Free tool
Standard time calculator
Standard time is the time a trained operator needs to do a job at normal pace, with allowances for personal needs, fatigue and unavoidable delays. Normal time = observed time × rating ÷ 100. Standard time = normal time × (1 + allowance), or normal time ÷ (1 − allowance) if your allowance is a share of the shift. Ten cycles averaging 0.50 minutes, rated at 110 with a 15% allowance, give a standard time of 0.6325 minutes: 94.9 units an hour.
Standard time formula
Normal timeequalsobserved time × rating divided by 100
Standard timeequalsnormal time × (1 + A)
or Standard timeequalsnormal time divided by 1 − A
Units per hourequals60 divided by standard minutes per unit
Labour cost per unitequalsstandard minutes divided by 60 × hourly rate
10 readings read. Separate them with spaces, commas or new lines, a point for decimals (up to 500). Leave out cycles with an interruption you saw and noted.
100 is normal pace
Personal, fatigue and delay
Example allowances
Personal 5 + basic fatigue 4 + standing 2 + delays 4 (example). These are examples, written as percentages added to normal time. Use the allowances your site has set.
For pieces per shift
For labour cost per unit
Pre-filled with the worked example below: ten cycles of packing a carton. For a job timed by element, run each element with its own rating, add the normal times, then apply the allowance once.
Standard time per unit
0.6325 min
37.95 s per unit. Allowance of 15% added to normal time.
The working
1. Observed time = average of 10 readings = 30 s = 0.5 min.
2. Normal time = 0.5 × 110 ÷ 100 = 0.55 min.
3. Standard time = 0.55 × (1 + 0.15) = 0.6325 min.
4. Units per hour = 60 ÷ 0.6325 = 94.9.
5. Pieces per shift = 480 ÷ 0.6325 = 758.9, so 758 whole pieces.
6. Labour cost per unit = 0.6325 ÷ 60 × $24.00 = $0.253.
Normal time
0.55 min
Observed 0.5 min at a rating of 110
Allowance per unit
0.0825 min
4.95 s on top of normal time
Units per hour
94.9
At standard, for one operator
Pieces per shift
758
480 min, of which 63 min is allowance
Labour cost per unit
$0.253
$25.30 per 100 units at $24.00 an hour. Direct labour only.
Read as a share of the shift, the same 15% would give 0.6471 min and 92.7 units per hour (741 per shift). Your 15% added to normal time equals 13.04% as a share of the shift. Check which one your allowance table means before you publish the standard.
Next step
Want to track this every week?
Bring this result to a 45-minute demo and we will show where it fits in LeanSuite's Time and Motion Study.
How to use it
From stopwatch readings to a standard
1. Paste the observed times. Use the readings of the whole job, or of one element, from a trained operator working the agreed method. Leave out a cycle only if you saw what went wrong and wrote it down.
2. Enter the rating. 100 is normal pace on your site's scale. A machine-controlled element is not rated: enter 100.
3. Enter the allowance and say what it is a percentage of. Added to normal time, or a share of the shift. If you do not know, ask whoever owns the allowance table how the numbers were built.
4. Add the paid shift and a labour rate if you want output and cost. Use the paid minutes when the allowance covers breaks. If breaks are scheduled stops that the allowance does not cover, enter the working minutes after breaks.
5. For a job timed by element, run each element with its own rating, add the normal times (dividing an occasional element by how often it happens), then apply the allowance once to the total. The standard time guide works a four-element job this way.
Standard time calculation example
Illustrative numbers, not a benchmarkAn operator packs cartons. Ten cycles were timed in seconds: 29, 31, 30, 28, 32, 30, 31, 29, 30 and 30. The observer rated the pace at 110. The site allowance is 15%, added to normal time. The shift is 480 paid minutes and the labour rate is $24 an hour. Illustrative numbers.
Step 1
Observed time = 300 ÷ 10 = 30.0 s = 0.50 min.Step 2
Normal time = 0.50 × 110 ÷ 100 = 0.55 min.Step 3
Standard time = 0.55 × (1 + 0.15) = 0.6325 min, or 37.95 s per carton.Step 4
Units per hour = 60 ÷ 0.6325 = 94.9.Step 5
Pieces per shift = 480 ÷ 0.6325 = 758.9, so 758 whole cartons.Step 6
Labour cost per carton = 0.6325 ÷ 60 × $24 = $0.253.
