Skip to content
LeanSuite

Line balancing: the method, the formulas and one line worked from start to finish

Short answer

Line balancing is dividing the work of a line among its stations so that each one carries close to the same load and none takes longer than takt time. Done well, the line meets demand with the fewest people and nobody stands waiting.

To balance a line, list the work elements with their times and what must come before each one, work out takt time, then group elements into stations without breaking the order and without any station going over takt. The fewest stations you can hope for is total work content divided by takt, rounded up. For example, 213 seconds of work at a 50 second takt is 4.26, so at least 5 stations. Balance efficiency is total work content divided by stations times cycle time: 213 / (5 x 50) = 85.2%.

Last reviewed:

What is line balancing?

Line balancing in one picture

Example numbers

The target: work content ÷ takt

  1. 1
    50 s
  2. 2
    50 s
  3. 3
    50 s
  4. 4
    50 s
  5. 5
    13 s

213 s ÷ 50 s = 4.26, so at least 5 stations

The balance: 12 elements, in order

  1. S1
    ABC
    44 s
  2. S2
    DE
    44 s
  3. S3
    FHI
    42 s
  4. S4
    JG
    48 s
  5. S5
    KL15 s idle
    35 s

5 stations, 37 s idle, efficiency 85.2%

Left: 213 seconds of work poured into 50 second strips fills 4.26 of them. Right: the 12 real work elements packed into five stations of 44, 44, 42, 48, 35 seconds, with 37 seconds idle.

Every strip is one station and holds one takt time, 50 seconds. If work could be poured, 213 seconds would fill 4.26 strips. Real work comes as whole elements that must be done in order, so the job is to pack them into the fewest strips with the least empty space.

A line makes a product by passing it from station to station. Each station does a few small jobs, called work elements, and the product can only move as fast as the slowest station lets it. Line balancing is deciding which elements each station does, so that the loads come out close to equal and every station finishes inside takt time, the interval at which customers need one unit.

It exists because unequal loads cost you twice. The station with too much work caps the output of the whole line. The stations with too little wait for it, and that waiting is paid time. A line with six people where one is overloaded and three are half idle can often make more with five once the work is shared out properly.

Two limits make it a puzzle and not a simple division. Some elements have to come before others: you cannot drive the housing screws before the housing is closed. And an element is a lump of work: you cannot give a station a third of one. The method below is how you respect both and still get close to the best split.

Why lines go out of balance

Very few lines are designed badly. Most were balanced once and then the world moved. These are the usual causes.

  • Demand changed. Takt is available time divided by demand, so when orders rise or fall the target for every station moves, and the old split no longer fits.
  • The product changed. An engineering change adds a clip, a second label or a test, and the extra seconds land on whichever station was nearest.
  • One station got better. A fixture or a kaizen takes ten seconds out of one job. That station now waits, and nobody moved work into the gap.
  • The mix changed. A variant with more work content now makes up most of the schedule, and the stations it loads hardest run over.
  • People changed. New operators are slower while they learn, and absence leaves a line running one short with the work shared out on the spot.
  • It was set up by feel. Stations were drawn around benches and machines that already existed, and the times were never measured.

You can usually see it before you measure it. Units pile up in front of one station, people downstream of it wait with empty hands, and the same operator is always the one who needs help. A yamazumi chart puts numbers on what you are seeing.

The terms and the formulas

Line balancing has its own small vocabulary. Each term below is used on the worked example further down, a cordless drill line with 213 seconds of work and a 50 second takt.

Line balancing terms and formulas (example values are illustrative)
TermWhat it meansFormulaOn the example line
Work elementThe smallest piece of work it makes sense to move from one station to anotherMeasured in a time study12 elements, 6 to 34 s each
Total work contentAll the operator time one unit needsSum of the element times213 s
Takt timeHow often the customer needs one unitAvailable time / demand27,000 s / 540 = 50 s
Cycle timeThe pace the line is balanced to. At most takt, and less if you leave a margin for stoppagesYou choose it, at or under takt50 s
Station timeThe element times at one station added upSum of that station's elements35 to 48 s after balancing
Theoretical minimum stationsThe fewest stations that could hold the work if it split perfectlyTotal work content / cycle time, rounded up213 / 50 = 4.26, so 5
Balance efficiencyThe share of paid station time that is workTotal work content / (stations x cycle time)213 / (5 x 50) = 85.2%
Balance delayThe share of paid station time that is idle1 minus balance efficiency14.8%
Idle timeSeconds per unit that stations spend waitingStations x cycle time, minus total work content250 minus 213 = 37 s
Smoothness indexHow uneven the stations are. Zero means every station is equalSquare root of the sum of (longest station minus each station) squared15.4

Station is used for one operator's share of the work. Where two people work at one bench, count two.

