Practical guide · Standard work, SOPs and training
Standard time: how to calculate it, with performance rating and allowances explained
Short answer
Standard time is the time a trained operator needs to do a job at normal pace, with allowances for personal needs, fatigue and unavoidable delays. Normal time = observed time x rating / 100. Standard time = normal time x (1 + allowance).
Time the job over enough cycles and average the readings you keep: that is the observed time. Multiply by the performance rating (100 is normal pace) to get normal time. Then add the allowance. If your allowance is a percentage added to working time, standard time = normal time x (1 + allowance). If it is a share of the whole shift, standard time = normal time / (1 - allowance). A job observed at 0.50 minutes, rated at 110 with a 15% allowance added to normal time, has a standard time of 0.50 x 1.10 x 1.15 = 0.6325 minutes, which is 94.9 units an hour.
Last reviewed:
What is standard time?
The whole method: from the stopwatch to a rate
Example numbersMeasure
Observed time
0.50min
Average of the 10 cycles you kept
Rate
Normal time
0.55min
The same work at normal pace (rating 110)
Allow
Standard time
0.6325min
Plus personal, fatigue and delay allowance
Use
Units per hour
94.9an hour
What one operator makes at standard
Four stages in a row. Observed time 0.50 minutes, multiplied by a rating of 110 over 100, gives a normal time of 0.55 minutes. Multiplied by 1 plus a 15 percent allowance, that gives a standard time of 0.6325 minutes. Sixty divided by the standard time gives 94.9 units an hour.
Standard time is how long a job should take a trained operator who works at a normal pace, follows the agreed method and gets the usual breaks and interruptions. The ILO's Introduction to Work Study defines it as the total time in which a job should be completed at standard performance. It is the number behind a production schedule, a quote, a line balance and a labour cost, which is why it has to be built in the open and in the same way every time.
You get there in three moves from a time study, and each move has its own name. Mixing the names up is the most common reason two people get different standards from the same readings.
- Observed time: what the stopwatch or the video shows for one cycle or one element. It belongs to that operator, on that day, at that pace.
- Selected time: the one figure you choose to represent an element once the abnormal readings are out. Most plants use the average of the readings they kept.
- Normal time: the selected time adjusted to normal pace with a performance rating. If the operator worked faster than normal, normal time is longer than what you observed. The ILO calls it basic time.
- Standard time: normal time plus allowances for personal needs, fatigue and unavoidable delays. This is the only one of the four you can plan a shift on.
Standard time is not cycle time and it is not takt time. Cycle time is what you measure at the station today. Takt is what the customer needs. Standard time sits between them: it says what the work content really is, so you can tell whether the station can meet takt and how many people the job needs.
How to calculate standard time
Two formulas do the work. Normal time = observed time x rating / 100. Standard time = normal time x (1 + allowance), with the allowance as a decimal. The steps below are the same whether you time with a stopwatch or from video.
- 1
Time the job and choose the selected time
Break the job into elements with clear end points and time a trained operator over enough cycles. The time study sample size calculator tells you how many. Ring any reading where you saw something go wrong, write down what happened, and average the rest.
- 2
Rate the pace and work out normal time
Judge the operator's pace against normal pace, where normal is 100. Normal time = selected time x rating / 100. An element timed at 0.12 minutes and rated at 110 has a normal time of 0.132 minutes. Machine-controlled elements are not rated: they stay at 100.
- 3
Spread occasional elements over the pieces they serve
Work that happens every fifth or fiftieth piece, such as gauging or changing a tote, is timed when it happens and divided by its frequency. A 0.25 minute check on 1 piece in 5 adds 0.05 minutes to each piece.
- 4
Add the normal times
The sum of the element normal times is the normal time of the job: what one piece takes at normal pace with no breaks and no interruptions.
- 5
Apply the allowance, on the right basis
Use the allowance your site has set, and check what it is a percentage of. Added to normal time: standard time = normal time x (1 + allowance). A share of the whole shift: standard time = normal time / (1 - allowance). The next section shows why this matters.
- 6
Turn the standard into output and cost
Units per hour = 60 / standard minutes. Pieces per shift = shift minutes / standard minutes. Labour cost per piece = standard minutes / 60 x the hourly rate.
A short example before the full one. An operator packs cartons, and ten cycles average 30 seconds, which is 0.50 minutes. You rate the pace at 110. The site allowance is 15%, added to normal time. Normal time = 0.50 x 110 / 100 = 0.55 minutes. Standard time = 0.55 x 1.15 = 0.6325 minutes, or 37.95 seconds a carton. That is 60 / 0.6325 = 94.9 cartons an hour.
The standard time calculator is pre-filled with this carton job. Paste your own readings and it shows each step, both allowance formulas, pieces per shift and labour cost per unit.
Two allowance formulas, and why they give different answers
Ask two plants for their standard time formula and you may get two answers. One multiplies normal time by (1 + allowance). The other divides it by (1 - allowance). Both are correct. They disagree because the allowance percentage means something different in each.
One job, one "15%", two different shifts
Example numbersAdded to normal time
ST = 0.672 x (1 + 0.15)
417.4 min working
62.6 min allowance
Allowance is 15% of the minutes worked: 417.4 x 0.15 = 62.6.
- Standard time
- 0.7728 min
- Pieces in the shift
- 621
Share of the shift
ST = 0.672 / (1 - 0.15)
408.0 min working
72.0 min allowance
Allowance is 15% of the whole shift: 480 x 0.15 = 72.
