Skip to content
LeanSuite

Free tool

Standard time calculator

Standard time is the time a trained operator needs to do a job at normal pace, with allowances for personal needs, fatigue and unavoidable delays. Normal time = observed time × rating ÷ 100. Standard time = normal time × (1 + allowance), or normal time ÷ (1 − allowance) if your allowance is a share of the shift. Ten cycles averaging 0.50 minutes, rated at 110 with a 15% allowance, give a standard time of 0.6325 minutes: 94.9 units an hour.

Standard time formula

Normal timeequalsobserved time × rating divided by 100

Standard timeequalsnormal time × (1 + A)

or Standard timeequalsnormal time divided by 1 − A

Units per hourequals60 divided by standard minutes per unit

Labour cost per unitequalsstandard minutes divided by 60 × hourly rate

Observed time is the average of the cycles you kept. Rating is the pace you judged against normal, with 100 as normal. A is the allowance as a decimal (0.15 for 15%). Use the first standard time line when A is a percentage added to normal time, as in the ILO tables, and the second when A is a share of the whole shift. Freivalds (Niebel's Methods, Standards, and Work Design, chapter 10) gives both. The ILO calls normal time basic time.
Observed times

10 readings read. Separate them with spaces, commas or new lines, a point for decimals (up to 500). Leave out cycles with an interruption you saw and noted.

Time unit of the readings

100 is normal pace

Personal, fatigue and delay

Example allowances

Personal 5 + basic fatigue 4 + standing 2 + delays 4 (example). These are examples, written as percentages added to normal time. Use the allowances your site has set.

How your allowance is defined

Standard = normal × (1 + allowance). Use it when the percentage is added to working time, as in the ILO tables.

For pieces per shift

For labour cost per unit

Pre-filled with the worked example below: ten cycles of packing a carton. For a job timed by element, run each element with its own rating, add the normal times, then apply the allowance once.

Standard time per unit

0.6325 min

37.95 s per unit. Allowance of 15% added to normal time.

The working

1. Observed time = average of 10 readings = 30 s = 0.5 min.

2. Normal time = 0.5 × 110 ÷ 100 = 0.55 min.

3. Standard time = 0.55 × (1 + 0.15) = 0.6325 min.

4. Units per hour = 60 ÷ 0.6325 = 94.9.

5. Pieces per shift = 480 ÷ 0.6325 = 758.9, so 758 whole pieces.

6. Labour cost per unit = 0.6325 ÷ 60 × $24.00 = $0.253.

Normal time

0.55 min

Observed 0.5 min at a rating of 110

Allowance per unit

0.0825 min

4.95 s on top of normal time

Units per hour

94.9

At standard, for one operator

Pieces per shift

758

480 min, of which 63 min is allowance

Labour cost per unit

$0.253

$25.30 per 100 units at $24.00 an hour. Direct labour only.

Read as a share of the shift, the same 15% would give 0.6471 min and 92.7 units per hour (741 per shift). Your 15% added to normal time equals 13.04% as a share of the shift. Check which one your allowance table means before you publish the standard.

Email me my results

Optional. Get these inputs and results in your inbox, with a link back to this calculator.

We may follow up about LeanSuite. See our Privacy Notice.

Next step

Want to track this every week?

Bring this result to a 45-minute demo and we will show where it fits in LeanSuite's Time and Motion Study.

How to use it

From stopwatch readings to a standard

1. Paste the observed times. Use the readings of the whole job, or of one element, from a trained operator working the agreed method. Leave out a cycle only if you saw what went wrong and wrote it down.

2. Enter the rating. 100 is normal pace on your site's scale. A machine-controlled element is not rated: enter 100.

3. Enter the allowance and say what it is a percentage of. Added to normal time, or a share of the shift. If you do not know, ask whoever owns the allowance table how the numbers were built.

4. Add the paid shift and a labour rate if you want output and cost. Use the paid minutes when the allowance covers breaks. If breaks are scheduled stops that the allowance does not cover, enter the working minutes after breaks.

