Stakeholder map template: power-interest grid and stakeholder list

A stakeholder map is a picture of the people who can affect a change or are affected by it, sorted by how much power they have over the outcome and how much interest they have in it. The usual form is the power-interest grid, usually credited to Aubrey Mendelow (1981): manage closely the people with high power and high interest, keep satisfied those with power but little interest, keep informed those with interest but little power, and monitor the rest. This template adds what a map alone leaves out: each person's stance now and the stance you need, what they need from the change, what they worry about, and the date of your next conversation with them. In the Excel file you score power and interest from 1 to 5 on the list and the Map sheet places each person in the right box, with a filled-in example. The PDF has the grid and the list to fill in by hand.

See the sheet before you downloadPDF, 2 pages. Also Excel

Free to use: print it, copy it and edit it for your team. Enter your name and work email once to download.

Stakeholder map templateA power-interest grid with four boxes, manage closely, keep satisfied, keep informed and monitor.
Power-interest gridManage closelyKeep satisfiedKeep informedMonitorStance now and neededNeeds and worriesNext conversationExample

Page 1 of the real file. PDF, 2 pages. Also Excel. See every page

When to use it

When to use a stakeholder map

  • In the first weeks of a new role, to decide who to meet first and what each person needs from you.
  • Before a kaizen event, a new SOP or a layout change, to find who can stop it and who has to live with it.
  • When a project stalls and you are not sure who is against it, or why.
  • Before the leadership meeting where a plan is decided, to plan the one to one conversations that come first.

How to fill it in

  1. 1

    List everyone who can affect the change or is affected by it

    Start wide: the sponsor, the managers who give people and time, finance, maintenance and quality, the supervisors on every shift, the operators who do the work, HR, and anyone outside the plant who has a say. Use roles if names are sensitive.
  2. 2

    Score power and interest from 1 to 5

    Power is how much they can change the outcome: approve, block, give or take people, time and money. Interest is how much the change affects them or how much they care. The Excel file puts each person in a box; scores of 3 or more count as high, and you can change that.
  3. 3

    Write the stance now and the stance you need

    Champion, supporter, neutral, skeptic or opposed. Not everyone has to become a champion; the gap between now and needed shows where your time goes.
  4. 4

    Write what they need and what they worry about

    In their words, not yours: no missed shipments, savings counted the way finance counts them, being asked rather than told. A worry you have not heard is a guess, so ask.
  5. 5

    Plan the next conversation with a date

    Meet the people in the manage closely box one to one before any meeting where the plan is decided. Update the stance after each conversation and look at the map again each week.

What is in the download

Stakeholder map template: every page of the PDF

All 2 pages, pictured from the file you download. The download also comes as Excel.

  1. Page 1 of 2 of the Stakeholder map template PDF: Stakeholder map
    PDF page 1 of 2Stakeholder map
  2. Page 2 of 2 of the Stakeholder map template PDF: Stakeholder list
    PDF page 2 of 2Stakeholder list
Back to the download buttons

A filled-in example

Illustrative, not a benchmark

Illustrative, from the Example sheets: a new CI manager maps the people around her first project, cutting changeover time on two presses. Roles, not real people.

  • Manage closely: the plant manager (sponsor, supporter now, champion needed) and the production manager (skeptic, worried the project takes people and gives nothing back), plus maintenance, quality and the day shift supervisor.
  • Keep satisfied: the plant controller, who needs savings counted the way finance counts them, HR and the corporate operations director.
  • Keep informed: the night shift supervisor, who wants to be asked rather than told, and the lead setter, who is worried about being filmed and judged.
  • Her first conversation is with the production manager, a day before she talks to the plant manager, with a plan that keeps shipments whole during the kaizen week.

Ten people on the map, each with a stance, a need, a worry and a date. The plant and the people are made up.

Common mistakes

  • Mapping only the people above you

    The operators and supervisors who do the work have low power on paper and decide in practice whether a change sticks. Put them on the map.

  • Guessing what people worry about

    Write what you heard them say. If you have not asked, the next conversation is the place to ask.

  • Meeting the skeptic in the big meeting

    A person who hears a plan for the first time in front of their peers has to defend their position. Talk one to one first.

  • Sharing the sheet

    Scores and stances are your own judgment about named people. Keep the map private and talk about the plan, not the scores.

Download the template

Free to use: print it, copy it and edit it for your team. Enter your name and work email once to download.

Run this template in LeanSuite

In LeanSuite each level's meeting runs as a series with its own cadence and agenda: owners prepare their item, KPIs fill in against target, and actions carry over to the next meeting.

See it in a 45-minute demo

FAQ

Stakeholder map template: common questions

  1. A picture of the people who can affect a change or are affected by it, sorted by their power over the outcome and their interest in it. The power-interest grid puts each person in one of four boxes: manage closely, keep satisfied, keep informed or monitor.

  2. High power and high interest: manage closely. High power and low interest: keep satisfied. Low power and high interest: keep informed. Low power and low interest: monitor. The grid is usually credited to Aubrey Mendelow (1981) and was made widely known by Johnson and Scholes' Exploring Corporate Strategy.

  3. List everyone who can affect the change or is affected by it, score each on power and interest, place them on the grid, then write each person's stance, what they need, what they worry about and the date of your next conversation. Talk one to one with the people in the manage closely box before the decision meeting.

  4. A stakeholder map is about influence and support: who can make or break the change and how they feel about it. A RACI matrix is about roles on the work: who is responsible, accountable, consulted and informed for each task. Most changes need both.

More free templates

All templates
Browse all 290 templates

Can't find the template you need?

Tell us what you're looking for. We'll make it and send it to your inbox, free.

A shift handover sheet, a red tag log, a changeover checklist for one machine: if your team uses it on the floor, ask.