The line balancing sums on the example line

Example numbers

Balance efficiency = total work content ÷ (stations × cycle time)

Balance delay is what is left: 1 minus balance efficiency.

  1. Takt =27,000 s ÷ 540 drills= 50 s
  2. Minimum stations =213 ÷ 50 = 4.26, rounded up= 5
  3. Balance efficiency =213 ÷ (5 × 50)= 85.2%
  4. Balance delay =1 minus 85.2%= 14.8%
  5. Idle time =5 × 50 minus 213= 37 s per drill
Balance efficiency85.2%
Three inputs (work content, takt, number of stations) give every other number. The five stations are the ranked positional weight balance worked out below.

Watch which cycle time a number was worked out with. The research literature and many operations textbooks divide by the cycle time the line was balanced to. Others, including Groover's and Niebel's, divide by the longest station time, because that is the pace the line actually runs at. On the example the first gives 85.2% and the second 213 / (5 x 48) = 88.8%. Both are right. Say which one you used, and compare like with like.

The smoothness index comes from Moodie and Young (1965). It is useful for comparing two balances that have the same number of stations: the lower one spreads the work more evenly. It says nothing about whether the line meets takt, so never use it on its own.

Types of line balancing problem

The question you are asking decides the type. Researchers call the basic case the simple assembly line balancing problem, SALBP for short, and number its versions. In a plant you will meet the first two all the time.

The main types of line balancing problem
TypeWhat is fixedWhat you minimiseWhen you meet it
Type 1 (SALBP-1)Cycle time, set from taktNumber of stationsA new line, or demand has changed and you need to know the crew
Type 2 (SALBP-2)Number of stations or peopleCycle time, so output goes upThe crew is fixed today and you want the most from it
Type E (SALBP-E)NeitherStations x cycle time, the total paid time per unitComparing several crew sizes and paces for the cheapest one
Mixed-modelOne line builds several variants in turnStations, with loads that hold across the mixVariants differ in work content and you cannot give each its own line
U-shaped lineThe line is bent so one person can reach stations on both legsStations, with more ways to combine elementsCells where operators walk a loop and crew size changes with demand

The two questions you will meet most

Example numbers

Type 1: the line is fixedCycle time 50 s. Find the fewest stations.

Type 1: the line is fixed5 stations of 44, 44, 42, 48, 35 seconds with the line at 50 seconds.4444424835

Answer: 5 stations

Type 2: the bars are fixed5 stations. Find the lowest line.

Type 2: the bars are fixed5 stations of 46, 46, 46, 40, 35 seconds with the line at 46 seconds.4646464035

Answer: 46 s

Both charts are the drill line from the worked example. On the left the line is takt and the answer is a number of stations. On the right the number of stations is given and the answer is how low the line can go.

Mixed-model lines are usually balanced on the weighted average work content of the mix, then checked against the heaviest variant so no station is swamped when two heavy units arrive together. Leveling the schedule with heijunka keeps that from happening often. U-shaped lines give you more freedom because an operator can take an early element and a late one that sit across the aisle from each other.

How to balance a line, step by step

The steps are the same for a line you are designing and a line you are fixing. Only the source of the times differs: estimates for a new line, a time study for a running one.

Balancing a line in eight steps

  1. 1

    Break the job into work elements

  2. 2

    Put a time on each element

  3. 3

    Write down what must come before what

  4. 4

    Draw the precedence diagram

  5. 5

    Work out takt and choose the cycle time

  6. 6

    Work out the theoretical minimum

  7. 7

    Assign elements to stations

  8. 8

    Check, try it, then fix the standard

The first four steps describe the work. The last four do the sums and test the answer on the floor.
  1. 1

    Break the job into work elements

    List every piece of work in the order it is done today. An element should have a clear start and end, and be small enough to move to another station as a whole. Keep walking, waiting and rework as their own elements so you can see them.