- Standard time
- 0.7906 min
- Pieces in the shift
- 607
Two bars of the same 480 minute shift for a job with 0.672 minutes of normal time. With 15 percent added to normal time, the shift is 417.4 minutes of work and 62.6 minutes of allowance, the standard time is 0.7728 minutes and the shift gives 621 pieces. With 15 percent as a share of the shift, it is 408 minutes of work and 72 minutes of allowance, the standard time is 0.7906 minutes and the shift gives 607 pieces.
| Added to normal time | Share of the shift | |
|---|---|---|
| Formula | ST = NT x (1 + A) | ST = NT / (1 - A) |
| What A is a percentage of | The time spent working at normal pace | The whole shift, breaks and delays included |
| Who writes it this way | The ILO (relaxation allowance as a percentage of basic time), and the first form in Freivalds (Niebel) | Freivalds's alternative form, for allowances stated as a fraction of the workday |
| 15% of a 480 minute shift means | 62.6 min of allowance, 417.4 min of work | 72 min of allowance, 408 min of work |
| The same allowance on the other basis | 13.04% of the shift | 17.65% added to normal time |
| Bracket job below (NT 0.672 min) | ST 0.7728 min, 621 pieces a shift | ST 0.7906 min, 607 pieces a shift |
Illustrative job. 15 / 115 = 13.04% and 15 / 85 = 17.65%. All figures are recomputed in the page's tests.
Here is the reason. Under the first convention, 15% is extra time earned by each minute of work, so a shift of 480 minutes splits into W minutes of work and 0.15 x W of allowance: W = 480 / 1.15 = 417.4 minutes. Under the second, 15% comes off the top of the shift: 72 minutes of allowance and 408 of work. The second gives the operator 9.4 more minutes away from the work, so it gives a longer standard and fewer pieces.
How to tell which one your company uses
- Look at how the allowance was built. If it came from a table of percentages for personal needs, fatigue, standing and so on, it is almost certainly a percentage of normal time: use x (1 + A).
- If it came from minutes in the day, such as two 15 minute breaks, 10 minutes of clean-up and 32 minutes of measured delay in a 480 minute shift, it is a share of the shift: use / (1 - A).
- Check an old standard by hand. Take its normal time and its allowance and see which formula reproduces the published figure.
- Write the basis on every study sheet next to the percentage. An allowance of 15% with no basis is not a complete number.
The gap grows with the allowance. At 10% the two formulas differ by 1%. At 15% they differ by 2.3%, and at 25% by 6.7%. If the plant quotes and pays on standards, that difference is in every part number.
A complete worked example
Illustrative example. An operator drills and deburrs a steel bracket at a single drill press, standing. The job has four elements. Ten cycles were timed in decimal minutes. In cycle 6 the operator dropped the bracket during element 3, so that reading (0.34) was ringed, the cause was noted and the element's selected time is the average of the other nine: 0.20. With the dropped part left in it would have been 0.214, 7% too high.
| Element | Selected time (min) | Rating | Per piece | Normal time (min) |
|---|---|---|---|---|
| 1. Load bracket in fixture and clamp | 0.12 | 110 | Every piece | 0.132 |
| 2. Drill two holes, power feed | 0.30 | 100, machine-controlled | Every piece | 0.300 |
| 3. Unclamp, deburr, place in tote | 0.20 | 95 | Every piece | 0.190 |
| 4. Gauge hole diameter | 0.25 | 100 | 1 piece in 5 | 0.050 |
| Job total | 0.67 per piece | 0.672 |
Element 1: 0.12 x 110 / 100 = 0.132. Element 3: 0.20 x 95 / 100 = 0.190. Element 4: 0.25 / 5 = 0.050 per piece.
The bracket job: observed, normal and standard time, drawn to scale
Example numbers- 1 Load and clamp
- 2 Drill, power feed
- 3 Unclamp and deburr
- 4 Gauge, 1 piece in 5
- Allowance
Observed time0.67 min
0.12 + 0.30 + 0.20 + 0.05 = 0.67
- x rating: 110, 100, 95, 100
Normal time0.672 min
0.132 + 0.300 + 0.190 + 0.050 = 0.672
- x (1 + 0.15) allowance
Standard time0.7728 min
0.672 + 0.1008 allowance = 0.7728
Three bars on one time scale. Observed time per piece is 0.67 minutes, made of four elements. After rating, normal time is 0.672 minutes: element 1 grows from 0.12 to 0.132, element 3 shrinks from 0.20 to 0.190, and elements 2 and 4 stay the same. Standard time is 0.7728 minutes: the normal time plus 0.1008 minutes of allowance.
Three things in that table are worth a second look. The operator was quick at loading and a little slow at deburring, so one rating for the whole cycle would have been wrong for both. The drill feed is set by the machine, so no rating can change it. And the gauge check takes a quarter of a minute but costs each piece only a fifth of that.
The allowance for this job is 15%, added to normal time: 5 for personal needs, 4 for basic fatigue, 2 for standing and 4 for unavoidable delays measured at the press. The allowances section shows where each part comes from.
| Step | Working | Result |
|---|---|---|
| Normal time | 0.132 + 0.300 + 0.190 + 0.050 | 0.672 min |
| Standard time | 0.672 x (1 + 0.15) | 0.7728 min (46.4 s) |
| Allowance in each piece | 0.7728 - 0.672 | 0.1008 min |
| Units per hour | 60 / 0.7728 | 77.6 |
| Pieces per 8 hour shift | 480 / 0.7728 = 621.1 | 621 |
| Labour cost per piece at $24 an hour | 0.7728 / 60 x 24 | $0.309 |
| If 15% were a share of the shift | 0.672 / (1 - 0.15) | 0.7906 min, 75.9 an hour, 607 a shift |
The 480 minutes are paid minutes. Breaks are inside the allowance, so they are not taken off again.
So the standard is 0.773 minutes a bracket, or 1.288 standard hours per 100 pieces. One operator at standard makes 621 in a shift. The last row is the same job with the allowance read the other way: 14 fewer brackets a shift and a labour cost of $0.316 in place of $0.309. Nothing about the work changed between those two rows. Only the meaning of 15% did.
Performance rating: what 100 means and how to rate fairly
Performance rating is the step where the observer compares the pace they are watching with normal pace and writes down a number. It exists because you can only time a real person, and that person may be working faster or slower than a standard should assume. It is also the one judgement in the whole calculation, so it is where most arguments about a standard start.
What 100 means
100 means normal pace: a trained operator, used to the job, working steadily without hurrying and without holding back, at a pace they could keep up all day. American textbooks pin it to benchmarks. Walking on level ground at 3 miles an hour is the usual one, and dealing a deck of 52 cards into four hands in half a minute is another.