5. For a job timed by element, run each element with its own rating, add the normal times (dividing an occasional element by how often it happens), then apply the allowance once to the total. The standard time guide works a four-element job this way.

Standard time calculation example

Illustrative numbers, not a benchmark

An operator packs cartons. Ten cycles were timed in seconds: 29, 31, 30, 28, 32, 30, 31, 29, 30 and 30. The observer rated the pace at 110. The site allowance is 15%, added to normal time. The shift is 480 paid minutes and the labour rate is $24 an hour. Illustrative numbers.

  1. Step 1

    Observed time = 300 ÷ 10 = 30.0 s = 0.50 min.
  2. Step 2

    Normal time = 0.50 × 110 ÷ 100 = 0.55 min.
  3. Step 3

    Standard time = 0.55 × (1 + 0.15) = 0.6325 min, or 37.95 s per carton.
  4. Step 4

    Units per hour = 60 ÷ 0.6325 = 94.9.
  5. Step 5

    Pieces per shift = 480 ÷ 0.6325 = 758.9, so 758 whole cartons.
  6. Step 6

    Labour cost per carton = 0.6325 ÷ 60 × $24 = $0.253.
The standard is 0.6325 minutes a carton: about 95 an hour and 758 a shift. If the same 15% were a share of the shift, the standard would be 0.55 ÷ 0.85 = 0.647 minutes and the shift would give 741 cartons, 17 fewer. That gap is why the calculator asks how your allowance is defined.

Two allowance formulas, two answers

Both formulas are correct. They answer different questions about the same percentage.

  • Added to normal time: standard = normal × (1 + A). The allowance is extra time for each minute of work. 15% of a 480 minute shift worked this way is 62.6 minutes of allowance and 417.4 minutes of work.
  • Share of the shift: standard = normal ÷ (1 − A). The allowance is time out of the whole day. 15% of 480 minutes is 72 minutes of allowance and 408 minutes of work.

To convert: a share of the shift A equals A ÷ (1 − A) added to normal time, so 15% of the shift is 17.65% added. Going the other way, 15% added is 15 ÷ 115 = 13.04% of the shift. The calculator shows both.

The example allowances

The buttons are sums of entries in the table of allowances the ILO printed in the earlier editions of Introduction to Work Study and Niebel reprints. They are percentages added to normal time, and they are examples, not a recommendation for your job.

  • 9%: Personal 5 + basic fatigue 4 (the ILO table's constants).
  • 11%: Personal 5 + basic fatigue 4 + standing 2.
  • 15%: Personal 5 + basic fatigue 4 + standing 2 + delays 4 (example).
  • 20%: Personal 5 + basic fatigue 4 + standing 2 + bending 2 + lifting 20 lb 3 + delays 4 (example).

The 4% for delays is made up for the example. Measure yours with a work sampling or all-day study, and leave avoidable delays out. The allowances section of the guide shows how to build the figure for one job.

About the rating

The rating is the one judgement in the sum, and an error in it moves the standard by the same percentage. A rating of 110 where 100 was right makes the standard 10% too long.

  • Rate against a pace the observers have practised on together, not against the fastest person in the plant.
  • Write the rating down before you look at the times.
  • Rate each element when the job has machine time or the pace changes between elements.
  • If you use the Westinghouse system, add its four values (skill, effort, conditions, consistency) to 100 and enter the total.

The performance rating section of the guide has the scales and the Westinghouse table.

What the result does not tell you

  • Whether you timed enough cycles. The time study sample size calculator answers that from the spread of the readings.
  • Whether the method is right. A standard for a wasteful method is an accurate measure of waste. Fix the method first.
  • What a line will make. Units per hour is one operator at standard. A line is paced by its slowest station and loses time to stops that no personal allowance covers.
  • The full cost of the part. Labour cost per unit is direct labour at the rate you entered: no benefits, overhead, material or scrap.