  2. 2

    Put a time on each element

    Use a time a trained person can repeat all shift, not the fastest cycle you saw. A time and motion study gives you that. If the plant uses allowances, apply them the same way to every element, as a standard time does.

  3. 3

    Write down what must come before what

    For each element, list the elements that have to be finished first. Only write real physical or quality reasons. "We have always done it in that order" is not a predecessor.

  4. 4

    Draw the precedence diagram

    One circle per element, an arrow from each element to the ones that depend on it. The diagram shows at a glance which elements are free to move and which are chained together.

  5. 5

    Work out takt and choose the cycle time

    Takt is available time divided by demand. Balance to takt, or to a slightly shorter cycle time if the line loses time to small stops.

  6. 6

    Work out the theoretical minimum

    Total work content divided by cycle time, rounded up. This is the target. You may not reach it, but you will know how far off you are.

  7. 7

    Assign elements to stations

    Fill station 1, then station 2, and so on. Each time, pick an element whose predecessors are all done and that still fits in the time left. A rule such as ranked positional weight tells you which one to pick first.

  8. 8

    Check, try it, then fix the standard

    Work out the efficiency and look at the longest station. Check every station against skills, tools and ergonomics. Run the new split with the operators for a shift, adjust, and only then update the standard work.

How to draw a precedence diagram

A precedence diagram is the map of what depends on what. It is the one drawing in line balancing you cannot skip, because every rule for assigning work reads from it.

  1. 1

    Start from the predecessor list

    Take the table of elements and immediate predecessors. Immediate means the last things that must be done before this element, not everything upstream of it.

  2. 2

    Draw the elements with no predecessor first

    They go in the first column, on the left. On most assembly lines that is one element: loading the base part.

  3. 3

    Add each element after its last predecessor

    An element goes one column to the right of the latest of its predecessors. Elements in the same column do not depend on each other, so they can be done in any order.

  4. 4

    Draw the arrows and write the times

    One arrow from each immediate predecessor. Write the element time next to each circle. Do not draw arrows that are already implied: if A leads to B and B leads to D, there is no arrow from A to D.

  5. 5

    Check it with the people who do the job

    Walk the diagram with an operator and the process engineer. They will find the arrow you invented and the one you missed.

The drill line's precedence diagram

Example numbers
Precedence diagram of the drill linePrecedence diagram of 12 work elements. A, 6 seconds, no predecessor. B, 26 seconds, after A. C, 12 seconds, after A. D, 32 seconds, after B and C. E, 12 seconds, after A. F, 20 seconds, after C and E. G, 14 seconds, after B. H, 16 seconds, after A. I, 6 seconds, after D and F and H. J, 34 seconds, after I. K, 22 seconds, after G and J. L, 13 seconds, after K.A6B26C12D32E12F20G14H16I6J34K22L13
  • A has no arrow coming in. It is the only element that can start the job, so it opens station 1 in every balance.
  • I has three arrows coming in. The housing cannot be closed until D, F and H are all done, so most of the line has to pass through I.
  • G is the free one. It needs only B and is needed only by K, so it can sit in any station between them. Elements like this fill the gaps.
  • I, J, K and L form a chain. They can only be done in that order, one after the other.
Read it from the top. Each box is a work element with its time in seconds. An arrow means the lower element cannot start until the upper one is done.

Read the finished diagram for freedom. An element with one arrow in and one arrow out is locked in place. An element such as fitting the chuck on the example line, which needs only the gearbox and is needed only by the final test, can go to almost any station. Those free elements are what you use to fill gaps.

The two rules people actually use by hand

Finding the best possible balance means trying a huge number of combinations, and the number grows very fast with the element count. So for work done by hand, people use rules of thumb that give a good answer quickly. Two are in every textbook. Both build a priority list, then fill the stations from it in the same way.

Largest candidate rule

List the elements by time, longest first. To fill a station, start at the top of the list and take the first element whose predecessors are done and that fits in the time left. Go back to the top and repeat until nothing fits, then open the next station. The idea is simple: place the big lumps while there is room and use the small ones to fill the gaps.

