Time and motion study: what it is, the steps and a worked example

Short answer

A time and motion study watches a job closely to answer two questions: what is the best way to do it, and how long should that take a trained person at a normal pace? The answer is a standard time you can cost, staff and plan with.

Fix the method first, then time it. Split the job into elements, time them over enough cycles, rate the operator's pace and add allowances: standard time = observed time x rating x (1 + allowance). In the worked example below, 67.6 seconds observed becomes an 80.5 second standard, which is 44.7 units an hour.

Last reviewed:

What is a time and motion study?

A time and motion study in one picture

Example numbers
  1. 1Motion study

    Watch the job

    Film or observe a few cycles before you time anything.
  2. 2Motion study

    Fix the method

    Cut wasted motion. Agree one way and write it down.
  3. 3Time study

    Time the elements

    67.6 sobserved: 5 elements, 20 cycles, plus the tote swap
  4. 4Time study

    Rate the pace

    70.0 snormal time: what the job takes at a normal pace
  5. 5Time study

    Add allowances

    80.5 sstandard time: 70.0 × 1.15

Five stages. Watch the job, then fix the method: that is the motion study. Time the elements, 67.6 seconds a unit observed. Rate the pace, 70.0 seconds normal. Add allowances, 80.5 seconds standard: that is the time study.

Stages 1 and 2 change the job. Stages 3 to 5 measure it. The numbers are the worked example on this page: 67.6 s observed, 70.0 s normal, 80.5 s standard.

A time and motion study is two studies done in order. The motion study asks how the job should be done: which movements, in what sequence, with what within reach. The time study asks how long that method takes a trained person working at a normal pace, with fair allowances for rest and small delays. What comes out is a standard time.

The order matters. Time a clumsy method and you get a precise number for a job nobody should be doing that way. So you fix the method first, then put a stopwatch or a camera on it.

Four terms get used as if they meant the same thing. They don't, and a textbook, an auditor or a union representative will hold you to the difference.

How the four terms fit together

Work study

Examine the work, improve it, then measure it

First half

Method study

How should the job be done?

  • Motion studyThe hands, eyes and feet, up close
  • Process chartsEvery step of the job in sequence
  • Spaghetti diagramThe walking, drawn on the floor plan

Second half

Work measurement

How long should it take?

  • Time studyDirect timing with a stopwatch or video
  • Work samplingRandom observations over several days
  • Predetermined timesMTM, MOST and MODAPTS: times built from motions
  • EstimatesFrom similar jobs done before

Time and motion study = motion study + time study

Method first, then time.

Work study has two halves. Method study asks how the job should be done and includes motion study, process charts and the spaghetti diagram. Work measurement asks how long the job should take and includes time study, work sampling, predetermined times and estimates. A time and motion study is motion study followed by time study.

Work study is the whole. A time and motion study is the two yellow boxes, one from each half, done in that order: fix the motions, then time what is left.
Work study, method study, motion study and time study side by side
TermQuestion it answersWhat you doWhere the name comes from
Work studyCan this work be done better, and how long should it take?The umbrella term: method study plus work measurementThe International Labour Organization (ILO) and British practice
Method studyWhat is the best way to do the job?Record the present method, question every step, then design and install a better oneThe ILO's term for the first half of work study
Motion studyWhich hand and body movements can go?Watch or film the hands, eyes and feet, and cut reaches, searches and regraspsFrank and Lillian Gilbreth. Today it is the close-up end of method study
Work measurementHow long should the job take a qualified worker?Time study, work sampling, predetermined times or estimatesThe ILO's term for the second half of work study
Time studyHow long does this method take, measured directly?Time each element over many cycles, rate the pace and add allowancesFrederick W. Taylor

Who developed it

Frederick W. Taylor began timing work with a stopwatch at the Midvale Steel Company in Philadelphia in 1881. His idea was to split a job into small elements, time each one, and build a fair day's work from the parts instead of from a foreman's guess.

