New product line plan: from demand to takt, operators, stations, machines and ramp staffing

A new product line plan turns the demand for a product and its work content into the number of operators, stations, machines and people on the roster, and then into a staffing plan for the weeks of ramp-up. This template puts the whole chain on one page. You enter the available time a shift, the shifts a day, the work content, the stoppage factor, the absence rate and the machine cycle. The sheet works out, for five levels of demand, the takt time, the planned cycle time, the operators, the balance efficiency, the machines and the roster. It then splits the work into stations at the level you choose, and compares two ways of staffing the ramp: ramping the volume with the crew, or asking for the full demand from day one.

See the sheet before you downloadPDF, 2 pages. Also Excel

Free to use: print it, copy it and edit it for your team. Enter your name and work email once to download.

Page 1 of the new product line planAn inputs table, a table of staffing at five levels of demand, a station split and a ramp staffing table.
InputsTakt timePlanned cycle timeOperatorsBalance efficiencyMachines and rosterStation splitPlan A and Plan B ramp

Page 1 of the real file. PDF, 2 pages. Also Excel. See every page

When to use it

When to use the new product line plan

  • When a new product needs a line and someone has asked how many operators, stations and machines it takes.
  • When the demand is uncertain and you want to see what headcount each level of demand needs.
  • When you need a first station split to check that no station is longer than the planned cycle time.
  • When production and finance are planning the ramp and want to compare staffing the volume with staffing the full rate.
  • When one of the inputs changes, such as the absence rate or the work content, and you want to see what it does to the roster.

How to fill it in

  1. 1

    Enter the inputs

    Write the available time a shift after the breaks, the shifts a day, the work content in operator seconds at standard pace, the stoppage factor, the absence rate and the machine cycle time. Take the factors from your own records. A new line is rarely better than the old one in its first year.
  2. 2

    Enter five levels of demand

    Write five demands a day, from the low case to the high case. For each, the sheet gives the takt time, the planned cycle time after the stoppage factor, the operators (calculated and rounded up), the balance efficiency, the machines and the roster.
  3. 3

    Choose a level and split the work into stations

    Pick the demand level you will plan for. List the stations with what happens at each and its time. The sheet shows the spare seconds and whether each station is inside the planned cycle time, and the balance efficiency of the split.
  4. 4

    Read the machines and the roster

    A machine is a bottleneck if its cycle is longer than the planned cycle time, and the sheet adds machines as the demand rises. The roster adds the people for absence, so that a station is covered when someone is out.
  5. 5

    Enter the ramp efficiencies and the daily volumes

    For each week, write the efficiency the crew will reach and, for Plan A, the daily volume. The work content at that pace is the work content divided by the efficiency. Take the efficiencies from your last launch and from the pilot.
  6. 6

    Compare Plan A and Plan B

    Plan A ramps the volume and keeps the crew. Plan B asks for the full demand from day one. The operators needed in each week show what the difference costs, and where Plan B is not possible.

What is in the download

New product line plan: every page of the PDF

All 2 pages, pictured from the file you download. The download also comes as Excel.

  1. Page 1 of 2 of the New product line plan PDF: New product line plan
    PDF page 1 of 2New product line plan
  2. Page 2 of 2 of the New product line plan PDF: New product line plan: example
    PDF page 2 of 2New product line plan: example
Back to the download buttons

A filled-in example

Illustrative, not a benchmark

An illustrative example, not a customer: the LED work light line, 286 seconds of work content, 27,000 available seconds a shift (450 minutes), one shift, an 8 percent stoppage factor and 10 percent absence.

  • At 360 a day the takt is 75 seconds and the planned cycle time is 69. The work content divided by 69 is 4.14 operators, so 5, at 82.9 percent balance efficiency, and 6 on the roster.
  • The five demand levels give 3, 4, 5, 6 and 7 operators at 240, 300, 360, 450 and 540 a day, and 4, 5, 6, 7 and 8 on the roster.
  • The station split at 360 a day has five stations of 53 to 60 seconds, all inside 69, with a longest station of 60 seconds.
  • In week 1 at 55 percent efficiency and 120 a day, Plan A needs 2.51 operators' worth of time and Plan B needs 7.54, so 8.

The plan shows that the line needs five operators at the planned rate, that the ramp can start with three and grow, and that asking for the full rate in week 1 would need more than the line has. The product and the figures are made up to show the sheet at work.

Common mistakes

  • Dividing work content by takt and stopping there

    Takt is the customer's rate. The line is paced by the planned cycle time, which is takt after the stoppage factor, so the operators come from that.

  • Leaving out absence

    The operators at the line are not the people on the roster. Holidays, sickness and training mean a roster larger than the operators a shift needs.

  • Taking the stoppage factor from a brochure

    It is the share of the time you actually lose to downtime and shortages. Use your own figure from similar lines, and say what it covers.

  • Planning the ramp at full efficiency

    A new crew does not run at 100 percent in week 1. Use efficiencies from the pilot and from your last launch, and re-plan as the real ones come in.

  • Putting the allowance in twice

    If the work content already contains the allowance, do not take it out of the available time as well. State which way you counted.

Download the template

Free to use: print it, copy it and edit it for your team. Enter your name and work email once to download.

Run this template in LeanSuite

LeanSuite's Vision AI does the time study from one phone video of the process: it times every element, splits each operator's time into value-added, semi-value-added and non-value-added, and links each figure to its video frame for you to review and certify.

See it in a 45-minute demo

FAQ

New product line plan: common questions

  1. Divide the work content in operator seconds by the planned cycle time, and round up. The planned cycle time is the takt time reduced by the stoppage factor. In the example, 286 seconds of work divided by a planned cycle time of 69 seconds is 4.14, so five operators.

  2. Takt time is the available time divided by the customer demand. The planned cycle time is takt reduced by the share of time lost to stoppages, so the line finishes the demand even after the stops. At a takt of 75 seconds and an 8 percent stoppage factor it is 69 seconds.

  3. The work content divided by the number of operators times the planned cycle time. It shows how much of the paid time is used for work. With 286 seconds of work, five operators and a planned cycle time of 69 seconds it is 82.9 percent. The rest is waiting caused by uneven stations.

  4. Because people are absent. The roster is the operators needed in a shift, times the shifts, divided by one minus the absence rate, rounded up. With 5 operators, one shift and 10 percent absence it is 6. The extra person covers whoever is out.

  5. Plan A ramps the daily volume up over the weeks and keeps the crew, so the operators needed grow with the volume. Plan B is asked for the full rate from day one, with the same slower pace of work, so it needs far more operators early. The sheet shows both so the cost of each is visible.

More free templates

All templates
Browse all 312 templates

Can't find the template you need?

Tell us what you're looking for. We'll make it and send it to your inbox, free.

A shift handover sheet, a red tag log, a changeover checklist for one machine: if your team uses it on the floor, ask.