Free tool
Work sampling observations calculator
A work sampling study needs n = z² × p × (1 − p) ÷ e² random observations, where p is the share of time you expect for the activity, e is the accuracy you want in points, and z is 1.96 for 95% confidence. For an activity at about 20% of the time, measured to within 4 points, that is 1.96² × 0.20 × 0.80 ÷ 0.04² = 384.2, so 385 observations.
Work sampling sample size formula
Observations, nequalsz² × p × (1 − p) divided by e²
or nequalsz² × (1 − p) divided by s² × p
Accuracy reached, eequalsz × √(p × (1 − p) ÷ n)
Roundsequalsn divided by people or machines per round
Each one seen is one observation
At random times, to get the days
Shows the accuracy you have now, with the share above
Pre-filled with the worked example below: a packing cell where a pilot put waiting at 20% of the time.
Observations needed
385
To put a 20% share between 16% and 24% at 95% confidence.
The working
z = 1.96 for 95% confidence. p = 0.2. e = 0.04.
n = z² × p × (1 − p) ÷ e² = 1.96² × 0.2 × 0.8 ÷ 0.04² = 384.2, so 385.
Rounds = 385 ÷ 4 = 96.3, so 97.
Days = 97 ÷ 25 = 3.9, so 4.
Rounds
97
4 observed on each round
Days of study
4
At 25 rounds a day. Cover every weekday and shift the question spans.
The same accuracy, relative
± 20%
4 points as a share of 20%
With z rounded to 2
400
How Barnes and other older texts work the 95% sum
- People seen on the same round are not fully independent: one stopped line idles everyone at once. Treat the count as a minimum and spread the rounds over every shift and weekday the question covers.
Next step
Want to track this every week?
Bring this result to a 45-minute demo and we will show where it fits in LeanSuite's Time and Motion Study.
How to use it
Size the study before the first round
1. Pick the one activity the study is about. Waiting, walking, machine idle: the category whose share you need to know. Size the study for that one.
2. Enter the share you expect. Use a pilot of 50 to 100 observations if you have one. If you have nothing, 50% is the safe entry.
3. Say how the accuracy is stated, then enter it. In points of the whole, or as a percent of the share. Switching keeps the same interval and rewrites the figure, so you can see both.
4. Choose the confidence level. 95% unless you have a reason.
5. Add the people or machines per round and the rounds per day. You get the rounds to walk and the days the study takes.
6. Come back during the study. Enter the observations so far and the latest share. The calculator shows the accuracy you have and how many are left.
Work sampling sample size example
Illustrative numbers, not a benchmarkA packing cell has four packers. The supervisor believes the cell loses time waiting for product. A pilot of 80 observations found 16 waiting, so p is about 0.20. The team wants the answer to within 4 points at 95% confidence, and the observer can make 25 rounds a day. Illustrative numbers.
Step 1
z = 1.96, p = 0.20, e = 0.04.Step 2
n = 1.96² × 0.20 × 0.80 ÷ 0.04² = 3.8416 × 0.16 ÷ 0.0016 = 384.2, so 385 observations.Step 3
Rounds = 385 ÷ 4 = 96.3, so 97.Step 4
Days = 97 ÷ 25 = 3.9, so 4.Step 5
The same accuracy stated the other way: 4 points on a 20% share is plus or minus 20% of the share.
Observations needed at 95% confidence
| Expected share | ± 2 points | ± 3 points | ± 4 points | ± 5 points |
|---|---|---|---|---|
| 5% (or 95%) | 457 | 203 | 115 | 73 |
| 10% (or 90%) | 865 | 385 | 217 | 139 |
| 20% (or 80%) | 1,537 | 683 | 385 | 246 |
| 30% (or 70%) | 2,017 | 897 | 505 | 323 |
| 50% | 2,401 | 1,068 | 601 | 385 |
z = 1.96, rounded up. The count is highest at 50% and the same for p and 1 − p. Halving the error takes four times the observations.
Absolute or relative: say which
"Plus or minus 5%" can mean two things, and most sizing mistakes start here.
- Absolute, in points: 20% plus or minus 5 points is 15% to 25%. It needs 246 observations at 95%.
- Relative, a percent of the share: 20% plus or minus 5% of 20 is 19% to 21%. It needs 6,147.
Relative accuracy gets expensive fast for small shares, because the same percent is a thinner slice. Write the accuracy in points in the study plan and nobody has to guess.
What the count assumes
- Random times. Rounds on the hour catch the same part of every cycle and every break. Draw the times at random, and vary the route.
- Independent observations. Four packers on one line stop together. Treat the count as a minimum and add rounds.
- Instant coding. Record what the person is doing at the moment you see them, not what they were doing or are about to do.
- A representative period. A week with a launch or a breakdown answers a different question.
The work sampling guide covers the random schedule, the tally sheet and how to bring operators along.
