New product time study plan: the seven studies from quote to steady state

A new product time study plan lays out every study a new product needs between the quote and steady state, so the times are measured at the right moment and each one reaches the decision it was meant for. This template has seven rows: the estimate at quote, prototype or mock-up timing, the pilot run or line trial, launch week, the day 30 study, the day 90 study that locks the standard, and the re-study after a change. For each it holds the planned start and end, the owner, the method, the sample, the deliverable and the decision it feeds. You enter the start of production, and the Excel sheet counts the dates from it, shows which studies are late, compares each result with the estimate and draws a Gantt chart. The PDF has a blank page with the suggested timing written in, and a filled example.

See the sheet before you downloadPDF, 2 pages. Also Excel

Free to use: print it, copy it and edit it for your team. Enter your name and work email once to download.

Page 1 of the new product time study planSeven studies with owner, method, sample, deliverable and decision columns, and a Gantt grid in weeks.
7 studiesDates from start of productionOwner and methodSample and deliverableDecision it feedsLate and done countsResult against the estimateGantt chart

Page 1 of the real file. PDF, 2 pages. Also Excel. See every page

When to use it

When to use the new product time study plan

  • When a new product is quoted and you want the study schedule agreed before the first part is built, not after.
  • When the only time anyone measures is the one at quote, and the standard is never looked at again.
  • When production, quality and finance each expect a different number at a different date and nobody owns the sequence.
  • When a launch is slipping and you need to see which study is late and what it holds up.
  • When a customer or auditor asks how the labor in the quote will be checked against what the line does.

How to fill it in

  1. 1

    Fill in the header and the start of production

    Write the product, the line, the planned owner and the takt time. Enter the planned start of production. Every date on the sheet counts from that day, so a late start moves all of them together.
  2. 2

    Set the planned start and end of each study

    The sheet suggests a start for each study as a number of days from the start of production and a length. Keep them or change them. Studies 1 and 2 run before launch, so those dates are negative: the estimate sits months ahead, the prototype timing weeks ahead.
  3. 3

    Name an owner and agree the method and the sample

    Put a name against each study, not a department. Check the method fits the study: video of every station for the pilot, a short rated study per station for day 30, the full study with agreed allowances for day 90. Write the sample, for example every unit of the run.
  4. 4

    Say which decision each study feeds

    The last column is the reason for the study: quoted labor, design changes, the release to production, the rebalance, the lock of the standard and the headcount. If a study feeds no decision, drop it or move it.
  5. 5

    Update the status and enter each result

    As studies finish, mark them done and enter the result in seconds a unit. Launch week gives output counts and not a standard, so leave its result empty. The Excel sheet then shows how many studies are late and how far each result is from the estimate.
  6. 6

    Re-read the plan at every study

    Open it before each study and after it. The result of one study resets the next: a prototype that comes in 10 percent over the estimate changes what you look for in the pilot.

What is in the download

New product time study plan: every page of the PDF

All 2 pages, pictured from the file you download. The download also comes as Excel.

  1. Page 1 of 2 of the New product time study plan PDF: New product time study plan
    PDF page 1 of 2New product time study plan
  2. Page 2 of 2 of the New product time study plan PDF: New product time study plan: example
    PDF page 2 of 2New product time study plan: example
Back to the download buttons

A filled-in example

Illustrative, not a benchmark

An illustrative example, not a customer: the CP-40 coolant pump, with production starting on 1 March 2027 and a takt time of 120 seconds, five weeks after the start.

  • Studies 1 to 5 are done. The estimate at quote was 482 seconds a unit. The prototype built at 566 and came down to 539 after two design changes.
  • The pilot gave a working figure of 548 seconds and the day 30 study gave a provisional 536. Launch week gave an output count: 850 seconds a unit near unit 640 against a plan of 814.
  • Two studies ran late, by 2 days and by 1 day. The next one is the day 90 study and standard lock, planned to start on 26 May 2027.
  • The Gantt chart shows the done studies in grey and the planned ones in dark, in weeks from the start of production.

One page shows that the standard is 536 seconds against a quote of 482, which study found each difference, and that the standard is not locked yet. The product, the dates and the figures are made up to show the sheet at work.

Common mistakes

  • Timing the product once, at quote

    The quote estimate is a forecast. Prototype, pilot, day 30 and day 90 studies are what turn it into a standard, and each answers a different question.

  • Counting dates from the planning start

    When the start of production moves, every study moves. Count from that one date and a slip shows up in every row at once.

  • Locking the standard at launch week

    Launch week shows output counts for a crew still learning. The standard is locked at day 90, with the full study and the allowances agreed beforehand.

  • Studies with no owner and no decision

    A study that nobody runs does not happen, and one that feeds no decision is a cost. Each row needs a name and a purpose.

  • Skipping the re-study after a change

    A new fixture, a changed method or a design revision moves the standard. Re-study only the changed elements and compare them with the day 90 record.

Download the template

Free to use: print it, copy it and edit it for your team. Enter your name and work email once to download.

Run this template in LeanSuite

LeanSuite's Vision AI does the time study from one phone video of the process: it times every element, splits each operator's time into value-added, semi-value-added and non-value-added, and links each figure to its video frame for you to review and certify.

See it in a 45-minute demo

FAQ

New product time study plan: common questions

  1. Seven, in order: an estimate at quote, prototype or mock-up timing, the pilot run or line trial, launch week counts, a day 30 study, a day 90 study that locks the standard, and a re-study after any change. Each one feeds a different decision, from the quoted labor to the final headcount.

  2. At about day 90, after the crew has learned the job and the early problems are fixed. A time taken in the pilot or in launch week includes learning and stops, so it is a provisional figure. The day 30 study gives a provisional standard and day 90 locks it.

  3. Because everything else moves with it. If the start slips by two weeks, the pilot, launch week and the day 30 and day 90 studies all move by two weeks. One reference date means the plan is changed in one cell, and a study that runs late shows against the date it was set for.

  4. It depends on the spread of the element times and the accuracy you want, so work it out for each element rather than using a fixed number. The time study sample size calculator on this site gives the number of cycles from a pilot sample, and the plan has a column to write it in.

  5. No. It covers only the studies and the decisions they feed. Put the start of production and the study dates into the launch schedule, and keep this page as the place where the results are collected and compared with the estimate.

More free templates

All templates
Browse all 312 templates

Can't find the template you need?

Tell us what you're looking for. We'll make it and send it to your inbox, free.

A shift handover sheet, a red tag log, a changeover checklist for one machine: if your team uses it on the floor, ask.