ISO 45001 internal audit checklist
An ISO 45001 internal audit checklist is the set of questions an internal auditor uses to check that a site's occupational health and safety management system works as planned and meets ISO 45001. Clause 9.2 of the standard asks for internal audits at planned intervals; this checklist is for the part most audits do worst, the plant floor. It has 44 original questions in 16 topics, from task-level risk assessment, the hierarchy of controls, lockout and machine guarding to contractors, chemicals, change and legal requirements. Each question names the clause it tests (ISO 45001:2018 numbering), the evidence to look for and the sample to take, and 12 open interview prompts cover the people who do the work, which is where record-based audits fall short. The PDF has the audit plan, the checklist, an interview record, a finding report, a findings log, how to run the audit and a worked example. The Excel version grades each answer, works out conformance by topic and by clause, flags findings missing from the log and overdue actions, and checks that the interviews reached at least 5 people on more than one shift.
Free to use: print it, copy it and edit it for your team. Enter your name and work email once to download.
The audit plan with an independence check, the sample to take for each of 16 safety topics and the five grades.When to use it
When to use an ISO 45001 internal audit checklist
- Running the site's ISO 45001 internal audit programme: one area or department per audit, on the schedule the programme sets.
- Before a certification or surveillance audit, to find the gaps on the floor before the certification body does.
- After a serious injury, a run of near misses or a big change (a new line, a new chemical, a new contractor), as an audit of that area.
- When a customer asks for evidence that your safety management system is checked from the inside.
How to fill it in
- 1
Plan the audit from risk
Pick the area from the audit programme: the highest risks, recent injuries and near misses, changes, and what the last audit found. Fill in the audit plan, choose auditors who do not work in or manage the area, send the plan a few days ahead and book a visit to the night or weekend shift.
- 2
Start with the people who do the work
Talk to at least 5 people who are not managers or supervisors, on more than one shift, away from their supervisor. Use the 12 prompts, write roles and shifts, not names, and note which checklist question each answer feeds.
- 3
Watch the tasks, then check the records
Take the sample shown for each topic: watch the task, ask the operator, then follow it to the risk assessment, the permit, the training record. Write what you saw for every question, conforming ones too.
- 4
Grade each question
Conforming, opportunity, minor, major or N/A. The definitions are this template's choice; your audit programme decides them. Conformance = (conforming + opportunity) ÷ questions graded, with N/A left out.
- 5
Make it safe, then write the finding
Anyone at immediate risk: stop the work before you move on. Then write each finding in four parts: the condition, the requirement it fails, the evidence and the impact.
- 6
Follow up until each finding is checked
The area owner fixes it now, finds the cause and puts in a corrective action, using the strongest control that is practical. Close a finding only after someone has checked that it worked, and report the results to managers and to the workers concerned (9.2.2).
Worker interviews
12 open questions to ask the people who do the work
Clause 5.4 of ISO 45001:2018 asks for the consultation and participation of non-managerial workers, and a checklist answered from records cannot test it. Ask at least 5 people on more than one shift, away from their supervisor, and write roles, not names. Then check what they tell you on the floor and in the records.
| # | Ask | What you are listening for | Clause |
|---|---|---|---|
| 1 | Walk me through your job from the start of the shift. Which part of it could hurt you? | Hazards and non-routine steps that are not on the risk assessment. | 6.1.2.1 |
| 2 | What do you do when the machine jams or a part sticks? Can you show me? | Reaching past a guard, whether they lock out, inch mode, the tools they use. | 8.1 |
| 3 | Tell me about the last time you raised a safety concern. What happened next? | How they raised it, whether anyone came back to them, how long it took. | 5.4 |
| 4 | What has changed in your work in the last few months: machine, material, layout, hours, crew? | Changes that are missing from the change log. | 8.1.3 |
| 5 | Which job here do people least like doing, and why? | Lifting, reaching, repetition, heat or noise, and the workarounds people use. | 6.1.2.1 |
| 6 | If you thought a job could seriously hurt you, what would you do? What would happen to you? | Whether they know they can stop, and whether they fear what happens next. | 7.3 |
| 7 | Who decided what PPE you wear here? Does any of it get in the way of the work? | Whether they were asked, how it fits, items taken off because they slow the job down. | 8.1.2 |
| 8 | What did you hear about the last injury or near miss in this area? | Whether the findings and the changes reached them. | 10.2 |
| 9 | How did you learn to do this job safely? Who showed you, and how did they check? | Whether it agrees with the training record and the sign-off. | 7.2 |
| 10 | When contractors work near you, how do you find out what they are doing and what to keep clear of? | Whether the host tells the area, and contractors seen working with nobody from the site. | 8.1.4.2 |
| 11 | Is there anything that would make someone here think twice before reporting a small injury? | Bonuses, prizes or boards tied to injury-free days, blame, paperwork, waiting time. | 5.4 |
| 12 | If you could change one thing to make this job safer, what would it be? Have you told anyone? | Ideas nobody asked for, and ideas raised and then lost. | 5.4 |
1
- Ask
- Walk me through your job from the start of the shift. Which part of it could hurt you?
- What you are listening for
- Hazards and non-routine steps that are not on the risk assessment.
- Clause
- 6.1.2.1
2
- Ask
- What do you do when the machine jams or a part sticks? Can you show me?
- What you are listening for
- Reaching past a guard, whether they lock out, inch mode, the tools they use.
- Clause
- 8.1
3
- Ask
- Tell me about the last time you raised a safety concern. What happened next?
- What you are listening for
- How they raised it, whether anyone came back to them, how long it took.
- Clause
- 5.4
4
- Ask
- What has changed in your work in the last few months: machine, material, layout, hours, crew?
- What you are listening for
- Changes that are missing from the change log.
- Clause
- 8.1.3
5
- Ask
- Which job here do people least like doing, and why?
- What you are listening for
- Lifting, reaching, repetition, heat or noise, and the workarounds people use.
- Clause
- 6.1.2.1
6
- Ask
- If you thought a job could seriously hurt you, what would you do? What would happen to you?
- What you are listening for
- Whether they know they can stop, and whether they fear what happens next.
- Clause
- 7.3
7
- Ask
- Who decided what PPE you wear here? Does any of it get in the way of the work?
