Planning operators and stations for a new line: from demand to headcount
Short answer
Operators needed = work content of one unit divided by the time you have per unit, rounded up. With 286 seconds of work and 69 seconds per unit, that is 4.14, so 5 operators at 5 stations, and a roster of 6 to cover absence.
Start from demand. Takt time is available time divided by demand. Take your expected stoppages off takt to get a planned cycle time. Divide the work content of one unit by that planned cycle time and round up: that is the number of operators, and on a manual line the number of stations. Check the work really splits into that many stations without breaking the build order, check each machine's cycle against the same time, then divide by one minus your absence rate for the roster. During ramp-up people are slower than standard, so staff the weeks before standard separately.
Last reviewed:
The chain from demand to headcount
From demand to headcount in seven numbers
Example numbers- Demand360 a dayOne shift of 27,000 s
- Takt time75 s27,000 / 360
- Planned cycle time69 s75 x (1 minus 0.08)
- Work content286 s14 steps from the routing
- Operators, calculated4.14286 / 69
- Operators on the line5Round up, then check the stations fit
- Roster65 / (1 minus 0.10) = 5.56
4.14 operators is four people and 14% of a fifth. The fifth is on the line all day, so 59 seconds of every unit is spare. The dashed sixth is the roster's cover for absence, not a person standing by.
Sizing a line is a short chain of sums, and each one feeds the next. Demand and working time give takt. Takt less your losses gives the time each unit really has. Work content divided by that time gives people. People plus absence gives the roster.
On a new line every input is an estimate, which is the reason to lay the chain out plainly. When the forecast moves or the pilot shows the work content was 20 seconds light, you want to change one number and see the headcount change, not rebuild the plan.
| Step | Formula | On the example line |
|---|---|---|
| Available time | Shift time minus breaks and meetings when the line stops for them | 480 minus 30 = 450 min = 27,000 s |
| Takt time | Available time / demand | 27,000 / 360 = 75 s |
| Planned cycle time | Takt x (1 minus stoppage factor) | 75 x (1 minus 0.08) = 69 s |
| Work content | Sum of the operator time of every operation | 286 s |
| Operators, calculated | Work content / planned cycle time | 286 / 69 = 4.14 |
| Operators on the line | Round up, then check the stations fit | 5 |
| Balance efficiency | Work content / (operators x planned cycle time) | 286 / (5 x 69) = 82.9% |
| Machines of each type | Demand / (available time x (1 minus stoppage factor) / machine cycle), rounded up | 360 / 443 = 0.81, so 1 tester |
| Roster | Operators on the line / (1 minus absence rate), rounded up | 5 / 0.90 = 5.56, so 6 |
The stoppage factor and the absence rate are yours to set, from your own downtime and attendance records. The 8% and 10% here are example values, not typical ones.
Some textbooks write the operator sum another way: N = R x total standard minutes / E, where R is the rate needed in units a minute and E is the efficiency you expect. It is the same sum. Here R is 360 / 450 = 0.8 units a minute, the work is 4.77 standard minutes and E is 0.92, so N = 0.8 x 4.77 / 0.92 = 4.14.
The basics of each term are on their own pages: takt time, how many operators a line needs for the same sum on a line that already runs, and line balancing for how to group the work.
The five inputs, and how good each one has to be
| Input | Where it comes from | Watch for |
|---|---|---|
| Demand per day, by period | The sales forecast or the customer's release, as a low, likely and high figure | A single number. Ask for the range and for the launch curve month by month |
| Available time | The shift pattern you plan to run, less the breaks and meetings the line stops for | Counting breaks twice: once here and again as an allowance in the times |
| Work content | The routing from process planning, operator time only | Unattended machine time added in, and small steps such as unpacking left out |
| Stoppage factor | The downtime, shortage and quality-hold record of the most similar line you run | A round guess. A new line is rarely better than the old one in its first year |
| Absence rate | Your attendance records: holidays, sickness, training | Using the plant average for a shift or season that is known to be worse |
Work content is the input most likely to be wrong, and it is usually wrong on the low side. If the times came from predetermined times or a mock-up, say so and carry a range. The guide on estimating cycle time for a new product covers how. Then run the sums at the low and the high figure. If both give the same number of operators, the estimate is good enough. If they straddle a whole person, you know what the pilot run has to settle.
