Kanban sizing works out how many cards a pull loop needs so the using process never runs out and the store holds no more than it must. A common formula is daily demand × replenishment lead time in days × (1 + safety factor) ÷ quantity per container, rounded up to a whole card. The lead time is the whole trip of a card around the loop, not only the machine's run time, and the safety factor covers swings in demand and supply. Page 1 of this template is a worksheet to size loops by hand, one row per part, with the formula and a strip for two-bin loops. Page 2 has a worked example with the arithmetic, what goes into the replenishment lead time and a card count review table. The Excel version takes one row per part and works out the kanbans needed, the change from the cards in the loop now, what the loop holds in units and in days of demand, and the totals, with a two-bin sheet that rounds each bin up to whole packs. The card count then goes on the cards and in the card register of the kanban card template.

Free to use: print it, copy it and edit it for your team. Enter your name and work email once to download.

Page 1 of the kanban sizing worksheetFields for area, supplying and using process and date, the kanban formula with what each term means, a twelve-row table from daily demand to kanbans rounded up and the change against cards now, and a two-bin strip.
Kanban formulaOne row per partKanbans rounded upChange from cards nowLoop holds in daysTwo-bin sizingWorked exampleCard count review

When to use it

When to use a kanban sizing calculator

  • When setting up a new kanban loop, before printing the cards.
  • When demand, lead time or container size changes and the card count needs checking.
  • To review loops that run out, or stores that are always full.
  • To size two-bin loops for small parts and consumables.

How to fill it in

  1. 1

    Measure daily demand

    Use the average daily use over a period that reflects the coming weeks, not last year's total.
  2. 2

    Measure the replenishment lead time

    Follow a few cards around the loop: waiting to be collected, waiting to be made, the changeover, making and moving back. Add it up in days.
  3. 3

    Choose a safety factor

    Write it as a decimal or a percentage, for example 0.1 or 10%, enough to cover the swings you have seen.
  4. 4

    Work out the kanbans

    Daily demand × lead time × (1 + safety factor) ÷ quantity per container, rounded up only when there is a remainder.
  5. 5

    Compare with the loop today

    Add or remove cards to match, and write the change in the card register of the kanban card template.
  6. 6

    Review the count

    When demand or lead time changes, and when the store never drops below a full container or two, take a card out.

A filled-in example

Illustrative, not a benchmark

An example: three card loops and one two-bin loop (illustrative numbers).

The example's three card loops, worked out

Kanbans = daily demand × lead time (days) × (1 + safety factor) ÷ container quantity

  1. Bracket =400 × 0.5 × 1.1 ÷ 50 = 4.4= 5
  2. Cover =120 × 2 × 1.2 ÷ 24 = 12.0= 12
  3. Screw =2,000 × 3 × 1.1 ÷ 500 = 13.2= 14
Always round up: a fraction of a card means the loop runs short. 5 + 12 + 14 = 31 kanbans.
  • Bracket: 400 a day, half a day of lead time, safety factor 0.1, 50 per container: 400 × 0.5 × 1.1 ÷ 50 = 4.4, so 5 kanbans. It is the same loop as on the kanban card template.
  • Cover: 120 a day, 2 days, 0.2, 24 per container: 120 × 2 × 1.2 ÷ 24 = 12.0 exactly, so 12 kanbans and no extra card.
  • Screw: 2,000 a day, 3 days, 0.1, 500 per container: 2,000 × 3 × 1.1 ÷ 500 = 13.2, so 14 kanbans.
  • Washer, two-bin: 300 a day, 1 day, 0.2: 300 × 1 × 1.2 = 360 per bin, rounded up to 4 packs of 100, so two bins of 400.

The three card loops need 5 + 12 + 14 = 31 kanbans. The screw loop holds 14 × 500 = 7,000 screws, 3.5 days of demand, the most of the three, so its 3-day lead time is the one to shorten first.

Common mistakes

  • Using run time as the lead time

    A card spends most of its trip waiting. Lead time measured at the machine alone gives too few cards and the line runs short.

  • Rounding down

    4.4 kanbans means 5. Rounding down leaves the loop short every time demand peaks.

  • Setting the safety factor once

    As the loop proves itself, reduce the safety factor and take cards out.

  • Changing cards without the register

    Every card added or removed goes in the register, or missing cards go unnoticed.

Download the template

Free to use: print it, copy it and edit it for your team. Enter your name and work email once to download.

Run this template in LeanSuite

In LeanSuite video of each process step becomes a current-state value stream map with measured cycle times, inventory and lead time, and the inventory counted between steps is converted into days of WIP.

See it in a 45-minute demo

FAQ

Kanban sizing calculator: common questions

  1. A common formula is daily demand × replenishment lead time in days × (1 + safety factor) ÷ quantity per container, rounded up. For 400 parts a day, half a day of lead time, a 10% safety factor and 50 per container: 400 × 0.5 × 1.1 ÷ 50 = 4.4, so 5 kanbans.

  2. The whole time for a card to go around the loop: waiting to be collected, waiting in the queue, the changeover, making the container and moving it back to the store. It is usually much longer than the run time.

  3. There is no fixed number. Start with enough to cover the swings in demand and supply you have seen, then reduce it as the loop runs well and take cards out.

  4. Each bin holds enough for the replenishment lead time plus a safety margin: daily demand × lead time × (1 + safety factor), rounded up to whole packs. When one bin empties it goes for refilling while the second is used.

  5. At most the number of kanbans × the quantity per container, with every container full. Divided by daily demand, that is the days of stock the loop allows. The Excel version shows it for each part and the average across parts.

More free templates

All templates
Browse all 278 templates

Can't find the template you need?

Tell us what you're looking for. We'll make it and send it to your inbox, free.

A shift handover sheet, a red tag log, a changeover checklist for one machine: if your team uses it on the floor, ask.