Ranked positional weight

Helgeson and Birnie published this method in 1961. An element's positional weight is its own time plus the time of every element that follows it in the precedence diagram, directly or through a chain. List the elements by weight, largest first, then fill the stations exactly as before. It looks at more than size. An element with a lot of work waiting behind it gets done early, which frees those followers for later stations.

Neither rule promises the best answer, and on the same line they can disagree, as the example shows. A third hand method, Kilbridge and Wester's, works column by column through the precedence diagram. Software can search many more combinations, and for a small line it can try all of them. The sensible habit is to run two rules, compare both with the theoretical minimum and keep the better one.

Worked example: a 12-element line, from six stations to five

Illustrative example. A line assembles a cordless drill. It runs one shift of 480 minutes with 30 minutes of breaks, so it has 450 minutes, or 27,000 seconds, to work with. Customers take 540 drills a day. Takt time is 27,000 / 540 = 50 seconds.

Illustrative: the drill line's work elements and what each one needs first
ElementWorkTime (s)Must come after
APlace left housing half in the fixture6None
BFit motor and gearbox26A
CFit trigger switch12A
DRoute and connect motor leads to the switch32B, C
EFit battery terminal block12A
FConnect terminal leads to the switch20C, E
GFit chuck to the spindle14B
HFit worklight and lens16A
IClose right housing half6D, F, H
JDrive eight housing screws34I
KFunctional test: run, reverse, clutch22G, J
LLabel and pack13K
Total work content213

The line today

The line was set up around its benches and runs with six operators. Station 3 does both wiring jobs, D and F, and takes 52 seconds. That is 2 seconds over takt, so the line can make 27,000 / 52 = 519 drills in the shift, 21 short of demand, and the gap is covered with overtime. Meanwhile station 4 has 20 seconds of work.

Illustrative: the six stations as the line runs today, against a 50 s takt
StationElementsStation time (s)Against takt
1A, B3218 s under
2C, E, H4010 s under
3D, F522 s over
4G, I2030 s under
5J3416 s under
6K, L3515 s under
Total12 elements213

The line runs at the pace of station 3. Balance efficiency at that pace is 213 / (6 x 52) = 68.3%, so 99 of the 312 paid seconds per drill are waiting.

The target

The theoretical minimum is 213 / 50 = 4.26, so five stations. Six people are doing work that five could do, and the line still misses takt. That combination, too many people and not enough output, is the signature of a balance problem.

First try: largest candidate rule

Sorted by time, the list is J, D, B, K, F, H, G, L, C, E, A, I. Station 1 has to start with A, because nothing else is free. B is the first element on the list that is then free and fits, and H fills most of what is left. Carry on the same way and you get this.

Illustrative: the largest candidate rule at a 50 s cycle time
StationElements, in the order takenStation time (s)Idle (s)
1A, B, H482
2G, C, E3812
3D3218
4F, I2624
5J3416
6K, L3515

Six stations again. Every station is under takt, so the line would now meet demand, but it still needs six people. Efficiency is 213 / (6 x 50) = 71.0%.

The rule went wrong early. It spent station 2 on G, C and E because they were free, and left D, a 32 second element, to open station 3 on its own with nothing short enough to sit beside it.

Second try: ranked positional weight

Now weight each element by the work that depends on it. D's weight is its own 32 seconds plus I, J, K and L behind it: 32 + 6 + 34 + 22 + 13 = 107.

Ranked positional weights, largest first

Example numbers
#El.Time (s) + elements that follow itWeight
  1. 1A

    6 s + B C D E F G H I J K L

    213
  2. 2B

    26 s + D G I J K L

    147
  3. 3C

    12 s + D F I J K L

    139
  4. 4D

    32 s + I J K L

    107
  5. 5E

    12 s + F I J K L

    107
  6. 6F

    20 s + I J K L

    95
  7. 7H

    16 s + I J K L

    91
  8. 8I

    6 s + J K L

    75
  9. 9J

    34 s + K L

    69
  10. 10G

    14 s + K L

    49
  11. 11K

    22 s + L

    35
  12. 12L

    13 s and nothing after it

    13

D and E tie at 107. The longer element goes first.

