Free template
Updated
Kaizen event preparation checklist
A kaizen event preparation checklist is the dated list of what has to be in place before a kaizen event starts and done after it ends: the process and its target, the team and their release from normal work, a baseline measured before day 1, maintenance and engineering booked, the production schedule protected, the room and materials ready, and the follow-up to the 30-day check. The event week gets the attention, but it only works if this work is done. This template has 44 items in ten phases, each owned by a role, with five gate items that decide at a go or no-go review 5 days before day 1 whether the event runs or moves. Page 1 of the PDF is the timeline on one page, pages 2 to 4 the items, page 5 a day-by-day agenda for a five-day event with the report-out format, and page 6 how to use it with a worked example and a 30, 60 and 90 day sustain record. The Excel version works out every due date from the event date, flags overdue items, counts the status by phase and gives a readiness score and the go or no-go.
Free to use: print it, copy it and edit it for your team. Enter your name and work email once to download.
A timeline of ten phases from 6 weeks before day 1 to 30 days after the report-out, the five go or no-go gates and who does what.When to use it
When to use a kaizen event preparation checklist
- Six weeks before a three to five day kaizen event, as soon as the sponsor agrees to hold one.
- When the event needs people released from production, maintenance time or a protected schedule, all of which have to be booked weeks ahead.
- At the weekly preparation review with the sponsor, to see what is overdue and whether the gates will be met.
- After the report-out, to hand the follow-up to the process owner with dates.
How to fill it in
- 1
Enter day 1 and the event length
In the Excel version every due date fills in: phases before the event count back from day 1, phases after it count on from the report-out. On paper, write the dates under each phase on page 1.
- 2
Put a name against every role
At the scoping meeting, write a person next to the sponsor, process owner, team leader, facilitator, scribe and the support roles. One name per item, even when the role is a group.
- 3
Review it every week with the sponsor
Set the status of each item and write the evidence: a record, a booking, a signature. The sheet flags overdue items and items due within 7 days, and works out the readiness score: items done ÷ items due by today, leaving out the ones that do not apply.
- 4
Hold the go or no-go review 5 days before day 1
All five gate items done means go. Any open gate: fix it that week or move the event, and tell the team, the cover and maintenance the same day.
- 5
Run the week to the agenda
Day 1 teach and see, day 2 current state and causes, day 3 change and try, day 4 prove and standardize, day 5 report-out and hand-over, with a 15-minute check with the sponsor at the end of each day. Keep one action list from day 1.
- 6
Hand over and check at 30 days
The process owner runs weekly follow-up, posts the new standard work and walks the process with the sponsor at 30 days, measuring the main metric the same way as the baseline. The kaizen event tracker takes the 60 and 90 day checks.
The event week
A day-by-day agenda for a five-day kaizen event
A common shape for a five-day event, the same flow the EPA Lean in Government Starter Kit and the Lean Enterprise Institute's Lean Lexicon describe. Shorten the days for a smaller scope.
| Day | Focus | What the team does | Out by the end of the day |
|---|---|---|---|
| Day 1 | Teach and see | The sponsor opens with why this process, the scope and the safety rules. Short training on only the methods this event needs, then walk the process with the operators, check the baseline and start timing. | Charter confirmed by the team. Everyone has seen the process run. |
| Day 2 | Current state and causes | Finish timing and observing, draw the current state with its numbers, compare the work with takt where it applies, find the causes on the floor and choose what to try. | Current state with data, the causes, a ranked list of changes to try. |
| Day 3 | Change and try | Mock up in cardboard first, move equipment with maintenance under lockout, rebalance the work. Measure each trial the same way as the baseline. | First trials run and measured. |
| Day 4 | Prove and standardize | Run the new method at normal pace with the operators who will own it, measure it, write the standard work, train the operators, list what is not finished with owners and dates. | New standard work, the result, the action list. |
| Day 5 | Report-out and hand-over | Dry run, then a report-out under 45 minutes to the sponsor and plant leaders. Hand the actions to the process owner and book the follow-up. | The process owner owns the actions. Follow-up dates in diaries. |
Day 1
- Focus
- Teach and see
- What the team does
- The sponsor opens with why this process, the scope and the safety rules. Short training on only the methods this event needs, then walk the process with the operators, check the baseline and start timing.
- Out by the end of the day
- Charter confirmed by the team. Everyone has seen the process run.
Day 2
- Focus
- Current state and causes
- What the team does
- Finish timing and observing, draw the current state with its numbers, compare the work with takt where it applies, find the causes on the floor and choose what to try.
- Out by the end of the day
- Current state with data, the causes, a ranked list of changes to try.
Day 3
- Focus
- Change and try
- What the team does
- Mock up in cardboard first, move equipment with maintenance under lockout, rebalance the work. Measure each trial the same way as the baseline.
- Out by the end of the day
- First trials run and measured.
Day 4
- Focus
- Prove and standardize
- What the team does
- Run the new method at normal pace with the operators who will own it, measure it, write the standard work, train the operators, list what is not finished with owners and dates.
- Out by the end of the day
- New standard work, the result, the action list.
Day 5
- Focus
- Report-out and hand-over
- What the team does
- Dry run, then a report-out under 45 minutes to the sponsor and plant leaders. Hand the actions to the process owner and book the follow-up.
