Practical guide · Standard work, SOPs and training
Work sampling: how it works, the formula and a worked study
Short answer
Work sampling estimates how people or machines spend their time from many instant observations made at random moments. If 85 of 500 random looks at a packing cell find someone waiting, about 17 percent of the cell's time goes on waiting, give or take 3 points.
Work sampling is a way to measure where time goes without a stopwatch. You define a few activity categories, walk past at random times, and tally what each person or machine is doing at that instant. The share of tallies in a category estimates the share of time. The number of observations for 95 percent confidence is n = 1.96² x p x (1 - p) / e², where p is the expected share and e is the accuracy you want, both as decimals. Use it for long, irregular or shared work; use a time study for a short repeating cycle.
Last reviewed:
What is work sampling?
Work sampling in one picture
Example numbersLook at random moments
One packer's day, 07:00 to 15:30. Each mark is one of 25 random looks. Four packers for five days makes 500.
- Packing
- Waiting
- Walking
- Searching
- Rework
- Personal
- Unpaid lunch
Tally what each look found
- Packing305
- Waiting85
- Walking40
- Personal35
- Searching20
- Rework15
- Looks in the week500
Read the shares of time
85 / 500 looks found someone waiting
Packing 61% · Waiting 17% · Walking 8% · Searching 4% · Rework 3% · Personal 7%
Waiting 17.0%
Between 13.7% and 20.3% at 95 percent confidence: about 27 of the cell's 160 paid hours a week.
Three steps. One: look at random moments, here 25 marks on one packer's day. Two: tally what each look found; over a week of 500 looks at four packers, Packing 305, Waiting for product 85, Walking for cartons and labels 40, Personal and paid breaks 35, Searching 20, Rework 15. Three: the share of looks is the share of time; waiting is 17.0 percent, between 13.7 and 20.3 percent, which is 27.2 of 160 paid labour hours a week.
Work sampling is a way to find out how people or machines spend their time by looking at them briefly, many times, at random moments. Each look records one thing: what was happening at that instant. After a few hundred looks, the share of looks that landed on an activity is a fair estimate of the share of time that activity takes.
It works for the same reason a poll works. An activity that fills 20 percent of the day has a 20 percent chance of being the one in progress at any random moment. One look tells you almost nothing. Five hundred looks tell you the share to within a few points, and the arithmetic says exactly how many points.
25 looks against the truth: close, not exact
Example numbersWhat the 25 snapshots said
Packing 56% · Waiting 24% · Walking 12% · Searching 0% · Rework 0% · Personal 8% (counts out of 25)
What the whole day was
Packing 66% · Waiting 16% · Walking 8% · Searching 2% · Rework 2% · Personal 6% (minutes out of 480)
For one packer on one day, 25 snapshots found packing 14 times (56 percent) and waiting 6 times (24 percent). Over the whole day packing was 66 percent and waiting 16 percent.
The method came out of British textile mills in the 1930s, where the statistician L.H.C. Tippett needed to know how much of the time looms stood idle and could not put a person with a watch on every loom. He called it the snap-reading method. R.L. Morrow took it to American plants as the ratio delay study, and the name work sampling took over in the 1950s. You will also see activity sampling and occurrence sampling. They are all the same method.
Two things share the name and are not this. The Work Sampling System is a classroom assessment tool for young children. A work sample is a piece of work a job candidate hands in. This page is about the industrial engineering method.
When to use work sampling, and when not to
Sampling answers one kind of question well: what share of the time goes where? Reach for it when a stopwatch would be the wrong tool.
- The work is long or irregular. Maintenance, material handling, setters, warehouse picking, team leaders and office work have no short cycle to time.
- You want to cover many people or machines at once. One observer on a route can sample a whole department.
- You need the picture over weeks, not one hour. Sampling can run a few minutes at a time for a month and catch the slow days and the bad shifts.
- You want to know how much time is lost before deciding where to study in detail. Sampling finds the big losses cheaply. A time study then explains them.
- You need a delay or personal allowance for your standards and want it measured, not copied from a table.
- You need a rough standard for long-cycle work where a stopwatch study would take weeks.
It is the wrong tool in these cases.
- You need element times. Sampling gives shares of time, not how long each step of the job takes. For that, run a time study.
- The job is one person on a short repeating cycle. Timing 20 cycles is quicker and gives far more detail.
- The activity you care about is rare. A category that takes 1 percent of the time needs thousands of observations before you can say anything firm about it.
- You need to know why. Sampling counts that someone was waiting. It does not record what they were waiting for unless you add a reason code.
- People are spread out so far that one round takes most of an hour. The walking costs more than the answer is worth.