When work sampling is the wrong tool
- You need element times for a short repetitive job. Use a time study, and the time study sample size calculator for the number of cycles.
- The activity is rare. At 1% of the time, even plus or minus half a point takes 1,522 observations. Keep a log of each occurrence instead.
- You need to know the order things happen in. Sampling gives shares, not sequence.
Sources and how this calculator was checked
- Ralph M. Barnes, Motion and Time Study: Design and Measurement of Work, 7th ed. (Wiley, 1980): the work sampling formula in its relative form, with z rounded to 2.
- Andris Freivalds, Niebel's Methods, Standards, and Work Design, 12th ed. (McGraw-Hill, 2009): the binomial sample size for work sampling and the interval on a result.
- L. H. C. Tippett, who introduced the method in British textile mills in the 1930s as the "snap reading" method.
Unit tests recompute the packing cell by hand, all twenty cells of the table above, the relative form, the three confidence levels and the interval on a finished study.
Embed this calculator
Teaching this, or writing about it? Paste this code into your site, course page or intranet and the calculator works right there. It is free, with no sign-up.
<iframe src="https://www.theleansuite.com/tools/work-sampling-observations-calculator/embed" title="Work sampling observations calculator by LeanSuite" width="100%" height="1950" style="border:0;max-width:1000px" loading="lazy" allow="clipboard-write"></iframe>
<p style="font:13px/1.4 sans-serif"><a href="https://www.theleansuite.com/tools/work-sampling-observations-calculator">Work sampling observations calculator</a> by LeanSuite</p>How LeanSuite helps
LeanSuite's AI time and motion study times every element from one phone video of the process, and its study report gives cycle time, standard time, takt and units per hour, each linked to the video it came from. Use work sampling to find where a team's time goes, then film the job that turns out to matter.
See Time and Motion StudyRead more
- Free template: Time study sheet
- Time study sample size calculator: how many cycles to time
- Overall labor effectiveness calculator: what the lost time costs
- Time study in the lean glossary
- Work sampling: how to plan the study, take the observations and read the result
- Time study or work sampling: which one fits the question
FAQ
Work sampling observations calculator: common questions
n = z² × p × (1 − p) ÷ e², where p is the share of time you expect for the activity, e is the accuracy you want in points as a decimal, and z is 1.96 for 95% confidence. For an activity at about 20% that you want to within 4 points, n = 1.96² × 0.20 × 0.80 ÷ 0.04² = 384.2, so 385 observations. Halving the error takes four times as many.
Absolute accuracy is in points of the whole: 20% plus or minus 5 points is 15% to 25%. Relative accuracy is a fraction of the estimate itself: 20% plus or minus 5% of 20 is 19% to 21%. The second is five times tighter here and needs 25 times the observations, 6,147 against 246. Always write which one you mean.
95% is the usual choice, with z = 1.96. It means that if you repeated the study many times, about 95 in 100 would land within the accuracy you set. 90% (z = 1.645) needs about 30% fewer observations and suits a first look. 99% (z = 2.576) needs about 73% more and is rarely worth it for a floor study.
Run a pilot. Take 50 to 100 observations over a day or two, work out the share, and use it to size the full study. If you cannot, enter 50%, which gives the largest count for any accuracy in points. Then recheck as the tallies come in: enter the observations so far and the latest share, and the calculator shows the accuracy you already have.
Divide the observations by the number of people or machines you see on each round to get rounds, then by the rounds you can make in a day. 385 observations of a four-person cell is 97 rounds, and at 25 rounds a day that is 4 days. Run at least a full week anyway, at random times, so every weekday and shift is in the sample.
Two reasons. Many older texts, Barnes among them, round z to 2 for 95% confidence, which turns 385 into 400. And they often state accuracy as relative, using n = z² × (1 − p) ÷ (s² × p). That is the same formula with e = s × p. The calculator shows both forms and the count with z = 2 so you can match either.
More free lean tools
All tools- OEE calculatorOverall equipment effectiveness from shift time, downtime, ideal cycle time and part counts.
- Downtime cost calculatorWhat an hour, an event and a year of unplanned downtime cost, from lost output, idle labour, scrap and overtime.
- SMED changeover calculatorTime saved by moving changeover steps from internal to external, capacity freed per week and the smaller batch it allows.
- Takt time calculatorThe pace a line must hit to meet customer demand, from shift time, breaks and daily demand.
- Cycle time calculatorCycle time against takt, units per hour, capacity per shift and the gap to daily demand.
- Line balancing calculatorLine efficiency, balance delay and the minimum number of stations from station times and takt.
- Bottleneck calculatorThe step that limits your line, from each step's cycle time, machines and uptime, with daily capacity and the gap to demand.
- First pass yield (FPY) calculatorFirst pass yield at each step and rolled throughput yield (RTY) across the whole process.