- Out by the end of the day
- The process owner owns the actions. Follow-up dates in diaries.
What's on the checklist
The 44 items, from 6 weeks before day 1 to 30 days after the report-out
Ten phases. The role in front of each item owns it; write a name next to it on the sheet. Items before the event are due a set time before day 1, items after it a set time after the report-out. The five items that end in a gate are the go or no-go checks, a rule this template sets: if one is not done 5 days before day 1, fix it or move the event.
6 weeks before
Choose the process, the target and the owners
- 1Sponsor: Pick one process and one problem that shows in the plant's own numbers, such as changeover minutes, lead time, scrap or walking distance, not a wish to improve an area.
- 2Sponsor and facilitator: Set one main metric with a target for the week and its unit; add no more than two secondary metrics.
- 3Sponsor: Name the process owner, the person who runs this process every day and will own the result after the report-out.
- 4Facilitator: Check the problem suits an event: it needs several functions, the change can be made and tried within the week, and the cause can be found on the floor. If not, send it to daily kaizen or a longer project.
- 5Facilitator: Choose the event week away from audits, launches, shutdowns and peak shipping weeks, and put it on the CI calendar.
5 weeks before
Scope, team and the scoping meeting
- 6Sponsor and team leader: Draft the scope: where the process starts and stops, what is in and out, and what may not be changed, such as a customer-approved step or a capital limit.
- 7Team leader: Pick 6 to 10 people: operators who run the process, from each shift it runs on, the supervisor, maintenance, engineering or quality as needed, and one person from outside the area who will ask the obvious questions.
- 8Team leader: Give each person a role: team leader, facilitator, scribe (keeps the action list, data and photos), process owner and members. The sponsor supports the team but is not a full-time member.
- 9Facilitator: Hold a 2 to 4 hour scoping meeting at or near the process with the sponsor and the team; agree the scope, metric, target and pre-work, and write them on the charter.
- 10Sponsor: Write down how much the team may spend during the week without further approval, and who signs above that.
4 weeks before
Baseline and pre-work
- 11Process owner: Pull the main metric's history from existing records (production, scrap, downtime) for the last few months, so the event is compared with a normal week and not one good day.
- 12Facilitator: Write down how the main metric is measured: what is counted or timed, from which record, by whom and over what period. The result is measured the same way.
- 13Team leader: Measure the baseline on the floor: cycle time by element over at least 10 cycles per operator for a repeated job, changeover from last good part to first good part, lead time by following parts through, or defects per number checked. Gate: no baseline, no event.
- 14Team leader: Film the process with the operators' agreement, draw a spaghetti map of the walking, and sketch the steps with the waits and inventory between them.
- 15Process owner: Collect the current standard work, work instructions, layout drawing, quality records and notes from any earlier attempt to fix this problem.
- 16Facilitator: Give every pre-work task an owner and a due date, and check them each week until the event.
3 weeks before
Support booked, production protected
- 17Production planner: Protect the schedule: build ahead or move orders so the line can stop or slow for trials without missing a customer delivery, and agree the hours when trials may run. Gate: no protected schedule, no event.
- 18Supervisor: Plan cover for every operator on the team for the whole event, with overtime or borrowed people, so the line runs without them.
- 19Maintenance lead: Book a technician, and an electrician if equipment will move, to work with the team on days 3 and 4, with their tools and locks. Gate: no maintenance support, no event.
- 20Engineer: Book engineering and quality time for any change to a fixture, program, check or layout, and agree who approves a changed process before parts ship.
- 21Sponsor: Sign the charter with the process owner and team leader, and send it to the team and the area. Gate: no signed charter, no event.
2 weeks before
Confirm people, tell the area
- 22Team leader: Get written confirmation that every team member is released for the whole event and their normal work is covered. Gate: no released team, no event.
- 23Supervisor: Tell everyone in the area, on every shift, what the event is for and when it runs, and how to pass ideas or concerns to the team.
- 24Sponsor: Put the day 1 kick-off, a short check at the end of each day and the report-out in the diaries of the sponsor and the plant leaders.
- 25Safety: Review the planned changes for hazards: moving or modifying equipment follows the site's lockout procedure, and new layouts keep aisles, exits and safety equipment clear.
- 26Purchasing: Agree how the team can buy small items during the week, within the spending limit: petty cash, a purchasing card or a named buyer.
1 week before
Room, supplies and materials
- 27Team leader: Book a room close to the process for the whole week, with wall space, and a room for the report-out.
- 28Team leader: Stock the room: flip charts, sticky notes, markers, stopwatches or phone timers, tape measures, floor tape, labels, a camera and the printed pre-work data.
- 29Maintenance lead: Have materials for quick changes ready: hand tools, carts, shelving, cardboard for mock-ups, workshop time for fixtures, and a forklift booked if racks or machines will move.
- 30Safety: Have the area's PPE ready for every team member, including people from the office.
- 31Facilitator: Prepare the day 1 training (only the methods this event needs) and send the team the agenda, start times, PPE rules, charter and baseline.
5 days before
Go or no-go review
- 32Sponsor: Hold the go or no-go review with the team leader and facilitator. If any gate item is not done, fix it this week or move the event.
