Time observation sheet: stopwatch study template with continuous and snap-back timing

A time observation sheet is the form you record a stopwatch time study on: the elements of the job down the side, the cycles across the top, a reading line and an element time line for each element, then rating, selected time, normal time and standard time. This one handles both ways of timing. In snap-back timing you reset the watch at each break point and write the element time; in continuous timing the watch runs and you write the reading at each break point, and the sheet subtracts. The Excel file does the sums for up to 12 elements and 20 cycles, switches the allowance between added to normal time and a share of the shift, and checks whether you have timed enough cycles. It has a filled-in example of each timing method. For a lighter 10-cycle sheet see the time study sheet.

See the sheet before you downloadPDF, 3 pages. Also Excel and Word

Free to use: print it, copy it and edit it for your team. Enter your name and work email once to download.

The time observation sheetElements down the side, ten cycles across with a reading line and a time line for each element, then rating, selected time and normal time.
12 elements by 20 cyclesSnap-back or continuousRating columnLeft-out readingsOccasional elementsAllowance switchCycle checkTwo filled examples

Page 1 of the real file. PDF, 3 pages. Also Excel and Word. See every page

Filled-in Time observation sheet: a junction box job timed over 20 cycles
The same sheet filled in with the worked example (page 2 of the PDF, illustrative numbers). Open full size (opens the picture in a new tab)

When to use it

When to use the time observation sheet

  • When you are going to time a job with a stopwatch or from video and want one sheet that does the arithmetic.
  • When you need to choose between snap-back and continuous timing and want to see both worked.
  • When a standard time must include rating and an allowance, and the allowance convention has to be stated.
  • When you want an automatic check of how many cycles you need against the cycles you have timed.
  • When the sheet has to be printed for the floor and typed up afterwards, or typed in live.

How to fill it in

  1. 1

    Head up the sheet and list the elements

    Job, station, part, operator, analyst, date, shift and the method sheet revision. Then the elements in order, each with the break point where it ends. Use the element breakdown sheet to build this list.
  2. 2

    Pick the settings

    Time unit (seconds or minutes), timing method (snap-back or continuous), selected time (average or lowest repeatable), the allowance percent, how it is applied, and the confidence and accuracy for the cycle check.
  3. 3

    Time the cycles

    Type one reading per element per cycle on the R line. Continuous: the watch reading at each break point. Snap-back: the element time. Rate each manual element as you go, 100 for normal pace; machine elements stay at 100.
  4. 4

    Leave out readings with a known cause, and add occasional elements

    A dropped part or a question from the supervisor goes in the left-out readings table with its cycle, element and cause. It shows in brackets and drops out of the average. Occasional elements go in with how often they happen, and their time is spread over the units they serve.
  5. 5

    Read the result and the cycle check

    Selected time x rating / 100 gives normal time. Standard time adds the allowance. The cycle check compares the cycles you timed with the cycles the formula needs for the most variable element: keep timing until you have enough.

What is in the download

Time observation sheet: every page of the PDF

All 3 pages, pictured from the file you download. The download also comes as Excel and Word.

  1. Page 1 of 3 of the Time observation sheet PDF: Time observation sheet
    PDF page 1 of 3Time observation sheet
  2. Page 2 of 3 of the Time observation sheet PDF: Time observation sheet: example
    PDF page 2 of 3Time observation sheet: example
  3. Page 3 of 3 of the Time observation sheet PDF: Time observation sheet: how to use it
    PDF page 3 of 3Time observation sheet: how to use it
Back to the download buttons

Formulas on the sheet

How each figure is worked out

The sheet uses these formulas, written as the sheet does and matching the time study sample size calculator on this site.