Decide once where each allowance lives. If the element times are standard times they already include personal and fatigue allowance, so do not take the same minutes out of available time unless the whole line stops for breaks. Whichever way you choose, a loss should appear in the chain exactly once.
How to plan the line, step by step
Sizing a new line in seven steps
- 1
Fix the demand and the available time
- 2
Set the planned cycle time
- 3
Divide work content by the planned cycle time
- 4
Round up and test the split
- 5
Check every machine
- 6
Size the roster
- 7
Run it again for the other demand levels and for the ramp-up weeks
- 1
Fix the demand and the available time
Agree the daily demand for the period you are staffing and the shift pattern. Work out takt. Write down the low and high demand as well.
- 2
Set the planned cycle time
Take your stoppage factor off takt. This is the time each station really has, and the number the line is balanced to.
- 3
Divide work content by the planned cycle time
Keep the decimal. It tells you how close you are to needing one person fewer or one more.
- 4
Round up and test the split
Group the operations into that many stations in an order the build allows, with every station at or under the planned cycle time. If it can't be done, change the method or add a station.
- 5
Check every machine
For each machine, compare the time it is tied up per unit with the planned cycle time. Over means a second machine or a faster one.
- 6
Size the roster
Divide the operators on the line by one minus the absence rate and round up, for each crew. Add the people the line needs who are not at a station: material handling, team leader, quality.
- 7
Run it again for the other demand levels and for the ramp-up weeks
One table for the range of demand, one for the weeks before the crew reaches standard. Those two tables are what the launch meeting needs.
Worked example: 360 units a day, 5 operators
The line builds the LED work light from the process planning guide: 14 steps and 286 seconds of operator time. The plan is one shift and 360 lights a day. It is illustrative.
Takt is 27,000 / 360 = 75 seconds. With an 8% stoppage factor the planned cycle time is 69 seconds. Work content over that is 286 / 69 = 4.14, so 5 operators.
Now the test: do 14 steps split into 5 stations of 69 seconds or less without breaking the build order? They do.
| Station | Steps | What happens there | Station time | Spare against 69 s |
|---|---|---|---|---|
| 1 | O-2, O-3, O-4 | Build the LED module | 60 s | 9 s |
| 2 | I-1, O-7, O-8 | Test the module, build the handle | 59 s | 10 s |
| 3 | O-1, O-5, O-6 | Housing, LED module in, driver board | 56 s | 13 s |
| 4 | O-9, O-10 | Handle on, bezel on | 58 s | 11 s |
| 5 | I-2, O-11, O-12 | Final test, label, pack | 53 s | 16 s |
| Total | 14 steps | 286 s | 59 s |
Station is one operator's share of the work. The longest station, 60 s, is the pace the line can actually hold.
Balance efficiency is 286 / (5 x 69) = 82.9%. The other 17.1% is the 59 seconds of spare shown in the last column. Machines next: the tester is tied up 56 seconds a unit, under 69, so one is enough. It can pass 27,000 x 0.92 / 56 = 443 units a day.
The roster: 5 / (1 minus 0.10) = 5.56, so 6 people trained on this line for one crew. The sixth is not a spare pair of hands standing by. It means six people can each run at least a couple of the five stations, so a holiday or a sick day does not stop the line.
Rounding: what to do with 4.14 operators
You can't staff 0.14 of a person, so the sum rounds up and the difference becomes waiting. At 360 a day the line pays for 5 x 75 = 375 seconds of labour per light and uses 286 of them. That is 76% of paid time spent on work content. The size of the decimal tells you which way to push.
What 4.14 operators means in seconds
Example numbers- Work content
- Spare time in the stations
- Set aside for stoppages (8% of takt)
- Work that does not fit
| The sum gives | What it means | What to do |
|---|---|---|
| Just over a whole number, such as 4.14 | One operator is mostly waiting | Look for the seconds that would get you under: 4 operators need work content of 4 x 69 = 276 s, so 10 s has to go. Or give the spare time real work, such as feeding parts or the next sub-assembly |
| Around the middle, such as 4.5 | Rounding up wastes half a person, rounding down needs overtime every day | Round up and use the spare for off-line work, or share an operator with a neighbouring line |
| Just under a whole number, such as 4.9 | A good fit with little margin | Round up and check the longest station. There is no slack if an element was underestimated |
Do not round down and hope. A line staffed with 4 where the sum says 4.14 has to find 14% of a person every single day, and it finds it in overtime or in skipped checks. And do not hide the decimal by quietly loosening the stoppage factor until the sum comes out whole.