- 33Facilitator: If the event moves, tell the team, the cover, maintenance and the area the same day, and book the support again for the new date.
Event week
Day 1 to the report-out
- 34Sponsor: Open day 1: why this process matters, what is in and out of scope, and that what the team proves this week becomes the new way of working, not a recommendation.
- 35Team leader: Hold a 15-minute check with the sponsor at the end of each day: progress against the target, help needed, decisions to make.
- 36Scribe: Keep one action list from day 1, each action with one owner and a due date.
- 37Team: Measure the new method the same way as the baseline, write the new standard work, and train the operators who will run it, or book the training for the other shifts.
- 38Team: Give the report-out on the last day: result against target, the new standard, open actions with owners and dates, and the follow-up dates.
1 week after
Hand over to the process owner
- 39Process owner: Start weekly follow-up meetings the week after the event, and hold them until every open action is closed.
- 40Process owner: Post the new standard work at the process, and check on every shift that it is followed.
- 41Facilitator: Add the event to the kaizen event tracker with its baseline, target, result and the 30, 60 and 90 day check dates.
30 days after
First sustain check
- 42Process owner: Walk the process with the sponsor: is the new standard followed on every shift, and does the main metric hold, measured the same way as the baseline?
- 43Process owner: Close or re-date every open action, and take any action past its date to the sponsor.
- 44Facilitator: Share what worked with similar lines and areas, and confirm the 60 and 90 day re-measures on the tracker.
A filled-in example
Illustrative, not a benchmarkAn example: a five-day event on a hose assembly cell, checked seven days before day 1 (illustrative, the same as the Excel worked example).
The example checklist seven days before day 1
- Done: 26 items due by today
- Open: 4 items due by today
- N/A: 1 item due by today
The five gate items
- Done: Schedule protected
- Done: Charter signed
- Done: Team released
- Open: Floor baseline: 2 of 5 stations timed
- Open: Maintenance technician: asked, not confirmed
Readiness = items done ÷ (items due − N/A)
- Readiness =26 ÷ (31 − 1)= 87%
31 of the 44 items are due: 26 done, 4 open and 1 not applicable. Readiness is 26 divided by 30, 87 percent. 3 of the 5 gate items are done; the floor baseline, with 2 of 5 stations timed, and the maintenance technician, asked but not confirmed, are open, so the sheet says no-go.
- The cell makes 380 hoses a shift against 430 needed, so the main metric is hoses a shift with four operators, from 380 to 430.
- 31 of the 44 items are due by today. Item 20, booking engineering, is N/A: no fixture, program or check change is in scope.
- 26 are done. Four are open: the floor baseline (2 of 5 stations timed, 21 days overdue), the maintenance technician (asked, not confirmed, 14 days overdue), the report-out room and the forklift to move a rack (both due today).
- Two of the open items are gates: no baseline, no event, and no maintenance support, no event.
Readiness = 26 ÷ (31 − 1) = 87%, and 3 of the 5 gates are done, so the sheet says NO-GO. The team leader times the other three stations the next day and the maintenance lead confirms the technician before the go or no-go review.
Common mistakes
Measuring the baseline during the event
Day 1 is for seeing the process, not for finding out there are no numbers. Measure before, with the method you will use for the result, or the report-out compares two different things.
Operators on the team with no cover
If nobody runs their machine, they get called back on day 2. Book cover for the whole week and get the release in writing.
Maintenance on call instead of booked
A rack or machine that cannot move on day 3 stops the trial. Book the technician for the days the team will change things, and the forklift if anything heavy moves.
A team of managers and engineers
The people who do the work every day know where the time goes and have to live with the new method. Most of the team should be them, plus the support the change needs and one outsider.
Ending at the report-out
Some actions are always open on day 5. Weekly follow-up starts the next week, run by the process owner, not the facilitator, who moves on to the next event.
Download the template
Free to use: print it, copy it and edit it for your team. Enter your name and work email once to download.
Run this template in LeanSuite
In LeanSuite every action in a Kaizen has an owner and a due date, and projects line up on a Gantt timeline with the reason for each delay.
See it in a 45-minute demoIn the lean glossary
Free tools
FAQ
Kaizen event preparation checklist: common questions
More free templates
All templates- 1-1-90 method worksheetOne page: score areas 1 to 5, write the pain point with a before and target number, check days 30, 60 and 90, and plan the next three areas.
- Kaizen event charter templateProblem, goal, scope in and out, boundaries, metrics from baseline to target, team and roles, and sign-off before day one.
- RACI matrix template17 kaizen project tasks by 10 roles, with R, A, C, I drop-downs and a check for one accountable per task.
- Idea suggestion formA one-page idea form with the supervisor's answer and points, and an idea log that tracks days to answer.
- Just Do It (JDI) card templateSix Just Do It cards per sheet for quick fixes, with the rules for what counts and a log of every card.
- Quick kaizen templateOne page for a small improvement: before and after, the cause, the countermeasure, the results and whether the standard changed.
- Kaizen event trackerEvery kaizen event on one sheet: status, roles, the metric against target, open actions and the 30, 60 and 90 day checks.
- Waste walk checklist (TIMWOODS)32 things to look for across the eight wastes, with where and how much, and a findings log with dot votes, owners and dates.