The types of work sampling
Textbooks sort work sampling by what the study is for. The observation method is the same in all three. What changes is how many categories you tally and whether you rate pace.
| Type | What you tally | What you get | Typical use |
|---|---|---|---|
| Ratio delay study | Two states: working or not working (or running and stopped, for a machine) | The delay ratio: the share of time lost | Machine utilization, crane or forklift idle time, setting a delay allowance |
| Activity sampling | Several named activities, such as packing, waiting, walking, searching, rework | The share of time on each activity | Finding where labour hours go in a cell, a warehouse, a maintenance crew or an office |
| Performance sampling | The activity, plus a pace rating each time the person is seen working | A performance index and, with the output count, a standard time | Standards for long-cycle or indirect work that is too slow to time with a watch |
Ratio delay is the oldest name and the simplest case. Performance sampling is ratio delay plus a rating, which is what lets you turn the result into a standard.
Studies also differ in how the observation times are chosen. Random sampling picks every time by chance and is the default. Systematic sampling looks at a fixed interval from a random start, which is easier to run but only safe when the work has no rhythm that could line up with the interval. Stratified sampling splits the day into blocks, such as start-up, mid-shift and end of shift, and draws random times inside each block so that none is missed.
Time study vs work sampling
A time study watches one job continuously and times each element of it. Work sampling glances at many jobs at random moments and counts. They answer different questions, so the choice follows from the question.
| Time study | Work sampling | |
|---|---|---|
| Question it answers | How long does this job take, element by element? | What share of the time goes on each activity? |
| How you observe | Continuously, for a run of cycles | For an instant, at random times, over days or weeks |
| Best for | Short, repeating cycles at one station | Long, irregular or shared work across many people or machines |
| People covered by one observer | One operator, or a small crew | A whole area on one route |
| Equipment | Stopwatch or video | A tally sheet, a list of random times and a watch |
| Output | Element times, cycle time, standard time, the method written down | Percent of time per category, a delay allowance, a rough standard |
| Detail on the method | High: you see every motion | None: you only see which category was in progress |
| Effect on the operator | Watched closely for a short time | Glanced at briefly, many times |
| Accuracy comes from | Enough cycles timed | Enough observations, taken at random |
| Main weakness | One short window: it can miss the bad hour or the bad day | No element times and no reasons behind the counts |
Which method for which job
Is the job still on paper: a new product or a line that does not run yet?
YesPredetermined times or standard data
There is nothing to observe, so the time is built up from motions or from past studies.
No
Is it one station with a short cycle that repeats?
YesTime study, by stopwatch or video
You get element times, the cycle time and a standard, and you see the method.
No
Is the question what share of time goes where, across many people, machines or days?
YesWork sampling
Random looks give the shares with a known accuracy for little observer time.
No
A long job in one place, such as a changeover or a repair: film it once and log every element
It does not repeat often enough to time cycles and it is too rare to sample. One video, listed task by task, is the study.
The two are often used one after the other. Sample first to find which loss is biggest and where. Then study that one job in detail. The guide to time and motion study covers the family of methods, and standard time covers rating and allowances, which both methods share.
The work sampling formula: how many observations?
Each observation is a yes or a no for a category, so the result follows the binomial distribution. For a category that takes a share p of the time, the number of observations needed is:
n = z² x p x (1 - p) / e²
- n is the number of observations, counting each person or machine seen on each round as one.
- p is the share of time you expect the category to take, as a decimal. Get it from a pilot day of 50 to 100 observations.
- e is the accuracy you want, as a decimal, in points of the total. For plus or minus 4 points, e = 0.04.
- z is 1.96 for 95 percent confidence. Many textbooks, Barnes among them, round it to 2. Use 1.645 for 90 percent and 2.576 for 99 percent.
Once the study is done, the same formula turned round gives the interval on the result: p plus or minus z x the square root of p x (1 - p) / n.
| Expected share p | Plus or minus 2 points | Plus or minus 3 points | Plus or minus 4 points | Plus or minus 5 points |
|---|---|---|---|---|
| 5% (or 95%) | 457 | 203 | 115 | 73 |
| 10% (or 90%) | 865 | 385 | 217 | 139 |
| 20% (or 80%) | 1,537 | 683 | 385 | 246 |
| 30% (or 70%) | 2,017 | 897 | 505 | 323 |
| 50% | 2,401 | 1,068 | 601 | 385 |
Rounded up to the next whole observation. The count is highest at 50 percent and the same for p and 1 - p. Halving the error takes four times the observations.
How the number of observations changes with the share and the accuracy
n = 1.96² x p x (1 - p) / e², at 95 percent confidence. The number on each curve is its peak, at p = 50%.
Absolute or relative accuracy: say which
This is where most studies go wrong on paper. Plus or minus 5 percent can mean two things. Absolute accuracy is in points of the whole: 20 percent plus or minus 5 points is 15 to 25 percent. Relative accuracy is a fraction of the estimate itself: 20 percent plus or minus 5 percent of 20 is 19 to 21 percent. The second is five times tighter and needs 25 times the observations.
Plus or minus 5 percent, read two ways
Absolute: plus or minus 5 points: 15% to 25% · 246 observations
Relative: plus or minus 5% of the estimate: 19% to 21% · 6,147 observations
For an estimate of 20 percent: plus or minus 5 points is 15 to 25 percent and needs 246 observations; plus or minus 5 percent of the estimate is 19 to 21 percent and needs 6,147.