The catch is that not every scale puts 100 in the same place. The British Standard 0 to 100 scale, which the ILO uses, sets 100 at standard rating: the brisk, business-like pace of a qualified worker on piecework, compared with walking at 4 miles an hour. On that scale the unhurried 3 miles an hour pace is 75. The older 60-80 and 100-133 scales name both points: the lower number is the day-rate pace and the higher one the incentive pace.
So a rating of 100 in one plant can be 75 in another for the identical pace. Before you compare standards between sites, or use a rating from a textbook, find out which scale it is on.
The same five paces on three rating scales
2 mi/h
3.2km/h
3 mi/h
4.8km/h
4 mi/h
6.4km/h
5 mi/h
8.0km/h
6 mi/h
9.6km/h
100-133 scale: 100 is normal pace, as in American texts
60-80 scale: 60 is day-rate pace, 80 incentive pace
0-100 scale: British Standard, used by the ILO
- 2 mi/h: Very slow, clumsy, fumbling
- 3 mi/h: Steady and unhurried, like a worker on day rate
- 4 mi/h: Brisk and business-like, like a qualified worker on piecework
- 5 mi/h: Very fast, with skill well above the average trained worker
- 6 mi/h: Exceptionally fast, not a pace to keep up for long
A grid. Each column is a pace, given as a walking speed from 2 to 6 miles an hour. Each row is a rating scale. Walking at 3 miles an hour is 100 on the 100-133 scale, 60 on the 60-80 scale and 75 on the British Standard 0-100 scale. Walking at 4 miles an hour is 133, 80 and 100.
Four ways to rate
- Speed rating. The observer judges pace alone against their picture of normal and writes one number, such as 95 or 110. It is the quickest method and the most used, and it depends entirely on how well the observer's picture of normal has been trained.
- The Westinghouse system. The observer grades four factors (skill, effort, conditions and consistency) and adds the values from a table. It makes the reasons for a rating visible, at the cost of four judgements in place of one.
- Synthetic rating. The observed times of a few elements are compared with times for the same motions from a predetermined motion time system, and the ratio becomes the rating for the study. It takes the observer's opinion out, and it only works if those elements were done by the standard motions.
- Objective rating. Pace is rated against a single benchmark that is the same for every job, then a separate adjustment is added for how difficult the job is. It was proposed by Marvin Mundel to stop observers from mixing up speed and difficulty.
The Westinghouse system
The Westinghouse system, also called levelling, was published by Lowry, Maynard and Stegemerten in 1927. Skill is how well the operator follows the method. Effort is the will to work. Conditions are the heat, light and noise at the workplace compared with how the job normally runs. Consistency is how tightly the readings repeat. Each has a grade from A to F with a value, average is zero, and the four values are added to 1.00. The best possible total is 1.38 and the worst is 0.50.
Say an operator shows good skill (C1, +0.06), good effort at the lower degree (C2, +0.02), average conditions (D, 0.00) and good consistency (C, +0.01). The factor is 1.00 + 0.09 = 1.09, a rating of 109. An observed time of 0.50 minutes becomes a normal time of 0.50 x 1.09 = 0.545 minutes. One caution: the Westinghouse factor is given once for the whole study, so it suits short, repetitive jobs and not a job where the pace changes from element to element.
The Westinghouse table, with one operator rated on it
Example numbersSkill
How well the method is followed
- A1Superskill+0.15
- A2Superskill+0.13
- B1Excellent+0.11
- B2Excellent+0.08
- C1Good (picked in the example)+0.06
- C2Good+0.03
- DAverage0.00
- E1Fair-0.05
- E2Fair-0.10
- F1Poor-0.16
- F2Poor-0.22
Effort
The will to work
- A1Excessive+0.13
- A2Excessive+0.12
- B1Excellent+0.10
- B2Excellent+0.08
- C1Good+0.05
- C2Good (picked in the example)+0.02
- DAverage0.00
- E1Fair-0.04
- E2Fair-0.08
- F1Poor-0.12
- F2Poor-0.17
Conditions
Heat, light, noise
- AIdeal+0.06
- BExcellent+0.04
- CGood+0.02
- DAverage (picked in the example)0.00
- EFair-0.03
- FPoor-0.07
Consistency
How tightly times repeat
- APerfect+0.04
- BExcellent+0.03
- CGood (picked in the example)+0.01
- DAverage0.00
- EFair-0.02
- FPoor-0.04
Four columns: skill, effort, conditions and consistency. Skill runs from plus 0.15 for superskill to minus 0.22 for poor. Effort runs from plus 0.13 to minus 0.17. Conditions run from plus 0.06 to minus 0.07. Consistency runs from plus 0.04 to minus 0.04. Average is zero in every column. The example picks skill C1 plus 0.06, effort C2 plus 0.02, conditions D zero and consistency C plus 0.01, which add to a factor of 1.09.
Rating errors and rating drift
- Loose rating: the rating is too high, so the standard has more time in it than the work needs. Tight rating is the opposite. Both are ILO terms.
- Flat rating: the observer pulls every rating toward 100, marking fast work too low and slow work too high. New observers do it most, and it is one reason to study operators who work close to normal pace.
- Rating the person. Liking the operator, knowing they are the fastest in the department, or expecting the job to be slow all leak into the number. Rate the pace of this element, now.
- Rating the difficulty. A hard job done at a normal pace is still a 100. Difficulty belongs in the time and the allowance, not in the rating.
- Drift. Without practice, an observer's picture of normal moves over the months, usually toward the pace of the people they watch most. Two analysts in the same plant can end up several points apart and not know it.
Calibration: keeping observers on the same 100
- Rate the same video clips as a group on a fixed schedule, write the ratings down before anyone speaks, then compare with the reference rating and with each other.
- Use clips of your own jobs as well as generic benchmarks such as walking or card dealing, because pace is easier to judge on work you know.
- Plot each observer's ratings against the reference. A line flatter than the diagonal is flat rating; a line shifted up or down is a loose or tight observer.
