Production readiness checklist: 36 checks before a new product goes into production

A production readiness checklist is the gate review before a new product starts regular production: a list of checks, each with the evidence that shows it is ready, reviewed by the people who will run the line. This template has 36 checks in nine groups: product and design, process and line, time and capacity, people and training, material and suppliers, quality, safety and ergonomics, documents and systems, and the launch plan. Eleven of the checks are gate lines, which must be ready for a Go. The others can go with an owner and a due date. The Excel file counts each group, shows the percent ready and gives the decision as Go, Go with conditions or No-go from the answers. The PDF has the checklist on two pages, and a summary example.

See the sheet before you downloadPDF, 3 pages. Also Excel

Free to use: print it, copy it and edit it for your team. Enter your name and work email once to download.

Page 1 of the production readiness checklistNine groups of checks with ready-when evidence, a gate column and boxes for ready, not ready and N/A.
36 checks in 9 groups11 gate linesReady when evidenceReady, Not ready, N/AOwner and dateSummary by groupPercent readyGo, Go with conditions, No-go

Page 1 of the real file. PDF, 3 pages. Also Excel. See every page

When to use it

When to use the production readiness checklist

  • When a new product is about to start regular production and someone has to say it is ready.
  • When the pilot has passed and you want to be sure nothing outside the line itself is missing.
  • When a customer requires a readiness or launch review before they accept the first shipment.
  • When launches go wrong in the same ways each time and you want a fixed list of what to check.
  • When the gate meeting runs on opinions and you want each line to have an answer and an owner.

How to fill it in

  1. 1

    Fill in the header and agree the date of the gate meeting

    Write the product, the line, the planned start of production and who reviews it. Set the review date a few days before the start so open lines can still be closed.
  2. 2

    Go through the lines with the evidence in hand

    Each line has a Ready when column: the evidence that makes it ready, such as a pilot record on file or a skills matrix with two names a station. Answer Ready only when you can see it.
  3. 3

    Use Not ready for anything that is open, and N/A only with a reason

    A line that is not ready gets an owner and a due date in the last column. Mark a line N/A only with a reason in the note. A gate line marked N/A is flagged for the meeting.
  4. 4

    Check the gate lines first

    Eleven lines are gates: released design, special characteristics, gauges, the pilot run, takt and capacity, trained operators, stopping the line, approved parts, risk assessment, ergonomics, and guarding and lockout. Any gate line that is not Ready means No-go.
  5. 5

    Take the decision at the meeting

    Go if every line is Ready or N/A. Go with conditions if the only open lines are not gates and each has an owner and a date. No-go otherwise. Sign it with the industrial engineer, production, quality and safety.
  6. 6

    Follow the open lines to closure

    Review the open lines at the daily launch meeting until each is ready. Keep the signed checklist with the pilot record: it is the evidence that the gate was held.

What is in the download

Production readiness checklist: every page of the PDF

All 3 pages, pictured from the file you download. The download also comes as Excel.

  1. Page 1 of 3 of the Production readiness checklist PDF: Production readiness checklist
    PDF page 1 of 3Production readiness checklist
  2. Page 2 of 3 of the Production readiness checklist PDF: Production readiness checklist, continued
    PDF page 2 of 3Production readiness checklist, continued
  3. Page 3 of 3 of the Production readiness checklist PDF: Production readiness checklist: example
    PDF page 3 of 3Production readiness checklist: example
Back to the download buttons

A filled-in example

Illustrative, not a benchmark

An illustrative example, not a customer: the LED work light line after its second pilot, reviewed on 29 January 2027, with the gate meeting on 1 February.

  • Thirty-six lines are answered: 32 are ready, 1 is N/A and 3 are not ready. The ready share is 91 percent of the lines that apply.
  • The three open lines are the tester that runs at 58 seconds against a rated 56, a station with one trained person, and a PFMEA missing two pilot defects. Each has an owner and a date.
  • The N/A line is traceability, because the product has no serial numbers, and the note says so.
  • No gate line is open and no open line is missing an owner or a date, so the decision is Go with conditions.

The summary shows each group's count and percent ready, lists the open lines with their owners and dates, and gives the decision. The product and the figures are made up to show the sheet at work.

Common mistakes

  • Ticking Ready on a promise

    Ready means the evidence exists. A promise to have the gauge study done is a Not ready with an owner and a date.

  • Going with conditions on a gate line

    A gate line is never a condition. If one is open, the answer is No-go until it closes.

  • Open lines with no owner or no date

    A line that nobody owns does not close. The sheet will not give a Go with conditions until every open line has both.

  • Using N/A to skip a hard line

    N/A is for a line that does not apply to this product, with the reason written. Used for a line that is hard, it hides the risk the checklist is there to show.

  • Holding the review after the first shipment is due

    A gate held at the last minute cannot stop a launch. Set the review early enough that a No-go can still be fixed.

Download the template

Free to use: print it, copy it and edit it for your team. Enter your name and work email once to download.

Run this template in LeanSuite

LeanSuite's Vision AI does the time study from one phone video of the process: it times every element, splits each operator's time into value-added, semi-value-added and non-value-added, and links each figure to its video frame for you to review and certify.

See it in a 45-minute demo

FAQ

Production readiness checklist: common questions

  1. A review held before a new product starts regular production, in which the team checks a fixed list of items, from the released design to trained operators and the launch plan, and decides whether the product can go. It is sometimes called a launch gate, a production readiness gate or a start of production review.

  2. Checks on the product and its design, the process and the line, the times and capacity, the people and their training, material and suppliers, quality, safety and ergonomics, documents and systems, and the launch plan. This one has 36 checks in nine groups, each with the evidence that makes it ready.

  3. A check that must be ready for a Go. Here 11 lines are gates, such as the pilot run having passed its criteria, takt and capacity being calculated, operators being trained and the risk assessment being done. If any gate line is not ready, the decision is No-go, and it cannot be waived by an owner and a date.

  4. Go means every line is ready or not applicable. Go with conditions means the only open lines are not gate lines and each has an owner and a due date. The product starts, and the open lines are followed at the launch meeting until they close.

  5. The people who will run and support the line: the industrial engineer, the production manager, quality and safety. The form has four signature lines. Your plant may add maintenance, supply chain or the customer's representative.

More free templates

All templates
Browse all 312 templates

Can't find the template you need?

Tell us what you're looking for. We'll make it and send it to your inbox, free.

A shift handover sheet, a red tag log, a changeover checklist for one machine: if your team uses it on the floor, ask.