Barnes and many older texts work in relative accuracy, s, with the formula n = z² x (1 - p) / (s² x p). It is the same formula with e = s x p. For p = 0.20 and a relative accuracy of 10 percent, n = 1.96² x 0.80 / (0.10² x 0.20) = 1,537, exactly the figure in the table for plus or minus 2 points. Write the accuracy down in points and nobody has to guess.
From observations to rounds and days
Rounds needed = n divided by the number of people or machines you see on each round. Days needed = rounds divided by the rounds you can fit in a day. Size the study on the category you most need to be right about, and spread it over enough days to cover a normal cycle of the work: every weekday at least, and every shift you want to speak for.
One caution on the people-per-round shortcut. The formula assumes each observation is independent. Four packers fed by one conveyor are not: when the line stops, all four wait together. The honest reading is that the real precision sits somewhere between what the number of rounds and what the number of observations would give. More rounds on more days is the cure, not more people per round.
Random observation times: how to build the schedule
Randomness is what makes the arithmetic true. If people can predict when you will appear, or if your rounds line up with the rhythm of the work, the tallies stop being a fair sample of the day. Build the schedule before the study starts and then follow it.
- 1
List every minute you could observe
Take the shift from start to end and number the minutes. Leave out unpaid meal breaks. Keep paid breaks in, with a category for them, or the percentages will not add up to the paid day.
- 2
Draw the times at random
Use a random number table, or in a spreadsheet give every minute a RAND() value, sort by it and take the first 25. Draw a fresh set for every day so Tuesday is not a copy of Monday.
- 3
Sort them and check the gaps
Put the times in clock order. If two are closer together than one round takes, redraw one of them. Do not space them out evenly by hand. Uneven gaps are what random looks like.
- 4
Cover every part of the shift
Check that start-up, the hour before a break and the end of the shift each have times. If you want to guarantee it, split the shift into blocks and draw times inside each block. Cover every shift and weekday you want the result to speak for.
- 5
Vary the route
If the round covers several areas, change the direction or the starting point by a coin toss so the same person is not always seen first.
- 6
Keep the schedule to yourself
Tell people the study is happening and why. Do not post the times. If you miss one, note it and carry on. Do not make it up with an extra look when it suits you.
Fixed intervals, such as every 20 minutes, are tempting because they are easy to remember. They fail when the work has its own rhythm. A pallet change every 20 minutes will be caught every time or never. If you must use a fixed interval, start it at a random minute and check that nothing in the process repeats on the same beat.
Why fixed intervals fail: a pallet change every 20 minutes
Example numbersEvery 20 minutes, starting on the hour: 0 of 6 looks see a pallet change, 0%
Every 20 minutes, starting at 18 minutes past: 6 of 6 looks see a pallet change, 100%
20 random times: 4 of 20 looks see a pallet change, 20%
- Pallet change, 3 minutes in every 20
- A look that lands on it
- A look that does not
Two hours of a line where a pallet change takes 3 minutes in every 20, which is 15 percent of the time. Every 20 minutes, starting on the hour: 0 of 6 looks land on a pallet change, 0 percent. Every 20 minutes, starting at 18 minutes past: 6 of 6 looks land on a pallet change, 100 percent. 20 random times: 4 of 20 looks land on a pallet change, 20 percent.
The observation sheet and the tally
The sheet is a grid: one row for each round, with its time, and one column for each person or machine. In each cell goes a one-letter code for what you saw. At the foot of the sheet you count the codes. A second sheet adds up the days.
- Keep the categories few: five to eight. Too many and you will dither on every look.
- Make them exclusive and complete. Every look must fit one category and only one. Include one for away or personal time, or absences will vanish from the result.
- Define each one by what you can see. Write that walking means on foot and away from the bench, with or without material, and waiting means at the bench with no product to work on. Two observers should code the same scene the same way.
- Pick the instant. Record what the person is doing at the moment you first see them from a marked spot. Do not wait to see what they do next.
- Add a note column for reasons. A W for waiting is worth more with conveyor empty next to it.
- If you want a standard time from the study, add a pace rating for every look that lands on working, and collect the output count for the period.
The sheet below is one day of the worked example: 25 random rounds past four packers, 100 observations in all.