There is a second trap. The sum gives the least number of operators, and it assumes the work divides freely. Real operations come in lumps and have to follow the build order, so the stations may not fit even when the total does. The split in the table above was found by trying every allowed grouping. Do the same on yours with a yamazumi chart or the method in the line balancing guide, before the headcount goes into a budget.
Before and after: demand rises from 360 to 540 a day
Six months in, the forecast is 540 a day on the same shift. Nothing about the product has changed, so the work content is still 286 seconds. Everything else moves.
| Line item | Before: 360 a day | After: 540 a day |
|---|---|---|
| Takt time | 75 s | 50 s |
| Planned cycle time (8% stoppages) | 69 s | 46 s |
| Operators, calculated | 4.14 | 6.22 |
| Operators and stations | 5 | 7 |
| Station times | 60, 59, 56, 58, 53 s | 40, 40, 41, 36, 46, 46, 37 s |
| Balance efficiency | 82.9% | 88.8% |
| Spare time per unit | 59 s | 36 s |
| Paid labour per unit (operators x takt) | 375 s | 350 s |
| Units per operator hour | 9.6 | 10.3 |
| Testers needed (one passes 443 a day) | 1 | 2 |
| Roster for one crew (10% absence) | 6 | 8 |
The seven-station split is O-2 and O-3, O-7 and O-1, O-4 and O-8, I-1 and O-5, O-6 and O-9, O-10 and I-2, O-11 and O-12.
The same 286 seconds of work, split five ways and then seven
Example numbersBefore
360 a day, 5 operators
- Planned cycle time 69 s
- Takt 75 s
- Operators, calculated
- 4.14
- Balance efficiency
- 82.9%
- Units per operator hour
- 9.6
- Testers (one passes 443 a day)
- 1
- Roster for one crew
- 6
Paid per unit 375 s: work 286, spare 59, stoppages 30
After
540 a day, 7 operators
- Planned cycle time 46 s
- Takt 50 s
- Operators, calculated
- 6.22
- Balance efficiency
- 88.8%
- Units per operator hour
- 10.3
- Testers (one passes 443 a day)
- 2
- Roster for one crew
- 8
Paid per unit 350 s: work 286, spare 36, stoppages 28
Demand went up by half and operators by two fifths, from 5 to 7, because the rounding wasted less. Labour per unit fell from 375 to 350 seconds. That is common: a line is cheapest per unit just below the point where it needs one more person.
Three things in the table would have been missed by a plan that only scaled headcount. The tester: at 46 seconds a unit, one tester tied up for 56 seconds can't keep up, so a second has to be ordered. The margin: two of the seven stations sit at exactly 46 seconds, so any element that runs long will show at once. And the stations themselves: all seven are new groupings, which means new work instructions, new training and a new layout for parts. A demand change is a small relaunch.
Absence, utilisation and the other allowances: count each once
Most staffing plans that come out wrong added the same loss twice or left one out. Each loss has one place in the chain.
| Loss | Where it goes | Why there |
|---|---|---|
| Personal needs and fatigue | In the element times, as the allowance in the standard time. Or out of available time, if the whole line stops for breaks | It is part of doing the work at a pace a person can hold all day |
| Line stoppages: breakdowns, shortages, quality holds | Off takt, as the stoppage factor, to give the planned cycle time | The line still owes the same units, so it has to run faster while it is up |
| Changeovers, where the line runs more than one product | Out of available time | The line makes nothing during a changeover |
| Scrap and rework | On demand: units to start = good units needed / yield | Scrapped units used up the same work content |
| Absence: holidays, sickness, training | On the roster | It changes how many people you need on the books, not how the line is balanced |
| Operators not yet at standard | On the work content, week by week during ramp-up | The same step takes a new operator longer |
Utilisation needs a plain definition before anyone quotes it. On this page it is work content divided by paid operator time: 286 / 375 = 76% at 360 a day. A plan that shows 100% has no room for a dropped screw. A plan in the low 70s is paying for a lot of waiting and should say what that time is for.
