Planning operators and stations for a new line: from demand to headcount

Short answer

Operators needed = work content of one unit divided by the time you have per unit, rounded up. With 286 seconds of work and 69 seconds per unit, that is 4.14, so 5 operators at 5 stations, and a roster of 6 to cover absence.

Start from demand. Takt time is available time divided by demand. Take your expected stoppages off takt to get a planned cycle time. Divide the work content of one unit by that planned cycle time and round up: that is the number of operators, and on a manual line the number of stations. Check the work really splits into that many stations without breaking the build order, check each machine's cycle against the same time, then divide by one minus your absence rate for the roster. During ramp-up people are slower than standard, so staff the weeks before standard separately.

Last reviewed:

The chain from demand to headcount

From demand to headcount in seven numbers

Example numbers
  1. Demand360 a dayOne shift of 27,000 s
  2. Takt time75 s27,000 / 360
  3. Planned cycle time69 s75 x (1 minus 0.08)
  4. Work content286 s14 steps from the routing
  5. Operators, calculated4.14286 / 69
  6. Operators on the line5Round up, then check the stations fit
  7. Roster65 / (1 minus 0.10) = 5.56
4.14 operators drawn as peopleFour people filled in, a fifth filled to 14 percent, and a sixth in dashed outline for absence cover.

4.14 operators is four people and 14% of a fifth. The fifth is on the line all day, so 59 seconds of every unit is spare. The dashed sixth is the roster's cover for absence, not a person standing by.

Each number comes from the one before it. The sum asks for 4.14 operators, the line gets 5, and the roster needs 6 trained people to keep 5 at the stations through holidays and sickness. Change the demand and every number after it moves.

Sizing a line is a short chain of sums, and each one feeds the next. Demand and working time give takt. Takt less your losses gives the time each unit really has. Work content divided by that time gives people. People plus absence gives the roster.

On a new line every input is an estimate, which is the reason to lay the chain out plainly. When the forecast moves or the pilot shows the work content was 20 seconds light, you want to change one number and see the headcount change, not rebuild the plan.

The sums, in order (example values are illustrative)
StepFormulaOn the example line
Available timeShift time minus breaks and meetings when the line stops for them480 minus 30 = 450 min = 27,000 s
Takt timeAvailable time / demand27,000 / 360 = 75 s
Planned cycle timeTakt x (1 minus stoppage factor)75 x (1 minus 0.08) = 69 s
Work contentSum of the operator time of every operation286 s
Operators, calculatedWork content / planned cycle time286 / 69 = 4.14
Operators on the lineRound up, then check the stations fit5
Balance efficiencyWork content / (operators x planned cycle time)286 / (5 x 69) = 82.9%
Machines of each typeDemand / (available time x (1 minus stoppage factor) / machine cycle), rounded up360 / 443 = 0.81, so 1 tester
RosterOperators on the line / (1 minus absence rate), rounded up5 / 0.90 = 5.56, so 6

The stoppage factor and the absence rate are yours to set, from your own downtime and attendance records. The 8% and 10% here are example values, not typical ones.

Some textbooks write the operator sum another way: N = R x total standard minutes / E, where R is the rate needed in units a minute and E is the efficiency you expect. It is the same sum. Here R is 360 / 450 = 0.8 units a minute, the work is 4.77 standard minutes and E is 0.92, so N = 0.8 x 4.77 / 0.92 = 4.14.

The basics of each term are on their own pages: takt time, how many operators a line needs for the same sum on a line that already runs, and line balancing for how to group the work.

The five inputs, and how good each one has to be

What you need before you start, and where to get it for a line that does not exist yet
InputWhere it comes fromWatch for
Demand per day, by periodThe sales forecast or the customer's release, as a low, likely and high figureA single number. Ask for the range and for the launch curve month by month
Available timeThe shift pattern you plan to run, less the breaks and meetings the line stops forCounting breaks twice: once here and again as an allowance in the times
Work contentThe routing from process planning, operator time onlyUnattended machine time added in, and small steps such as unpacking left out
Stoppage factorThe downtime, shortage and quality-hold record of the most similar line you runA round guess. A new line is rarely better than the old one in its first year
Absence rateYour attendance records: holidays, sickness, trainingUsing the plant average for a shift or season that is known to be worse

Work content is the input most likely to be wrong, and it is usually wrong on the low side. If the times came from predetermined times or a mock-up, say so and carry a range. The guide on estimating cycle time for a new product covers how. Then run the sums at the low and the high figure. If both give the same number of operators, the estimate is good enough. If they straddle a whole person, you know what the pilot run has to settle.

Decide once where each allowance lives. If the element times are standard times they already include personal and fatigue allowance, so do not take the same minutes out of available time unless the whole line stops for breaks. Whichever way you choose, a loss should appear in the chain exactly once.

How to plan the line, step by step

Sizing a new line in seven steps

  1. 1

    Fix the demand and the available time

  2. 2

    Set the planned cycle time

  3. 3

    Divide work content by the planned cycle time

  4. 4

    Round up and test the split

  5. 5

    Check every machine

  6. 6

    Size the roster

  7. 7

    Run it again for the other demand levels and for the ramp-up weeks

Steps 4 and 5 are the checks that catch a headcount that works on paper and not on the floor.
  1. 1

    Fix the demand and the available time

    Agree the daily demand for the period you are staffing and the shift pattern. Work out takt. Write down the low and high demand as well.

  2. 2

    Set the planned cycle time

    Take your stoppage factor off takt. This is the time each station really has, and the number the line is balanced to.

  3. 3

    Divide work content by the planned cycle time

    Keep the decimal. It tells you how close you are to needing one person fewer or one more.