- What you are listening for
- Whether they were asked, how it fits, items taken off because they slow the job down.
- Clause
- 8.1.2
8
- Ask
- What did you hear about the last injury or near miss in this area?
- What you are listening for
- Whether the findings and the changes reached them.
- Clause
- 10.2
9
- Ask
- How did you learn to do this job safely? Who showed you, and how did they check?
- What you are listening for
- Whether it agrees with the training record and the sign-off.
- Clause
- 7.2
10
- Ask
- When contractors work near you, how do you find out what they are doing and what to keep clear of?
- What you are listening for
- Whether the host tells the area, and contractors seen working with nobody from the site.
- Clause
- 8.1.4.2
11
- Ask
- Is there anything that would make someone here think twice before reporting a small injury?
- What you are listening for
- Bonuses, prizes or boards tied to injury-free days, blame, paperwork, waiting time.
- Clause
- 5.4
12
- Ask
- If you could change one thing to make this job safer, what would it be? Have you told anyone?
- What you are listening for
- Ideas nobody asked for, and ideas raised and then lost.
- Clause
- 5.4
What's on the checklist
The 44 audit questions, by plant-floor topic
Sixteen topics, each with the sample to take: watch the work, talk to the people who do it, then check the records. Every question names the ISO 45001:2018 clause it tests and what to look for; the OSHA references apply to US plants only. On the sheet each question has space for the evidence you saw, a grade and a finding number.
Hazard identification and risk assessment
Sample: 3 tasks running today, at least one of them non-routine (clearing a jam, a die change, cleaning, a repair), and the newest risk assessment in the area.
- 1Watch a task being done, then read its risk assessment: does the assessment describe the job as it is really done, including setting up, clearing and cleaning? Look for: steps and hazards you saw that the assessment leaves out. (6.1.2.1 Hazard identification)
- 2Are non-routine jobs assessed, or only normal running? Ask an operator what they do when the machine jams, then find that job in the assessments. Look for: assessments for clearing jams, changeovers, cleaning and breakdown repairs. (6.1.2.1 Hazard identification)
- 3Did the people who do the task take part in its assessment, and was the assessment reviewed after the last incident, change or new information on that task? Look for: who took part, the review date, the last incident on the task and what changed in the assessment after it. (6.1.2.2 Assessment of OH&S risks and other risks to the OH&S management system)
- 4Is the site's rating method used the same way on every task, and does each rating count only the controls that are really in place? Look for: the method and its criteria, two ratings compared side by side, any rating that relies on a control you found missing. (6.1.2.2 Assessment of OH&S risks and other risks to the OH&S management system)
Hierarchy of controls
Sample: the 3 highest-rated risks in the area and every control listed for them, each control seen in place.
- 5For the highest risks, were removing the hazard, substituting it and engineering controls considered before procedures and PPE, with a reason written down where a stronger control was not used? Look for: the options considered, the control chosen and the reason for it. (8.1.2 Eliminating hazards and reducing OH&S risks)
- 6Is each control on the assessment in place and working at the station? Ask the operator whether it ever gets bypassed, and when. Look for: the guard fitted, the interlock working, the extraction running, the barrier in place, signs of a workaround. (8.1.2 Eliminating hazards and reducing OH&S risks)
- 7When an action was taken on a risk, did someone check afterwards that it worked and rate the risk again? Look for: one completed action, the check made after it (a measurement or an observation), the new rating. (6.1.4 Planning action)
Lockout/tagout and energy control
Sample: 2 machines with written energy control procedures, 1 lockout done this week (or one done for you), and the last periodic inspection of each procedure.
- 8Does each machine in the sample have its own energy control procedure that lists every energy source, stored energy included (springs, air, hydraulics, gravity, capacitors)? Look for: the procedure checked against the machine itself and its labelled isolation points. US plants: OSHA 29 CFR 1910.147(c)(4). (8.1 Operational planning and control)
- 9Walk through a recent lockout with the person who did it: was every source isolated and locked with their own lock, and was zero energy checked before work started? Look for: personal locks and tags, the try or test step, a group lockout box where a crew worked. (8.1 Operational planning and control)
- 10Has each procedure in the sample been inspected in the last 12 months by an authorized person who does not use it, including a talk with the people who do? Look for: the inspection record, who inspected, who was reviewed. US plants: OSHA 29 CFR 1910.147(c)(6) sets at least once a year. (9.1 Monitoring, measurement, analysis and performance evaluation)
Machine guarding
Sample: 4 machines, including the oldest, one changed in the last year and one where operators clear jams.
- 11On each machine in the sample, are the point of operation, nip points, rotating parts and flying chips or sparks guarded, with guards fixed in place or interlocked? Look for: each machine walked round while it runs; missing, open or modified guards. US plants: OSHA 29 CFR 1910.212(a). (8.1.2 Eliminating hazards and reducing OH&S risks)
- 12Are interlocks, light curtains and emergency stops tested at a set frequency, and does a test you watch agree with the record? Look for: the test record, one test watched with maintenance. (9.1 Monitoring, measurement, analysis and performance evaluation)
- 13Ask the operator to show you how they clear a jam or make an adjustment: can it be done without reaching past a guard while the machine can move? Look for: the method against the procedure, the tools provided, tape, ties or magnets on interlocks. (8.1 Operational planning and control)
Emergency preparedness
Sample: the area's emergency plan, the last drill, 3 workers from different shifts and 5 pieces of emergency equipment.
- 14Ask 3 workers what they would do if the alarm sounded now, or if someone near them was hurt: where they go, who they call, who gives first aid. Look for: answers that agree with the plan; first aiders named for every shift. (8.2 Emergency preparedness and response)
- 15Was the response tested by a drill at the interval the site set, on more than one shift, and was something changed after the drill was reviewed? Look for: the drill record, the time to clear and account for everyone, the review and what changed. (8.2 Emergency preparedness and response)
- 16Is emergency equipment in place, unblocked and checked: extinguishers, eyewash stations and showers, spill kits, exits? Look for: 5 items against their check tags. US plants: OSHA 29 CFR 1910.157(e) asks for a monthly visual check and annual maintenance of portable extinguishers. (8.2 Emergency preparedness and response)
Contractor control
Sample: every contractor on site on the audit day, and 2 contractor jobs from the last month.