- DMAIC project charter templateThe Define-phase charter on one page: problem and goal, metrics, scope, team and phase dates, with savings and a tollgate checklist.
- Cost deployment matrixCost deployment on paper and in Excel: loss quantities by process, causal and resultant losses, the cost of each loss, a Pareto and the projects that recover them.
- Yokoten tracker (horizontal deployment)Copy a proven improvement line by line: the source result, each candidate's own before and after, its share of the source's improvement and the standard updated.
- Coaching kata template (improvement kata storyboard)The learner's storyboard (target condition, current condition, obstacles, PDCA cycles) and a fold-over card with the coach's five questions.
- SMART goals templateWrite a goal, test it against the five SMART letters, then track progress toward the target against the time used.
- Lean readiness assessment templateTwenty statements in four factors, scored 1 to 5 by several people on their own, with averages, the spread between them and the actions.
- Nemawashi template (stakeholder plan)Plan the one-to-one conversations before a decision: who to talk to in what order, their concerns, what changed and where they stand.
- Value stream plan (VSM action plan)The future-state map cut into loops, each with an objective and a measurable goal, and its kaizen bursts turned into owned, dated projects on a 12-month timeline.
- Kaizen project plan (Gantt chart)One improvement project as a Gantt chart: tasks by phase with owners, predecessors and working days, a 16-week grid, milestones and a status from planned against actual % done.
- Employee recognition program templateDesign a recognition program on one page, then run it: points per action, prizes, budget, a points ledger, a monthly leaderboard and a fairness check by team and shift.
- Lean transformation roadmapA plant-wide lean program on one sheet: six phases with exit criteria, six workstreams by quarter over 24 months, the model line, metrics with baseline and target, cadence and risks.
- Continuous improvement software evaluation scorecardCompare CI software vendors: a must-have gate, eight weighted criteria scored 1 to 5, points out of 100 and a rank, with a demo script and reference questions.
- Lean principles assessment templateThe five lean principles as 25 things you can see on one value stream, answered yes, partly or no on a walk, with a score per principle, the next step and a trend over walks.
- Hansei reflection sheet (lessons learned)A written look back at one finished project, event or launch: goals against results in numbers, causes rather than blame, lessons to keep or change, and where else they apply.
- Daily kaizen routine boardA team's 10 to 15 minute daily routine at the board: one problem from each person, small fixes with one owner, counted every week.
- Quality circle meeting recordA circle's charter, a one-page record for each meeting and a problem register that follows every problem from selected to closed or escalated.
- Operational excellence assessment templateThe ten principles of operational excellence as 30 behaviors and practices you can see, scored 1 to 5 by several people, with the spread, the three lowest principles and an action plan.
- Toyota Production System (TPS) house templateThe TPS house for one plant or value stream: roof, two pillars and foundation, with what you do today, the evidence, a status and the next step for each element.
- Process improvement method selectorEight questions about one problem, an example rule that suggests a method and a matrix of nine methods: when each fits, the usual team and time, and the template to start with.
- Focused improvement 90-day model area planThirteen weeks from the loss Pareto to standardized fixes on one model line, a KPI board, the day-90 gate and expansion waves.
- Moving from Excel to one system checklistA 34-point checklist and a file inventory for moving trackers from spreadsheets to one system: keep, move, connect or retire, clean, pilot, run both, retire.
- Prioritization matrix templateScore up to 20 improvement ideas on weighted criteria, rank them, test the ranking with equal weights and place each one on an effort and benefit grid.
- 5S audit checklist template25 checks, five per S, scored 1 to 5, with a score summary and a chart of the five S's.
- Gemba walk checklistA walk plan and route, 30 prompts in six groups and a findings table with owners and due dates.
- Leader standard work templateA team leader's daily, weekly and monthly routine with a box per day, follow-ups and a weekly review.
- Supervisor leader standard work templateA supervisor's daily, weekly and monthly routine with a box per day, an escalation log and a weekly review.
- Production manager leader standard work templateA production or value stream manager's routine by day, week and month, with an escalation log and a weekly review.
- Plant manager leader standard work templateA plant manager's short routine by day, week and month, with an escalation log and a weekly review.
- Autonomous maintenance (CILR) checklist20 clean, inspect, lubricate and retighten checks with a box per day, an abnormality log and sign-off.
- A3 problem solving templateThe standard seven-box A3 from background to follow-up, with a filled-in worked example. PDF and Excel.
- PDCA templateOne improvement cycle on one page: plan, do, check against the goal, then standardize or adjust. PDF and Excel.
- 5 Whys templateA problem statement, a why chain that can branch, evidence for every answer, root causes and countermeasures that are checked.
- 5W1H templateWho, what, when, where, why and how: a problem statement built from checked facts, and an action plan with nothing left open.
- 8D report templateD0 to D8 with targets, containment counts, occurrence, escape and systemic causes, verified actions and a worked example.
- Poka-yoke worksheetEach step's errors and what they cost, the device (approach, function, method), payback, and a log that proves each device works.
- Skills matrix templatePeople by tasks on a 0 to 4 scale, coverage and gaps per task and shift, and a training plan that closes them.
- Standard work sheet templateTakt time, each element's manual, machine and walk time on a time chart, key points and standard WIP.