A filled-in observation sheet: Monday, 25 random rounds, four packers
Example numbers| Round | Time | Packer 1 | Packer 2 | Packer 3 | Packer 4 |
|---|---|---|---|---|---|
| 1 | 07:01 | P Packing | P Packing | P Packing | P Packing |
| 2 | 07:11 | K Walking | K Walking | P Packing | P Packing |
| 3 | 07:47 | P Packing | P Packing | R Rework | P Packing |
| 4 | 08:06 | W Waiting | W Waiting | W Waiting | W Waiting |
| 5 | 08:27 | W Waiting | P Packing | W Waiting | W Waiting |
| 6 | 08:40 | P Packing | P Packing | A Personal | P Packing |
| 7 | 08:44 | P Packing | P Packing | P Packing | P Packing |
| 8 | 09:38 | K Walking | S Searching | P Packing | P Packing |
| 9 | 09:45 | P Packing | P Packing | W Waiting | P Packing |
| 10 | 10:02 | A Personal | P Packing | P Packing | K Walking |
| 11 | 10:31 | P Packing | P Packing | A Personal | A Personal |
| 12 | 10:41 | W Waiting | W Waiting | W Waiting | W Waiting |
| 13 | 10:58 | W Waiting | P Packing | P Packing | W Waiting |
| Round | Time | Packer 1 | Packer 2 | Packer 3 | Packer 4 |
|---|---|---|---|---|---|
| 14 | 11:37 | A Personal | P Packing | P Packing | P Packing |
| 15 | 12:30 | P Packing | P Packing | P Packing | S Searching |
| 16 | 12:46 | P Packing | P Packing | P Packing | S Searching |
| 17 | 13:21 | P Packing | P Packing | P Packing | A Personal |
| 18 | 13:43 | W Waiting | W Waiting | W Waiting | W Waiting |
| 19 | 13:49 | K Walking | P Packing | K Walking | K Walking |
| 20 | 13:54 | P Packing | K Walking | P Packing | A Personal |
| 21 | 14:09 | P Packing | P Packing | P Packing | P Packing |
| 22 | 14:13 | W Waiting | W Waiting | W Waiting | P Packing |
| 23 | 14:19 | P Packing | R Rework | P Packing | P Packing |
| 24 | 15:07 | P Packing | P Packing | P Packing | P Packing |
| 25 | 15:27 | P Packing | P Packing | S Searching | P Packing |
The day's tally
- Packing58
- Waiting for product21
- Walking for cartons and labels8
- Searching4
- Rework2
- Personal and paid breaks7
- Observations100
With 100 observations the counts are also the percentages for the day: waiting 21%.
An observation sheet with 25 rounds at random times between 07:01 and 15:27 and one code for each of four packers on each round, 100 observations. The tally: Packing 58, Waiting 21, Walking 8, Searching 4, Rework 2, Personal 7.
How to run a work sampling study
A study takes a week or two of elapsed time and very little of yours on each day. Most of the thinking is in the first three steps.
A work sampling study from question to result
- 1
Write the question
- 2
Tell the people involved
- 3
Define the categories
- 4
Run a pilot
- 5
Work out the observations, rounds and days
- 6
Build the random schedule
- 7
Observe and tally
- 8
Work out the result and share it
- 1
Write the question
One sentence that names the area and the decision. For example: how much of the packing cell's time is lost to waiting, and is it enough to justify fixing the feed?
- 2
Tell the people involved
Explain to the team and their supervisor what you are counting, that it is activities and not individuals, and what will be done with the result. Do this before the first round, not after someone asks.
- 3
Define the categories
Five to eight, exclusive and complete, each defined by what can be seen. Test them on the floor for half an hour and fix any that cause doubt.
- 4
Run a pilot
Make 50 to 100 observations in a day. The pilot gives a first p for the formula, tests the categories and shows how long a round takes.
- 5
Work out the observations, rounds and days
Put the pilot p and the accuracy you need into n = z² x p x (1 - p) / e². Divide by people per round to get rounds, and plan enough days to cover the normal week.
- 6
Build the random schedule
Draw the times for every day in advance, sort them, check the gaps and print one sheet per day.
- 7
Observe and tally
Walk to the marked spot at each time and code what each person is doing at the instant you see them. Total the sheet every day and plot the running percentage. When the line goes flat, the study has enough.
- 8
Work out the result and share it
Give each category its share, the interval around it and the hours it stands for. Show the team first. Then decide what to study in detail or fix.
A worked work sampling example
Illustrative example. A packing cell has four packers on one shift, 07:00 to 15:30 with a 30 minute unpaid lunch, so each is paid for 480 minutes a day. The supervisor believes the cell loses a lot of time waiting for product from the wrapper upstream. Nobody has a number. The question: what share of the cell's paid time is waiting, to within about 4 points?
Pilot and sample size
The engineer defines six categories: packing, waiting for product, walking for cartons and labels, searching, rework and personal time including paid breaks. A pilot of 20 rounds gives 80 observations, and 16 of them are waiting, so the first estimate of p is 16 / 80 = 0.20.
| Step | Working | Result |
|---|---|---|
| Pilot estimate of waiting | 16 / 80 | p = 0.20 |
| Accuracy wanted | Plus or minus 4 points | e = 0.04 |
| Observations at 95 percent | 1.96² x 0.20 x 0.80 / 0.04² | 384.2, so 385 |
| Same sum with z = 2 | 4 x 0.20 x 0.80 / 0.0016 | 400 |
| Rounds, four packers a round | 385 / 4 | 96.3, so 97 |
| Plan | 25 rounds a day x 5 days x 4 packers | 125 rounds, 500 observations |
The plan runs a full week so every weekday is covered, and the extra 28 rounds give some room for the fact that four packers on one line are not fully independent.