- 17Were the contractors on site today selected using safety criteria, and told the site rules and the hazards of the area before they started? Look for: the approval record, a sign-in or induction for each person, the hazards they were told about. (8.1.4.2 Contractors)
- 18For high-risk contractor work (at height, hot work, confined space, energy isolation), is there a permit or an agreed plan, and does the work you see match it? Look for: the permit at the job; for lockout, each employer knows the other's procedure (US plants: OSHA 29 CFR 1910.147(f)(2)). (8.1.4.2 Contractors)
- 19Does someone from the site check contractor work while it is going on, and do contractor injuries and near misses go into the site's reports? Look for: a check record or a named host, contractor entries in the incident log. (8.1.4.2 Contractors)
Incident reporting and investigation
Sample: the last 3 incidents or near misses in the area, at least one of them an injury, and 2 workers asked how they report.
- 20Ask 2 workers how they would report an injury, a near miss or a hazard, and what happened the last time they did. Look for: they know the route, their report is in the system, they heard back. US plants: OSHA 29 CFR 1904.35 requires a reporting procedure that does not discourage reporting. (10.2 Incident, nonconformity and corrective action)
- 21Were the 3 investigations started promptly, with the workers involved, and do they find causes in the work and the system instead of stopping at operator error? Look for: dates, who took part, the cause statements, actions that change conditions. (10.2 Incident, nonconformity and corrective action)
- 22Were serious incidents reported to the authority within the legal time limits? Look for: the incident log against the reports made. US plants: OSHA 29 CFR 1904.39 sets 8 hours for a death and 24 hours for an in-patient hospitalization, an amputation or the loss of an eye. (6.1.3 Determination of legal requirements and other requirements)
Worker participation and consultation
Sample: at least 5 workers who are not managers or supervisors, from more than one shift, talked to away from their supervisor. Use the worker interview prompts.
- 23Can workers give a real example of having a say in a risk assessment, a control or the last change in their area? Look for: examples from at least 3 of the 5 people, worker names on assessments, safety committee minutes with worker members. (5.4 Consultation and participation of workers)
- 24What stops people raising a concern or reporting a small injury: no time, language, fear of blame, nothing coming back, a bonus or prize tied to injury-free days? Look for: what workers say, the rules of any incentive scheme, meetings held in paid time, material in the languages people read. (5.4 Consultation and participation of workers)
- 25Do workers know they can remove themselves from work they believe puts them in imminent, serious danger, and that they are protected when they do? Look for: workers' own answers, where the rule is written down and trained. (7.3 Awareness)
- 26Did the results of the last audit and the last investigations reach the workers they concern? Look for: a briefing record or the area board; ask workers whether they heard and what changed. (9.2.2 Internal audit programme)
Competence and training
Sample: 5 workers, including the newest person in the area and someone recently moved to a new task, and their training records.
- 27Is the safety competence each job needs written down, including spotting hazards, and do the 5 people meet it? Look for: the training matrix or job requirements, the 5 records, gaps and how they are covered until closed. (7.2 Competence)
- 28Ask the newest person to show you a safety-critical step of their job: does it match the procedure and the training they signed for? Look for: what you watch against the procedure, the trainer's sign-off. (7.2 Competence)
- 29Is training checked for effect, not only attendance, and are refreshers in date (forklift, first aid, lockout)? Look for: a test or an observed sign-off, expiry dates against today. US plants: OSHA 29 CFR 1910.178(l)(4)(iii) asks for a forklift operator evaluation at least every 3 years. (7.2 Competence)
Personal protective equipment
Sample: 6 workers at 3 tasks and the PPE assessment for those tasks.
- 30Is the PPE for each task set by a written hazard assessment, and is it what the people at the task wear? Look for: the assessment against what you see on 6 workers. US plants: OSHA 29 CFR 1910.132(d) asks for a written, certified hazard assessment. (8.1.2 Eliminating hazards and reducing OH&S risks)
- 31Ask workers whether their PPE fits, how they get a worn item replaced on their shift, and when they were shown how to use it. Look for: fit and condition, a replacement route that works on nights and weekends, training records (OSHA 29 CFR 1910.132(f) in US plants). (8.1.2 Eliminating hazards and reducing OH&S risks)
Ergonomics
Sample: 2 tasks with lifting, repetition or awkward posture: the one workers name as the hardest and one with reports of discomfort.
- 32Have lifting, repetition and posture been assessed for the tasks workers say are hardest, with a stated method (for example the NIOSH lifting equation or an observation checklist)? Look for: the assessment and its method, the worker's own account of the task. (6.1.2.1 Hazard identification)
- 33Where a task was assessed as high risk, was the work itself changed (height, reach, weight, lift assist, rotation), not only lifting training given? Look for: the change in place; ask the operator whether it helped. (8.1 Operational planning and control)
Chemical management
Sample: 5 chemicals used in the area, including the newest one bought.
- 34Is every chemical in the area on the inventory, with a current safety data sheet that workers can reach on every shift? Look for: 5 containers against the list; ask a worker to find one sheet. US plants: OSHA 29 CFR 1910.1200(e) and (g)(8). (6.1.2.1 Hazard identification)
- 35Are containers labelled (secondary containers too), stored away from incompatible chemicals, and used with the controls the safety data sheet calls for? Look for: labels, storage, extraction running, the gloves and eye protection in use. (8.1.2 Eliminating hazards and reducing OH&S risks)
- 36Before the newest chemical was bought, did someone check its hazards and set the controls? Look for: the purchase approval, who signed it, the safety data sheet reviewed before first use. (8.1.4 Procurement)
Management of change
Sample: the last 3 changes in the area (equipment, layout, chemical, staffing, shift pattern or procedure), temporary ones too.
- 37Was each change reviewed for safety before it was made, with the people affected, and were the risk assessment, procedures and training updated? Look for: the change record, a risk review dated before the change, the updated documents. (8.1.3 Management of change)
- 38Are there changes nobody reviewed? Ask workers what has changed in the last 3 months and compare their answers with the change log. Look for: a moved machine, a new supplier's material, overtime or crew changes missing from the log. (8.1.3 Management of change)
Monitoring and measurement
Sample: the area's safety measures for the last 3 months and 3 measuring devices (gas detector, sound level meter, air sampling pump, load tester).