- One point lesson (OPL) templateOne topic on one page: wrong way and right way pictures, checkable key points, the standard it belongs to and a sign-off record.
- SMED changeover worksheetChangeover steps with times, internal or external, what can move, ideas and before/after totals.
- Layered process audit (LPA) checklist20 yes, no or N/A checks at the station, a fixed-on-the-spot box, scores by group and a findings table.
- PFMEA template (process FMEA)Failure modes, effects and causes rated for severity, occurrence and detection, with RPN before and after action.
- 5S red tag log and red tagsA log of every red-tagged item with its decision, and six printable red tags to cut out.
- Shift handover templateSafety, production against plan, holds, downtime events, materials and people, and the open actions the next shift takes over.
- Kanban card templateSix production and six withdrawal kanban cards to print and cut out, with loop sizing and a card register.
- Pareto chart templateA tally sheet, the Pareto by count and by cost with the cumulative line and the 80% cut, and a before and after comparison. Excel sorts and draws it.
- Control plan templateWhat is checked at each step, against which limits, how, how often, and what to do when a result is out.
- Corrective action request (CAPA) formOne problem from containment to proof the fix worked, with occurrence and escape causes and a closure check that tells you when it can close.
- Time study sheetTime each element over 10 cycles and work out the average, lowest repeatable and standard time. Excel does the sums.
- Spaghetti diagram templateSquared paper to trace every trip, a trip log that turns grid squares into feet, meters and walking time, and a before and after comparison.
- OEE tracking sheetOne row per shift for a week. The Excel version works out availability, performance, quality and OEE and charts the week.
- Near miss report formA two-page near miss report from the first report to closure, and an Excel log with status and days open.
- Safety observation card templateFour behavior-based safety cards per sheet, with safe and at-risk checks, the conversation and a tally sheet.
- Job safety analysis (JSA) templateJob steps, hazards, risk scored before and after the controls, the hierarchy of controls, PPE and sign-off.
- Risk assessment matrix template (5×5)A color-coded 5 × 5 severity and likelihood matrix, a scoring guide and a risk register.
- Incident investigation report templateFacts and a sourced timeline, causes at three levels, actions by the hierarchy of controls, a US recordkeeping screen and a closure check.
- Toolbox talk templateA record of a short safety talk: topic, key points, questions raised, actions and an attendee sign-in sheet.
- Lockout/tagout (LOTO) procedure templateA machine-specific LOTO procedure: energy sources and isolation points, the steps from shutdown to restart, and the annual review.
- Forklift inspection checklist23 pre-shift checks for a week on one page, a do-not-operate rule, and a defect and repair log.
- Non-conformance report (NCR) formA two-page NCR from the requirement against what was found to disposition and closure, and an Excel NCR log.
- CAPA log templateAn Excel CAPA tracker with status, days open, late flags and counts by source, plus a printable log and monthly review.
- Supplier corrective action request (SCAR) formA SCAR from the problem and containment asked for to the supplier's 8D-style response, verification and closure.
- First article inspection (FAI) report templatePart information, a ballooned characteristic table with tolerances and results, material and process certificates, and sign-off.
- Preventive maintenance checklist templateA PM checklist per machine with readings and sign-off, and a PM schedule that works out the next due date.
- Equipment downtime log (MTTR and MTBF)A breakdown and downtime log, with MTTR, MTBF and downtime by machine and cause worked out in Excel.
- Environmental aspects and impacts registerAn ISO 14001-style register of aspects and impacts, with significance scoring, legal requirements, controls and owners.
- Manufacturing process instruction (MPI) templateOperation steps with parameters, tools, quality checks, safety and a photo each, plus revision history and approval.
- Engineering process instruction (EPI) templateScope, parameters and limits, equipment and materials, validation steps, acceptance criteria, change history and approvals.
- Training sign-off sheetAn attendance and sign-off record where each person signs they understood, with a competence check and an Excel log.
- On-the-job training (OJT) checklistThe training record for one trainee on one job: the four TWI steps signed, every try judged, qualified when your rule is met, then tapering follow-up checks.
- New hire onboarding checklist (manufacturing)29 onboarding items from before day 1 to the 90-day review, with owners, dates and review notes.
- Competency assessment formThe one-person assessment behind a skills matrix rating: each task rated 0 to 4 from evidence, checked, with a training plan for every gap.
- Cross-training plan templateWho is learning which task, from and to which level, by when, and how many are qualified on each task.
- Absenteeism tracker templateA monthly attendance grid with codes, absence rate by person and team, and an optional Bradford factor.
- Engineering change request (ECR) formAn ECR form with the change, what it touches, risk and approvals, and an Excel log that tracks each change to done.
- Design FMEA (DFMEA) templateA design FMEA worksheet with S, O, D and RPN before and after action, a class column and a design rating guide.
- Process flow diagram templateA squared sheet to draw the flow with a symbol key, and a step table that counts operations, moves, checks, waits and storage.
- PPAP checklistThe 18 PPAP elements with owner, due date and status, the five submission levels and a readiness count.
- Process capability (Cpk) study sheet25 subgroups of readings with Cp, Cpk, Pp and Ppk worked out, control limits to check stability, and a histogram.