Two allowance formulas, two answers
Both formulas are correct. They answer different questions about the same percentage.
- Added to normal time: standard = normal × (1 + A). The allowance is extra time for each minute of work. 15% of a 480 minute shift worked this way is 62.6 minutes of allowance and 417.4 minutes of work.
- Share of the shift: standard = normal ÷ (1 − A). The allowance is time out of the whole day. 15% of 480 minutes is 72 minutes of allowance and 408 minutes of work.
To convert: a share of the shift A equals A ÷ (1 − A) added to normal time, so 15% of the shift is 17.65% added. Going the other way, 15% added is 15 ÷ 115 = 13.04% of the shift. The calculator shows both.
The example allowances
The buttons are sums of entries in the table of allowances the ILO printed in the earlier editions of Introduction to Work Study and Niebel reprints. They are percentages added to normal time, and they are examples, not a recommendation for your job.
- 9%: Personal 5 + basic fatigue 4 (the ILO table's constants).
- 11%: Personal 5 + basic fatigue 4 + standing 2.
- 15%: Personal 5 + basic fatigue 4 + standing 2 + delays 4 (example).
- 20%: Personal 5 + basic fatigue 4 + standing 2 + bending 2 + lifting 20 lb 3 + delays 4 (example).
The 4% for delays is made up for the example. Measure yours with a work sampling or all-day study, and leave avoidable delays out. The allowances section of the guide shows how to build the figure for one job.
About the rating
The rating is the one judgement in the sum, and an error in it moves the standard by the same percentage. A rating of 110 where 100 was right makes the standard 10% too long.
- Rate against a pace the observers have practised on together, not against the fastest person in the plant.
- Write the rating down before you look at the times.
- Rate each element when the job has machine time or the pace changes between elements.
- If you use the Westinghouse system, add its four values (skill, effort, conditions, consistency) to 100 and enter the total.
The performance rating section of the guide has the scales and the Westinghouse table.
What the result does not tell you
- Whether you timed enough cycles. The time study sample size calculator answers that from the spread of the readings.
- Whether the method is right. A standard for a wasteful method is an accurate measure of waste. Fix the method first.
- What a line will make. Units per hour is one operator at standard. A line is paced by its slowest station and loses time to stops that no personal allowance covers.
- The full cost of the part. Labour cost per unit is direct labour at the rate you entered: no benefits, overhead, material or scrap.
Sources and how this calculator was checked
- Andris Freivalds, Niebel's Methods, Standards, and Work Design, 12th ed. (McGraw-Hill, 2009), chapter 10: standard time as normal time × (1 + allowance), and the alternative with the allowance as a fraction of the workday, normal time ÷ (1 − allowance).
- International Labour Office, Introduction to Work Study, ed. George Kanawaty (4th rev. ed., 1992, and the editions of 1969 to 1979): basic time = observed time × rating ÷ standard rating, relaxation allowances as a percentage of basic time, and the constants of 5% for personal needs and 4% for basic fatigue.
- Benjamin W. Niebel, Motion and Time Study, 7th ed. (Irwin, 1982): the reprinted table of ILO recommended allowances.
Unit tests reproduce the example on this page, both allowance formulas and the conversion between them, the four-element job in the guide, and the edge cases: one reading, a zero allowance, a share of the shift of 100%, a blank shift and a blank labour rate.
Embed this calculator
Teaching this, or writing about it? Paste this code into your site, course page or intranet and the calculator works right there. It is free, with no sign-up.
<iframe src="https://www.theleansuite.com/tools/standard-time-calculator/embed" title="Standard time calculator by LeanSuite" width="100%" height="2300" style="border:0;max-width:1000px" loading="lazy" allow="clipboard-write"></iframe>
<p style="font:13px/1.4 sans-serif"><a href="https://www.theleansuite.com/tools/standard-time-calculator">Standard time calculator</a> by LeanSuite</p>How LeanSuite helps
LeanSuite's AI time and motion study times every element from one phone video of the process, and its study report gives cycle time, standard time, takt and units per hour, each linked to the video it came from. Use this calculator to check a standard by hand or to see what a different rating or allowance would do to it.