- 39Does the area track leading measures (inspections done, actions closed on time, near misses reported) as well as injuries, and act when one moves the wrong way? Look for: the board or report, the last time a measure slipped and what was done. (9.1 Monitoring, measurement, analysis and performance evaluation)
- 40Is equipment used to measure exposure or to test safety devices calibrated or bump-tested as required? Look for: records for 3 devices, with dates against today. (9.1 Monitoring, measurement, analysis and performance evaluation)
Legal requirements
Sample: the register of legal and other requirements for the area, the last compliance evaluation, and 3 requirements traced to the floor.
- 41Does the site know which legal and other requirements apply to this area (machinery, chemicals, noise, lifting gear, permits, customer rules), and is the list kept up to date? Look for: the register, its last update, one new or changed rule on it. (6.1.3 Determination of legal requirements and other requirements)
- 42Has compliance been evaluated at the set frequency, with the gaps closed? Pick 3 requirements and check them on the floor yourself. Look for: the evaluation record; 3 items traced, for example a lifting gear inspection, a noise survey, an extinguisher check. (9.1.2 Evaluation of compliance)
Nonconformity and corrective action
Sample: 3 corrective actions from the area in the last 6 months, including one from the last internal audit.
- 43Do corrective actions use the hierarchy of controls and go through the change process, with the new risk checked before the action was put in? Look for: the type of control chosen in each of the 3, a change review where the action changed equipment or method. (10.2 Incident, nonconformity and corrective action)
- 44Were the actions checked for effect before they were closed, and are the last audit's findings closed and not seen again today? Look for: the effectiveness check, the last audit's findings against what you see now. (10.2 Incident, nonconformity and corrective action)
A filled-in example
Illustrative, not a benchmarkAn example: an internal safety audit of a press shop (presses 1 to 8, the die shop and the coil store) on day and night shift, by two trained auditors from other departments (illustrative, the same as the Excel worked example).
- 44 questions, 2 N/A: no incident in 12 months that had to be reported to the authority, and no high-risk manual task left after a coil upender was fitted.
- 42 graded: 35 conforming, 2 opportunities, 4 minor, 1 major.
- The major: two roofing contractors working at height above press 6 with no permit and no fall protection plan (8.1.4.2). The work was stopped and restarted only with a permit and checked harnesses.
- 6 worker interviews on two shifts turned up 2 of the 4 minors: night shift wearing torn cut-resistant gloves because stores only open on days, and small cuts going unreported because the crew loses its bonus with a recordable injury.
- The other 2 minors: a lockout procedure 14 months after its last annual inspection, and a parts washer cleaner swapped for a solvent with no change review.
Conformance = (35 + 2) ÷ 42 = 88.1%. Three weeks later 1 of the 7 findings is closed and verified, 1 is overdue (the gloves), and the major stays open until the next 3 contractor jobs at height have been checked.
Common mistakes
Auditing from the office
A risk assessment on file says nothing about a task you have not watched. Start at the station and work back to the paperwork, not the other way round.
Talking only to supervisors
Clause 5.4 is about the people who do the work. Supervisors tell you how the system is meant to run; operators tell you how it runs at 3 am.
Day shift only
PPE, permits, lockout and contractor control drift most when managers are not there. Plan at least part of every audit on nights or weekends.
Accepting PPE as the answer
ISO 45001 puts PPE last in the hierarchy of controls (8.1.2). Ask what stronger control was considered and why it was not used, and look for the reason in writing.
Treating the certificate as legal compliance
ISO 45001 certification is not OSHA compliance. The audit checks that the site knows and evaluates its legal requirements (6.1.3, 9.1.2); it does not replace an OSHA inspection or a legal review.
Download the template
Free to use: print it, copy it and edit it for your team. Enter your name and work email once to download.
Run this template in LeanSuite
In LeanSuite you run safety inspections, Gemba walks and LOTO checks from ready-made templates, a failed item raises a safety tag automatically, and every corrective action has an owner and a due date, with delays flagged.
See it in a 45-minute demoIn the lean glossary
Free tools
FAQ
ISO 45001 internal audit checklist: common questions
More free templates
All templates- 5S audit checklist template25 checks, five per S, scored 1 to 5, with a score summary and a chart of the five S's.
- Gemba walk checklistA walk plan and route, 30 prompts in six groups and a findings table with owners and due dates.
- Layered process audit (LPA) checklist20 yes, no or N/A checks at the station, a fixed-on-the-spot box, scores by group and a findings table.
- 5S red tag log and red tagsA log of every red-tagged item with its decision, and six printable red tags to cut out.
- Near miss report formA two-page near miss report from the first report to closure, and an Excel log with status and days open.
- Safety observation card templateFour behavior-based safety cards per sheet, with safe and at-risk checks, the conversation and a tally sheet.
- Job safety analysis (JSA) templateJob steps, hazards, risk scored before and after the controls, the hierarchy of controls, PPE and sign-off.
- Risk assessment matrix template (5×5)A color-coded 5 × 5 severity and likelihood matrix, a scoring guide and a risk register.
- Incident investigation report templateFacts and a sourced timeline, causes at three levels, actions by the hierarchy of controls, a US recordkeeping screen and a closure check.
- Toolbox talk templateA record of a short safety talk: topic, key points, questions raised, actions and an attendee sign-in sheet.
- Lockout/tagout (LOTO) procedure templateA machine-specific LOTO procedure: energy sources and isolation points, the steps from shutdown to restart, and the annual review.
- Forklift inspection checklist23 pre-shift checks for a week on one page, a do-not-operate rule, and a defect and repair log.
- Office 5S audit checklist25 checks written for offices and shared areas, five per S, scored 1 to 5, with a score summary and actions.
- Floor marking color guideA floor marking color standard with swatches, marks and line widths to fill in, and a floor marking check with a layout sketch.
- Shadow board plannerTool inventory with fetch time, a layout planned from each tool's outline size, a month of daily checks with 5S audit evidence, and a missing tool log.
- Warehouse safety inspection checklistThirty warehouse safety checks from aisles to fire exits, marked OK or Not OK, with an action for every finding.
- Pallet racking inspection checklistRack checks per aisle with a green, amber and red damage rating, and a damage log with repair dates.