The week's tallies
| Day | Packing | Waiting | Walking | Searching | Rework | Personal | Total |
|---|---|---|---|---|---|---|---|
| Monday | 58 | 21 | 8 | 4 | 2 | 7 | 100 |
| Tuesday | 63 | 16 | 7 | 4 | 3 | 7 | 100 |
| Wednesday | 66 | 11 | 9 | 3 | 4 | 7 | 100 |
| Thursday | 56 | 22 | 8 | 5 | 3 | 6 | 100 |
| Friday | 62 | 15 | 8 | 4 | 3 | 8 | 100 |
| Week | 305 | 85 | 40 | 20 | 15 | 35 | 500 |
Waiting ran from 11 to 22 percent by day. One day on its own would have given a very different answer, which is the argument for a full week.
The estimate settles as the observations pile up
Example numbersUnder each day: observations so far, then the plus or minus in points at 95 percent confidence.
The result, with its interval
For waiting, p = 85 / 500 = 0.17. The interval is 1.96 x the square root of 0.17 x 0.83 / 500, which is 1.96 x 0.0168 = 0.033. So waiting takes 17 percent of the cell's time, plus or minus 3.3 points: between 13.7 and 20.3 percent. That is inside the 4 points asked for.
| Category | Observations | Share of time | 95 percent interval | Labour hours a week |
|---|---|---|---|---|
| Packing | 305 | 61.0% | 56.7% to 65.3% | 97.6 |
| Waiting for product | 85 | 17.0% | 13.7% to 20.3% | 27.2 |
| Walking for cartons and labels | 40 | 8.0% | 5.6% to 10.4% | 12.8 |
| Personal and paid breaks | 35 | 7.0% | 4.8% to 9.2% | 11.2 |
| Searching | 20 | 4.0% | 2.3% to 5.7% | 6.4 |
| Rework | 15 | 3.0% | 1.5% to 4.5% | 4.8 |
| Total | 500 | 100.0% | 160.0 |
Hours = share x 160 paid labour hours (4 packers x 480 minutes x 5 days = 9,600 minutes). The small categories have wide intervals for their size: rework could be anywhere from 2.4 to 7.2 hours.
Where the cell's 160 paid hours a week go
Example numbers- Packing61.0% (56.7 to 65.3) · 97.6 h
- Waiting for product17.0% (13.7 to 20.3) · 27.2 h
- Walking for cartons and labels8.0% (5.6 to 10.4) · 12.8 h
- Personal and paid breaks7.0% (4.8 to 9.2) · 11.2 h
- Searching4.0% (2.3 to 5.7) · 6.4 h
- Rework3.0% (1.5 to 4.5) · 4.8 h
500 observations. After each name: share of time, its 95 percent interval, and labour hours a week (share x 160).
What the numbers say
- Waiting costs about 27 labour hours a week, and at least 22 even at the low end of the interval. That is more than half of one packer's week. The supervisor was right, and now there is a number to put against the cost of fixing the feed.
- Walking and searching together take 12 percent, or about 19 hours. Both are layout and material presentation problems, and both are cheap to attack.
- Personal time is 7 percent. The two paid 10 minute breaks account for 20 / 480 = 4.2 points of it, so the rest is in line with a normal personal allowance.
- Packing is 61 percent. The other 39 percent is the room for improvement, and almost two thirds of it is waiting and walking.
- The study does not say why the cell waits. The note column does: 20 of Monday's 21 W codes came in six rounds when the conveyor was empty. The next step is the wrapper, not the packers.
Turning work sampling results into a standard time
If you also rated pace on every working observation and counted the output, a sampling study gives a standard time. The logic is the same as in a stopwatch study: observed time, then normal time, then standard time. Only the observed time comes from a share and not from a watch.
Normal time per unit = total study time x working share x average rating / units produced. Standard time = normal time x (1 + allowance).
| Step | Working | Result |
|---|---|---|
| Total study time | 4 packers x 480 min x 5 days | 9,600 labour min |
| Time spent packing | 9,600 x 0.61 | 5,856 min |
| Good cases packed in the week | From the production count | 7,320 cases |
| Observed time per case | 5,856 / 7,320 | 0.80 min |
| Normal time (average rating 105) | 0.80 x 1.05 | 0.84 min |
| Standard time (allowance 12 percent) | 0.84 x 1.12 | 0.94 labour min a case |
| Output at standard, four packers | 4 x 60 / 0.94 | 255 cases an hour |
| Output today | 7,320 / 40 hours | 183 cases an hour |
The 105 rating and the 12 percent allowance are example figures. Applied here as a share of normal time, the way the ILO and Niebel do. Some texts, Barnes among them, express the allowance as a share of the working day and divide: 0.84 / (1 - 0.12) = 0.95 min. Pick one convention and state it.