- Write the rating before you total the times. If you know the answer the rating will produce, you will steer toward it.
- Where video exists, keep the clip with the study. A rating that can be watched again can be checked by a second person, and that is the best protection a standard has.
Allowances: personal, fatigue and delay
Normal time assumes the operator works every second of the shift. Nobody does, and nobody should be planned to. Allowances add the time a person needs away from the work, and the time the job loses for reasons the operator cannot control. In the US they are grouped as PFD: personal, fatigue and delay. The ILO calls the first two relaxation allowances and the third a contingency allowance.
- Personal: time for the washroom, a drink, a short pause. It does not depend much on the job.
- Fatigue: time to recover from the effort of the work. A basic amount applies to every job, and a variable amount is added for standing, awkward posture, force, heat, noise, close visual work, mental strain and monotony.
- Delay: short interruptions that are part of the job as it runs, such as waiting for a tote change, a word from the supervisor, clearing chips or a minor adjustment. Only unavoidable delays count.
- Special or policy allowances: extra time a company grants for a stated reason, such as a learner's allowance during training, a small-batch allowance or time for rework on a known material problem. Keep them separate from the standard so they can be removed when the reason ends.
Unavoidable and avoidable delays
An unavoidable delay is one a trained operator following the method could not have prevented: the crane was busy, the inspector stopped by, a tool needed a planned change. An avoidable delay is one the operator chose or the plant should fix: a chat, a late start, hunting for a tool that has no home, waiting for material that is late every day. The first kind goes in the allowance. The second kind does not, because putting it in a standard makes the waste permanent and invisible. Record it and remove the cause.
Typical values, and whose they are
There is no universal allowance. The most quoted figures come from a table the ILO printed as an example in the earlier editions of Introduction to Work Study, and which Niebel's textbook reprints as the ILO recommended allowances. They are percentages added to normal time.
| Allowance | Value | Applies when |
|---|---|---|
| Personal needs (constant) | 5 | Every job |
| Basic fatigue (constant) | 4 | Every job |
| Standing | 2 | The job is done standing |
| Abnormal position | 0 to 7 | Slightly awkward 0, awkward such as bending 2, very awkward such as lying or stretching 7 |
| Use of force | 0 to 22 | By weight lifted or force applied, from 5 lb (0) to 70 lb (22); 20 lb is 3 |
| Bad light | 0 to 5 | Slightly below what is recommended 0, well below 2, quite inadequate 5 |
| Close attention | 0 to 5 | Fairly fine work 0, fine or exacting 2, very fine 5 |
| Noise | 0 to 5 | Continuous 0, intermittent and loud 2, intermittent and very loud or high-pitched 5 |
| Mental strain | 1 to 8 | Fairly complex process 1, complex or needing a wide span of attention 4, very complex 8 |
| Monotony | 0 to 4 | Low 0, medium 1, high 4 |
| Tediousness | 0 to 5 | Rather tedious 0, tedious 2, very tedious 5 |
The table also has a row for heat and humidity, set from measured conditions. It printed higher figures for women in some rows; set one figure for the job, not for the person doing it. A delay allowance is not in the table: it has to be measured.
Read the table as arithmetic, not as a rule. The two constants make 9%. A standing job makes 11%. Add bending and a 20 lb lift and you are at 16% before any delay. The 1992 edition of the ILO book replaced this table with a points system that scores physical strain, mental strain and working conditions and converts the points to a percentage. Many companies, and many union agreements, have their own tables. Use the one that governs your site and treat the ILO figures as a cross-check.
How to build an allowance for one job
- 1
Start with the constants
Take the personal and basic fatigue figures from your site's table. In the ILO example they are 5 and 4.
- 2
Walk the job for the variable fatigue items
Stand at the station and go down the table: posture, force, light, noise, attention, monotony. Add only what applies to this job as it is done today. The bracket job is done standing, so it gets 2.
- 3
Measure the delays
Watch the job for a full shift, or take random observations over several days, and add up the unavoidable delay time. Divide by the time spent working. At the drill press an all-day study found 16 minutes of unavoidable delay against 400 minutes of work: 16 / 400 = 4%.
- 4
Add them up and write down the basis
5 + 4 + 2 + 4 = 15%, added to normal time. If your site states allowances as a share of the shift, divide the delay minutes by the shift minutes and use the other formula.
- 5
Check it against the day
15% added to normal time is 62.6 minutes of a 480 minute shift. If the plant already gives 30 minutes of paid breaks, about 33 minutes are left for everything else. If that does not look like the job you watched, find out why before you publish the standard.
Building the bracket job's allowance, part by part
Example numbers- Personal needs: 5%ILO table constant
- Basic fatigue: 4%ILO table constant
- Standing: 2%ILO table, variable
- Unavoidable delays: 4%Measured: 16 min in 400 min of work
A bar made of four parts: personal needs 5 percent, basic fatigue 4 percent, standing 2 percent and unavoidable delays 4 percent, which add to 15 percent of normal time. On the bracket job that is 0.1008 minutes a piece and 62.6 minutes of a 480 minute shift.
Traps with allowances
- Counting breaks twice: once in the allowance and again by taking them off the shift. Pick one.
- Using one plant-wide percentage for every job. It is quick and it is unfair to the heavy jobs, because a seated inspector and a person loading castings do not tire at the same rate.
- Hiding problems in the delay allowance. A machine that jams every hour is a maintenance problem. Give it a temporary special allowance with an end date.
- Applying fatigue to machine time. While a machine runs on its own the operator is recovering. Some systems give machine-controlled time the personal allowance only.
- Using an allowance to fix a rating. If a standard feels tight, check the rating and the method. Do not pad the allowance until it feels right.
Outliers and abnormal readings: what to keep and what to leave out
Some readings will be far from the rest. The rule is simple and it is about cause, not size: leave a reading out only if you saw why it happened and wrote it down at the time. The ILO calls such readings rogues and says to examine both the long ones and the short ones, because a very short time is as likely to be a timing error as a very long one.