- Safety audit checklistThirty-four plant-wide safety checks answered Yes, No or N/A, scored by area, with a risk rating and an action for every No.
- Ergonomic risk assessment checklistScreen a task for 21 ergonomic risk factors, score how long each lasts, and rank tasks so the worst get controls first.
- Standard work audit checklist24 checks of a job against its written standard, ten timed cycles, and each gap sorted by cause before anyone acts.
- Waste walk checklist (TIMWOODS)32 things to look for across the eight wastes, with where and how much, and a findings log with dot votes, owners and dates.
- Lean readiness assessment templateTwenty statements in four factors, scored 1 to 5 by several people on their own, with averages, the spread between them and the actions.
- Visual management audit checklist29 checks of whether anyone can tell normal from abnormal at a glance, scored by group, with a trend and actions.
- TQM self-assessment templateThe eight TQM principles in 24 statements you can check on the floor, scored 0 to 4 by several people, with the spread, the top 3 gaps and an action plan.
- Safety cross calendarA month drawn as the green cross, colored each day by the most serious safety event, with totals and days since the last injury.
- Safety pillar 90-day model area planThirteen weeks from the incident pyramid to safety standards on one model area, a KPI board, the day-90 gate and expansion waves.
- Training matrix template with expiry datesPeople by required trainings with expiry dates, OK, due, expired and missing flags, compliance by person and area, cover per training and a renewal list.
- HACCP plan template: hazard analysis and CCP worksheetThe Codex 12 steps in one workbook: team and product, process steps checked on site, hazard analysis with the CCP decision tree, the CCP table with completeness checks, an allergen matrix and a verification schedule.
- Forklift operator training and evaluation recordPer-operator training and evaluation record, a register with three-year due dates and refresher triggers, and a weighted practical evaluation scoresheet.
- REBA worksheet (Rapid Entire Body Assessment)Score up to six postures with REBA: body-part drop-downs, Tables A, B and C as lookups, final score and action level, and a before and after comparison.
- ISO 9001 internal audit checklist (production area)46 audit questions for the production floor in 11 processes, each with its ISO 9001:2015 clause, what evidence to look for and the sample to take, plus five defined grades, a findings log, a finding report and a summary by clause.
- Food plant GMP inspection checklist (21 CFR 117 subpart B)55 checks in the order of 21 CFR 117 subpart B, each citing its paragraph and saying what to look at, with a grade, finding, owner and due date; results by section and grade, a walk route and a bakery example.
- Master sanitation schedule with pre-op verificationA master list of cleaning tasks by area and equipment with frequency, chemical, lockout, who and next due date, a weekly on-time count, and the pre-operational verification log with a release step.
- Overhead crane inspection checklist: frequent and periodic34 crane checks tied to OSHA 1910.179: an operator's pre-shift card, frequent and periodic inspections with signed records, a deficiency and tag-out log, and a register of next due dates.
- 1-1-90 method worksheetOne page: score areas 1 to 5, write the pain point with a before and target number, check days 30, 60 and 90, and plan the next three areas.
- Leader standard work templateA team leader's daily, weekly and monthly routine with a box per day, follow-ups and a weekly review.
- Supervisor leader standard work templateA supervisor's daily, weekly and monthly routine with a box per day, an escalation log and a weekly review.
- Production manager leader standard work templateA production or value stream manager's routine by day, week and month, with an escalation log and a weekly review.
- Plant manager leader standard work templateA plant manager's short routine by day, week and month, with an escalation log and a weekly review.
- Autonomous maintenance (CILR) checklist20 clean, inspect, lubricate and retighten checks with a box per day, an abnormality log and sign-off.
- A3 problem solving templateThe standard seven-box A3 from background to follow-up, with a filled-in worked example. PDF and Excel.
- PDCA templateOne improvement cycle on one page: plan, do, check against the goal, then standardize or adjust. PDF and Excel.
- 5 Whys templateA problem statement, a why chain that can branch, evidence for every answer, root causes and countermeasures that are checked.
- 5W1H templateWho, what, when, where, why and how: a problem statement built from checked facts, and an action plan with nothing left open.
- 8D report templateD0 to D8 with targets, containment counts, occurrence, escape and systemic causes, verified actions and a worked example.
- Poka-yoke worksheetEach step's errors and what they cost, the device (approach, function, method), payback, and a log that proves each device works.
- Skills matrix templatePeople by tasks on a 0 to 4 scale, coverage and gaps per task and shift, and a training plan that closes them.
- Standard work sheet templateTakt time, each element's manual, machine and walk time on a time chart, key points and standard WIP.
- One point lesson (OPL) templateOne topic on one page: wrong way and right way pictures, checkable key points, the standard it belongs to and a sign-off record.
- SMED changeover worksheetChangeover steps with times, internal or external, what can move, ideas and before/after totals.
- Kaizen event charter templateProblem, goal, scope in and out, boundaries, metrics from baseline to target, team and roles, and sign-off before day one.
- RACI matrix template17 kaizen project tasks by 10 roles, with R, A, C, I drop-downs and a check for one accountable per task.
- PFMEA template (process FMEA)Failure modes, effects and causes rated for severity, occurrence and detection, with RPN before and after action.
- Shift handover templateSafety, production against plan, holds, downtime events, materials and people, and the open actions the next shift takes over.
- Kanban card templateSix production and six withdrawal kanban cards to print and cut out, with loop sizing and a card register.
- Pareto chart templateA tally sheet, the Pareto by count and by cost with the cumulative line and the 80% cut, and a before and after comparison. Excel sorts and draws it.
- Control plan templateWhat is checked at each step, against which limits, how, how often, and what to do when a result is out.
- Corrective action request (CAPA) formOne problem from containment to proof the fix worked, with occurrence and escape causes and a closure check that tells you when it can close.
- Idea suggestion formA one-page idea form with the supervisor's answer and points, and an idea log that tracks days to answer.
- Just Do It (JDI) card templateSix Just Do It cards per sheet for quick fixes, with the rules for what counts and a log of every card.
- Quick kaizen templateOne page for a small improvement: before and after, the cause, the countermeasure, the results and whether the standard changed.
- Time study sheetTime each element over 10 cycles and work out the average, lowest repeatable and standard time. Excel does the sums.