The bar is the element's own time plus everything that waits on it. A short element such as A or C ranks high because so much work sits behind it. G is long enough to rank sixth by time, but only K and L depend on it, so it drops to tenth.

Fill the stations from this list. Each time, take the highest ranked element that is free and fits.

Illustrative: filling the stations by ranked positional weight at a 50 s cycle time
PickStationElement takenTime (s)Time left in the station (s)Why the station closes
11A644
21B2618
31C126D, E, H and G are free but none fits in 6 s
42D3218
52E126F, H and G are free but none fits in 6 s
63F2030
73H1614
83I68J and G are free but neither fits in 8 s
94J3416
104G142K is free but does not fit in 2 s
115K2228
125L1315No elements left

Five stations: 44, 44, 42, 48 and 35 seconds. That is the theoretical minimum, so no balance can use fewer.

The five stations drawn on the precedence diagram

Example numbers
Precedence diagram of the drill line with station groupingsPrecedence diagram of 12 work elements. A, 6 seconds, no predecessor. B, 26 seconds, after A. C, 12 seconds, after A. D, 32 seconds, after B and C. E, 12 seconds, after A. F, 20 seconds, after C and E. G, 14 seconds, after B. H, 16 seconds, after A. I, 6 seconds, after D and F and H. J, 34 seconds, after I. K, 22 seconds, after G and J. L, 13 seconds, after K. Stations: station 1 A, B, C at 44 seconds; station 2 D, E at 44 seconds; station 3 F, H, I at 42 seconds; station 4 J, G at 48 seconds; station 5 K, L at 35 seconds.Station 144 sStation 244 sStation 342 sStation 448 sStation 535 sA6B26C12D32E12F20G14H16I6J34K22L13

Takt is 50 s, so no band may add up to more than 50.

  1. Station 1ABC6 + 26 + 12 = 44 s
  2. Station 2DE32 + 12 = 44 s
  3. Station 3FHI20 + 16 + 6 = 42 s
  4. Station 4JG34 + 14 = 48 s
  5. Station 5KL22 + 13 = 35 s

G was free from station 2 onwards. It waited until station 4 had a 16 second gap that nothing else could fill.

Each shaded band is one station of the ranked positional weight balance. Every arrow points down, into the same band or a later one, which is the test that the order of work is respected.

Compare the three

The same 12 elements packed by two rules

Example numbers

Largest candidate rule: 6 stations

List: J D B K F H G L C E A I

  1. S1
    ABH
    48 s
  2. S2
    GCE12 s idle
    38 s
  3. S3
    D18 s idle
    32 s
  4. S4
    FI24 s idle
    26 s
  5. S5
    J16 s idle
    34 s
  6. S6
    KL15 s idle
    35 s

Efficiency 71.0%, idle 87 s per drill

Ranked positional weight: 5 stations

List: A B C D E F H I J G K L

  1. S1
    ABC
    44 s
  2. S2
    DE
    44 s
  3. S3
    FHI
    42 s
  4. S4
    JG
    48 s
  5. S5
    KL15 s idle
    35 s

Efficiency 85.2%, idle 37 s per drill

Largest candidate rule: 6 stations of 48, 38, 32, 26, 34, 35 seconds. Ranked positional weight: 5 stations of 44, 44, 42, 48, 35 seconds.

Every strip is one station and is 50 seconds long, the takt time. Dark blocks are work, striped space is idle. The largest candidate rule strands D on its own in station 3. Ranked positional weight packs the same work into five strips.
Illustrative: the drill line today and after each rule
TodayLargest candidate ruleRanked positional weight
Stations665
Longest station52 s48 s48 s
Meets the 50 s taktNoYesYes
Output at the longest station519 a day562 a day562 a day
Balance efficiency68.3% at 52 s71.0% at 50 s85.2% at 50 s
Idle time per drill99 s87 s37 s
Smoothness index46.734.715.4

Output is 27,000 s divided by the longest station time, rounded down. Demand is 540 a day.