Ten readings of element 3, and the one that was ringed
Example numbersCycle 6: 0.34, dropped bracket
- Cycle 1: 0.19 minutes
- Cycle 2: 0.21 minutes
- Cycle 3: 0.20 minutes
- Cycle 4: 0.20 minutes
- Cycle 5: 0.19 minutes
- Cycle 6: 0.34 minutes, ringed
- Cycle 7: 0.21 minutes
- Cycle 8: 0.20 minutes
- Cycle 9: 0.20 minutes
- Cycle 10: 0.20 minutes
- Selected time 0.20: average of the 9 kept
- 0.214: average if all 10 were kept
A dot for each of ten cycles. Nine readings sit between 0.19 and 0.21 minutes. Cycle 6 is 0.34 minutes, where the operator dropped the bracket; it is ringed and left out. The average of the nine kept readings is 0.20 minutes. With the ringed reading included it would be 0.214 minutes.
| What you saw | What it is | What to do |
|---|---|---|
| A dropped part, a fumble, a question from someone | An irregular event during the element | Ring it, note the cause, leave it out of the average |
| The watch was read late, or an end point was missed | A timing error | Leave it out, and note that the next element's reading may be short |
| Changing a tote, clearing chips, a gauge check | An occasional element | Time it separately and divide by its frequency |
| Waiting for material or a crane | A delay | Take it out of the element and count it toward the delay allowance if it is unavoidable |
| Nothing. The reading is just long | Normal variation in the job | Keep it |
| Half the readings are long and half are short | Two methods mixed together | Stop, settle the method, then time again |
Deleting readings because they look untidy is the fastest way to a standard nobody can meet. Real work varies, and the long cycles with no visible cause are part of what the job takes. If you want a statistical check, a reading more than about three standard deviations from the mean deserves a second look at your notes, but the notes decide, not the statistic. The standard time calculator points out the reading furthest from the average and shows the average without it, so you can see how much is at stake.
Units per hour, pieces per shift and labour cost per piece
A standard time in minutes is the same information as a rate in pieces per hour. People on the floor think in pieces, planners in hours, and cost accountants in money, so it helps to state all three.
One standard, read four ways
Example numbersStandard time
0.7728
minutes a piece
0.672 x 1.15
Per hour
77.6
pieces an hour
60 / 0.7728
Per shift
621
pieces in 480 min
480 / 0.7728 = 621.1
Labour cost
$0.309
a piece at $24 an hour
0.7728 / 60 x 24
The bracket job's standard time of 0.7728 minutes a piece gives 77.6 pieces an hour, 621 pieces in a 480 minute shift and a labour cost of 0.309 dollars a piece at 24 dollars an hour.
| You want | Formula | Bracket job |
|---|---|---|
| Standard minutes per unit | Normal time x (1 + allowance) | 0.7728 |
| Units per hour | 60 / standard minutes | 77.6 |
| Pieces per shift | Shift minutes / standard minutes | 480 / 0.7728 = 621 |
| Standard hours per 100 pieces | Standard minutes x 100 / 60 | 1.288 |
| Labour cost per piece | Standard minutes / 60 x hourly rate | $0.309 at $24 an hour |
| Performance against standard | Pieces made x standard minutes / minutes worked | 590 x 0.7728 / 480 = 95% |
- Do not take breaks off twice. If the allowance covers personal time and rest, use the paid shift. If your plant schedules breaks as stops and the allowance covers only fatigue and delay, use the minutes left after breaks.
- One operator at standard is not a line. A line runs at the pace of its slowest station and stops for breakdowns and changeovers that no personal allowance covers. Use takt time and the line balancing calculator for the line.
- Labour cost per piece is direct labour only. A full cost per unit adds benefits, overhead, material and scrap; the manufacturing cost per unit worksheet lays those out.
- A new operator or a new product will not hit standard on day one. Plan the ramp with a learning curve and keep the standard where it is.
The last row of the table is the one supervisors use. If the operator made 590 brackets in the shift, they earned 590 x 0.7728 = 456 standard minutes in 480 minutes worked, which is 95% of standard. Read that number together with what stopped the job that day. On its own it says nothing about why.
Labor standards: engineered, estimated and historical
A labor standard is the time a job is allowed, used to plan, cost and measure work. Standard time from a time study is one way to set it. Not every standard in a plant comes from a study, and it helps to know which kind you are looking at before you trust it.
| Kind | How it is set | Good for | Watch out for |
|---|---|---|---|
| Engineered | Measured with a recognised method: time study, a predetermined motion time system, standard data or work sampling, with the method written down | Repetitive work, costing, incentive pay, line balancing | Costs time to set and must be kept current |
| Estimated | A person who knows the work judges how long it should take | One-off jobs, maintenance, quotes that cannot wait | Depends on who estimates; no method on record to check against |
| Historical | Taken from past records: hours booked divided by pieces made | A first figure where no study exists | Bakes in every delay and bad habit of the past, and nobody knows what method it describes |
Operations textbooks such as Heizer and Render list the sources the same way: historical experience, time studies, predetermined time standards and work sampling. The US defence work measurement standard, MIL-STD-1567A, drew the line more sharply. Its Type I engineered standard had to be set with a recognised technique and reach an accuracy of plus or minus 10 percent at 90 percent confidence, and everything else was Type II. You do not need a military standard to borrow the idea: label each standard with how it was set.
How to set labor standards across a plant
- Start with the jobs that carry the most hours. A handful of part numbers usually account for most of the direct labour, and those deserve engineered standards first.
- Fix the method before you measure it. A standard for a wasteful method is an accurate measure of waste.
- Build standard data as you go. Once you have timed loading a fixture ten times across similar parts, you can set the next part's standard from a table in minutes.
- Use estimates where study would cost more than it saves, and mark them as estimates.
- Replace historical standards on a schedule. They are the least reliable figures in the system and they often sit under the most important quotes.
A note on the term. In US law, labor standards also means wage and hour rules such as the Fair Labor Standards Act. That is a different subject. This page is about time standards for work.