From the sampled share to a standard time
Example numbersObserved time
Packing minutes divided by cases packed: 5,856 / 7,320
Normal time
Adjusted for the pace that was rated, 105: 0.80 x 1.05
Standard time
With a 12 percent allowance added: 0.84 x 1.12
What that standard means for the cell of four
Output today
Output at standard
Observed time 0.80 minutes a case, normal time 0.84, standard time 0.94. At standard the cell of four packs 255 cases an hour; today it packs 183.
The cell runs at 183 cases an hour against 255 at standard, or 72 percent. The gap is not slow packers. Their pace was rated above normal. It is the waiting, walking, searching and rework the study counted.
Treat a sampling standard as a coarse one. It has no element breakdown and no record of the method, so it cannot tell you what changed when the time drifts, and it has to be redone when the method changes. It suits long-cycle and indirect work. For a short repeating job, set the standard with a time study. Standard time explains rating and allowances in full.
Getting operators on board
Someone appearing with a clipboard at odd moments makes people uneasy, and with reason: studies have been used to cut jobs and tighten rates. An uneasy team also gives you bad data, because people change what they do when the observer comes into view. Deal with it directly.
- Say what the study is for before it starts, in the team's own meeting, and say what it is not for. If it will not be used for discipline or headcount, say so, and only if that is true.
- Sample activities, not people. Record the position or a number, not a name, unless there is a real need, and report results for the cell as a whole.
- Show the categories and the sheet. Ask the team whether the list fits their day. They will tell you about work you did not know existed.
- Involve the union or the works council early where there is one. Many agreements have rules on work measurement, and it is easier to follow them than to repair trust afterwards.
- Share the result with the team first, and act on something they care about. Waiting for parts annoys operators more than it annoys anyone else.
- Let an operator or team leader do some of the rounds. A study the team helped run is a study the team believes.
Errors that spoil a work sampling study
- Non-random times. Rounds on the hour, after your own meetings, or never in the first and last half hour all miss part of the day.
- Too few observations for the small categories. Five hundred looks pin a 17 percent category to about 3 points. They leave a 3 percent category anywhere between 1.5 and 4.5.
- Counting people as independent when they are not. Forty people seen on five rounds is much closer to five looks at the department than to 200.
- Anticipation. If people see you coming, they move. Observe from a spot where the first sight is the true one, and record that first instant.
- Fuzzy categories. If two observers would code the same scene differently, the difference ends up in the result.
- No category for absence. Leaving out people who are not at the station makes the working share look better than it is.
- A week that is not typical. A study run during a launch, a stock count or a holiday week describes that week only.
- Quoting a percentage with no interval. 17 percent from 50 observations and 17 percent from 500 are not the same finding.
- Mixing up absolute and relative accuracy when sizing the study, which can leave you with a twenty-fifth of the observations you needed.
- Stopping when the answer looks right. Decide the number of rounds first and finish them.
Where video and AI change the picture
Work sampling exists because watching all of the time used to be too expensive. A camera removes that limit for one station. A phone on a tripod records every second of the cell, not 25 instants, so there is no sampling error at all for the period filmed, and you get the element times and the reasons along with the shares.
That moves the line between the two methods. For one cell or one station, film it. LeanSuite's time and motion study takes the video and times every element on a timeline that links back to the footage, split into value-added, necessary and waste, for an engineer to check and certify.
Sampling still wins where a camera cannot follow: a maintenance crew that moves across the plant, forklift drivers, a whole department over a month. And one hour of video is still one hour. If the question is about a typical week, film on several days at random times, which is the sampling idea applied to video.
Templates and tools for a study
- Time study sheet: for the detailed study of the one job the sampling study points at.
- Video time study filming checklist: where to put the camera and what to tell the team before filming.
- Time study sample size calculator: how many cycles to time in a stopwatch study, which uses a different formula from the one on this page.
- Spaghetti diagram template: to trace the walking that the sampling study counted.
- How to conduct a time study: the step-by-step method for the follow-up study.
Go deeper
This page is the short version. These guides cover each part in full.
- How to Improve Shop Floor ProductivityWhat to do about the waiting, walking and searching once a study has put a number on them.
- How to Improve Production Efficiency: 7 Practical WaysThe wider set of levers on output, of which labour time is one.
- Standard Work in Manufacturing: A Complete GuideWriting down the method once the losses are out, so the gain stays.
- Yamazumi Chart: What It Is and How to Make One in 7 StepsStacking each operator's work against takt once you have element times from a detailed study.
All our articles on this subject are in the standard work, sops and training topic.
Free templates and tools
- Time study sheetTime each element over 10 cycles and work out the average, lowest repeatable and standard time. Excel does the sums.
- Video time study filming checklistA pre-shoot checklist and shot log for filming a time study on video: camera, light, people, settings, power and review.
- Spaghetti diagram templateSquared paper to trace every trip, a trip log that turns grid squares into feet, meters and walking time, and a before and after comparison.
- Standard work sheet templateTakt time, each element's manual, machine and walk time on a time chart, key points and standard WIP.