The drill line before and after, against a 50 second takt

Example numbers

Today: 6 stations

Station times todaySix stations of 32, 40, 52, 20, 34, 35 seconds against a takt of 50 seconds. Station 3 is over takt.0204060sABS1CEHS2DFS3GIS4JS5KLS6Takt50 s32 s40 s52 s20 s34 s35 s

After: 5 stations

Station times after balancing by ranked positional weightFive stations of 44, 44, 42, 48, 35 seconds against a takt of 50 seconds. All are under takt.0204060sABCS1DES2FHIS3JGS4KLS5Takt50 s44 s44 s42 s48 s35 s
Stations
6 to 5
Longest station
52 s to 48 s
Drills a day at that pace
519 to 562
Smoothness index
46.7 to 15.4
Today one station is over the line and one is barely used. After the balance, five stations all sit under takt, and the spare time is on station 5 where it can be seen. Letters are the work elements.

The five-station balance meets demand with one operator fewer, and nobody was asked to work faster: the longest station dropped from 52 seconds to 48. The freed operator is not a saving until that person is doing useful work somewhere else, so plan where they go before you change the line.

Notice where the slack ended up. Station 5 has 15 spare seconds and the others have very little. Classic balancing would try to spread that evenly. Lean practice usually prefers it in one place, where everyone can see it and the next improvement can aim at it. The Lean Lexicon puts the goal as work for each operator that is very nearly equal to takt but slightly less.

Leave a margin: the best five-station balance

A line never runs for every available second. Say the drill line loses 5% of the shift to small stops. It then has 27,000 x 0.95 = 25,650 seconds, and the cycle time it must hold is 25,650 / 540 = 47.5 seconds. The ranked positional weight balance has a 48 second station, so on a normal day it makes 25,650 / 48 = 534 drills. Six short.

This is the type 2 question: with five stations, what is the shortest cycle time possible? The line is small enough to try every assignment, and the answer is 46 seconds.

Illustrative: the best possible five-station balance for the drill line
StationElementsStation time (s)
1A, C, E, H46
2B, F46
3D, G46
4I, J40
5K, L35

Longest station 46 s. With 5% lost to stops the line makes 25,650 / 46 = 557 a day against a demand of 540. Smoothness index 12.5.

Five stations two ways: the rule of thumb and the best split

Example numbers

Ranked positional weight: longest 48 s

Ranked positional weight balanceFive stations of 44, 44, 42, 48, 35 seconds against a takt of 50 seconds.0204060sABCS1DES2FHIS3JGS4KLS5Takt50 s44 s44 s42 s48 s35 s

Best possible: longest 46 s

Best possible five-station balanceFive stations of 46, 46, 46, 40, 35 seconds against a takt of 50 seconds.0204060sACEHS1BFS2DGS3IJS4KLS5Takt50 s46 s46 s46 s40 s35 s
Both use five stations. The best split trims the longest station from 48 to 46 seconds, which is the difference between 534 and 557 drills on a day with 5% lost to stops.

Two seconds off the longest station is the difference between meeting demand on a normal day and missing it. A rule of thumb found the right number of stations. It took a search to find the best split among them. That is the honest limit of hand methods, and the reason a line balancing calculator or software earns its place once a line has more than a dozen elements.

What the sums leave out: real constraints

A balance that works on paper can fail on the floor for reasons the precedence diagram does not hold. Check every station against these before you move anything.

Practical constraints on a line balance
ConstraintWhat it does to the balanceHow to handle it
Skill and certificationAn element can only go to someone trained and signed off for it, such as a test, a weld or a torque that is safety criticalMark those elements on the list. Use the skills matrix to see who can take them, and train before you move
Fixed equipmentA press, a test rig or a fixture that cannot move pins its element to one placeLock the element to its station and balance the rest around it
ZoningSome elements must share a station (same tool, same side of the product). Others must not (a clean job next to a greasy one)Write these as must-be-together and must-be-apart rules beside the precedence list
ErgonomicsA station can fit takt and still overload a shoulder or a wrist if every element in it uses the same posture or gripMix heavy and light elements in a station, and check reach and force for the new combination
Walking and layoutTwo elements that sit far apart add walking that is not in either element timeAdd the walk as its own element and count it, or move the parts
Machine timeAn operator can do other work while an automatic cycle runs, so operator time and machine time are not the sameBalance on operator time, and check each machine against takt separately
VariationElement times vary from cycle to cycle. A station loaded to 49 of 50 seconds will run over oftenLeave more room on stations whose elements vary a lot, and fix the cause of the variation
LearningFor the first days after a change, everyone is slower on the elements that are new to themChange the line at a quiet time, add help for the first shifts and time the stations again after two weeks

If a constraint forces a worse balance, write it down next to the balance. A locked element is a fact about today. Next year's fixture or cross-training plan may free it.