- Spaghetti diagram templateSquared paper to trace every trip, a trip log that turns grid squares into feet, meters and walking time, and a before and after comparison.
- OEE tracking sheetOne row per shift for a week. The Excel version works out availability, performance, quality and OEE and charts the week.
- Non-conformance report (NCR) formA two-page NCR from the requirement against what was found to disposition and closure, and an Excel NCR log.
- CAPA log templateAn Excel CAPA tracker with status, days open, late flags and counts by source, plus a printable log and monthly review.
- Supplier corrective action request (SCAR) formA SCAR from the problem and containment asked for to the supplier's 8D-style response, verification and closure.
- First article inspection (FAI) report templatePart information, a ballooned characteristic table with tolerances and results, material and process certificates, and sign-off.
- Preventive maintenance checklist templateA PM checklist per machine with readings and sign-off, and a PM schedule that works out the next due date.
- Equipment downtime log (MTTR and MTBF)A breakdown and downtime log, with MTTR, MTBF and downtime by machine and cause worked out in Excel.
- Environmental aspects and impacts registerAn ISO 14001-style register of aspects and impacts, with significance scoring, legal requirements, controls and owners.
- Manufacturing process instruction (MPI) templateOperation steps with parameters, tools, quality checks, safety and a photo each, plus revision history and approval.
- Engineering process instruction (EPI) templateScope, parameters and limits, equipment and materials, validation steps, acceptance criteria, change history and approvals.
- Training sign-off sheetAn attendance and sign-off record where each person signs they understood, with a competence check and an Excel log.
- On-the-job training (OJT) checklistThe training record for one trainee on one job: the four TWI steps signed, every try judged, qualified when your rule is met, then tapering follow-up checks.
- New hire onboarding checklist (manufacturing)29 onboarding items from before day 1 to the 90-day review, with owners, dates and review notes.
- Competency assessment formThe one-person assessment behind a skills matrix rating: each task rated 0 to 4 from evidence, checked, with a training plan for every gap.
- Cross-training plan templateWho is learning which task, from and to which level, by when, and how many are qualified on each task.
- Absenteeism tracker templateA monthly attendance grid with codes, absence rate by person and team, and an optional Bradford factor.
- Engineering change request (ECR) formAn ECR form with the change, what it touches, risk and approvals, and an Excel log that tracks each change to done.
- Design FMEA (DFMEA) templateA design FMEA worksheet with S, O, D and RPN before and after action, a class column and a design rating guide.
- Process flow diagram templateA squared sheet to draw the flow with a symbol key, and a step table that counts operations, moves, checks, waits and storage.
- PPAP checklistThe 18 PPAP elements with owner, due date and status, the five submission levels and a readiness count.
- Process capability (Cpk) study sheet25 subgroups of readings with Cp, Cpk, Pp and Ppk worked out, control limits to check stability, and a histogram.
- Lubrication schedule templateEvery lube point with lubricant, method, amount, frequency and who, with next due dates and a monthly sign-off record.
- TPM tag logEvery abnormality tag with type, who fixes it, priority and dates, with days open and counts by type and week.
- Autonomous maintenance step auditCriteria for each of the seven autonomous maintenance steps, scored 0 to 2, with the step result and the decision to move on.
- Inventory cycle count sheetA blind count sheet with variance and tolerance, an ABC count schedule and record accuracy, worked out in Excel.
- Hour-by-hour production boardHourly plan against actual with running totals and the reason for each miss, plus a shift summary by reason.
- Cost savings trackerA savings log with hard and soft savings, payback and Finance's sign-off, plus a glide path against the year's target.
- CapEx request formA capital request with options, costs, benefits, payback and NPV, and the approval levels the amount needs.
- Cost-benefit analysis templateUp to three options side by side with costs, hard and soft benefits, payback, NPV and the benefit-cost ratio.
- Cost of poor quality (COPQ) worksheetCost of quality by prevention, appraisal, internal and external failure, with COPQ as a share of sales.
- Incoming inspection checklistReceiving inspection checks from paperwork to sample, the sampling plan, the decision, and an Excel log by supplier.
- Supplier audit checklistA supplier process audit of 32 questions scored 0 to 3, with section scores, a rating and the findings.
- Supplier scorecardMonthly PPM, on-time delivery and SCAR measures turned into points, a weighted score and a rating per supplier.
- Receiving logA dock receiving log with quantities, damage, QC holds and putaway, plus a discrepancy report and dock-to-stock time.
- Pre-shipment inspection checklistThe last check before shipping: part, quantity, labels, packaging, paperwork and photos, then release.
- Material shortage logEvery part short with its need date, line impact, ETA and escalation, and counts by reason and supplier.
- Maintenance work order formOne form per maintenance job from request to handback, and a log that tracks response, completion and backlog by priority.
- Six big losses worksheetWhere a machine's planned time goes: the six big losses in minutes, ranked, with A, P, Q and OEE worked out.
- Andon response logEvery andon call with response and fix times, flags against your targets, and counts by type and station.
- Changeover checklist25 checks for every changeover, a record of planned and actual times, and a log of changeover time against target.
- Kanban sizing calculatorHow many kanban cards each loop needs, per part, with the change from today's cards and what the loop holds in days.
- Kaizen event trackerEvery kaizen event on one sheet: status, roles, the metric against target, open actions and the 30, 60 and 90 day checks.
- Defect check sheetTally defects by type and day, with units inspected, defect rates, a location sheet and the week's Pareto.
- TWI job breakdown sheetThe TWI Job Instruction breakdown of a job into important steps, key points and reasons, with a worked example and the four steps.
- Standard work combination tableOne operator's manual, machine, walk and wait time on a time chart against takt, with machine cycles and a process capacity sheet.
- Lead time worksheetProduction lead time from the inventory waiting at each step, value-added time and process cycle efficiency, plus an order traced from order to delivery.
- Maintenance KPI trackerMTBF, MTTR, availability and PM compliance per asset and month, plant figures from the totals, planned maintenance % and backlog in weeks.
- Daily huddle agendaA 15-minute start-of-shift stand-up in six timed blocks, with yesterday's SQCDP results, today's plan, actions and escalations.
