day, on the day shift, and reads the night shifts' boards first. Escalations from nights wait on the board, not in someone's memory.
Several plantsEach plant keeps its own tiers 1 to 3. A tier 4 review compares sites weekly or monthly, on the same KPI definitions, and sends standard actions back to every plant.
Continuous process (24/7)Handovers carry more weight than huddles. A short daily review at a fixed hour covers all crews, and the weekly review reads the full week, not just the day shift.

How to set a meeting cadence in six steps

  1. 1

    List the decisions, not the meetings

    Write down the decisions that have to be made every shift, every day, every week and every month: who covers a missing operator, which order runs first, whether a line gets a capital fix. Each decision belongs to the lowest level that can make it.

  2. 2

    Give each level one meeting, one owner and one time

    One tier 1 huddle per team, one tier 2 review per area, one plant review. Name an owner for each and fix the time and the place. Do not add a meeting for a decision an existing meeting can make.

  3. 3

    Stagger them so problems move up the same day

    Tier 1 before tier 2, tier 2 before tier 3. Leave enough time between them for a supervisor to walk the huddles. Put the weekly and monthly reviews on fixed days.

  4. 4

    Fix the agenda and the KPIs for each meeting

    Write the agenda once and keep it. Choose only the KPIs that level can act on, each with a target. A huddle reads yesterday and the month so far; a plant review reads the week, the month and the year.

  5. 5

    End every item with a decision, an action or an escalation

    Actions get a name and a date before the meeting ends. Anything the level cannot settle goes on the next level's agenda with its history, and the answer comes back to the meeting that asked.

  6. 6

    Review the cadence after a month

    Drop a meeting nobody decides anything in, shorten one that always runs over, and move one people keep missing. A cadence is a standard: improve it like any other.

A standard agenda for each meeting

Tier 1 huddle (10 to 15 minutes)

  • Safety: anything from the last 24 hours, and today's risks
  • Yesterday's results against target: safety, quality, delivery, cost, people
  • Today's plan and staffing
  • Open actions: done, late or blocked
  • New problems: fix today, or escalate

Tier 2 area review (20 to 30 minutes)

  • Safety across the area
  • The lines' boards read together: where is the area red
  • Escalations from tier 1: decide, assign or escalate
  • Cross-shift and cross-line actions
  • What goes to the plant review

Tier 3 plant review (45 to 60 minutes)

  • Safety and people
  • Plant KPIs against plan for the week and the month
  • Escalations from the areas
  • Repeat problems: start a project or an A3
  • Decisions on priorities and resources, and the answers sent back down

Free printable versions: the daily huddle agenda, the tier 2 meeting agenda and the monthly business review.

Signs your meeting cadence needs fixing

  • The same red comes back week after week and nobody owns it: the escalation path is missing.
  • Supervisors hear about night-shift problems in the corridor: the handover is not written down.
  • The plant review spends its first half hour building the numbers: the KPIs are not ready before the meeting.
  • Actions are agreed but never checked: nobody reads open actions at the start of the next meeting.
  • People skip a meeting and nothing changes: that meeting has no decision to make.
  • Tier 2 starts before tier 1 has finished: the timetable is not staggered.

Running the cadence in LeanSuite

In LeanSuite each level's meeting is a series in Daily Standard Work with its own cadence, purpose and agenda, and each agenda item has an owner and its minutes. Owners prepare their item before the meeting: highlights, lowlights, issues, priorities and the support they need. Their KPIs fill in by themselves, met or missed against target. In the room you go item by item, turn a request for support into an action, and actions from earlier meetings come back until they are ticked off. The tier boards run in Lean Studio, and anything a tier cannot fix is escalated to the next one with its history. See how a meeting runs.

Structured Meetings

Run every level's meeting on its cadence in LeanSuite

LeanSuite keeps every level's meeting as a series, with each item's KPIs filled in before anyone walks in and the open actions carried from week to week.

FAQ

Questions about meeting cadence

  1. The fixed rhythm of a team's recurring meetings: which meetings happen, how often, how long they last, who attends and in what order. In a plant it usually runs from a daily huddle on each line to a weekly plant review and a monthly business review.

  2. A short handover at every shift change, a 10 to 15 minute tier 1 huddle at the start of each shift, a 20 to 30 minute tier 2 area review once a day after the huddles, a weekly tier 3 plant review and a monthly business review. Adjust the times and lengths to your shifts.

  3. Tier 1 every shift or every day, tier 2 every day or every week depending on how fast the area's problems move, tier 3 weekly in most plants and daily in some, and tier 4 monthly. The rule is that each tier meets often enough to answer what the tier below sends up.

  4. Ten to fifteen minutes, standing at the board. If it runs longer it has usually turned into problem solving, which should be its own session with the people who can fix the problem.

  5. Frequency is how often one meeting happens. Cadence is the whole rhythm: every recurring meeting, its length, who attends, and the order they run in so that each one feeds the next.

  6. Problems raised on the line reach the right level the same day or the same week, actions are checked at the next meeting, the same red does not come back for weeks, and nobody spends the first half of a review building the numbers.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.