  • Element time (continuous)

    Formula
    This reading minus the reading before it
  • Selected time

    Formula
    Average of the readings used, or the lowest time that came up at least twice
  • Normal time

    Formula
    Selected time x rating / 100
  • Occasional element, per unit

    Formula
    Normal time / units between occurrences
  • Standard time, allowance added to normal time

    Formula
    Normal time x (1 + allowance)
  • Standard time, allowance as a share of the shift

    Formula
    Normal time / (1 - allowance)
  • Units an hour

    Formula
    3,600 / standard time in seconds
  • Cycles needed, each element

    Formula
    (t x s / (k x mean)) squared, rounded up; take the largest

A filled-in example

Illustrative, not a benchmark

An illustrative study: the junction box job, 20 cycles, snap-back, element times in seconds, allowance 15% added to normal time.

  • Five manual elements average 9.0, 15.0, 23.0, 12.0 and 6.0 seconds. Elements 1 and 2 are rated 110, the rest 100.
  • A screw was dropped in cycle 8 of element 3 (36 seconds). It is left out with its cause, so element 3 uses 19 readings.
  • Tote swap and screw restock takes 52 seconds, once in 20 units: 2.6 seconds a unit.
  • Normal time is 9.9 + 16.5 + 23.0 + 12.0 + 6.0 + 2.6 = 70.0 seconds. Standard time is 70.0 x 1.15 = 80.5 seconds, or 44.7 units an hour.

The cycle check says 11 cycles are needed for the most variable element and 20 were timed, so there is enough. The same 15% taken as a share of the shift gives 70.0 / 0.85 = 82.4 seconds, so the sheet makes you say which convention you used. The job and the numbers are made up.

Common mistakes

  • Rating the machine

    Machine-controlled time is not rated. Keep the rating at 100 on machine elements and rate the manual ones one by one.

  • Leaving a reading out without a reason

    A reading leaves the average only if you know what caused it. Circle it during the study, write the cause, and list it in the left-out table.

  • Mixing up the two allowance conventions

    A 15% allowance added to normal time gives 80.5 from 70.0. As a share of the shift it gives 82.4. Pick one, write it on the sheet and apply it the same way every time.

  • Stopping at ten cycles for every job

    The number of cycles depends on how much the element varies. Run the cycle check after the first ten and keep timing until the most variable element has enough.

  • Using the lowest repeatable time for a standard time

    Lowest repeatable is for a Toyota-style standardized work sheet. For a standard time with rating and allowances, use the average.

Download the template

Free to use: print it, copy it and edit it for your team. Enter your name and work email once to download.

Run this template in LeanSuite

LeanSuite's Vision AI does the time study from one phone video of the process: it times every element, splits each operator's time into value-added, semi-value-added and non-value-added, and links each figure to its video frame for you to review and certify.

See it in a 45-minute demo

FAQ

Time observation sheet: common questions

  1. A form for recording a time study: the job and operator, the elements in order, the readings for each cycle, the rating, and the calculation that turns them into a standard time. This one is an observation sheet in Excel, PDF and Word, built for a stopwatch.

  2. In snap-back timing you reset the watch to zero at each break point and write down the element time. In continuous timing the watch runs through the whole cycle, you write the reading at each break point, and subtract to get element times. Continuous never loses time between elements.

  3. Normal time is the average observed time x rating / 100. Standard time is normal time plus an allowance: normal time x (1 + allowance) when the allowance is added to normal time, or normal time / (1 - allowance) when it is a share of the shift. State which one you use.

  4. Enough that the average is within the accuracy you want at the confidence you want. The formula is n = (t x s / (k x mean)) squared, rounded up, taking the largest across the elements. The sheet runs this check as you type the readings.

  5. Yes. Upload the Excel file to Google Drive and open it with Google Sheets. It uses ordinary formulas, drop-down lists and conditional formatting, and no macros. Check the print settings in Sheets before you print, as page setup there differs.

More free templates

All templates
Browse all 312 templates

Can't find the template you need?

Tell us what you're looking for. We'll make it and send it to your inbox, free.

A shift handover sheet, a red tag log, a changeover checklist for one machine: if your team uses it on the floor, ask.

By sending this form you agree to our Terms of Service and Privacy Policy.