Allowance calculator: personal, fatigue and delay

An allowance is the time added to normal time for personal needs, fatigue and unavoidable delays (PFD). Add the parts for one job, then apply the total: standard time = normal time × (1 + allowance) when the parts are percentages of normal time, or normal time ÷ (1 − allowance) when they are shares of the shift. Personal 5, basic fatigue 4, standing 2 and a measured delay of 4 make 15%, which turns a normal time of 0.672 minutes into a standard of 0.7728.

Allowance formula

Allowance, Aequalspersonal + basic fatigue + variable fatigue + delay

Standard timeequalsnormal time × (1 + A)

or Standard timeequalsnormal time divided by 1 − A

Delay allowanceequalsunavoidable delay time divided by working time

Share of the shiftequalsA added to normal time divided by 1 + A

A is a decimal (0.15 for 15%). Use the first standard time line when each part is a percentage added to normal time, as in the ILO table, and the second when each part is a share of the whole shift. Freivalds (Niebel's Methods, Standards, and Work Design) gives both. The last line converts one to the other: 15% added to normal time is 13.04% of the shift.

Washroom, a drink, a short pause. ILO example: 5

Recovery every job needs. ILO example: 4

Variable fatigue: what this job adds

Example values from the table the ILO printed in its earlier editions and Niebel reprints, in percent of normal time. They are examples, not a rule: use your site's table if it has one.

Heat, or a grade not listed above

Measured at the job. No table gives it.

How your site states allowances

Standard = normal × (1 + allowance). Use it when each part is a percentage added to working time, as in the ILO table.

For the standard time

For allowance minutes per shift

Pre-filled with the worked example below: a standing drill press job with a measured delay of 4%.

Total allowance

15%

Added to normal time: standard time = normal time × (1 + 0.15), which is normal time × 1.15.

What the allowance is made of

Personal needs5%
Basic fatigue4%
Variable fatigue2%
Unavoidable delay4%

The working

Variable fatigue = 2 (standing) = 2%.

Total = 5 + 4 + 2 + 4 = 15%.

Standard time = 0.672 × (1 + 0.15) = 0.7728 min.

Allowance in the shift = 480 − 480 ÷ 1.15 = 62.6 min.

Standard time

0.7728 min

46.4 s. 0.1008 min of it is allowance.

Units per hour

77.6

60 ÷ standard minutes, one operator

Allowance per shift

62.6 min

417.4 min of work in 480

The same, as a share of the shift

13.04%

15 ÷ (100 + 15)

Read as a share of the shift, the same 15% would multiply normal time by 1.1765, not 1.15, and give 0.7906 min. Check which one your allowance table means before the standard is published.

Email me my results

Optional. Get these inputs and results in your inbox, with a link back to this calculator.

We may follow up about LeanSuite. See our Privacy Notice.

Next step

Want to track this every week?

Bring this result to a 45-minute demo and we will show where it fits in LeanSuite's Time and Motion Study.

How to use it

Build the allowance for one job

1. Enter the two constants. Personal needs and basic fatigue apply to every job. Use your site's figures. The fields start at the ILO example values of 5 and 4.

2. Walk the job and tick what it adds. Standing, bending, lifting, poor light, noise, close attention. Each tick adds an example value. Type anything else, such as heat, in the other field.

3. Enter the delay you measured. Unavoidable delay minutes divided by working minutes. No table can give you this one.

4. Say how your site states allowances. Added to normal time, or a share of the shift. The calculator shows the same allowance both ways.

5. Add the normal time and the shift if you want the standard. You get the standard time, units per hour and the minutes of the shift the allowance covers.

Allowance calculation example

Illustrative numbers, not a benchmark

An operator drills brackets at a press, standing. The site uses 5% for personal needs and 4% for basic fatigue. An all-day study found 16 minutes of unavoidable delay against 400 minutes of work. Normal time for the job is 0.672 minutes and the shift is 480 paid minutes. Illustrative numbers.

  1. Step 1

    Variable fatigue = 2% for standing.
  2. Step 2

    Delay = 16 ÷ 400 = 4%.
  3. Step 3

    Total allowance = 5 + 4 + 2 + 4 = 15%, added to normal time.
  4. Step 4

    Standard time = 0.672 × (1 + 0.15) = 0.7728 min.
  5. Step 5

    Units per hour = 60 ÷ 0.7728 = 77.6.
  6. Step 6

    Allowance in the shift = 480 − 480 ÷ 1.15 = 62.6 min, leaving 417.4 min of work.
The allowance is 15% and the standard is 0.7728 minutes a bracket. The same 15% read as a share of the shift would give 0.672 ÷ 0.85 = 0.7906 minutes, 2.3% longer. Stated the other way round, 15% added to normal time is 13.04% of the shift.

The example values, and where they come from

The ticks use entries from the table of allowances the ILO printed in the earlier editions of Introduction to Work Study, which Niebel's textbook reprints. All are percentages of normal time. They are examples, not a recommendation for your job.

