Man-machine chart template, with the number of machines formula

A man-machine chart, also called a worker-machine chart or multiple activity chart, draws what an operator and one or more machines are each doing against a single time scale, so idle time on either side shows as a gap. This template has the chart for one operator and up to three machines: you type the length of each interval and pick a state (working or idle for the operator; running, loading or idle for a machine), and the sheet adds up the cycle time, the working and idle time and the utilization of each. A second sheet answers the question the chart usually raises, how many machines one operator can run, with n = (l + m) / (l + w), and compares the whole number below the answer with the one above: cycle time, idle time, pieces per hour and cost per piece for each. A filled example with two machining centers comes with it. The PDF is the same chart to fill in by hand.

See the sheet before you downloadPDF, 2 pages. Also Excel

Free to use: print it, copy it and edit it for your team. Enter your name and work email once to download.

Page 1 of the man-machine chartTime, operator and three machine columns, a summary of one cycle and the machines formula.
Common time scaleOperator and 3 machinesIdle timeUtilization of eachCycle totalNumber of machines formulaCost per pieceFilled example

Page 1 of the real file. PDF, 2 pages. Also Excel.

When to use it

When to use a man-machine chart

  • When an operator stands and watches a machine run, and you want to know how much of the cycle that is.
  • Before you give an operator a second or third machine, to see whether the cycle has room for it.
  • When a machine waits for its operator and nobody can say for how long.
  • When you plan a cell and need the cycle, the output and the labor cost per piece for different numbers of machines.
  • After a time study has split the job into manual time, machine time and walking, and you need to see them together.

How to fill it in

  1. 1

    Pick one repeating cycle

    Start at a point you can see, such as the start of loading machine 1, and end when everything is back where it began. Time the manual work, the automatic run and the walking: a time study sheet or a video gives you these.
  2. 2

    Write one row per interval

    Start a new row each time the operator or any machine changes what it is doing. Type the length of the interval; the start and end times add up down the sheet, so every column shares one time scale.
  3. 3

    Say what each is doing and pick a state

    For the operator: working or idle. For each machine: running, loading (stopped while it is loaded or unloaded) or idle. The cells turn dark, purple or pink, so the chart reads like the hand-drawn one.
  4. 4

    Read the summary

    Cycle time, working time, loading time, idle time and utilization for the operator and each machine. Utilization is working time divided by cycle time. A switch decides whether loading counts as machine working time: say which way you counted.
  5. 5

    Work out the number of machines

    On the second sheet type l (loading and unloading), m (automatic run) and w (walking and other operator time per machine). The answer is rarely a whole number, so the sheet compares the whole number below it with the one above.
  6. 6

    Chart the proposed method

    Draw the cycle again with the extra machine or the new task in it. The formula assumes a fixed round; the chart shows whether the round really works.

What is in the download

Every page and every sheet of the Man-machine chart template

2 PDF pages and 4 Excel sheets, as they come. The worked examples use made-up numbers.

Excel, 4 sheets

The pictures show the top of each sheet with the formulas worked out; the file keeps every row.

The formula

How many machines one operator can run

For machines of the same kind served in a fixed round, which textbooks call synchronous servicing. With fewer machines than the answer the operator waits; with more, the machines wait.

  • Machines the operator could serve

    Formula
    (l + m) / (l + w)
    In the example (l 1.0, m 4.0, w 0.5 min)
    5.0 / 1.5 = 3.33
  • Cycle time with n machines

    Formula
    The longer of l + m and n x (l + w)
    In the example (l 1.0, m 4.0, w 0.5 min)
    5.0 min with three, 6.0 min with four
  • Operator idle time per cycle

    Formula
    Cycle time minus n x (l + w)
    In the example (l 1.0, m 4.0, w 0.5 min)
    0.5 min with three, none with four
  • Idle time of each machine per cycle

    Formula
    Cycle time minus (l + m)
    In the example (l 1.0, m 4.0, w 0.5 min)
    None with three, 1.0 min with four
  • Cost per piece

    Formula
    (K1 + n x K2) x cycle time / n
    In the example (l 1.0, m 4.0, w 0.5 min)
    5.83 with three, 6.75 with four

A filled-in example

Illustrative, not a benchmark

Illustrative example, not a customer: one operator runs two machining centers on a pump housing.