Frank and Lillian Gilbreth came at it from the other side. Frank was a bricklaying contractor, and he studied the movements themselves: in Taylor's own 1911 account, Gilbreth cut bricklaying from 18 motions a brick to 5. The Gilbreths filmed people working with a clock in the frame and gave names to the basic hand motions, which they called therbligs (their surname, more or less backwards). A video time study today is the same idea with a better camera.

Taylor cared most about the time and the Gilbreths about the one best way. Current practice keeps both and follows the Gilbreths' order: method first, then time.

Why do a time study: the eight decisions it feeds

A standard time is an input. Without one, the decisions below get made on last year's numbers or on somebody's feel for the job. The figures use the example further down this page: one bench assembly job with a standard time of 80.5 seconds a unit.

Eight decisions one standard time feeds

Example numbers

Standard time

80.5 s a unit

  1. Costing

    What does the labor in one unit cost?

    80.5 s x $24.00 an hour / 3,600 = $0.54 a unit

  2. Quoting

    How many hours is this order?

    5,000 units x 80.5 s / 3,600 = 111.8 standard hours

  3. Staffing

    How many people does demand need?

    600 units a day x 80.5 s = 13.4 hours of work, so 2 operators on an 8 hour shift

  4. Line balance

    Does the job fit inside takt?

    Takt is 28,800 s / 600 = 48 s. 80.5 s does not fit, so the work is split across 2 stations

  5. Capacity

    What can one bench make in a shift?

    28,800 s / 80.5 s = 357 units

  6. Layout

    Where do the seconds go?

    Fetching the housing takes 9 of the 65 observed seconds (14%), so its rack is the first thing to move

  7. Ergonomics

    How often is each motion repeated?

    4 screws x 357 units = 1,428 screws a shift, all driven with the same hand

  8. Incentives

    What counts as fair performance?

    380 units in 8 hours = 8.5 standard hours earned, a performance of 106%

One measured number answers all eight questions. Change the standard and every answer moves with it, which is why it has to be right. The $24.00 labor rate, the demand of 600 units a day and the 8 hour shift are example figures.

The study itself shows you things no report does. Watch 20 cycles closely and you see the reach behind the operator, the part that never seats the first time, the wait for a shared tool. Sometimes those fixes are worth more than the number.

Each decision has its own guide: takt time for the pace demand sets, how many operators for the staffing sum, and line balancing for sharing the work across stations.

When a time study is the wrong tool

Direct timing suits repetitive manual work with a settled method and a cycle short enough to watch many times in one sitting: assembly, packing, machine loading, kitting. Outside that, another tool is cheaper or more honest.

When a time study is the wrong tool, and what to use
SituationUse thisWhy
Long, irregular work: maintenance, material handling, supervision, office workWork samplingRandom observations over several days give the share of time spent on each activity, without following anyone with a watch
The job does not exist yet: a new product or a new lineA predetermined motion time system (MTM, MOST or MODAPTS), or times from a similar partThese build a time from the motions on paper. Check it with a time study once the job is running
The machine sets the paceThe machine's own cycle dataA counter is more exact than a watch. Time only the manual loading, unloading and checks
The method changes from cycle to cycleStandard work, then a time studyTiming an unsettled job gives you the average of several methods
Very short cycles, a few seconds longVideo played frame by frame, or a predetermined motion time systemAn observer with a stopwatch cannot read break points that close together
One-off or rarely repeated jobsAn estimate from similar past jobsThere are not enough cycles to measure
A changeover, not a production cycleA SMED studyThe filming and timing are the same, but the aim is to move work outside the stop, not to set a standard
The question is distance or posture, not timeA spaghetti diagram or an ergonomic assessmentThey measure walking and physical risk directly

Is a time study the right tool for this job?

  1. Does the job exist yet, with a trained person doing it?

    If no

    Build the time from a predetermined motion time system or a similar part, then check it with a time study once the job runs.

  2. Is the method settled, the same way on every cycle?

    If no

    Fix the method first. Timing a job that changes from cycle to cycle gives the average of several methods.