- Time study sample size calculatorHow many cycles of an element to time, from your first readings, with the t formula, the ILO formula and the range method.
- Cycle time calculatorCycle time against takt, units per hour, capacity per shift and the gap to daily demand.
- Overall labor effectiveness (OLE) calculatorHow well paid labor hours turn into good output: availability, performance and quality of the crew.
Doing this in LeanSuite
Time and Motion Study
Film the station and the AI times every element on a timeline that links to the video, split into value-added, necessary and waste.
See Time and Motion StudyAI Video Analysis
Turns video of real work into time studies, line balance charts, changeover splits and other studies you review and certify.
See AI Video Analysis
See it on your own lines
Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.
FAQ
Questions about work sampling
Work sampling is a method for estimating how people or machines spend their time from many instant observations made at random moments. You tally what is happening at each look. The share of looks that land on an activity estimates the share of time it takes. It is also called activity sampling, occurrence sampling and the ratio delay study.
A work sampling study is one planned use of the method: a question, a set of five to eight activity categories, a schedule of random observation times, and enough rounds to reach the accuracy you need. A typical plant study runs for one or two weeks and collects a few hundred to a few thousand observations.
There are three by purpose. A ratio delay study tallies two states, working or not, to find the share of time lost. Activity sampling tallies several named activities to show where time goes. Performance sampling adds a pace rating to each working observation so the result can become a standard time. By timing, studies are random, systematic or stratified.
The number of observations is n = z² x p x (1 - p) / e², where p is the expected share of time for the category, e is the accuracy wanted in points as a decimal, and z is 1.96 for 95 percent confidence. For p = 0.20 and plus or minus 4 points, n = 1.96² x 0.20 x 0.80 / 0.04² = 385 observations.
It depends on the share you expect and the accuracy you want. At 95 percent confidence, a category near 20 percent needs 385 observations for plus or minus 4 points and 1,537 for plus or minus 2 points. A category near 50 percent needs 601 and 2,401. Halving the error takes four times the observations.
A time study watches one job continuously and times each element, which suits short repeating cycles and gives element times and a detailed standard. Work sampling takes instant observations at random times across many people or machines, which suits long or irregular work and gives the share of time spent on each activity. Sampling is cheaper per person covered and gives less detail.
An observer walks past a packing cell of four people at 25 random times a day for five days and codes what each is doing: 500 observations. If 85 are waiting for product, waiting takes 85 / 500 = 17 percent of the time, plus or minus 3.3 points at 95 percent confidence. On 160 paid labour hours a week, that is about 27 hours.
Because the arithmetic only holds if every moment of the day has the same chance of being observed. Rounds at fixed or convenient times can line up with breaks, deliveries or machine cycles and catch them every time or never. Random times also stop people from predicting the observer and changing what they do.
Yes, as a coarse one. Normal time per unit = total study time x working share x average performance rating / units produced, and standard time adds allowances. It suits long-cycle and indirect work. It gives no element times and no record of the method, so short repeating jobs are better set with a time study.
No. The Work Sampling System is a classroom assessment tool for young children, and a work sample is a piece of work a job applicant hands in. Work sampling in industrial engineering is a statistical method for measuring how working time is spent, first used in British textile mills in the 1930s.
Related guides and tools
- Time and motion study: the family of methods and when to use each
- How to conduct a time study: the stopwatch and video method step by step
- Standard time: observed time, rating and allowances
- Time study sample size calculator: how many cycles to time
- How many operators do you need: work content divided by takt
- Standard work: writing the method down once the losses are out
More method guides
- The 6 Ms of production
- Poka-yoke
- Model area 90-day plans
- Moving from Excel to one system
- Reducing machine downtime: a worked month
- Andon
- Cycle time vs lead time, worked through
- Root cause analysis
- How many operators a line needs
- Reducing scrap and rework: a worked month
- Unsafe acts and unsafe conditions
- Just culture
- Stop-work authority
- Material review board (MRB)
- Nonconformance and NCRs
- Problem solving methods
- Quad chart
- OEE calculation
- Quality assurance vs quality control
- SOP meaning and format
- Job hazard analysis
- Near miss reporting
- Fishbone diagram
- Pareto chart
- Histogram
- Control chart
- What is a gemba walk
- What is lead time
- What is operational excellence
- How to improve product quality
- Preventive vs predictive maintenance
- Kanban
- FMEA
- PDSA cycle
- Safety moments
- Just-in-time manufacturing
- Kaizen
- 5S
- Total quality management (TQM)
- CAPA (corrective and preventive action)
- Layered process audit (LPA)
- Lean tools
- Lockout tagout (LOTO)
- A3 problem solving
- Preventive maintenance
- APQP