Plan for a range of demand, not one number
The forecast for a new product is the least reliable number in the plan. So work out the staffing at several demand levels and design the line so it can move between them without a rebuild.
| Demand a day | Takt | Planned cycle time | Operators, calculated | Operators | Balance efficiency | Testers | Roster |
|---|---|---|---|---|---|---|---|
| 240 | 112.5 s | 103.5 s | 2.76 | 3 | 92.1% | 1 | 4 |
| 300 | 90 s | 82.8 s | 3.45 | 4 | 86.4% | 1 | 5 |
| 360 | 75 s | 69 s | 4.14 | 5 | 82.9% | 1 | 6 |
| 450 | 60 s | 55.2 s | 5.18 | 6 | 86.4% | 2 | 7 |
| 540 | 50 s | 46 s | 6.22 | 7 | 88.8% | 2 | 8 |
Each row was checked for a station split that fits. One tester passes 443 units a day, so 450 a day already needs the second.
Headcount moves in steps, demand does not
Example numbers- Operators on the line
- Calculated: demand / 86.9
- Paid waiting from rounding
Four design choices make moving between these rows cheap.
- Lay the line out so people can cover more than one station: a U shape or stations close enough to step between, with no fixed seats and nothing that traps an operator in place.
- Write a balance for each staffing level before launch, as a set of work instructions per level, so going from 5 to 6 operators is a planned switch.
- Train wider than the line needs. A skills matrix with every operator on at least two stations is what lets the roster number work.
- Buy or reserve space for the machine that runs out first. On this line that is the tester, and the table says at what demand.
Once the line runs, rebalancing from real times is quicker than from estimates. LeanSuite's Line Balancing builds the yamazumi from a video of the line and compares it with takt.
Ramp-up staffing: the weeks before standard
The 286 seconds is the time for trained operators at standard pace. In the first weeks the same work takes longer, so the sum has one more term: divide the work content by the efficiency you expect that week. At 55% efficiency the light needs 286 / 0.55 = 520 seconds of operator time, not 286.
That leaves two ways to plan the launch. Ramp the volume and hold the crew, or hold the volume and add people.
| Week | Expected efficiency | Work content at that pace | Plan A: daily volume | Plan A: operators needed | Plan B: operators needed for 360 a day |
|---|---|---|---|---|---|
| 1 | 55% | 520 s | 120 | 2.51 | 7.54, so 8 |
| 2 | 70% | 409 s | 200 | 3.29 | 5.92, so 6 |
| 3 | 85% | 336 s | 280 | 3.79 | 4.88, so 5 |
| 4 | 95% | 301 s | 360 | 4.36 | 4.36, so 5 |
| 5 | 100% | 286 s | 360 | 4.14 | 4.14, so 5 |
The efficiency column is an assumption for the example. Set yours from the pilot run and from how your last launch actually went.
Two ways to staff the first five weeks
Example numbers- Plan A: volume ramps 120, 200, 280, 360, 360 a day
- Plan B: 360 a day throughout, rounded up
- Plan B needs more than the planned crew
- Planned crew of 5
Plan A keeps the full crew of 5 on the line from the first day while the schedule climbs from 120 to 360. In week 1 the schedule needs only 2.51 operators' worth of time, and the rest is where training, problem solving and the daily launch meeting fit. Plan B asks for 360 from day one, which takes 8 people in week 1 and 6 in week 2. Three of those are temporary. They learn the job and are gone within a fortnight.
Plan A is nearly always the better launch, and it needs sales to agree a launch curve. If the customer needs full volume on day one, build stock ahead on Plan A before the start date. Use Plan B's numbers to show what the alternative costs.
Where the efficiency numbers come from, and how to turn a learning rate into a weekly plan, is in ramp-up plan and the learning curve. The first real evidence comes from the pilot run.
Where the sums stop working
- Machine-paced lines. If a machine sets the rate and people tend it, staff from the tending tasks and how many machines one person can cover, not from work content over takt.
- Mixed models. Use the weighted average work content across the mix to size the crew, then check the heaviest model against the planned cycle time, because that one unit still has to fit.