  3. Does the work repeat in a cycle you can watch many times in one session?

    If no

    Use work sampling. It suits maintenance, material handling and other long, irregular work.

  4. Is the time set by the person and not by the machine?

    If no

    Take the machine's cycle from its counter or controller, and time only the manual loading, unloading and checks.

  5. Every answer right

    Run a time study: direct timing, by stopwatch or from video.

Four questions in order. If the job does not exist yet, use predetermined times. If the method is not settled, fix the method first. If the work does not repeat in a cycle you can watch many times, use work sampling. If the machine sets the time, use machine data. If every answer is yes, run a time study.

Ask the questions in this order. The first No tells you which tool to pick up, and a time study is what is left when all four answers are Yes.

Even where it fits, a time study has limits. It measures the job as one person did it, on one day, with those parts. It says nothing about quality. It does not see work that happens away from the bench. And the two judgment steps, rating and allowances, are only as good as the plant's agreed definitions. Say so when you present the number.

The steps of a time and motion study, in brief

Six steps cover it. How to conduct a time study takes the timing steps one at a time, with a filled-in observation sheet.

The six steps of a time and motion study

  1. 1

    Decide what the number is for

  2. 2

    Tell the people

  3. 3

    Study and fix the method

  4. 4

    Break the job into elements and time them

  5. 5

    Rate the pace and add allowances

  6. 6

    Use the standard and keep it current

Steps 1 to 3 happen before any timing. Step 6 never finishes: the standard is only good for the method it was set on.
  1. 1

    Decide what the number is for

    A standard for costing needs less precision than one that sets incentive pay. Write down the job, the purpose and the accuracy you need before anything else.

  2. 2

    Tell the people

    Explain the study to the operator and the supervisor, and to the union representative where there is one, before the first observation. Say what is being measured, why, and what will happen with the result.

  3. 3

    Study and fix the method

    Watch or film several cycles. Remove the wasted motion you can see, agree the method and write it down. This is the motion study, and it comes before any timing.

  4. 4

    Break the job into elements and time them

    Split the cycle into elements with clear end points and time each one over enough cycles. The General Electric guide suggests 20 cycles for a job of one to two minutes, and the sample size calculator checks it against your own readings.

  5. 5

    Rate the pace and add allowances

    Adjust the observed time to a normal pace, which is performance rating, then add allowances for personal needs, fatigue and unavoidable delays. Standard time explains both in depth.

  6. 6

    Use the standard and keep it current

    Publish the time together with the method it belongs to. Study the job again when the method, tooling, material or layout changes.

The time study sheet has the columns for steps 4 and 5, and the Excel version does the sums.

A worked example, start to finish

Illustrative example. A plant assembles electrical junction boxes at a bench. One operator seats a housing in a fixture, fits a gasket and cover, drives four screws, labels the unit and places it in a tote. Once every 20 units the operator swaps the full tote and restocks screws. The plant wants a standard time for costing and to decide how many benches it needs.

Method first

The engineer films five cycles before timing anything. Two things stand out: the screw bin sits behind the operator, and housings arrive in a pallet box on the floor. The bin moves to the front of the bench and the housings go on a waist-high rack. Only then does the timing start.

Time the elements

The job splits into five elements, each ending at something you can see or hear. The General Electric guide suggests 20 cycles for a job of this length, so the engineer times 20. In cycle 8 the operator drops a screw. That reading is circled and left out of the average for element 3.

Illustrative: element times for the junction box job (seconds)
ElementEnds whenAverage observedRatingNormal time
1. Get housing and seat it in the fixtureHousing clicks into the fixture9.01109.9
2. Fit gasket and position coverHand leaves the cover15.011016.5
3. Drive four screwsDriver is back in its holder23.010023.0
4. Apply label and checkHand leaves the label12.010012.0
5. Place unit in toteUnit is released into the tote6.01006.0
Swap tote and restock screws, once every 20 unitsEmpty tote is in place52.0 / 20 = 2.61002.6
Total per unit67.670.0

Normal time = average observed time x rating / 100. Averages are over 20 cycles (19 for element 3). The how-to guide shows every reading on the sheet.