See Time and Motion StudyRead more
- Free template: Time study sheet
- Free template: Process capacity sheet template
- Free template: Cost per unit worksheet (manufacturing cost per good unit)
- Time study in the lean glossary
- Standard time: observed, normal and standard time, rating and allowances
- Time study sample size calculator: how many cycles to time
- Takt time: the pace demand sets, to compare the standard with
- How many operators do you need: work content divided by takt
- Cycle time in the lean glossary
FAQ
Standard time calculator: common questions
Average the observed times, multiply by the performance rating to get normal time, then add the allowance. Normal time = observed time × rating ÷ 100. Standard time = normal time × (1 + allowance) when the allowance is a percentage of normal time, or normal time ÷ (1 − allowance) when it is a share of the shift. Ten cycles averaging 0.50 minutes, rated at 110 with a 15% allowance added to normal time, give 0.50 × 1.10 × 1.15 = 0.6325 minutes.
Normal time is the observed time adjusted for pace: observed time × rating ÷ 100. An operator timed at 0.50 minutes while working at 110% of normal pace has a normal time of 0.55 minutes. Standard time then adds the allowance for personal needs, fatigue and unavoidable delays: 0.55 × 1.15 = 0.6325 minutes with a 15% allowance on normal time. Normal time is what the work takes; standard time is what you can plan on across a whole shift.
It depends on what your allowance percentage is a percentage of. If it is added to working time, as in the ILO allowance tables, use normal time × (1 + A). If it is the share of the whole shift given to personal time, rest and delays, such as 72 minutes of a 480 minute shift, use normal time ÷ (1 − A). Freivalds gives both forms. At 15% the second gives a standard 2.3% longer, so the wrong choice moves every standard by that much.
100, meaning the pace of a trained operator working steadily without rushing. American texts tie it to benchmarks such as walking at 3 miles an hour or dealing 52 cards into four hands in half a minute. The British Standard scale used by the ILO puts 100 at a brisker, incentive pace, about walking at 4 miles an hour. Find out which scale your site uses before you compare ratings or standards with another plant.
The one your site has set or agreed with its workforce. The buttons are examples built from the allowance table the ILO published in its earlier editions, which Niebel reprints: 5% for personal needs and 4% for basic fatigue as constants, plus variable additions such as 2% for standing. A delay allowance has no table. It comes from a work sampling or all-day study of the job.
Units per hour = 60 ÷ standard minutes per unit. Pieces per shift = paid shift minutes ÷ standard minutes. Labour cost per unit = standard minutes ÷ 60 × the hourly rate. A standard of 0.6325 minutes gives 94.9 units an hour, 758 pieces in a 480 minute shift and, at 24 an hour, a labour cost of 0.253 per unit. If the allowance already covers the breaks, do not take the breaks off the shift as well.
More free lean tools
All tools- OEE calculatorOverall equipment effectiveness from shift time, downtime, ideal cycle time and part counts.
- Downtime cost calculatorWhat an hour, an event and a year of unplanned downtime cost, from lost output, idle labour, scrap and overtime.
- SMED changeover calculatorTime saved by moving changeover steps from internal to external, capacity freed per week and the smaller batch it allows.
- Takt time calculatorThe pace a line must hit to meet customer demand, from shift time, breaks and daily demand.
- Cycle time calculatorCycle time against takt, units per hour, capacity per shift and the gap to daily demand.
- Line balancing calculatorLine efficiency, balance delay and the minimum number of stations from station times and takt.
- Bottleneck calculatorThe step that limits your line, from each step's cycle time, machines and uptime, with daily capacity and the gap to demand.
- First pass yield (FPY) calculatorFirst pass yield at each step and rolled throughput yield (RTY) across the whole process.
- Cost of poor quality (COPQ) calculatorTotal COPQ and cost of quality, and each as a share of revenue, from the four quality cost categories.
- Process capability (Cp, Cpk) calculatorCp and Cpk against your specification limits, plus Pp and Ppk from pasted measurements, with a distribution chart.
- DPMO and sigma level calculatorDPMO, defects per unit, yield and sigma level from the defects found, units checked and opportunities per unit.
- MTBF and MTTR calculatorMean time between failures, mean time to repair and availability from operating time, failures and repair time.
