Pilot run record: what to time and write down, and how to decide pass or repeat

A pilot run record is the form that captures what happens when a new product is built in production conditions for the first time, so that the decision to release it, to release it with conditions or to repeat the run rests on written evidence. This template has nine parts. It starts with the conditions of the run and the exit criteria with targets written before the run. Then it has a station time grid with one row for each unit, a stop log, a defect log, element times with the cycles timed, departures from the work instruction, and an issue list with an owner and a date for every item. The Excel file works out the averages by station, the learning rate, the share of run time stopped, whether each criterion passes and the decision. The PDF has the form and a filled example, and the Word file is the form to edit.

See the sheet before you downloadPDF, 6 pages. Also Excel and Word

Free to use: print it, copy it and edit it for your team. Enter your name and work email once to download.

Page 1 of the pilot run recordConditions of the run with yes and no boxes, the seven exit criteria with target and result, and a decision line.
Run conditions7 exit criteriaStation times by unitLearning rateStop logDefect logElement times and cyclesIssue listDecision

Page 1 of the real file. PDF, 6 pages. Also Excel and Word. See every page

When to use it

When to use the pilot run record

  • When a new product is going through its first run on the production line, with production tooling and production parts.
  • When the release to production needs written evidence and not an opinion that the pilot went well.
  • When one person will log the run and you want the form to tell them what to write down and when.
  • When a customer or an auditor asks for the record of a pilot and what was done about it.
  • When a second pilot is needed and you want to compare it with the first against the same criteria.

How to fill it in

  1. 1

    Agree the exit criteria and write the targets before the run

    Seven criteria are listed: rate in the last hour, first pass yield, stations inside the planned cycle time, elements with enough cycles, open safety findings, work instructions that match the method, and open high priority issues. Write a target for each before the run, with the people who will sign.
  2. 2

    Check the conditions and write down what is not production standard

    Answer the seven conditions: criteria agreed, line trial closed, production tooling, production parts, work instructions, logs ready and operators briefed. If a part is a substitute or a tool is temporary, write it down: the result means less.
  3. 3

    Log every unit, stop and defect as it happens

    One person logs and does nothing else. Station times go in the grid in the order the units are built, each stop gets a start, an end, the station and the cause, and each defect gets where it was made, where it was found and why.
  4. 4

    Time the elements of the last units

    For the last units, when the crew has settled, record each element's time. Write how many cycles were timed against the number you need. Elements without enough cycles are not a basis for the standard yet.
  5. 5

    Write the issue list while the run is fresh

    Each issue gets a station, a type, a priority, an owner and a due date. Mark safety and ergonomic issues high. A high priority safety issue is never a condition of release.
  6. 6

    Enter the counts, read the result and decide

    Enter the counts for the criteria. The sheet compares each result with its target and shows pass or fail. Choose pass, pass with conditions, or repeat the pilot, and have the engineer, the supervisor and quality sign.

What is in the download

Pilot run record: every page of the PDF

All 6 pages, pictured from the file you download. The download also comes as Excel and Word.

  1. Page 1 of 6 of the Pilot run record PDF: Pilot run record
    PDF page 1 of 6Pilot run record
  2. Page 2 of 6 of the Pilot run record PDF: Pilot run record: times and logs
    PDF page 2 of 6Pilot run record: times and logs
  3. Page 3 of 6 of the Pilot run record PDF: Pilot run record: elements and issues
    PDF page 3 of 6Pilot run record: elements and issues
  4. Page 4 of 6 of the Pilot run record PDF: Pilot run record: example
    PDF page 4 of 6Pilot run record: example
  5. Page 5 of 6 of the Pilot run record PDF: Pilot run record: example, times and logs
    PDF page 5 of 6Pilot run record: example, times and logs
  6. Page 6 of 6 of the Pilot run record PDF: Pilot run record: example, elements and issues
    PDF page 6 of 6Pilot run record: example, elements and issues
Back to the download buttons

A filled-in example

Illustrative, not a benchmark

An illustrative example, not a customer: the first pilot of an LED work light line, 40 units, five stations against a planned cycle time of 69 seconds.

  • Station 3 averages 80.2 seconds over units 31 to 40 against 69. The other four stations are inside the planned time.
  • 40 of 210 minutes were lost to stops, 19.0 percent of run time. The first pass yield was 82.5 percent and the rate in the last hour 54.2 percent of plan.
  • 12 of 14 elements have the 10 cycles needed. 9 high priority issues are open and 2 of them are safety or ergonomic.
  • All seven criteria fail, so the decision is to repeat the pilot after the fixes. The learning rate fitted over the 40 units is about 91 percent.

The record shows that the line is learning as the ramp plan assumed, that station 3 is a method and part problem and not a learning problem, and that the two safety items must close before another run. The product, the line and the figures are made up.

Common mistakes

  • Writing the targets after the run

    A target written after the results are in moves to wherever the results are. Write and sign the criteria before the first unit.

  • Running the pilot on substitute parts or temporary tools

    Then the result describes something that will not run in production. If you cannot avoid it, list it on the form and read the result with that in mind.

  • Letting the logger also fix the problems

    A person who stops to help stops writing. Keep one person on the log and give the fixing to someone else, so that every stop and defect is recorded.

  • Treating a slow station as learning

    A station that does not settle after the other stations have is not learning. Look at its elements: if they stay slow, the cause is the method, the part or the fixture.

  • Passing with a safety issue as a condition

    Conditions are for items with an owner and a date that can wait. A high risk safety or ergonomic finding is closed before work goes on.

Download the template

Free to use: print it, copy it and edit it for your team. Enter your name and work email once to download.

Run this template in LeanSuite

LeanSuite's Vision AI does the time study from one phone video of the process: it times every element, splits each operator's time into value-added, semi-value-added and non-value-added, and links each figure to its video frame for you to review and certify.

See it in a 45-minute demo

FAQ

Pilot run record: common questions

  1. A pilot run is a first run of a new product on the production line, with production tooling, parts from the production suppliers and the operators who will build it. Its purpose is to prove that the product can be built to the planned rate and quality, and to find what must be fixed before release.

  2. The conditions of the run, the time of each station for each unit, every stop with its cause, every defect with where it was made and found, the element times of the last units, any departure from the work instruction, and an issue list with owners and dates. The pilot run record has a place for each.

  3. They are the pass marks the run must meet before the product is released, agreed and written before the run. This record lists seven: rate in the last hour, first pass yield, stations inside the planned cycle time, elements with enough cycles, open safety findings, work instructions that match the method, and open high priority issues.

  4. It is the share of the time left each time cumulative output doubles. The sheet fits it between the average unit total of the first five units and the last five. It is indicative only, and it is wrong if units were built out of order or the method changed during the run.

  5. Repeat it after the fixes. Failing is information: the record shows which criteria failed and which issues caused it. Write the conditions for the repeat, give each fix an owner and a date, and run the second pilot against the same criteria so the two can be compared.

More free templates

All templates
Browse all 312 templates

Can't find the template you need?

Tell us what you're looking for. We'll make it and send it to your inbox, free.

A shift handover sheet, a red tag log, a changeover checklist for one machine: if your team uses it on the floor, ask.