Rate the pace, then add allowances

Rating adjusts for pace. This operator was quicker than the plant's definition of normal on the two handling elements, so those are rated 110. Screw driving is paced by the tool and the last two elements looked normal, so they stay at 100. That turns 67.6 observed seconds into 70.0 normal seconds.

Allowances cover what nobody can avoid over a shift. This plant uses 15 percent for bench assembly: 5 for personal needs, 4 for basic fatigue, 2 for standing and 4 for unavoidable delays. Standard time = 70.0 x 1.15 = 80.5 seconds, or 1.34 minutes a unit.

From observed time to standard time

Example numbers
  • Observed
  • Added by rating
  • Added by allowances
  1. Observed timeWhat the timer said, averaged over the good readings

    67.6 s

  2. Rating: elements 1 and 2 at 110 add 2.4 s

    Normal timeThe same work at a normal pace

    70.0 s

  3. Allowance: 15% of normal time adds 10.5 s

    Standard timeNormal time plus allowances for a full shift

    80.5 s

Units an hour
44.7
3,600 ÷ 80.5
Minutes a unit
1.34
80.5 ÷ 60
Standard hours per 100 units
2.24
80.5 × 100 ÷ 3,600

Three bars on the same scale. Observed time is 67.6 seconds a unit. Rating adds 2.4 seconds to give a normal time of 70.0 seconds. The 15 percent allowance adds 10.5 seconds to give a standard time of 80.5 seconds.

Each bar keeps the one above it and adds a piece. Rating moves the time a little, 2.4 s here. The allowance moves it a lot, 10.5 s, so an allowance picked without thought does more damage than a rating that is slightly off.
Illustrative: what the 80.5 second standard gives the plant
MeasureWorkingResult
Units an hour3,600 / 80.544.7
Standard hours per 100 units80.5 x 100 / 3,6002.24
One bench in an 8 hour shift28,800 / 80.5357 units
Benches for 600 units a day600 / 357 = 1.682 benches

One caution on the allowance. Some plants state it as a percent of normal time, as here. Others state it as a percent of the working day, and then standard time = normal time / (1 minus allowance): 70.0 / 0.85 = 82.4 seconds. Both conventions are in the textbooks. Know which one your plant uses before you compare two standards.

The motion half: what to look for before you time

Most of the gain in a time and motion study comes from the motion half. Before you time anything, watch the hands and feet for these.

  • Reaches beyond the forearm: parts, tools and bins that sit behind, above or across the operator.
  • Walking: to a shared tool, a printer, a rack. A spaghetti diagram adds up the distance.
  • Searching and choosing: picking the right part from a mixed bin, reading a label to find a setting.
  • Regrasping: turning a part over in the hand because it arrived the wrong way up.
  • One hand used as a clamp while the other works. A fixture can hold the part.
  • Waiting: for a machine to finish, a cure time, a second person.
  • Bending, twisting and lifting above the shoulder. These cost time and they hurt people. An ergonomic assessment scores the risk.

The junction box bench before and after the motion study

Example numbers

Before

The bench before the motion study, seen from aboveThe screw bin is behind the operator and the housings are in a pallet box on the floor to the left. Both are outside the reach zone.easy reachfixturetoteoperatorscrewsturn and reach behindhousingson floorstep, bend and lift

Screws behind the operator, housings in a pallet box on the floor. Two picks a unit leave the easy reach zone.

After

The bench after the motion study, seen from aboveThe screw bin is on the bench in front of the operator and the housings are on a waist-high rack at the left hand. Both are inside the reach zone.easy reachfixturetoteoperatorscrewshousings on a rack

Screws at the front of the bench, housings on a waist-high rack. Every pick is inside easy reach.

Nothing was timed to make this change. The engineer watched five cycles, saw two picks leave the yellow zone on every unit, and moved the screws and the housings inside it. The time study then measures the bench on the right.