Keeping standards current
A standard describes one method. When the method changes, the standard is wrong, even if nobody touched the number. Most plants do not have a problem setting standards. They have a problem noticing when a standard has stopped being true.
| Change | Example | What to do |
|---|---|---|
| Method | A fixture replaces a hand clamp; two elements are combined | Re-time the elements that changed |
| Tooling or equipment | New feeds and speeds, a faster press, an automatic ejector | Recalculate machine elements, re-time the manual ones around them |
| Material or design | A casting replaces a weldment; a hole is added | Re-study the affected elements |
| Layout | The tote moves from behind the operator to arm's reach | Re-time the walking and reaching elements |
| Batch size or frequency | The gauge check goes from 1 in 5 to 1 in 20 | Change the frequency divisor; no new timing needed |
| Working conditions | A hoist is installed; the job moves to a cooled area | Review the fatigue allowance |
| Results that do not fit | An area beats its standards by a wide margin every week, or never reaches them | Audit the standard before you draw conclusions about the people |
Take the bracket job. Quality changes the inspection plan and the gauge check goes from 1 piece in 5 to 1 in 20. The check now costs each piece 0.25 / 20 = 0.0125 minutes in place of 0.050. Normal time falls to 0.6345 minutes and the standard to 0.6345 x 1.15 = 0.7297 minutes, which is 657 brackets a shift where the old standard said 621. No stopwatch was needed, only someone who knew the standard had a frequency in it.
Before and after: the gauge check goes from 1 piece in 5 to 1 in 20
Example numbersBefore
Gauge 1 piece in 5
Elements 1 to 3: 0.622 + gauge 0.0500 + allowance 0.1008
- Gauge per piece
- 0.25 / 5 = 0.0500
- Standard time
- 0.7728 min
- Pieces in the shift
- 621
After
Gauge 1 piece in 20
Elements 1 to 3: 0.622 + gauge 0.0125 + allowance 0.0952
- Gauge per piece
- 0.25 / 20 = 0.0125
- Standard time
- 0.7297 min
- Pieces in the shift
- 657
Two bars of the bracket job's standard time. Before, the gauge check on 1 piece in 5 adds 0.0500 minutes a piece and the standard is 0.7728 minutes, 621 pieces a shift. After, the check on 1 piece in 20 adds 0.0125 minutes a piece and the standard is 0.7297 minutes, 657 pieces a shift.
- Keep the method with the number. File the element breakdown, layout sketch, tools, feeds and speeds, rating, allowance and its basis, date and observer with every standard. Without them nobody can tell whether the job still matches.
- Tie standards to engineering change. A change request that alters method, tooling or material should not close until someone has answered the question: does the standard change?
- Audit on a schedule, most often for the standards that carry the most hours. Freivalds recommends setting the audit frequency by how many hours a year the standard is applied.
- Change standards in both directions. If standards only ever get tighter after an improvement, people stop telling you about improvements.
- Small method changes add up. Ten small improvements that each saved a second are a 10 second error in a standard that was right three years ago.
The people side of rating and standards
To the person being timed, a time study can look like a test with their pay or their job at the end of it. If they believe that, they will work slower than usual, or faster, or differently, and your readings will describe a performance, not the job. How you run the study decides whether the numbers are any good.
- Say why before you start. Tell the operator, the supervisor and, where there is one, the union representative what the study is for and what it will not be used for.
- Study openly. Never time someone from a distance or without telling them. Hidden studies end the trust that every later study depends on.
- Choose a qualified operator, not the fastest one. You want someone trained, experienced and working the standard method at an ordinary pace. A standard built on the best person in the plant will be missed by everyone else.
- Rate the pace, not the person. The rating says how this element was performed in this cycle compared with normal. It is not a mark of the operator's worth, and it should never be discussed as one.
- Show the sheet. Let the operator see the elements, the times, the ringed readings and the reasons. Ask what was unusual about the run; they will know things you could not see.
- Give people a way to question a standard. A request for a re-study that is answered with a second study, done by someone else, settles more disputes than any formula.
Where a collective agreement covers work measurement, it sets the rules for who may be studied, how standards are challenged and when they can change. Follow it, and involve the representatives from the start. This is general practice, not legal advice.
When a time-study standard is the wrong tool
- The job does not exist yet. You cannot time a line that has not been built. Use a predetermined motion time system or standard data from similar parts, and re-study once the job is running.
- The method is not settled. If operators do the job three ways, an average of the three describes none of them. Agree the method, train to it, then time it.
- The work is long and irregular, such as maintenance, material handling or set-up. Work sampling gives a better picture for less effort than a stopwatch.
- The cycle is machine-paced. When 90% of the cycle is the machine, the standard is the machine's rate, and the study's value is in the load, unload and waiting around it.
- The work is mostly thinking. Inspection decisions, troubleshooting and programming do not repeat in a way a rating can judge.
- You want to find waste, not set a rate. A standard tells you how long the current method takes. To shorten it, break the cycle into value-added and non-value-added time and change the method first.
Even when a study is the right tool, remember what it carries: an observer's judgement of pace, an allowance table somebody chose and a method that will change. State the standard with its date, its rating basis and its allowance basis, and it will stay useful for as long as it stays true.
Tools and templates for standard time
- Standard time calculator: observed times, rating and allowance in; normal time, standard time, units per hour, pieces per shift and labour cost out, under either allowance formula.
- Time study sample size calculator: how many cycles to time for the accuracy you want.
- Time study sheet: elements by 10 cycles, with rating, allowance and standard time columns. The Excel version does the sums.
- Process capacity sheet: what each machine can make in a shift once you know the times.
- Learning curve workbook: how long a new operator or a new product takes to reach standard.
- How many operators do you need: work content divided by takt, once the standard gives you the work content.
If the stopwatch is the slow part, LeanSuite's Time and Motion Study times every element from one phone video and reports cycle time, standard time, takt and units per hour, each linked to the video frame it came from. That also gives you something a stopwatch never does: a recording a second person can watch when a rating or a ringed reading is questioned.