- Office 5S audit checklist25 checks written for offices and shared areas, five per S, scored 1 to 5, with a score summary and actions.
- Floor marking color guideA floor marking color standard with swatches, marks and line widths to fill in, and a floor marking check with a layout sketch.
- Shadow board plannerTool inventory with fetch time, a layout planned from each tool's outline size, a month of daily checks with 5S audit evidence, and a missing tool log.
- Lubrication schedule templateEvery lube point with lubricant, method, amount, frequency and who, with next due dates and a monthly sign-off record.
- TPM tag logEvery abnormality tag with type, who fixes it, priority and dates, with days open and counts by type and week.
- Autonomous maintenance step auditCriteria for each of the seven autonomous maintenance steps, scored 0 to 2, with the step result and the decision to move on.
- Inventory cycle count sheetA blind count sheet with variance and tolerance, an ABC count schedule and record accuracy, worked out in Excel.
- Hour-by-hour production boardHourly plan against actual with running totals and the reason for each miss, plus a shift summary by reason.
- Cost savings trackerA savings log with hard and soft savings, payback and Finance's sign-off, plus a glide path against the year's target.
- CapEx request formA capital request with options, costs, benefits, payback and NPV, and the approval levels the amount needs.
- Cost-benefit analysis templateUp to three options side by side with costs, hard and soft benefits, payback, NPV and the benefit-cost ratio.
- Cost of poor quality (COPQ) worksheetCost of quality by prevention, appraisal, internal and external failure, with COPQ as a share of sales.
- Incoming inspection checklistReceiving inspection checks from paperwork to sample, the sampling plan, the decision, and an Excel log by supplier.
- Supplier audit checklistA supplier process audit of 32 questions scored 0 to 3, with section scores, a rating and the findings.
- Supplier scorecardMonthly PPM, on-time delivery and SCAR measures turned into points, a weighted score and a rating per supplier.
- Receiving logA dock receiving log with quantities, damage, QC holds and putaway, plus a discrepancy report and dock-to-stock time.
- Warehouse safety inspection checklistThirty warehouse safety checks from aisles to fire exits, marked OK or Not OK, with an action for every finding.
- Pallet racking inspection checklistRack checks per aisle with a green, amber and red damage rating, and a damage log with repair dates.
- Pre-shipment inspection checklistThe last check before shipping: part, quantity, labels, packaging, paperwork and photos, then release.
- Material shortage logEvery part short with its need date, line impact, ETA and escalation, and counts by reason and supplier.
- Safety audit checklistThirty-four plant-wide safety checks answered Yes, No or N/A, scored by area, with a risk rating and an action for every No.
- Ergonomic risk assessment checklistScreen a task for 21 ergonomic risk factors, score how long each lasts, and rank tasks so the worst get controls first.
- Maintenance work order formOne form per maintenance job from request to handback, and a log that tracks response, completion and backlog by priority.
- Six big losses worksheetWhere a machine's planned time goes: the six big losses in minutes, ranked, with A, P, Q and OEE worked out.
- Andon response logEvery andon call with response and fix times, flags against your targets, and counts by type and station.
- Changeover checklist25 checks for every changeover, a record of planned and actual times, and a log of changeover time against target.
- Kanban sizing calculatorHow many kanban cards each loop needs, per part, with the change from today's cards and what the loop holds in days.
- Standard work audit checklist24 checks of a job against its written standard, ten timed cycles, and each gap sorted by cause before anyone acts.
- Defect check sheetTally defects by type and day, with units inspected, defect rates, a location sheet and the week's Pareto.
- TWI job breakdown sheetThe TWI Job Instruction breakdown of a job into important steps, key points and reasons, with a worked example and the four steps.
- Standard work combination tableOne operator's manual, machine, walk and wait time on a time chart against takt, with machine cycles and a process capacity sheet.
- Lead time worksheetProduction lead time from the inventory waiting at each step, value-added time and process cycle efficiency, plus an order traced from order to delivery.
- Maintenance KPI trackerMTBF, MTTR, availability and PM compliance per asset and month, plant figures from the totals, planned maintenance % and backlog in weeks.
- Daily huddle agendaA 15-minute start-of-shift stand-up in six timed blocks, with yesterday's SQCDP results, today's plan, actions and escalations.
- Water spider route plan (mizusumashi)A water spider's fixed route: stops with arrival times, what is delivered and collected, route time against the cycle, cart load and a trip log.
- Equipment criticality analysisAssets scored 1 to 5 on six criteria with your own weights, ranked and sorted into classes A, B and C with a safety override and a suggested maintenance strategy.
- Bottleneck analysis worksheetEffective capacity per station from cycle time, parallel units, availability and yield, the bottleneck, takt and utilization, a queue cross-check and the five focusing steps.
- QA matrix templateDefect modes against stations in flow order: where each is made and first caught, a weight × occurrence × detection score, an AA to C class and the escapes flagged.
- Fault tree analysis templateA drawing area with the FTA symbols, an event table with probabilities and minimal cut sets, and the gates worked out bottom-up in Excel.
- Is / is not analysis templateWhat, where, when and extent with is, is not, distinctions and changes, then each possible cause tested against every pair and ranked.