For each one, ask four questions in this order: can it be eliminated, combined with another step, rearranged or simplified? Engineers call that ECRS. Each motion you remove comes off the cycle for every unit made afterwards, which is why it is worth doing before the standard is set and not after.

Stopwatch, video or AI from video

The method is the same whichever tool does the timing. What changes is who watches, what record is left behind and where the analyst's hours go.

Stopwatch, video and AI from video compared
Stopwatch at the benchVideo, timed by a personAI from video
How it worksAn observer stands at the job with a watch and a board and writes each reading as it happensThe job is filmed once. An analyst plays it back and marks each break pointThe job is filmed once. Software marks the elements and times each cycle, then a person checks and corrects the draft
TimingTo 0.01 minute on a decimal-minute watch, limited by how fast the observer can read and writeTo one frame: 1/30 of a second at 30 frames a secondTo one frame, as with any video
Record left behindA sheet of numbers. Nobody can recheck a readingThe film. Anyone can replay a cycle and check a break pointThe film, plus a timeline that ties each time to its frames
Rating the paceDone live, once, by the observerCan be done again later, by more than one personStill a human judgment. Software does not know your plant's normal pace
Where the hours goThe observation, then the write-upOften the most: filming, then replaying each cycle several timesInto review. The timing itself is drafted for you
What it missesShort elements, two hands doing different things, anything that happens during a glance at the watchAnything out of frame. Weight and effort are hard to judge from a screenAnything out of frame, unusual work, and every judgment call
How operators take itSomeone standing over them with a watchA camera. The footage can be shown to them and questionedA camera, plus the question of who sees the film and how long it is kept
Best forA quick check on one job with no setupDisputed standards, training and method improvementMany jobs, long recordings, and studies repeated after each change

One stopwatch tick against video frames

Stopwatch: 1 tick = 0.01 min = 0.6 s

Video: 0.6 s × 30 frames a second = 18 frames

Each frame is 1/30 of a second.

One tick of a decimal-minute stopwatch is 0.01 minute, which is 0.6 seconds. Video at 30 frames a second has 18 frames in that time.

A decimal-minute stopwatch cannot place a break point more finely than one tick. Video at 30 frames a second gives 18 places to put it inside the same tick, and you can go back and check which one you chose.

LeanSuite's time and motion study software works the third way: you film the station on a phone, it times every element and cycle and drafts the report, and you correct and certify it. AI video analysis lists the other studies the same film can feed. Whichever tool you pick, the rating, the allowances and the decision to publish a standard stay with a person who knows the job.

If you film, the filming guide and the video time study filming checklist cover camera angle, distance and what to agree with the operator first.

The people side: operators, unions and being watched

Operators have good reasons to distrust a time study. For more than a century the stopwatch has been followed by a higher quota often enough that the fear is reasonable. Ignore it and what you time is a show put on for the observer.

What to tell the operator before the study

  • Why this job, and why now.
  • What the number will be used for. If it will affect pay or staffing, say so. If it will not, say that, and only if it is true.
  • That you are studying the job, not the person. The rating step exists so that one person's fast or slow day does not become the standard.
  • That they will see the readings first and can question any element.
  • For video: who will see the film, where it is kept and when it is deleted.
  • Then ask a question: what gets in your way on this job? The answer is usually the start of the motion study.

What the operator should hear, and when

  1. Before

    Why, what and what for

    Why this job, what is being measured, what the number will and will not be used for, and who sees any film.
  2. During

    Work the way you normally do

    Stand where you agreed to stand. Let the first cycles pass. Ask about anything unusual and do not guess.
  3. After

    Here are the readings

    Show the sheet or the film first to the person on it. Let them question any element before the standard is published.
The talk before the study matters most. An operator who first learns about the study when the tripod appears will assume the worst, and the timing will show it.

Where there is a union

Read the collective agreement before you plan the study. Many agreements say how standards are set, who may be present, what data the union may see and how a standard is challenged. Bring the steward in early, share the method and the readings, and never study anyone covertly. This is general practice, not legal advice. Your labor relations or HR lead should confirm what applies at your site.