- High reliability organization (HRO)
- Manufacturing KPIs
- Quality metrics
- Practical problem solving
- CMMS
- Risk assessment
- Production efficiency
- Total productive maintenance (TPM)
- Reliability-centered maintenance (RCM)
- Hierarchy of controls
- Personal protective equipment (PPE)
- Emergency action plan
- Safety signs
- Warehouse safety
- ISO 9001
- SIPOC diagram
- Rolling action item list (RAIL)
- Pugh matrix
- Flowchart
- Project charter
- ISO 9001:2026
- Fleet maintenance
- IATF 16949
- AS9100
- ISO 14001
- ISO 45001
- One point lesson
- Standard work
- Meeting cadence
- OSHA penalties and the top 10 cited standards
- OSHA 300A summary
- SMART goals examples for manufacturing
- Year-end review for manufacturing plants
- 2027 goals for a manufacturing plant
- Lean manufacturing principles
- Toyota Production System
- 5W1H
- 5 Whys
- Continuous improvement
- Takt time
- DMAIC
- PDCA
- 8D problem solving
- Prioritization matrix
- Gemba walk questions
- 5W1H questions
- Layered process audit questions
- 5S audit questions
- Difficult conversations at work
- How to talk to an employee about poor performance
- How to resolve conflict between employees
- High performer, bad attitude
- How to get employees to follow procedures
- Resistance to change on the shop floor
- Influence without authority for CI, quality and safety people
- Quality vs production: the hold against the ship date
- Hard savings vs soft savings
- How to handle a customer quality complaint call
- 30 60 90 day plan for a manufacturing manager
- First 90 days in a new manufacturing role
- New supervisor training: the first 90 days
- Night shift supervisor
- Engineer to manager in manufacturing
- What to do after a serious workplace accident
- Disagree and commit: disagreeing with your boss in a plant
- How to deliver bad news to your boss
- How to present audit findings to management
- How to get leadership buy-in for continuous improvement
- How to ask for more headcount or resources
- How to ask for a promotion in manufacturing
- PPE compliance
- Language barriers on the shop floor
- Train the trainer in manufacturing
- Contractor safety management
- Return to work after an injury
- Attendance conversation with an employee
- Managing former peers after a promotion
- Managing older or more experienced employees
- Inheriting a team
- How to delegate as a supervisor
- Holding supervisors accountable
- How to tell employees about layoffs or a shift change
- How to deny a raise request or a promotion
- Time and motion study
- How to conduct a time study
- Standard time
- SMED
- Line balancing
- Yamazumi chart
- Ergonomic assessment in manufacturing
- Spaghetti diagram
- Time study vs motion study vs method study
- Why do a time study
- How to plan a time study
- How to break a job into elements
- How many cycles to time
- Stopwatch time study
- Time study mistakes
- Time study vs work sampling
- Value added vs non value added
- Labor losses in manufacturing
- New product time study playbook
- How to estimate cycle time for a new product
- New product introduction for industrial engineers
- Process planning for a new product
- Planning operators and stations for a new line
- Pilot run and line trial
- Ramp-up plan and the learning curve
- Workstation design
- Designing a future workstation
- Time study and ergonomic study in one pass
- Predetermined motion time systems (PMTS)
- MTM (Methods-Time Measurement)
- MOST and MODAPTS
- Therbligs and motion economy
- RULA assessment
- REBA assessment
- RULA vs REBA
- NIOSH lifting equation
- Production capacity calculation
- Precedence diagram
- Labor efficiency and labor variance
- Labor cost and quoting with time standards
- SMV and SAM in garment manufacturing
- From time study to standard work
- Standard work combination table
- Standard work vs SOP vs work instruction
- Standard WIP
- Updating standard work after an improvement
- Time study from video
- Time study app or software
- Man-machine chart
- Timing long-cycle and team work
- Time study in a union plant
- History of time and motion study
- Golden zone (power zone)
- Workstation assessment
- Reach envelope and work area study
- Standing, seated and sit-stand workstations
- Line-side material presentation
- Time study in automotive assembly
- Time study in electronics assembly
- Time study in CNC machining
- Time study in metal fabrication and welding
- Time study in plastics injection molding
- Time study in warehouse operations
- Time study in garment manufacturing
- Time study in maintenance work
- Time study in aerospace assembly and MRO
- Time study in food and beverage manufacturing
- Time study examples
- Historical and machine data as time standards
- Line balancing examples
- How to measure cycle time
- Manpower planning from standard time
- Bottleneck analysis from a time study
- Standard work examples
- U-cells and one-piece flow
- Flow process chart and operation process chart
- Two-handed process chart
- 3P production preparation process
- Plant layout basics
- Design for assembly
- Time study, PFMEA, control plan and work instructions
- Explaining a time study to a worried operator
- The observer effect in time studies
- Time standards and incentive pay
- Seven wastes vs eight wastes
- Job safety analysis (JSA)
- JSRA (job safety risk assessment)
- JSA vs JHA vs JSRA
- Job safety analysis from video
- HIRA (hazard identification and risk assessment)
- Management of change (MOC)
- Safe work method statement (SWMS)
- Permit to work (PTW)
- Pre-task plan (PTP)
- Field level risk assessment (FLRA)
- Safety observation
- Safety walk
Or browse the topics, the full library and the lean glossary.