How to rebalance when demand changes

When demand moves, takt moves, and the number of stations the line needs moves in steps. The element list and the precedence diagram stay the same, so a rebalance is a short job if you kept them. Here is the drill line at three levels of demand, balanced by ranked positional weight each time.

Illustrative: the drill line rebalanced for three levels of demand
Demand a dayTakt (s)Work content / taktStationsStation times (s)Efficiency at takt
450603.55456, 52, 56, 4988.8%
540504.26544, 44, 42, 48, 3585.2%
675405.33632, 40, 32, 40, 34, 3588.8%

Available time is 27,000 s a day in every row.

One line, three levels of demand

Example numbers

450 a dayTakt 60 s, 4 stations

Station times at a demand of 450 a day4 stations of 56, 52, 56, 49 seconds against a takt of 60 seconds.56525649

213 ÷ 60 = 3.55

540 a dayTakt 50 s, 5 stations

Station times at a demand of 540 a day5 stations of 44, 44, 42, 48, 35 seconds against a takt of 50 seconds.4444424835

213 ÷ 50 = 4.26

675 a dayTakt 40 s, 6 stations

Station times at a demand of 675 a day6 stations of 32, 40, 32, 40, 34, 35 seconds against a takt of 40 seconds.324032403435

213 ÷ 40 = 5.33

The line across each chart is takt. Numbers are station times in seconds.

As demand rises the takt line drops, each station can hold less, and the same 213 seconds of work needs more stations. The bars are drawn to one scale.
  • Keep one balance ready for each demand level you expect, with its crew size and its standard work, so a change of volume is a change of sheet and not a new project.
  • Review on a rhythm, not daily. A line that is rebalanced every time orders wobble never settles. Level the schedule first and rebalance when takt moves enough to change the crew.
  • Cross-train before you need it. Going from five stations to four gives each person elements they did not do yesterday. A cross-training plan makes that a routine move.
  • Know the floor. The longest element on the drill line is 34 seconds, so no balance can run faster than that. Above 27,000 / 34 = 794 drills a day, driving the screws has to be split, shortened or done at two stations in parallel.
  • When takt drops, use the bottleneck calculator to check machines and tests as well. A leak tester with a fixed 45 second cycle does not care how you share out the manual work.

Line balancing from a time study or from video

The balance is only as good as the element times under it. For a running line they come from a time and motion study: watch each station, break the work into elements, time enough cycles to trust the average and note anything unusual.

  • Break elements where the work could be handed over, not where it is convenient to click the stopwatch. "Fit and wire the switch" cannot be split later. "Fit switch" and "connect leads" can.
  • Time walking, waiting, searching and rework as separate elements. They are the first seconds to remove, and you cannot see them inside a station total.
  • Use the same basis for every station: the same operator skill level, the same rating and allowance policy. Mixing a rated time at one station with a raw stopwatch time at the next builds a hidden imbalance in.
  • Record what each element needs: tool, fixture, skill, side of the product. Those notes become your constraints.
  • Put occasional work in as an average per unit. A carton change every 20 units that takes 40 seconds is 2 seconds a unit.

Video makes this easier because you can replay a cycle, agree the element breaks with the operator and time several people from the same footage. LeanSuite's Line Balancing works from a video of the line: it times each operator's elements, draws every station against takt, and lets you drag an element to another operator to see the balance redraw before anything moves on the floor. You still check the result and decide.

Tell people why you are filming or timing before you start. Say what the study is for, that you are studying the work and not the person, and show the operators the chart first. A balance built with the people who do the job gets tried properly. One handed down gets proved wrong by Friday.