The observer effect

People work differently when they are watched. Some speed up, some slow down, most become more careful. Three things reduce it. Let the first few cycles pass before you record. Watch long enough for the novelty to wear off. And rate the pace, so that an unusual tempo is corrected and not built into the standard.

Video helps, because a camera on a tripod is less of a presence than a person with a clipboard, and because the operator can go through the footage with you afterwards. A hidden camera does the opposite. It destroys trust and may breach the law or your agreement.

Two guides help with the conversations: resistance to change on the shop floor and difficult conversations at work.

Common mistakes

  • Timing before fixing the method. You set a careful standard for a wasteful job, and every later improvement makes the standard wrong.
  • Studying the fastest operator, or the newest. Pick a trained person who works at a steady pace, and rate what you see.
  • Too few cycles. Three or five readings can hide most of the variation. Use a table or the formula to decide.
  • Elements with fuzzy end points. If two observers would stop the watch at different moments, the element is not defined yet.
  • Skipping the rating, or giving everyone 100. Then the standard is simply how fast that person happened to work.
  • Forgetting occasional work: tote changes, restocking, a check on every tenth unit. Time it and spread it over the units it serves.
  • Dropping readings you do not like. Leave a reading out only when you saw the cause and wrote it down.
  • Copying an allowance from a website. Allowances belong to a plant and its conditions, and should be agreed before the study.
  • Publishing the time without the method. A standard time only means something next to the method, layout and tools it was set for.
  • Never studying the job again. A new fixture, a new material or a moved rack makes the old number fiction.

Tools and templates for a time and motion study

Time and motion study software

Run a time study in LeanSuite

Time and motion study software that works from phone video: LeanSuite times every element, gives cycle and standard time, and draws a Yamazumi chart.

FAQ

Questions about time and motion study

  1. A time and motion study is a close look at one job to find the best way to do it and how long that should take. The motion study removes wasted movement and settles the method. The time study then times that method over many cycles, adjusts for the operator's pace and adds allowances. The result is a standard time for a trained person working at a normal pace.

  2. To give a plant a time it can trust for one job done one way. That standard time feeds costing and quoting, staffing, line balancing, capacity planning, layout, ergonomics and, in some plants, incentive pay. The study also exposes wasted motion, because someone has to watch the job closely for 20 cycles or more.

  3. Frederick Taylor used time study from the 1880s to set a fair day's work and the pay that went with it, in place of a foreman's guess. Frank and Lillian Gilbreth used motion study to find the least tiring way to do a job, starting with bricklaying. Plants still use both for the same ends: labor standards, costing, staffing and better methods.

  4. Two sets of people. Frederick W. Taylor developed stopwatch time study at the Midvale Steel Company, starting in 1881. Frank and Lillian Gilbreth developed motion study in the early 1900s, filming work and naming the basic hand motions therbligs. The two approaches were later combined under the name time and motion study.

  5. Work study is the umbrella term used by the International Labour Organization. It has two halves: method study, which improves how the job is done, and work measurement, which sets how long it should take. Time study is one technique of work measurement, next to work sampling and predetermined motion time systems. So every time study is work study, but not the other way round.

  6. An engineer films a bench assembly job, moves the screw bin within reach, then times five elements over 20 cycles. The elements average 65.0 seconds, plus 2.6 seconds a unit for an occasional tote change. Rating brings that to 70.0 normal seconds and a 15 percent allowance gives a standard time of 80.5 seconds, or 44.7 units an hour. These are illustrative numbers.

  7. When the work is long and irregular, such as maintenance or material handling, use work sampling. When the job does not exist yet, use a predetermined motion time system such as MTM or MOST. When a machine sets the pace, use its cycle data. And when the method still changes from cycle to cycle, settle the method before you time anything.

  8. Whenever the job changes: a new method, fixture, tool, material, layout or product variant. Some plants also review standards on a set cycle, such as yearly, and look again when actual output drifts well away from the standard for no clear reason. A standard time is only valid for the method it was set on.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.