Sources and how this calculator was checked

  • Andris Freivalds, Niebel's Methods, Standards, and Work Design, 12th ed. (McGraw-Hill, 2009), chapter 10: standard time as normal time × (1 + allowance), and the alternative with the allowance as a fraction of the workday, normal time ÷ (1 − allowance).
  • International Labour Office, Introduction to Work Study, ed. George Kanawaty (4th rev. ed., 1992, and the editions of 1969 to 1979): basic time = observed time × rating ÷ standard rating, relaxation allowances as a percentage of basic time, and the constants of 5% for personal needs and 4% for basic fatigue.
  • Benjamin W. Niebel, Motion and Time Study, 7th ed. (Irwin, 1982): the reprinted table of ILO recommended allowances.

Unit tests reproduce the example on this page, both allowance formulas and the conversion between them, the four-element job in the guide, and the edge cases: one reading, a zero allowance, a share of the shift of 100%, a blank shift and a blank labour rate.

Embed this calculator

Teaching this, or writing about it? Paste this code into your site, course page or intranet and the calculator works right there. It is free, with no sign-up.

<iframe src="https://www.theleansuite.com/tools/standard-time-calculator/embed" title="Standard time calculator by LeanSuite" width="100%" height="2300" style="border:0;max-width:1000px" loading="lazy" allow="clipboard-write"></iframe>
<p style="font:13px/1.4 sans-serif"><a href="https://www.theleansuite.com/tools/standard-time-calculator">Standard time calculator</a> by LeanSuite</p>

How LeanSuite helps

LeanSuite's AI time and motion study times every element from one phone video of the process, and its study report gives cycle time, standard time, takt and units per hour, each linked to the video it came from. Use this calculator to check a standard by hand or to see what a different rating or allowance would do to it.

See Time and Motion Study

FAQ

Standard time calculator: common questions

  1. Average the observed times, multiply by the performance rating to get normal time, then add the allowance. Normal time = observed time × rating ÷ 100. Standard time = normal time × (1 + allowance) when the allowance is a percentage of normal time, or normal time ÷ (1 − allowance) when it is a share of the shift. Ten cycles averaging 0.50 minutes, rated at 110 with a 15% allowance added to normal time, give 0.50 × 1.10 × 1.15 = 0.6325 minutes.

  2. Normal time is the observed time adjusted for pace: observed time × rating ÷ 100. An operator timed at 0.50 minutes while working at 110% of normal pace has a normal time of 0.55 minutes. Standard time then adds the allowance for personal needs, fatigue and unavoidable delays: 0.55 × 1.15 = 0.6325 minutes with a 15% allowance on normal time. Normal time is what the work takes; standard time is what you can plan on across a whole shift.

  3. It depends on what your allowance percentage is a percentage of. If it is added to working time, as in the ILO allowance tables, use normal time × (1 + A). If it is the share of the whole shift given to personal time, rest and delays, such as 72 minutes of a 480 minute shift, use normal time ÷ (1 − A). Freivalds gives both forms. At 15% the second gives a standard 2.3% longer, so the wrong choice moves every standard by that much.

  4. 100, meaning the pace of a trained operator working steadily without rushing. American texts tie it to benchmarks such as walking at 3 miles an hour or dealing 52 cards into four hands in half a minute. The British Standard scale used by the ILO puts 100 at a brisker, incentive pace, about walking at 4 miles an hour. Find out which scale your site uses before you compare ratings or standards with another plant.

  5. The one your site has set or agreed with its workforce. The buttons are examples built from the allowance table the ILO published in its earlier editions, which Niebel reprints: 5% for personal needs and 4% for basic fatigue as constants, plus variable additions such as 2% for standing. A delay allowance has no table. It comes from a work sampling or all-day study of the job.

  6. Units per hour = 60 ÷ standard minutes per unit. Pieces per shift = paid shift minutes ÷ standard minutes. Labour cost per unit = standard minutes ÷ 60 × the hourly rate. A standard of 0.6325 minutes gives 94.9 units an hour, 758 pieces in a 480 minute shift and, at 24 an hour, a labour cost of 0.253 per unit. If the allowance already covers the breaks, do not take the breaks off the shift as well.

More free lean tools

All tools

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.