- 5G investigation sheetConfirm the facts before naming a cause: 5W1H, the five G's with 20 prompts, the gap against the principle and the standard, and the countermeasures.
- Breakdown analysis reportOne equipment breakdown from the stop to the 90-day check, plus a breakdown log with repeat flags, MTBF and MTTR by asset and a Pareto of causes.
- Heijunka box planner (production leveling)Weekly demand turned into containers a day, takt, pitch and slots, a leveled sequence of products and the heijunka box, with a check that the changeovers fit.
- 4M change management sheet (change point)A shift log of every change to Man, Machine, Material, Method or Design, the extra checks after it and when normal checks resume, with a change point board.
- Future state value stream map worksheetThe eight future-state questions worked through in order: takt, pitch, flow, supermarkets, the pacemaker and the mix, with an EPEI check and current against future lead time.
- Histogram templateReadings, bins set by the square root rule, a tally and counts, the spec limits drawn and the share out of spec, with the common shapes explained.
- Scatter diagram templateUp to 50 pairs with a group code, r and R², the least squares line, the quadrant count and r for each group.
- Gauge calibration logA gauge register with next due dates and status, a calibration record with as-found and as-left readings, and the steps when a gauge fails.
- Escalation matrix templateWho is called for each type of issue and after how long, with severity rules, contacts and an escalation log.
- Visual management audit checklist29 checks of whether anyone can tell normal from abnormal at a glance, scored by group, with a trend and actions.
- Quality alert formA quality alert to post at the line, a sign-off sheet for every shift, and a log of open, expired and closed alerts.
- TQM self-assessment templateThe eight TQM principles in 24 statements you can check on the floor, scored 0 to 4 by several people, with the spread, the top 3 gaps and an action plan.
- Obeya room plannerPlan the walls, owners, cadence, agenda and rules of an obeya, then run the weekly review of KPIs, problems, actions and milestones.
- Paper forms inventory (paperless manufacturing worksheet)Every paper form, checklist and log in one list: hours a month, who acts on it, how long the paper waits, and which forms to move first.
- Employee engagement survey templateA short anonymous pulse survey for shop floor staff: 14 statements in six drivers, two open questions, results by driver and team, and the actions.
- Safety cross calendarA month drawn as the green cross, colored each day by the most serious safety event, with totals and days since the last injury.
- Weekly maintenance schedule templateNext week's maintenance jobs, scheduled only when ready, loaded against each craft's hours by day, with schedule compliance and break-ins at week end.
- Scrum meeting agenda templateTimed agendas for the five scrum meetings, a sprint planning sheet, a retrospective sheet, and an Excel sprint backlog with a burndown.
- EPEI and batch size calculatorHow often each part can come round on a shared machine (EPEI) and how big each batch must be, from demand, cycle times and changeovers, now and after SMED.
- People, process, technology (PPT) assessmentCheck one change before go-live: 18 people, process and technology statements scored 1 to 4 by the people who will use it, the lowest element and the actions.
- Process capacity sheet templateEach machine in a part's routing with manual, auto and tool change time, its capacity per shift, and the step that limits the cell against demand.
- Jidoka worksheet (stop at abnormality)For one line or cell, every abnormality that should stop the work: how it is detected, how the work stops, who is called, the immediate fix and the root cause step, plus a log of real stops.
- Team charter templateA one-page charter for a standing team: purpose, scope, roles, the KPIs it owns, which decisions it makes itself, norms and cadence.
- Chaku-chaku line plannerPlan a load-load cell: time each machine, load and walk, check that every machine is ready when the operator comes back, compare the cell cycle with takt and size the crew.
- Standard operating procedure (SOP) templateA full SOP in the hierarchical step format, from purpose and scope to the steps, records, revision history and approvals, with review checks and an SOP register.
- X-bar and R control chart template25 subgroups with means and ranges, control limits from A2, D3 and D4, signal flags, both charts and a reaction log.
- Gage R&R study sheet10 parts, 2 or 3 appraisers, 2 or 3 trials: EV, AV, GRR, PV, %GRR and ndc by the average and range method.
- Root cause analysis templateOne report from problem statement to proof: containment, evidence, analysis, verified causes, actions and the effectiveness check.
- Safety pillar 90-day model area planThirteen weeks from the incident pyramid to safety standards on one model area, a KPI board, the day-90 gate and expansion waves.
- Quality control pillar 90-day model area planThirteen weeks from the QA matrix to the QM matrix on one model area, a KPI board, the day-90 gate and expansion waves.
- Autonomous maintenance 90-day model area planAM steps 0 to 3 on one model machine in 13 weeks, a KPI board, the day-90 gate and expansion waves for months 4 to 12.
- Professional maintenance (PM) 90-day model area planThirteen weeks from breakdown analysis to a running PM calendar on one model machine, a KPI board, the day-90 gate and expansion waves.
- Environment and energy pillar 90-day model area planThirteen weeks from waste and energy maps to area standards on one model area, a KPI board, the day-90 gate and expansion waves.
- Logistics and customer service pillar 90-day model area planThirteen weeks from the current-state map to pull on one model value stream, a KPI board, the day-90 gate and expansion waves.
- People development pillar 90-day model area planThirteen weeks from the skills matrix to trained cover on critical tasks in one model area, a KPI board, the day-90 gate and expansion waves.