- Lead time calculatorManufacturing lead time from WIP and throughput (Little's Law), and the share of it that adds value.
- Throughput time calculatorThroughput time from process, inspection, move and wait time, the share of it that adds value, and units per hour.
- Kaizen savings calculatorYearly savings, payback in months and first-year ROI of an improvement, from time saved, scrap avoided and its costs.
- TEEP calculatorTotal effective equipment performance: OEE multiplied by how much of all calendar time you plan to run.
- Overall labor effectiveness (OLE) calculatorHow well paid labor hours turn into good output: availability, performance and quality of the crew.
- Inventory turnover and days on hand calculatorHow many times stock turns over in a period and how many days of it you hold, from COGS and average inventory.
- Safety stock calculatorSafety stock and reorder point from the service level you want, average demand and lead time, and how much each varies.
- Scrap rate calculatorScrap rate, the cost of scrap per period and per year, and what reaching a target rate would save.
- TRIR and DART rate calculatorOSHA recordable and DART incident rates from your 300A case counts and hours, and what one more case does to them.
- NIOSH lifting equation calculatorRecommended weight limit and lifting index for a two-handed lift, with every multiplier shown so you can see what to redesign.
- Time study sample size calculatorHow many cycles of an element to time, from your first readings, with the t formula, the ILO formula and the range method.
- Production capacity calculatorMachine and labor steps in; each step's capacity per shift, the bottleneck, line capacity, takt time and utilization against demand out, with the working.
- TMU to seconds converterA time in TMU, MODs, seconds, minutes or hours, shown in all five at once, with the standard time and units per hour after your allowance.
- Work sampling observations calculatorThe number of random observations a work sampling study needs for the accuracy you want, with the working, the rounds and the days it takes.
- Allowance calculator: personal, fatigue and delayPersonal, fatigue and delay allowances for one job added up, applied under either allowance formula, with the standard time and the minutes per shift.
- Maintenance strategy selectorAnswer the RCM questions for one failure mode and get the maintenance strategy, the reasoning and the check or test interval.
- Noise dose and TWA calculatorDose and 8-hour TWA for a shift of noise levels under OSHA and NIOSH, which limits are reached and how much loud time to cut.
- Risk matrix calculatorSeverity times likelihood on a 3 x 3, 4 x 4 or 5 x 5 risk matrix, the band and its action, editable banding, and the score after further controls.
- Repair or replace calculatorEquivalent annual cost of keeping and repairing an old machine against buying a new one, with each one's economic life and the break-even figures.
- Compressed air leak cost calculatorAir lost, kW and cost a year for each tagged leak from its size and the pressure, ranked so the biggest gets fixed first.
- Machine hour rate calculatorWhat one productive hour of a machine costs, with and without the operator, the cost per part and how utilisation moves the rate.
- Total manufacturing cost calculatorTotal manufacturing cost, cost of goods manufactured, cost per unit and the overhead rate from materials, labor and overhead.
- Acceptance sampling calculatorRead the OC curve and the real risks of a sampling plan, find the plan for your AQL and LTPD, or size a zero-defect test.
- Shift schedule plannerTen shift patterns on real dates: calendar for each crew, hours a week, weekends off, coverage and the weeks over 40 hours.
- Pareto chart makerPaste categories and counts: sorted bars, cumulative percentage line and the vital few at the 80% line, as a PNG or SVG.
- Histogram makerPaste measurements: the histogram with automatic or chosen bins, plus mean, median and standard deviation, as a PNG or SVG.
- Box plot makerPaste one or more groups of numbers: box plots with quartiles, IQR, whiskers and outliers by the 1.5 IQR rule, as a PNG or SVG.
- Fishbone diagram makerName the problem, list causes under the 6M bones, and download the Ishikawa diagram as a PNG or SVG.
- 5 Whys canvasWrite the problem, answer up to five whys, state the root cause and countermeasure, then print the one-page canvas.
- Lean maturity self-assessmentScore 27 statements across nine dimensions and get a band for each, an overall band, where to start and the guides to read.
- Lean method navigatorSix questions about one problem, then the lean method to start with, the two that follow, why each fits, five steps for Monday and what it will not solve.
- Manufacturing ROI calculatorAnswer a few questions about your shop floor, shifts and downtime to estimate your potential ROI with LeanSuite.