- Cost of poor quality (COPQ) calculatorTotal COPQ and cost of quality, and each as a share of revenue, from the four quality cost categories.
- Process capability (Cp, Cpk) calculatorCp and Cpk against your specification limits, plus Pp and Ppk from pasted measurements, with a distribution chart.
- DPMO and sigma level calculatorDPMO, defects per unit, yield and sigma level from the defects found, units checked and opportunities per unit.
- MTBF and MTTR calculatorMean time between failures, mean time to repair and availability from operating time, failures and repair time.
- Lead time calculatorManufacturing lead time from WIP and throughput (Little's Law), and the share of it that adds value.
- Throughput time calculatorThroughput time from process, inspection, move and wait time, the share of it that adds value, and units per hour.
- Kaizen savings calculatorYearly savings, payback in months and first-year ROI of an improvement, from time saved, scrap avoided and its costs.
- TEEP calculatorTotal effective equipment performance: OEE multiplied by how much of all calendar time you plan to run.
- Overall labor effectiveness (OLE) calculatorHow well paid labor hours turn into good output: availability, performance and quality of the crew.
- Inventory turnover and days on hand calculatorHow many times stock turns over in a period and how many days of it you hold, from COGS and average inventory.
- Safety stock calculatorSafety stock and reorder point from the service level you want, average demand and lead time, and how much each varies.
- Scrap rate calculatorScrap rate, the cost of scrap per period and per year, and what reaching a target rate would save.
- TRIR and DART rate calculatorOSHA recordable and DART incident rates from your 300A case counts and hours, and what one more case does to them.
- NIOSH lifting equation calculatorRecommended weight limit and lifting index for a two-handed lift, with every multiplier shown so you can see what to redesign.
- Time study sample size calculatorHow many cycles of an element to time, from your first readings, with the t formula, the ILO formula and the range method.
- Standard time calculatorObserved times, a rating and an allowance in; normal time, standard time, units per hour, pieces per shift and labour cost per unit out, with the working.
- Production capacity calculatorMachine and labor steps in; each step's capacity per shift, the bottleneck, line capacity, takt time and utilization against demand out, with the working.
- TMU to seconds converterA time in TMU, MODs, seconds, minutes or hours, shown in all five at once, with the standard time and units per hour after your allowance.
- Allowance calculator: personal, fatigue and delayPersonal, fatigue and delay allowances for one job added up, applied under either allowance formula, with the standard time and the minutes per shift.
- Maintenance strategy selectorAnswer the RCM questions for one failure mode and get the maintenance strategy, the reasoning and the check or test interval.
- Noise dose and TWA calculatorDose and 8-hour TWA for a shift of noise levels under OSHA and NIOSH, which limits are reached and how much loud time to cut.
- Risk matrix calculatorSeverity times likelihood on a 3 x 3, 4 x 4 or 5 x 5 risk matrix, the band and its action, editable banding, and the score after further controls.
- Repair or replace calculatorEquivalent annual cost of keeping and repairing an old machine against buying a new one, with each one's economic life and the break-even figures.
- Compressed air leak cost calculatorAir lost, kW and cost a year for each tagged leak from its size and the pressure, ranked so the biggest gets fixed first.
- Machine hour rate calculatorWhat one productive hour of a machine costs, with and without the operator, the cost per part and how utilisation moves the rate.
- Total manufacturing cost calculatorTotal manufacturing cost, cost of goods manufactured, cost per unit and the overhead rate from materials, labor and overhead.
- Acceptance sampling calculatorRead the OC curve and the real risks of a sampling plan, find the plan for your AQL and LTPD, or size a zero-defect test.
- Shift schedule plannerTen shift patterns on real dates: calendar for each crew, hours a week, weekends off, coverage and the weeks over 40 hours.
- Pareto chart makerPaste categories and counts: sorted bars, cumulative percentage line and the vital few at the 80% line, as a PNG or SVG.
- Histogram makerPaste measurements: the histogram with automatic or chosen bins, plus mean, median and standard deviation, as a PNG or SVG.
- Box plot makerPaste one or more groups of numbers: box plots with quartiles, IQR, whiskers and outliers by the 1.5 IQR rule, as a PNG or SVG.
- Fishbone diagram makerName the problem, list causes under the 6M bones, and download the Ishikawa diagram as a PNG or SVG.
- 5 Whys canvasWrite the problem, answer up to five whys, state the root cause and countermeasure, then print the one-page canvas.
- Lean maturity self-assessmentScore 27 statements across nine dimensions and get a band for each, an overall band, where to start and the guides to read.
- Lean method navigatorSix questions about one problem, then the lean method to start with, the two that follow, why each fits, five steps for Monday and what it will not solve.
- Manufacturing ROI calculatorAnswer a few questions about your shop floor, shifts and downtime to estimate your potential ROI with LeanSuite.