- Early equipment management 90-day model area planThirteen weeks from lessons on current machines to a tracked start-up on one model equipment project, a KPI board, the day-90 gate and expansion waves.
- Cost deployment pillar 90-day model area planThirteen weeks from the loss map to costed, ranked projects in one model area, a KPI board, the day-90 gate and expansion waves.
- Cost per unit worksheet (manufacturing cost per good unit)One product's cost per good unit by materials, labor, machine and overhead, the gap to target, and which cost lever is worth most a year.
- Digital manufacturing readiness assessmentScore 24 statements on process, technology and people from 0 to 4, check the balance between them and rank the gaps by what matters in your plant.
- Manufacturing KPI dashboard templateWeekly plant numbers in, 14 KPIs out: OEE and its parts, first pass yield, scrap, on-time delivery, recordable rate, cost and absence, each against a target.
- RCM worksheet (failure mode and task selection)Failure modes classed as hidden, safety, operational or non-operational, then a task chosen for each: condition-based, discard, failure-finding, redesign or run to failure.
- Error-proofing verification log (daily master-sample check)Each poka-yoke device proved every day or week with a known-bad sample, with missed checks counted and the hours and parts at risk worked out when one fails.
- Training matrix template with expiry datesPeople by required trainings with expiry dates, OK, due, expired and missing flags, compliance by person and area, cover per training and a renewal list.
- Downtime reason codes template26 starter codes mapped to the six big losses, a log with drop-downs, a Pareto by code and by loss, and a code card for the line.
- Defect catalogue template with boundary samplesEvery defect with a definition, a class and the reason for it, measured accept and reject limits by zone, boundary samples, a defect log with DPU and Pareto, and an inspector agreement check.
- I-MR chart template (individuals and moving range)Up to 100 single readings with moving ranges, limits from a baseline, five run-rule flags, both charts, a second phase and a reaction log.
- Attribute control chart template (p, np, c and u charts)p, np, c and u charts in one workbook: a chart selector, a sample size check, limits for each subgroup, signal flags and four worked examples.
- Critical spare parts list and stocking levelsAssets ranked by consequence, each part classed and given a stocking policy, and min and max worked out from usage and lead time, with the downtime each stock-out would cost.
- Tier 2 meeting agenda and escalation sheetA 15-minute tier 2 agenda in ten timed blocks, fixed roles and rules, escalation triggers with time limits, and a log that ages every escalation and sends the answer back down.
- HACCP plan template: hazard analysis and CCP worksheetThe Codex 12 steps in one workbook: team and product, process steps checked on site, hazard analysis with the CCP decision tree, the CCP table with completeness checks, an allergen matrix and a verification schedule.
- Forklift operator training and evaluation recordPer-operator training and evaluation record, a register with three-year due dates and refresher triggers, and a weighted practical evaluation scoresheet.
- REBA worksheet (Rapid Entire Body Assessment)Score up to six postures with REBA: body-part drop-downs, Tables A, B and C as lookups, final score and action level, and a before and after comparison.
- Mock recall template: traceability exercise worksheetTrace a finished lot back to every input lot and forward to every first customer, reconcile the quantities against a tolerance and time it against your target.
- ISO 9001 internal audit checklist (production area)46 audit questions for the production floor in 11 processes, each with its ISO 9001:2015 clause, what evidence to look for and the sample to take, plus five defined grades, a findings log, a finding report and a summary by clause.
- ISO 45001 internal audit checklist44 audit questions for the plant floor in 16 safety topics, each with its ISO 45001:2018 clause, the evidence to look for and the sample to take, plus 12 worker interview prompts, a findings log and a summary by clause.
- Plan for every part (PFEP) templateOne row per part: supplier, pack, container, usage, lead time and locations, with ABC classes, market and line kanban counts and a lineside space check.
- Food plant GMP inspection checklist (21 CFR 117 subpart B)55 checks in the order of 21 CFR 117 subpart B, each citing its paragraph and saying what to look at, with a grade, finding, owner and due date; results by section and grade, a walk route and a bakery example.
- Master sanitation schedule with pre-op verificationA master list of cleaning tasks by area and equipment with frequency, chemical, lockout, who and next due date, a weekly on-time count, and the pre-operational verification log with a release step.
- Changeover matrix templateA from-to matrix of changeover minutes with the clean each transition needs (allergen, colour, format), and a weekly planner that totals the order and suggests a shorter one.
- Overhead crane inspection checklist: frequent and periodic34 crane checks tied to OSHA 1910.179: an operator's pre-shift card, frequent and periodic inspections with signed records, a deficiency and tag-out log, and a register of next due dates.
- Measurement uncertainty budget templateA GUM uncertainty budget: Type A and B rows, divisors by distribution, sensitivity coefficients, uc, νeff, k from the t-table, U, TUR and a guard band check.
- Maintenance job plan templateOne job planned on one sheet: steps and craft hours, parts checked against stock, tools, lockout and permits, documents, a ready check for the schedule, and technician feedback.
Can't find the template you need?
Tell us what you're looking for. We'll make it and send it to your inbox, free.
A shift handover sheet, a red tag log, a changeover checklist for one machine: if your team uses it on the floor, ask.