When line balancing is the wrong tool

  • The limit is a machine. If an oven, a press or a tester is slower than takt, moving manual work around changes nothing. Fix the machine cycle, add capacity there or run it for more hours.
  • Every station is over takt. That is a capacity problem. You need less work content or more stations, and how many operators the line needs is the sum to do first.
  • The work is mostly waste. Balancing a line full of walking and searching spreads the waste out evenly. Take the waste out first, then balance what is left.
  • The work does not repeat. A job shop making one-offs has no stable element list to balance. Use scheduling and cross-training there.
  • Times swing wildly from cycle to cycle. A balance assumes repeatable times. If an element takes 20 seconds one cycle and 50 the next, find out why before you balance around the average.

Line balancing also has a people side that the arithmetic hides. A fully loaded station leaves no time to recover from a dropped screw. Jobs that have been made very short and very repetitive are harder on bodies and on attention. Rotation between stations, some slack you chose on purpose and a say in how the work is split are part of a balance that lasts.

Common mistakes

  • Balancing to the average station. One station over takt limits the whole line, however fast the others are. Look at the longest station first, the efficiency second.
  • Chasing 100% efficiency. A line loaded to the last second has no room for variation and stops at the first small problem. A few seconds of planned slack is not waste.
  • Inventing precedence. Arrows that record habit, not need, take away the freedom you need to fill stations. Challenge every one.
  • Using times nobody trusts. Old standards, one stopwatch cycle or the best operator's best run all produce a balance that fails on the floor.
  • Ignoring who can do what. The sum says move the test to station 2. The person at station 2 is not certified to run it.
  • Leaving the standard work as it was. If the sheets at the stations still show the old split, the old split comes back within a week.
  • Balancing once. Demand, mix and methods keep moving. Put a review date on the balance, and time the stations again after any change to the product or the method.

Tools and templates for line balancing

Line balancing software

Balance a line in LeanSuite

One video of the line goes in. A Yamazumi chart against takt, and rebalancing scenarios you can test, come out.

FAQ

Questions about line balancing

  1. Line balancing is sharing out the work of a production line so that every station has about the same amount to do and none takes longer than takt time. A balanced line meets demand with the fewest people, has no station holding the others up and has very little waiting.

  2. There are three sums. Takt time = available time / demand. Theoretical minimum stations = total work content / cycle time, rounded up. Balance efficiency = total work content / (number of stations x cycle time). For 213 seconds of work at a 50 second takt, the minimum is 5 stations and the efficiency with 5 stations is 213 / 250 = 85.2%.

  3. By goal, type 1 fixes the cycle time and minimises the number of stations, and type 2 fixes the number of stations and minimises the cycle time. By line, there are single-model, mixed-model and U-shaped lines. By technique, the common hand methods are the largest candidate rule, ranked positional weight and Kilbridge and Wester's column method. Software searches many more combinations.

  4. Break the job into work elements, time each one, and list what must come before what. Work out takt time and the theoretical minimum number of stations. Then fill the stations one at a time with elements that are free to start and fit in the time left. Check the result against skills, tooling and ergonomics, try it with the operators and update the standard work.

  5. It means making the workload at each station as close to equal as the work allows, with every station at or just under takt time. Balance is about how evenly the work is spread, not how fast anyone works. An unbalanced line has one overloaded station setting the pace while others wait.

  6. A balanced line is one where every station's work fits inside takt time, the station times are close to each other, and the number of stations is at or near the theoretical minimum. Units do not queue in front of any station, and no operator spends much of each cycle waiting for the one before.

  7. It is a line balancing rule published by Helgeson and Birnie in 1961. Each element gets a weight equal to its own time plus the time of every element that follows it in the precedence diagram. Elements are ranked by weight, largest first, and assigned to stations in that order whenever their predecessors are done and they fit in the remaining time.

  8. A precedence diagram shows each work element as a circle and draws an arrow from every element to the ones that cannot start until it is finished. It tells you which elements are locked in sequence and which are free to move between stations, and every line balancing method reads from it.

  9. Balance delay is the share of paid station time that is idle because the work could not be split perfectly. It equals 1 minus balance efficiency. A five-station line balanced to a 50 second cycle with 213 seconds of work has 37 seconds idle per unit, a balance delay of 37 / 250 = 14.8%.

  10. Rebalance when takt time changes enough to change the number of stations, when the product or method changes, and after any improvement that takes real time out of a station. Between those events, review on a set rhythm such as monthly. Rebalancing every time daily orders move gives operators no stable job to learn.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.