- Long-cycle and project work. When one unit takes hours, staff from total hours per week against hours available, and expect the learning curve to dominate.
- Work that can't be split. If one operation is longer than the planned cycle time, no rounding fixes it. Split the operation, run two stations in parallel or change the method.
- Very low demand. Under about two operators the line is one person doing everything, and the question becomes skills and cover, not balance.
And the sums say nothing about who. A line of 5 new hires and a line of 5 people who built the last product are different lines for the first two months. Operators also tend to distrust headcount worked out from a spreadsheet. Show them the chain, tell them which numbers are estimates, and tell them the times will be studied on the real job with them in the room, as in how to conduct a time study. A crew that has seen the sum is far more likely to tell you where it is wrong.
Common mistakes
- Dividing by takt with no stoppage factor. The line then has to be perfect to make the number.
- Counting a loss twice: breaks out of available time and again as an allowance.
- Rounding the operators and stopping there. The split into stations is the real test.
- Sizing people and forgetting machines. The tester, the oven or the press runs out before the crew does.
- One demand number. The forecast will move, so the plan should already say what happens when it does.
- Staffing launch week at standard efficiency.
- Leaving out the people who are not at a station: material handling, the team leader, rework.
Templates and tools for staffing a new line
- Operator staffing calculator: the chain on this page as a workbook, with your own factors.
- Takt time calculator and line balancing calculator: the first two sums.
- Yamazumi chart template: stack each station's elements against the planned cycle time.
- Process capacity sheet: the machine check, station by station.
- Cross-training plan: turn the roster number into named people and stations.
- Learning curve and ramp-up workbook: the weekly plan for the weeks before standard.
- New product time study playbook: which study to run at each stage of the launch.
Go deeper
This page is the short version. These guides cover each part in full.
- Takt Time in JIT: Matching Production to DemandWhy the line is paced to the customer and what changes when takt changes.
- Yamazumi Chart: What It Is and How to Make One in 7 StepsStacking each operator's work against takt to see whether the split fits.
- Cell Design for JIT: Flow and Layout PlanningLaying the stations out so the crew can flex between staffing levels.
- Why One Employee Absence Shuts Down Production LinesWhat goes wrong when the roster has the right number of people and the wrong spread of skills.
All our articles on this subject are in the value stream mapping and flow topic.
Free templates and tools
- Operator staffing calculatorTakt, work content, the operators a line needs, a check of your station plan and the roster with absence cover, from your own demand and element times.
- Process capacity sheet templateEach machine in a part's routing with manual, auto and tool change time, its capacity per shift, and the step that limits the cell against demand.
- Cross-training plan templateWho is learning which task, from and to which level, by when, and how many are qualified on each task.
- Skills matrix templatePeople by tasks on a 0 to 4 scale, coverage and gaps per task and shift, and a training plan that closes them.
- Learning curve and ramp-up workbookBoth learning curve models side by side, a fit from your own observed hours, batch hours, the unit that reaches standard and a weekly ramp plan.
- Takt time calculatorThe pace a line must hit to meet customer demand, from shift time, breaks and daily demand.
- Line balancing calculatorLine efficiency, balance delay and the minimum number of stations from station times and takt.
- Cycle time calculatorCycle time against takt, units per hour, capacity per shift and the gap to daily demand.
- Shift schedule plannerTen shift patterns on real dates: calendar for each crew, hours a week, weekends off, coverage and the weeks over 40 hours.
Doing this in LeanSuite
Line Balancing
Drop in a video of your line and get a Yamazumi chart, a takt comparison and rebalancing recommendations.
See Line BalancingTime and Motion Study
Film the station and the AI times every element on a timeline that links to the video, split into value-added, necessary and waste.
See Time and Motion Study
See it on your own lines
Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.
FAQ
Questions about planning operators and stations for a new line
Divide the work content of one unit by the time available per unit, then round up. Time per unit is takt time, less an allowance for stoppages. For example, 286 seconds of work with a 75 second takt and 8 percent stoppages gives 286 / 69 = 4.14, so 5 operators. Then check that the work splits into 5 stations that each fit.
The theoretical minimum is total work content divided by the cycle time the line is balanced to, rounded up. On a manual line that equals the number of operators. It is a minimum, not a promise: operations come in lumps and must follow the build order, so test the split with a precedence diagram or a yamazumi chart before fixing the number.