Time and motion study software
Run a time study in LeanSuite
Time and motion study software that works from phone video: LeanSuite times every element, gives cycle and standard time, and draws a Yamazumi chart.
Go deeper
This page is the short version. These guides cover each part in full.
- The Three Elements of Standard Work: Takt Time, Work Sequence, Standard WIPWhere the element times from a study go next: takt time, the work sequence and standard in-process stock.
- Standard Work Tools: Combination Sheet, Standardized Work Chart, Job BreakdownThe documents that carry element times to the floor, and how to fill each one in.
- Yamazumi Chart: What It Is and How to Make One in 7 StepsStacking each operator's element times against takt to see who is overloaded and who has room.
- Standard Work in Manufacturing: A Complete GuideThe method the standard time describes, and how to write it down and keep it followed.
All our articles on this subject are in the standard work, sops and training topic.
Free templates and tools
- Time study sheetTime each element over 10 cycles and work out the average, lowest repeatable and standard time. Excel does the sums.
- Process capacity sheet templateEach machine in a part's routing with manual, auto and tool change time, its capacity per shift, and the step that limits the cell against demand.
- Cost per unit worksheet (manufacturing cost per good unit)One product's cost per good unit by materials, labor, machine and overhead, the gap to target, and which cost lever is worth most a year.
- Learning curve and ramp-up workbookBoth learning curve models side by side, a fit from your own observed hours, batch hours, the unit that reaches standard and a weekly ramp plan.
- Standard time calculatorObserved times, a rating and an allowance in; normal time, standard time, units per hour, pieces per shift and labour cost per unit out, with the working.
- Time study sample size calculatorHow many cycles of an element to time, from your first readings, with the t formula, the ILO formula and the range method.
- Line balancing calculatorLine efficiency, balance delay and the minimum number of stations from station times and takt.
- Takt time calculatorThe pace a line must hit to meet customer demand, from shift time, breaks and daily demand.
Doing this in LeanSuite
Time and Motion Study
Times every element from one phone video of the process and reports cycle time, standard time, takt and units per hour, each linked to its video frame.
See Time and Motion StudyLine Balancing
Drop in a video of your line and get a Yamazumi chart, a takt comparison and rebalancing recommendations.
See Line Balancing
See it on your own lines
Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.
FAQ
Questions about standard time
Average the observed times you kept, multiply by the performance rating to get normal time, then add the allowance. Normal time = observed time x rating / 100. Standard time = normal time x (1 + allowance). A job observed at 0.50 minutes, rated at 110 with a 15% allowance, has a standard time of 0.50 x 1.10 x 1.15 = 0.6325 minutes, which is 94.9 units an hour.
Normal time is the observed time adjusted for pace: observed time x rating / 100. An element timed at 0.12 minutes and rated at 110 has a normal time of 0.132 minutes. Standard time adds allowances for personal needs, fatigue and unavoidable delays to the sum of the normal times: a job with 0.672 minutes of normal time and a 15% allowance has a standard time of 0.672 x 1.15 = 0.7728 minutes.
Standard time = observed time x (rating / 100) x (1 + allowance), when the allowance is a percentage added to normal time. If your allowance is stated as a share of the whole shift, the last step is a division: standard time = normal time / (1 - allowance). For the same 15%, the second formula gives a standard 2.3% longer, so check which one your allowance table means.
Normal time is how long the work takes at normal pace with no breaks and no interruptions. Standard time is normal time plus allowances for personal needs, fatigue and unavoidable delays. Normal time tells you the work content. Standard time is the figure you can schedule a full shift on, because nobody works every second of the day.
With speed rating, the observer compares the operator's pace with normal pace and writes one number, where 100 is normal. With the Westinghouse system, the observer grades skill, effort, conditions and consistency and adds the table values to 1.00: good skill (+0.06), good effort (+0.02), average conditions (0) and good consistency (+0.01) give 1.09, a rating of 109. Normal time is the observed time multiplied by that factor.
Normal pace: a trained operator working steadily, without rushing and without holding back, at a pace they could keep up all day. American texts compare it with walking at 3 miles an hour. The British Standard scale used by the ILO puts 100 at a brisker incentive pace, about 4 miles an hour, so the same pace can be 100 on one scale and 75 on another.
Time added to normal time for things that are part of a working day but not part of the task: personal needs, recovery from fatigue and unavoidable delays. In the ILO example table, personal needs are 5% and basic fatigue 4% of normal time, with more for standing, awkward posture, force, heat or noise. A delay allowance has to be measured at the job.
The time a job is allowed, used to plan, cost and measure work. An engineered standard is measured with time study, predetermined times, standard data or work sampling. An estimated standard is a judgement by someone who knows the work, and a historical standard comes from past records. In US law the phrase also means wage and hour rules such as the Fair Labor Standards Act, which is a different subject.
Whenever the method, tooling, material, layout or working conditions change, and on a regular audit in between. A standard describes one method, so it stops being true the day the method changes. Audit the standards that carry the most labour hours most often, and review any area that beats its standards by a wide margin every week or never reaches them.
Divide 60 by the standard time in minutes. A standard of 0.7728 minutes a piece is 60 / 0.7728 = 77.6 pieces an hour. Pieces per shift is the shift minutes divided by the standard, so 480 / 0.7728 = 621. If the allowance already covers breaks, use the paid shift and do not take the breaks off again.
