Time study report template: objective, method, standard time, findings and signatures

A time study report is the record of a study that someone can read, check and use a year later: what it was for, what was timed and how, the observations, the working from normal time to standard time, the checks that make it believable, what it showed about the job beyond the number, and what to do about it, with signatures. This template has nine sections on two pages. The Word file is for typing into; the PDF has the blank pages and a filled-in example for the junction box job, with a standard of 80.5 seconds a unit. Attach the observation sheet, the element breakdown, the method sheet and a photo of the workplace.

See the sheet before you downloadPDF, 4 pages. Also Word

Free to use: print it, copy it and edit it for your team. Enter your name and work email once to download.

The time study report templateA header block, then boxes for objective, scope, method and conditions, an observations table, the standard time working, findings and recommendations.
Objective and scopeMethod and conditionsObservations tableStandard time workingChecksFindingsRecommendations with ownersValidity and reviewFour signatures

Page 1 of the real file. PDF, 4 pages. Also Word. See every page

Filled-in Time study report template: a junction box study, 80.5 seconds a unit
The same sheet filled in with the worked example (page 3 of the PDF, illustrative numbers). Open full size (opens the picture in a new tab)

When to use it

When to use the time study report template

  • When a study is finished and the standard time has to be issued to planning, costing or the floor.
  • When the result will be challenged, so the method, the conditions and the working need to be on one page.
  • When a different analyst will repeat or update the study in a year.
  • When you want every study in the plant written up the same way.

How to fill it in

  1. 1

    State the objective and the scope

    The decision the study feeds, and who makes it. Where the cycle starts and ends, and what is in and out. Two readers would time the same thing.
  2. 2

    Record the method and the conditions

    Method sheet and revision, operator and time on the job, shift, timing method, cycles timed, what 100 means on the rating scale, the allowance and how it is applied, and the workplace. The standard is valid only for this method.
  3. 3

    List the observations and work out the standard time

    One row per element: the break point, readings used, average, rating and normal time. Then normal time, allowance and standard time per unit, units an hour at standard and standard hours per 100 units, with the working shown.
  4. 4

    Show the checks

    Cycles needed by the formula against cycles timed, readings left out and why, occasional elements and how often, and output on the floor against the standard.
  5. 5

    Write the findings, the recommendations and the validity

    What the study showed about the job beyond the number, each recommendation with an owner and a date, what the standard is valid for, what change means a re-study, and the review date. Then the signatures: analyst, supervisor, operator has seen the results, approved by.

What is in the download

Time study report template: every page of the PDF

All 4 pages, pictured from the file you download. The download also comes as Word.

  1. Page 1 of 4 of the Time study report template PDF: Time study report
    PDF page 1 of 4Time study report
  2. Page 2 of 4 of the Time study report template PDF: Time study report, continued
    PDF page 2 of 4Time study report, continued
  3. Page 3 of 4 of the Time study report template PDF: Time study report: example
    PDF page 3 of 4Time study report: example
  4. Page 4 of 4 of the Time study report template PDF: Time study report: example, continued
    PDF page 4 of 4Time study report: example, continued
Back to the download buttons

A filled-in example

Illustrative, not a benchmark

An illustrative report on the junction box study: twenty cycles, a standard of 80.5 seconds a unit.

  • Objective: set the standard time for junction box assembly on bench 3, so the production manager can fix the second shift headcount and rebalance line B.
  • Normal time is 70.0 seconds a unit, the 15% allowance adds 10.5, and the standard is 80.5 seconds, 44.7 units an hour or 2.24 standard hours per 100 units.
  • The check shows 11 cycles needed and 20 timed, one reading left out for a dropped screw, and floor output of about 45 an hour against 44.7.
  • The time in the system was 72 seconds, an estimate made before the new driver and fixture. Driving four screws is the longest element, 23.0 of the 65.0 seconds, so that is where a method change would pay first.

Four recommendations follow, each with an owner and a date: issue the standard, time the JB-240 separately, count dropped screws for a week and trial a screw presenter. The job, the people and the numbers are made up.

Common mistakes

  • Reporting the number without the method

    A standard time belongs to a described method. Without the method sheet revision and the conditions, nobody can tell when it has stopped being true.

  • Hiding the working

    Show each step from normal time to standard time, and state the allowance convention. A reader who cannot follow the sums will not trust the answer.

  • Findings that only repeat the table

    The numbers are in section 4 and 5. Use the findings to say what the study showed about the job: what is missing from the old estimate, what is large, what is rare but costly.

  • Recommendations with no owner or date

    A recommendation nobody owns does not happen. Name a person and a date for each, and put the review date on the report.

Download the template

Free to use: print it, copy it and edit it for your team. Enter your name and work email once to download.

Run this template in LeanSuite

LeanSuite's Vision AI does the time study from one phone video of the process: it times every element, splits each operator's time into value-added, semi-value-added and non-value-added, and links each figure to its video frame for you to review and certify.

See it in a 45-minute demo

FAQ

Time study report template: common questions

  1. State the objective and scope, record the method and conditions, list the observations, show the working from normal time to standard time, show the checks, then write the findings, recommendations with owners and dates, and the validity. End with signatures and attach the observation sheet and method sheet.

  2. The decision it feeds, the scope, the method sheet revision, operator, shift, timing method and cycles, the rating scale and allowance, the elements with average and normal times, the standard time and units an hour, the checks, findings, recommendations and who signed.

  3. Two pages is enough for most jobs, with the observation sheet, element breakdown, method sheet and a workplace photo attached. A reader should be able to see the standard, how it was built and what it is valid for on those two pages.

  4. The analyst, the supervisor of the area, a line to show the operator has seen the results, and the person who approves the standard. Where an agreement covers how standards are set, shared and challenged, follow it.

More free templates

All templates
Browse all 312 templates

Can't find the template you need?

Tell us what you're looking for. We'll make it and send it to your inbox, free.

A shift handover sheet, a red tag log, a changeover checklist for one machine: if your team uses it on the floor, ask.

By sending this form you agree to our Terms of Service and Privacy Policy.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.