Capacity is the time available divided by the time the slowest resource needs per unit. For a balanced manual line, take available time, remove expected stoppages and divide by the longest station time. With 27,000 seconds a shift, 8 percent stoppages and a longest station of 60 seconds, capacity is 24,840 / 60 = 414 units a shift.
Divide the time the machine is available by the time it is tied up per unit, including loading and unloading. A tester that takes 16 seconds to load and unload and runs for 40 seconds is tied up 56 seconds a unit. With 27,000 seconds a shift less 8 percent stoppages, it passes 24,840 / 56 = 443 units.
There are three that go together. Takt time = available time / demand. Operators = work content / planned cycle time, rounded up. Output = available time x (1 minus stoppage share) / longest station time. Takt says how fast you must go, the operator sum says who you need, and the output sum says what the line as built can really make.
Up, unless you can remove enough work to get under the lower whole number. Rounding down leaves the line short every day, and the gap comes out as overtime or missed checks. If the sum is just over a whole number, look for the few seconds of waste that would let you run with one fewer, or give the spare time real work.
Divide the operators the line needs by one minus your absence rate and round up. Five operators at a 10 percent absence rate is 5 / 0.90 = 5.56, so six trained people for each crew. Use your own attendance records for the rate, and make sure the extra people are trained on several stations, not one.
Divide the work content by the efficiency you expect each week before dividing by the time per unit. At 55 percent efficiency, 286 seconds of work takes 520. Then choose: keep the planned crew and raise the daily volume week by week, or hold full volume and add temporary people. Ramping the volume is usually cheaper and trains the crew that stays.
Related guides and tools
- How many operators a line needs: the same sum on a line that already runs
- Line balancing: how to group the work into stations, with two rules worked by hand
- Takt time: the formula, examples and what to do when demand changes
- Process planning for a new product: where the work content comes from
- Ramp-up plan and the learning curve: staffing the weeks before standard
- New product introduction for industrial engineers: the whole launch
More method guides
- The 6 Ms of production
- Poka-yoke
- Model area 90-day plans
- Moving from Excel to one system
- Reducing machine downtime: a worked month
- Andon
- Cycle time vs lead time, worked through
- Root cause analysis
- How many operators a line needs
- Reducing scrap and rework: a worked month
- Unsafe acts and unsafe conditions
- Just culture
- Stop-work authority
- Material review board (MRB)
- Nonconformance and NCRs
- Problem solving methods
- Quad chart
- OEE calculation
- Quality assurance vs quality control
- SOP meaning and format
- Job hazard analysis
- Near miss reporting
- Fishbone diagram
- Pareto chart
- Histogram
- Control chart
- What is a gemba walk
- What is lead time
- What is operational excellence
- How to improve product quality
- Preventive vs predictive maintenance
- Kanban
- FMEA
- PDSA cycle
- Safety moments
- Just-in-time manufacturing
- Kaizen
- 5S
- Total quality management (TQM)
- CAPA (corrective and preventive action)
- Layered process audit (LPA)
- Lean tools
- Lockout tagout (LOTO)
- A3 problem solving
- Preventive maintenance
- APQP
- High reliability organization (HRO)
- Manufacturing KPIs
- Quality metrics
- Practical problem solving
- CMMS
- Risk assessment
- Production efficiency
- Total productive maintenance (TPM)
- Reliability-centered maintenance (RCM)
- Hierarchy of controls
- Personal protective equipment (PPE)
- Emergency action plan
- Safety signs
- Warehouse safety
- ISO 9001
- SIPOC diagram
- Rolling action item list (RAIL)
- Pugh matrix
- Flowchart
- Project charter
- ISO 9001:2026
- Fleet maintenance
- IATF 16949
- AS9100
- ISO 14001
- ISO 45001
- One point lesson
- Standard work
- Meeting cadence
- OSHA penalties and the top 10 cited standards
- OSHA 300A summary
- SMART goals examples for manufacturing
- Year-end review for manufacturing plants
- 2027 goals for a manufacturing plant
- Lean manufacturing principles
- Toyota Production System
- 5W1H
- 5 Whys
- Continuous improvement
- Takt time
- DMAIC
- PDCA
- 8D problem solving
- Prioritization matrix
- Gemba walk questions
- 5W1H questions
- Layered process audit questions