Related guides and tools
- Standard time calculator: readings, rating and allowance in, standard time and units per hour out
- Time study sample size calculator: how many cycles to time
- Time study sheet: the observation form with rating and allowance columns
- Takt time: the pace demand sets, to compare a standard with
- How many operators do you need: work content divided by takt
- Standard work: writing down the method a standard time describes
More method guides
- The 6 Ms of production
- Poka-yoke
- Model area 90-day plans
- Moving from Excel to one system
- Reducing machine downtime: a worked month
- Andon
- Cycle time vs lead time, worked through
- Root cause analysis
- How many operators a line needs
- Reducing scrap and rework: a worked month
- Unsafe acts and unsafe conditions
- Just culture
- Stop-work authority
- Material review board (MRB)
- Nonconformance and NCRs
- Problem solving methods
- Quad chart
- OEE calculation
- Quality assurance vs quality control
- SOP meaning and format
- Job hazard analysis
- Near miss reporting
- Fishbone diagram
- Pareto chart
- Histogram
- Control chart
- What is a gemba walk
- What is lead time
- What is operational excellence
- How to improve product quality
- Preventive vs predictive maintenance
- Kanban
- FMEA
- PDSA cycle
- Safety moments
- Just-in-time manufacturing
- Kaizen
- 5S
- Total quality management (TQM)
- CAPA (corrective and preventive action)
- Layered process audit (LPA)
- Lean tools
- Lockout tagout (LOTO)
- A3 problem solving
- Preventive maintenance
- APQP
- High reliability organization (HRO)
- Manufacturing KPIs
- Quality metrics
- Practical problem solving
- CMMS
- Risk assessment
- Production efficiency
- Total productive maintenance (TPM)
- Reliability-centered maintenance (RCM)
- Hierarchy of controls
- Personal protective equipment (PPE)
- Emergency action plan
- Safety signs
- Warehouse safety
- ISO 9001
- SIPOC diagram
- Rolling action item list (RAIL)
- Pugh matrix
- Flowchart
- Project charter
- ISO 9001:2026
- Fleet maintenance
- IATF 16949
- AS9100
- ISO 14001
- ISO 45001
- One point lesson
- Standard work
- Meeting cadence
- OSHA penalties and the top 10 cited standards
- OSHA 300A summary
- SMART goals examples for manufacturing
- Year-end review for manufacturing plants
- 2027 goals for a manufacturing plant
- Lean manufacturing principles
- Toyota Production System
- 5W1H
- 5 Whys
- Continuous improvement
- Takt time
- DMAIC
- PDCA
- 8D problem solving
- Prioritization matrix
- Gemba walk questions
- 5W1H questions
- Layered process audit questions
- 5S audit questions
- Difficult conversations at work
- How to talk to an employee about poor performance
- How to resolve conflict between employees
- High performer, bad attitude
- How to get employees to follow procedures
- Resistance to change on the shop floor
- Influence without authority for CI, quality and safety people
- Quality vs production: the hold against the ship date
- Hard savings vs soft savings
- How to handle a customer quality complaint call
- 30 60 90 day plan for a manufacturing manager
- First 90 days in a new manufacturing role
- New supervisor training: the first 90 days
- Night shift supervisor
- Engineer to manager in manufacturing
- What to do after a serious workplace accident
- Disagree and commit: disagreeing with your boss in a plant
- How to deliver bad news to your boss
- How to present audit findings to management
- How to get leadership buy-in for continuous improvement
- How to ask for more headcount or resources
- How to ask for a promotion in manufacturing
- PPE compliance
- Language barriers on the shop floor
- Train the trainer in manufacturing
- Contractor safety management
- Return to work after an injury
- Attendance conversation with an employee
- Managing former peers after a promotion
- Managing older or more experienced employees
- Inheriting a team
- How to delegate as a supervisor
- Holding supervisors accountable
- How to tell employees about layoffs or a shift change
- How to deny a raise request or a promotion
- Time and motion study
- How to conduct a time study
- Work sampling
- SMED
- Line balancing
- Yamazumi chart
- Ergonomic assessment in manufacturing
- Spaghetti diagram
- Time study vs motion study vs method study
- Why do a time study
- How to plan a time study
- How to break a job into elements
- How many cycles to time
- Stopwatch time study
- Time study mistakes
- Time study vs work sampling
- Value added vs non value added
- Labor losses in manufacturing
- New product time study playbook
- How to estimate cycle time for a new product
- New product introduction for industrial engineers
- Process planning for a new product
- Planning operators and stations for a new line
- Pilot run and line trial
- Ramp-up plan and the learning curve
- Workstation design
- Designing a future workstation
- Time study and ergonomic study in one pass
- Predetermined motion time systems (PMTS)
- MTM (Methods-Time Measurement)
- MOST and MODAPTS
- Therbligs and motion economy
- RULA assessment
- REBA assessment
- RULA vs REBA
- NIOSH lifting equation
- Production capacity calculation
- Precedence diagram
- Labor efficiency and labor variance
- Labor cost and quoting with time standards
- SMV and SAM in garment manufacturing
- From time study to standard work
- Standard work combination table
- Standard work vs SOP vs work instruction
- Standard WIP
- Updating standard work after an improvement
- Time study from video
- Time study app or software
- Man-machine chart
- Timing long-cycle and team work
- Time study in a union plant
- History of time and motion study
- Golden zone (power zone)
- Workstation assessment
- Reach envelope and work area study
- Standing, seated and sit-stand workstations
- Line-side material presentation
- Time study in automotive assembly
- Time study in electronics assembly
- Time study in CNC machining
- Time study in metal fabrication and welding
- Time study in plastics injection molding
- Time study in warehouse operations
- Time study in garment manufacturing
- Time study in maintenance work
- Time study in aerospace assembly and MRO
- Time study in food and beverage manufacturing
- Time study examples
- Historical and machine data as time standards
- Line balancing examples
- How to measure cycle time
- Manpower planning from standard time
- Bottleneck analysis from a time study
- Standard work examples
- U-cells and one-piece flow
- Flow process chart and operation process chart
- Two-handed process chart
- 3P production preparation process
- Plant layout basics
- Design for assembly
- Time study, PFMEA, control plan and work instructions
- Explaining a time study to a worried operator
- The observer effect in time studies
- Time standards and incentive pay
- Seven wastes vs eight wastes
- Job safety analysis (JSA)
- JSRA (job safety risk assessment)
- JSA vs JHA vs JSRA
- Job safety analysis from video
- HIRA (hazard identification and risk assessment)
- Management of change (MOC)
- Safe work method statement (SWMS)
- Permit to work (PTW)
- Pre-task plan (PTP)
- Field level risk assessment (FLRA)
- Safety observation
- Safety walk
Or browse the topics, the full library and the lean glossary.