Time study planning checklist: 20 checks to clear before the stopwatch starts

A time study planning checklist is the list of things that must be true before you time a job: the decision the result feeds is written down, the scope is fixed, there is one written method, the conditions are normal, the timing method and number of cycles are chosen, the operators and union have been told, and the owner of the standard has approved. This one is a single page of 20 checks in five groups, each with a note on what Ready looks like and an answer of Yes, No or N/A. One No means the study is not ready: fix the line, then book the study. Page 2 of the PDF, and the Example tab of the Excel file, show the plan for a junction box job checked three days ahead.

See the sheet before you downloadPDF, 2 pages. Also Excel

Free to use: print it, copy it and edit it for your team. Enter your name and work email once to download.

The time study planning checklistA header block, then 20 checks in five groups with a Ready when column, Yes, No and N/A boxes and a note column.
20 checks in 5 groupsWhat Ready looks likeYes, No or N/ACount and verdictSign-off linesFilled example

Page 1 of the real file. PDF, 2 pages. Also Excel.

Filled-in Time study planning checklist: a junction box study with one line still open
The same sheet filled in with the worked example (page 2 of the PDF, illustrative numbers). Open full size (opens the picture in a new tab)

When to use it

When to use the planning checklist

  • A few days before any stopwatch or video time study, so there is time to fix what comes up.
  • When a request lands and you want to know if the job is ready to study or needs method work first.
  • When a new analyst is learning to run a study and needs to see what experienced people check.
  • When a standard is challenged later and you need to show the conditions it was set under.

How to fill it in

  1. 1

    Fill in the header and the decision

    Write the job, station, product, date and shift, the analyst and who asked. Then write the decision the result feeds, in one sentence, with the name of the person who will use it. A study with no decision behind it is rarely worth the time.
  2. 2

    Answer each line Yes, No or N/A

    Walk the job and look; do not answer from memory. N/A is allowed, but write the reason in the note column, for example No union on site.
  3. 3

    Treat every No as work to do

    A No is not a failure. It is the list of what to fix before the watch starts: write the method down, tell the operators, choose the shift. The Excel file counts the answers and gives the verdict for you.
  4. 4

    Get the supervisor and the owner of the standard to sign

    The supervisor agrees the date before the operators are told. The person who owns the standard approves the plan. Union or works council notice goes before the operators hear.
  5. 5

    Keep the signed sheet with the study

    It shows the conditions the standard was set under: the method revision, the shifts, the planned cycles. When the job changes, it tells you what to re-check.

A filled-in example

Illustrative, not a benchmark

An illustrative plan: the junction box assembly study, checked three days before the study date.

  • The decision is the line balance and headcount for the second shift, used by the production manager.
  • The job has 3,000 labor hours a year and a new driver and fixture since January, so a study is worth it.
  • The method sheet is revision C and 15 cycles were watched on two shifts before the plan was signed.
  • Line 7, product mix, is a No: the JB-240 variant runs on Thursdays, so a Thursday sitting is added to the plan.

19 of 20 lines are Yes or N/A and one is No, so the verdict reads Not ready: 1 line is a No. The fix is to book the Thursday sitting, and then the study can go ahead. The job, the people and the numbers are made up to show how the sheet is used.

Common mistakes

  • Planning on the morning of the study

    Notice to operators, the union and the supervisor takes days. A plan filled in at the bench finds the problems after the time is booked.

  • Assuming the method is the written method

    If operators do the job three ways, the study measures all three. Watch the job on the floor and check it against the method sheet first.

  • Picking the allowance and the rating pace afterwards

    Choosing them after you have seen the numbers invites a result you wanted. Write both down before the first cycle.

  • Telling the operators last

    People told on the day assume the worst and work carefully, slowly and by the book. Tell them in person, at least a day ahead, what is measured, why, and what the result will not be used for.

Download the template

Free to use: print it, copy it and edit it for your team. Enter your name and work email once to download.

Run this template in LeanSuite

LeanSuite's Vision AI does the time study from one phone video of the process: it times every element, splits each operator's time into value-added, semi-value-added and non-value-added, and links each figure to its video frame for you to review and certify.

See it in a 45-minute demo

FAQ

Time study planning checklist: common questions

  1. Define the job and the decision it feeds, settle one written method, choose the operator and the shifts, tell the people involved, split the job into elements, time enough cycles, rate the pace, add allowances and compute the standard time. This checklist covers the first half, the part most studies skip.

  2. A written decision the study feeds, a fixed scope, one current method that operators follow, normal conditions, a chosen timing method, a planned number of cycles, a qualified operator who agreed, notice given to supervisors and any union, and an owner who approved the plan.

  3. Rank jobs by labor hours a year, or look for a trigger: a new product, a method or tooling change, a quote, a line balance or a challenged standard. A job with few hours and no trigger usually does not need one.

  4. The analyst, the supervisor of the area and the owner of the standard, who is often the industrial engineering or production manager. Where an agreement covers work measurement, the union or works council is told before the operators are.

More free templates

All templates
Browse all 312 templates

Can't find the template you need?

Tell us what you're looking for. We'll make it and send it to your inbox, free.

A shift handover sheet, a red tag log, a changeover checklist for one machine: if your team uses it on the floor, ask.

By sending this form you agree to our Terms of Service and Privacy Policy.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.