  • Loading and unloading takes 1.0 minute per machine, the automatic cycle is 4.0 minutes, and checking the part and walking to the next machine takes 0.5 minute.
  • The chart has five intervals. The operator works for 3.0 minutes of the 5.0 minute cycle and waits for 2.0, a utilization of 60%. Each machine runs for 4.0 minutes and is being loaded for 1.0, so it runs 80% of the cycle.
  • The formula gives (1.0 + 4.0) / (1.0 + 0.5) = 3.33 machines. With three, the cycle stays 5.0 minutes, the operator's idle time falls to 0.5 minute and the cell makes 36 pieces an hour.
  • With four, the cycle stretches to 6.0 minutes and every machine waits 1.0 minute for the operator. Output rises to 40 an hour, but at 0.50 a minute for the operator and 1.00 a minute for each machine the cost per piece is 6.75 against 5.83 with three.

Three machines is the answer on cost, and the chart for three still has to be drawn to check the walk. The times and rates are made up to show how the sheet works.

Common mistakes

  • Charting from memory

    The gaps are the point of the chart, and nobody remembers gaps. Time the cycle or film it, and chart what happened.

  • Treating machine watching as work

    An operator standing at a running machine is idle on this chart unless the method calls for a check during the run. Chart it as idle and decide what to do with the time.

  • Adding machines on the formula alone

    The formula assumes identical machines and a fixed round. Where machines stop at random, a stopped machine waits while the operator is busy elsewhere, and the real loss is larger.

  • Comparing charts that count loading differently

    Some charts count the time a machine is being loaded as working time and some do not. The sheet has a switch for it. Write down which way each chart was counted.

Download the template

Free to use: print it, copy it and edit it for your team. Enter your name and work email once to download.

Run this template in LeanSuite

LeanSuite's Vision AI does the time study from one phone video of the process: it times every element, splits each operator's time into value-added, semi-value-added and non-value-added, and links each figure to its video frame for you to review and certify.

See it in a 45-minute demo

FAQ

Man-machine chart template: common questions

  1. A man-machine chart records what an operator and one or more machines are doing during one cycle, in side by side columns against a common time scale. Each interval is marked as working or idle, so you can see where the operator waits for the machine and where the machine waits for the operator. It is also called a worker-machine chart or a multiple activity chart.

  2. For identical machines served in a fixed round, n = (l + m) / (l + w): loading and unloading time plus automatic running time, divided by loading and unloading time plus the operator's walking and other time per machine. With l = 1.0, m = 4.0 and w = 0.5 minutes, n = 5.0 / 1.5 = 3.33. Then compare the cost per piece with three machines and with four.

  3. Add up the working time in one cycle and divide by the cycle time, separately for the operator and for each machine. An operator who works 3.0 minutes of a 5.0 minute cycle has a utilization of 60%. A machine that runs 4.0 minutes of the same cycle runs 80% of it. Say whether loading time is counted as machine working time.

  4. A multiple activity chart is the general form: any number of workers, machines or pieces of equipment, each in its own column on one time scale. A man-machine chart is the common case of one operator and one or more machines. A chart of a crew working together, such as a changeover team, is usually called a gang chart.

  5. Yes, in the cells. Each interval is a row, and the state you pick colors the cell: dark for working or running, purple for loading, pink for idle. Row heights do not scale with time, so read the start and end columns for the scale. The PDF example is drawn to scale, and the blank PDF has a column to shade by hand.

More free templates

All templates
Browse all 312 templates

Can't find the template you need?

Tell us what you're looking for. We'll make it and send it to your inbox, free.

A shift handover sheet, a red tag log, a changeover checklist for one machine: if your team uses it on the floor, ask.

By sending this form you agree to our Terms of Service and Privacy Policy.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.