- 5S audit questions
- Difficult conversations at work
- How to talk to an employee about poor performance
- How to resolve conflict between employees
- High performer, bad attitude
- How to get employees to follow procedures
- Resistance to change on the shop floor
- Influence without authority for CI, quality and safety people
- Quality vs production: the hold against the ship date
- Hard savings vs soft savings
- How to handle a customer quality complaint call
- 30 60 90 day plan for a manufacturing manager
- First 90 days in a new manufacturing role
- New supervisor training: the first 90 days
- Night shift supervisor
- Engineer to manager in manufacturing
- What to do after a serious workplace accident
- Disagree and commit: disagreeing with your boss in a plant
- How to deliver bad news to your boss
- How to present audit findings to management
- How to get leadership buy-in for continuous improvement
- How to ask for more headcount or resources
- How to ask for a promotion in manufacturing
- PPE compliance
- Language barriers on the shop floor
- Train the trainer in manufacturing
- Contractor safety management
- Return to work after an injury
- Attendance conversation with an employee
- Managing former peers after a promotion
- Managing older or more experienced employees
- Inheriting a team
- How to delegate as a supervisor
- Holding supervisors accountable
- How to tell employees about layoffs or a shift change
- How to deny a raise request or a promotion
- Time and motion study
- How to conduct a time study
- Standard time
- Work sampling
- SMED
- Line balancing
- Yamazumi chart
- Ergonomic assessment in manufacturing
- Spaghetti diagram
- Time study vs motion study vs method study
- Why do a time study
- How to plan a time study
- How to break a job into elements
- How many cycles to time
- Stopwatch time study
- Time study mistakes
- Time study vs work sampling
- Value added vs non value added
- Labor losses in manufacturing
- New product time study playbook
- How to estimate cycle time for a new product
- New product introduction for industrial engineers
- Process planning for a new product
- Pilot run and line trial
- Ramp-up plan and the learning curve
- Workstation design
- Designing a future workstation
- Time study and ergonomic study in one pass
- Predetermined motion time systems (PMTS)
- MTM (Methods-Time Measurement)
- MOST and MODAPTS
- Therbligs and motion economy
- RULA assessment
- REBA assessment
- RULA vs REBA
- NIOSH lifting equation
- Production capacity calculation
- Precedence diagram
- Labor efficiency and labor variance
- Labor cost and quoting with time standards
- SMV and SAM in garment manufacturing
- From time study to standard work
- Standard work combination table
- Standard work vs SOP vs work instruction
- Standard WIP
- Updating standard work after an improvement
- Time study from video
- Time study app or software
- Man-machine chart
- Timing long-cycle and team work
- Time study in a union plant
- History of time and motion study
- Golden zone (power zone)
- Workstation assessment
- Reach envelope and work area study
- Standing, seated and sit-stand workstations
- Line-side material presentation
- Time study in automotive assembly
- Time study in electronics assembly
- Time study in CNC machining
- Time study in metal fabrication and welding
- Time study in plastics injection molding
- Time study in warehouse operations
- Time study in garment manufacturing
- Time study in maintenance work
- Time study in aerospace assembly and MRO
- Time study in food and beverage manufacturing
- Time study examples
- Historical and machine data as time standards
- Line balancing examples
- How to measure cycle time
- Manpower planning from standard time
- Bottleneck analysis from a time study
- Standard work examples
- U-cells and one-piece flow
- Flow process chart and operation process chart
- Two-handed process chart
- 3P production preparation process
- Plant layout basics
- Design for assembly
- Time study, PFMEA, control plan and work instructions
- Explaining a time study to a worried operator
- The observer effect in time studies
- Time standards and incentive pay
- Seven wastes vs eight wastes
- Job safety analysis (JSA)
- JSRA (job safety risk assessment)
- JSA vs JHA vs JSRA
- Job safety analysis from video
- HIRA (hazard identification and risk assessment)
- Management of change (MOC)
- Safe work method statement (SWMS)
- Permit to work (PTW)
- Pre-task plan (PTP)
- Field level risk assessment (FLRA)
- Safety observation
- Safety walk