- DMAIC project charter templateThe Define-phase charter on one page: problem and goal, metrics, scope, team and phase dates, with savings and a tollgate checklist.
- Water spider route plan (mizusumashi)A water spider's fixed route: stops with arrival times, what is delivered and collected, route time against the cycle, cart load and a trip log.
- Cost deployment matrixCost deployment on paper and in Excel: loss quantities by process, causal and resultant losses, the cost of each loss, a Pareto and the projects that recover them.
- Equipment criticality analysisAssets scored 1 to 5 on six criteria with your own weights, ranked and sorted into classes A, B and C with a safety override and a suggested maintenance strategy.
- Bottleneck analysis worksheetEffective capacity per station from cycle time, parallel units, availability and yield, the bottleneck, takt and utilization, a queue cross-check and the five focusing steps.
- QA matrix templateDefect modes against stations in flow order: where each is made and first caught, a weight × occurrence × detection score, an AA to C class and the escapes flagged.
- Fault tree analysis templateA drawing area with the FTA symbols, an event table with probabilities and minimal cut sets, and the gates worked out bottom-up in Excel.
- Is / is not analysis templateWhat, where, when and extent with is, is not, distinctions and changes, then each possible cause tested against every pair and ranked.
- 5G investigation sheetConfirm the facts before naming a cause: 5W1H, the five G's with 20 prompts, the gap against the principle and the standard, and the countermeasures.
- Yokoten tracker (horizontal deployment)Copy a proven improvement line by line: the source result, each candidate's own before and after, its share of the source's improvement and the standard updated.
- Coaching kata template (improvement kata storyboard)The learner's storyboard (target condition, current condition, obstacles, PDCA cycles) and a fold-over card with the coach's five questions.
- SMART goals templateWrite a goal, test it against the five SMART letters, then track progress toward the target against the time used.
- Nemawashi template (stakeholder plan)Plan the one-to-one conversations before a decision: who to talk to in what order, their concerns, what changed and where they stand.
- Breakdown analysis reportOne equipment breakdown from the stop to the 90-day check, plus a breakdown log with repeat flags, MTBF and MTTR by asset and a Pareto of causes.
- Heijunka box planner (production leveling)Weekly demand turned into containers a day, takt, pitch and slots, a leveled sequence of products and the heijunka box, with a check that the changeovers fit.
- 4M change management sheet (change point)A shift log of every change to Man, Machine, Material, Method or Design, the extra checks after it and when normal checks resume, with a change point board.
- Future state value stream map worksheetThe eight future-state questions worked through in order: takt, pitch, flow, supermarkets, the pacemaker and the mix, with an EPEI check and current against future lead time.
- Value stream plan (VSM action plan)The future-state map cut into loops, each with an objective and a measurable goal, and its kaizen bursts turned into owned, dated projects on a 12-month timeline.
- Kaizen project plan (Gantt chart)One improvement project as a Gantt chart: tasks by phase with owners, predecessors and working days, a 16-week grid, milestones and a status from planned against actual % done.
- Histogram templateReadings, bins set by the square root rule, a tally and counts, the spec limits drawn and the share out of spec, with the common shapes explained.
- Scatter diagram templateUp to 50 pairs with a group code, r and R², the least squares line, the quadrant count and r for each group.
- Gauge calibration logA gauge register with next due dates and status, a calibration record with as-found and as-left readings, and the steps when a gauge fails.
- Escalation matrix templateWho is called for each type of issue and after how long, with severity rules, contacts and an escalation log.
- Quality alert formA quality alert to post at the line, a sign-off sheet for every shift, and a log of open, expired and closed alerts.
- Employee recognition program templateDesign a recognition program on one page, then run it: points per action, prizes, budget, a points ledger, a monthly leaderboard and a fairness check by team and shift.
- Lean transformation roadmapA plant-wide lean program on one sheet: six phases with exit criteria, six workstreams by quarter over 24 months, the model line, metrics with baseline and target, cadence and risks.
- Obeya room plannerPlan the walls, owners, cadence, agenda and rules of an obeya, then run the weekly review of KPIs, problems, actions and milestones.
- Paper forms inventory (paperless manufacturing worksheet)Every paper form, checklist and log in one list: hours a month, who acts on it, how long the paper waits, and which forms to move first.
- Continuous improvement software evaluation scorecardCompare CI software vendors: a must-have gate, eight weighted criteria scored 1 to 5, points out of 100 and a rank, with a demo script and reference questions.
- Lean principles assessment templateThe five lean principles as 25 things you can see on one value stream, answered yes, partly or no on a walk, with a score per principle, the next step and a trend over walks.
- Employee engagement survey templateA short anonymous pulse survey for shop floor staff: 14 statements in six drivers, two open questions, results by driver and team, and the actions.
- Hansei reflection sheet (lessons learned)A written look back at one finished project, event or launch: goals against results in numbers, causes rather than blame, lessons to keep or change, and where else they apply.
- Daily kaizen routine boardA team's 10 to 15 minute daily routine at the board: one problem from each person, small fixes with one owner, counted every week.
- Quality circle meeting recordA circle's charter, a one-page record for each meeting and a problem register that follows every problem from selected to closed or escalated.
- Weekly maintenance schedule templateNext week's maintenance jobs, scheduled only when ready, loaded against each craft's hours by day, with schedule compliance and break-ins at week end.
- Operational excellence assessment templateThe ten principles of operational excellence as 30 behaviors and practices you can see, scored 1 to 5 by several people, with the spread, the three lowest principles and an action plan.
- Scrum meeting agenda templateTimed agendas for the five scrum meetings, a sprint planning sheet, a retrospective sheet, and an Excel sprint backlog with a burndown.
- Toyota Production System (TPS) house templateThe TPS house for one plant or value stream: roof, two pillars and foundation, with what you do today, the evidence, a status and the next step for each element.
- EPEI and batch size calculatorHow often each part can come round on a shared machine (EPEI) and how big each batch must be, from demand, cycle times and changeovers, now and after SMED.
- People, process, technology (PPT) assessmentCheck one change before go-live: 18 people, process and technology statements scored 1 to 4 by the people who will use it, the lowest element and the actions.
- Process capacity sheet templateEach machine in a part's routing with manual, auto and tool change time, its capacity per shift, and the step that limits the cell against demand.