Example allowances from the ILO table, percent of normal time
AllowancePercent
Personal needs (every job)5
Basic fatigue (every job)4
Standing2
Awkward position, such as bending2
Very awkward position, lying or stretching7
Lifting or force of 20 lb3
Lifting or force of 40 lb9
Light well below what is recommended2
Intermittent loud noise2
Fine or exacting work2
Complex process, wide span of attention4
Medium monotony1
Tedious work2

The table has more grades in each row, and a row for heat and humidity set from measured conditions. The allowances section of the standard time guide has the full ranges.

Measuring the delay allowance

Only unavoidable delays count: ones a trained operator following the method could not have prevented.

  • All-day study: watch a full shift and total the unavoidable delay minutes. Divide by the minutes spent working.
  • Work sampling: take random observations over several days. The share of tallies in unavoidable delay, divided by the share working, is the allowance. The work sampling calculator says how many observations that takes.

If your site states allowances as a share of the shift, divide the delay minutes by the shift minutes instead.

What does not belong in an allowance

  • Avoidable delays. A late start, a chat, waiting for material that is late every day. Fix them.
  • A recurring machine fault. A press that jams every hour is a maintenance problem. If it must be covered, give it a temporary allowance with an end date.
  • Fatigue on machine time. While a machine runs on its own the operator is recovering. Some systems give machine-controlled time the personal allowance only.
  • Breaks counted twice. If the allowance covers rest, do not take the same breaks off the shift again when you work out capacity.

Sources and how this calculator was checked

  • International Labour Office, Introduction to Work Study, ed. George Kanawaty: relaxation allowances as a percentage of basic time, with constants of 5% for personal needs and 4% for basic fatigue in the editions of 1969 to 1979, and a points system in the 4th revised edition of 1992.
  • Benjamin W. Niebel, Motion and Time Study, 7th ed. (Irwin, 1982): the reprinted table of ILO recommended allowances the example values come from.
  • Andris Freivalds, Niebel's Methods, Standards, and Work Design, 12th ed. (McGraw-Hill, 2009): standard time as normal time × (1 + allowance), and normal time ÷ (1 − allowance) when the allowance is a fraction of the workday.

Unit tests work the drill press job by hand under both conventions, check the conversion between them and the example table, and cover a zero allowance, a share of the shift of 100% and blank optional fields. This is general practice, not advice on any labor agreement: where allowances are negotiated, the agreed figures apply.

Embed this calculator

Teaching this, or writing about it? Paste this code into your site, course page or intranet and the calculator works right there. It is free, with no sign-up.

<iframe src="https://www.theleansuite.com/tools/allowance-calculator/embed" title="Allowance calculator: personal, fatigue and delay by LeanSuite" width="100%" height="2300" style="border:0;max-width:1000px" loading="lazy" allow="clipboard-write"></iframe>
<p style="font:13px/1.4 sans-serif"><a href="https://www.theleansuite.com/tools/allowance-calculator">Allowance calculator: personal, fatigue and delay</a> by LeanSuite</p>

How LeanSuite helps

LeanSuite's AI time and motion study times every element from one phone video of the process, and its study report gives cycle time, standard time, takt and units per hour, each linked to the video it came from. Use this calculator to build or check the allowance that goes into that standard.

See Time and Motion Study

FAQ

Allowance calculator: personal, fatigue and delay: common questions

  1. Time added to normal time for things that are part of a working day but not part of the task: personal needs, recovery from fatigue and unavoidable delays. Normal time assumes the operator works every second of the shift. Nobody does, so the allowance turns normal time into a standard time you can plan a whole shift on. In the US the three parts are called PFD.

  2. Add four parts. Take the personal and basic fatigue figures from your site's table. Walk the job and add a variable fatigue figure for each condition it has, such as standing or lifting. Measure the unavoidable delays and divide by working time. In the worked example, 5 + 4 + 2 for standing + 4 for delay makes 15%, added to normal time.

  3. Personal is time for the washroom, a drink and a short pause, and it hardly depends on the job. Fatigue is time to recover from the effort: a basic amount for every job, plus more for standing, awkward posture, force, heat, noise, close attention or monotony. Delay covers short interruptions a trained operator could not have prevented, such as a tote change or a word from the supervisor.

  4. No. Each site sets or negotiates its own. The most quoted figures come from an example table the ILO printed in earlier editions of Introduction to Work Study, where personal needs are 5% and basic fatigue 4% of normal time, with additions such as 2% for standing. The 1992 edition replaced that table with a points system. Treat any table as a starting point for your own.

  5. It depends on what your percentages are percentages of. If each part is added to working time, as in the ILO table, use normal time × (1 + A). If each part is minutes out of the whole shift, such as 72 of 480, use normal time ÷ (1 − A). At 15% the second gives a standard 2.3% longer, so mixing them up moves every standard.

  6. Watch the job for a full shift, or take random observations over several days, and add up the unavoidable delay time. Divide it by the time spent working. A study that finds 16 minutes of unavoidable delay against 400 minutes of work gives 16 ÷ 400 = 4%. Leave out avoidable delays: a late start, a chat, or hunting for a tool that has no home.