- Jidoka worksheet (stop at abnormality)For one line or cell, every abnormality that should stop the work: how it is detected, how the work stops, who is called, the immediate fix and the root cause step, plus a log of real stops.
- Team charter templateA one-page charter for a standing team: purpose, scope, roles, the KPIs it owns, which decisions it makes itself, norms and cadence.
- Chaku-chaku line plannerPlan a load-load cell: time each machine, load and walk, check that every machine is ready when the operator comes back, compare the cell cycle with takt and size the crew.
- Standard operating procedure (SOP) templateA full SOP in the hierarchical step format, from purpose and scope to the steps, records, revision history and approvals, with review checks and an SOP register.
- Process improvement method selectorEight questions about one problem, an example rule that suggests a method and a matrix of nine methods: when each fits, the usual team and time, and the template to start with.
- X-bar and R control chart template25 subgroups with means and ranges, control limits from A2, D3 and D4, signal flags, both charts and a reaction log.
- Gage R&R study sheet10 parts, 2 or 3 appraisers, 2 or 3 trials: EV, AV, GRR, PV, %GRR and ndc by the average and range method.
- Root cause analysis templateOne report from problem statement to proof: containment, evidence, analysis, verified causes, actions and the effectiveness check.
- Quality control pillar 90-day model area planThirteen weeks from the QA matrix to the QM matrix on one model area, a KPI board, the day-90 gate and expansion waves.
- Autonomous maintenance 90-day model area planAM steps 0 to 3 on one model machine in 13 weeks, a KPI board, the day-90 gate and expansion waves for months 4 to 12.
- Professional maintenance (PM) 90-day model area planThirteen weeks from breakdown analysis to a running PM calendar on one model machine, a KPI board, the day-90 gate and expansion waves.
- Environment and energy pillar 90-day model area planThirteen weeks from waste and energy maps to area standards on one model area, a KPI board, the day-90 gate and expansion waves.
- Focused improvement 90-day model area planThirteen weeks from the loss Pareto to standardized fixes on one model line, a KPI board, the day-90 gate and expansion waves.
- Logistics and customer service pillar 90-day model area planThirteen weeks from the current-state map to pull on one model value stream, a KPI board, the day-90 gate and expansion waves.
- People development pillar 90-day model area planThirteen weeks from the skills matrix to trained cover on critical tasks in one model area, a KPI board, the day-90 gate and expansion waves.
- Early equipment management 90-day model area planThirteen weeks from lessons on current machines to a tracked start-up on one model equipment project, a KPI board, the day-90 gate and expansion waves.
- Cost deployment pillar 90-day model area planThirteen weeks from the loss map to costed, ranked projects in one model area, a KPI board, the day-90 gate and expansion waves.
- Moving from Excel to one system checklistA 34-point checklist and a file inventory for moving trackers from spreadsheets to one system: keep, move, connect or retire, clean, pilot, run both, retire.
- Prioritization matrix templateScore up to 20 improvement ideas on weighted criteria, rank them, test the ranking with equal weights and place each one on an effort and benefit grid.
- Cost per unit worksheet (manufacturing cost per good unit)One product's cost per good unit by materials, labor, machine and overhead, the gap to target, and which cost lever is worth most a year.
- Digital manufacturing readiness assessmentScore 24 statements on process, technology and people from 0 to 4, check the balance between them and rank the gaps by what matters in your plant.
- Manufacturing KPI dashboard templateWeekly plant numbers in, 14 KPIs out: OEE and its parts, first pass yield, scrap, on-time delivery, recordable rate, cost and absence, each against a target.
- RCM worksheet (failure mode and task selection)Failure modes classed as hidden, safety, operational or non-operational, then a task chosen for each: condition-based, discard, failure-finding, redesign or run to failure.
- Error-proofing verification log (daily master-sample check)Each poka-yoke device proved every day or week with a known-bad sample, with missed checks counted and the hours and parts at risk worked out when one fails.
- Downtime reason codes template26 starter codes mapped to the six big losses, a log with drop-downs, a Pareto by code and by loss, and a code card for the line.
- Defect catalogue template with boundary samplesEvery defect with a definition, a class and the reason for it, measured accept and reject limits by zone, boundary samples, a defect log with DPU and Pareto, and an inspector agreement check.
- I-MR chart template (individuals and moving range)Up to 100 single readings with moving ranges, limits from a baseline, five run-rule flags, both charts, a second phase and a reaction log.
- Kaizen event preparation checklistEverything that has to be ready before a kaizen event and done after it: 44 items with owners and due dates from 6 weeks before day 1 to 30 days after, five go or no-go gates and a day-by-day agenda.
- Attribute control chart template (p, np, c and u charts)p, np, c and u charts in one workbook: a chart selector, a sample size check, limits for each subgroup, signal flags and four worked examples.
- Critical spare parts list and stocking levelsAssets ranked by consequence, each part classed and given a stocking policy, and min and max worked out from usage and lead time, with the downtime each stock-out would cost.
- Tier 2 meeting agenda and escalation sheetA 15-minute tier 2 agenda in ten timed blocks, fixed roles and rules, escalation triggers with time limits, and a log that ages every escalation and sends the answer back down.
- Mock recall template: traceability exercise worksheetTrace a finished lot back to every input lot and forward to every first customer, reconcile the quantities against a tolerance and time it against your target.
- Plan for every part (PFEP) templateOne row per part: supplier, pack, container, usage, lead time and locations, with ABC classes, market and line kanban counts and a lineside space check.
- Changeover matrix templateA from-to matrix of changeover minutes with the clean each transition needs (allergen, colour, format), and a weekly planner that totals the order and suggests a shorter one.
- Measurement uncertainty budget templateA GUM uncertainty budget: Type A and B rows, divisors by distribution, sensitivity coefficients, uc, νeff, k from the t-table, U, TUR and a guard band check.
- Maintenance job plan templateOne job planned on one sheet: steps and craft hours, parts checked against stock, tools, lockout and permits, documents, a ready check for the schedule, and technician feedback.
Can't find the template you need?
Tell us what you're looking for. We'll make it and send it to your inbox, free.
A shift handover sheet, a red tag log, a changeover checklist for one machine: if your team uses it on the floor, ask.