  4. 4

    Round up and test the split

    Group the operations into that many stations in an order the build allows, with every station at or under the planned cycle time. If it can't be done, change the method or add a station.

  5. 5

    Check every machine

    For each machine, compare the time it is tied up per unit with the planned cycle time. Over means a second machine or a faster one.

  6. 6

    Size the roster

    Divide the operators on the line by one minus the absence rate and round up, for each crew. Add the people the line needs who are not at a station: material handling, team leader, quality.

  7. 7

    Run it again for the other demand levels and for the ramp-up weeks

    One table for the range of demand, one for the weeks before the crew reaches standard. Those two tables are what the launch meeting needs.

Worked example: 360 units a day, 5 operators

The line builds the LED work light from the process planning guide: 14 steps and 286 seconds of operator time. The plan is one shift and 360 lights a day. It is illustrative.

Takt is 27,000 / 360 = 75 seconds. With an 8% stoppage factor the planned cycle time is 69 seconds. Work content over that is 286 / 69 = 4.14, so 5 operators.

Now the test: do 14 steps split into 5 stations of 69 seconds or less without breaking the build order? They do.

Illustrative: the work light line at 360 a day, 5 stations against a 69 s planned cycle time
StationStepsWhat happens thereStation timeSpare against 69 s
1O-2, O-3, O-4Build the LED module60 s9 s
2I-1, O-7, O-8Test the module, build the handle59 s10 s
3O-1, O-5, O-6Housing, LED module in, driver board56 s13 s
4O-9, O-10Handle on, bezel on58 s11 s
5I-2, O-11, O-12Final test, label, pack53 s16 s
Total14 steps286 s59 s

Station is one operator's share of the work. The longest station, 60 s, is the pace the line can actually hold.

Balance efficiency is 286 / (5 x 69) = 82.9%. The other 17.1% is the 59 seconds of spare shown in the last column. Machines next: the tester is tied up 56 seconds a unit, under 69, so one is enough. It can pass 27,000 x 0.92 / 56 = 443 units a day.

The roster: 5 / (1 minus 0.10) = 5.56, so 6 people trained on this line for one crew. The sixth is not a spare pair of hands standing by. It means six people can each run at least a couple of the five stations, so a holiday or a sick day does not stop the line.

Rounding: what to do with 4.14 operators

You can't staff 0.14 of a person, so the sum rounds up and the difference becomes waiting. At 360 a day the line pays for 5 x 75 = 375 seconds of labour per light and uses 286 of them. That is 76% of paid time spent on work content. The size of the decimal tells you which way to push.

What 4.14 operators means in seconds

Example numbers
Paid seconds per unit with five operators and with fourTwo bars on one scale of seconds per unit. With 5 operators the line pays for 375 seconds: 286 of work, 59 spare inside the stations and 30 set aside for stoppages. With 4 operators there would be 276 seconds of station time for 286 seconds of work, 10 seconds short.5 operators: 5 x 75 = 375 s paid per unitWork 28659304 operators: 4 x 69 = 276 s of station timeStation time 27610 s of work that does not fit
  • Work content
  • Spare time in the stations
  • Set aside for stoppages (8% of takt)
  • Work that does not fit
Top bar: with 5 operators the line pays for 375 seconds a unit and 286 of them are work, 76%. Bottom bar: 4 operators have only 276 seconds of station time, so the work overruns by the yellow 10 seconds. Find those 10 seconds and the line runs with one person fewer.
What to do with the decimal
The sum givesWhat it meansWhat to do
Just over a whole number, such as 4.14One operator is mostly waitingLook for the seconds that would get you under: 4 operators need work content of 4 x 69 = 276 s, so 10 s has to go. Or give the spare time real work, such as feeding parts or the next sub-assembly
Around the middle, such as 4.5Rounding up wastes half a person, rounding down needs overtime every dayRound up and use the spare for off-line work, or share an operator with a neighbouring line
Just under a whole number, such as 4.9A good fit with little marginRound up and check the longest station. There is no slack if an element was underestimated

Do not round down and hope. A line staffed with 4 where the sum says 4.14 has to find 14% of a person every single day, and it finds it in overtime or in skipped checks. And do not hide the decimal by quietly loosening the stoppage factor until the sum comes out whole.

There is a second trap. The sum gives the least number of operators, and it assumes the work divides freely. Real operations come in lumps and have to follow the build order, so the stations may not fit even when the total does. The split in the table above was found by trying every allowed grouping. Do the same on yours with a yamazumi chart or the method in the line balancing guide, before the headcount goes into a budget.

Before and after: demand rises from 360 to 540 a day

Six months in, the forecast is 540 a day on the same shift. Nothing about the product has changed, so the work content is still 286 seconds. Everything else moves.

Illustrative: the work light line before and after the demand change
Line itemBefore: 360 a dayAfter: 540 a day
Takt time75 s50 s
Planned cycle time (8% stoppages)69 s46 s
Operators, calculated4.146.22
Operators and stations57
Station times60, 59, 56, 58, 53 s40, 40, 41, 36, 46, 46, 37 s
Balance efficiency82.9%88.8%
Spare time per unit59 s36 s
Paid labour per unit (operators x takt)375 s350 s
Units per operator hour9.610.3
Testers needed (one passes 443 a day)12
Roster for one crew (10% absence)68

The seven-station split is O-2 and O-3, O-7 and O-1, O-4 and O-8, I-1 and O-5, O-6 and O-9, O-10 and I-2, O-11 and O-12.

The same 286 seconds of work, split five ways and then seven

Example numbers

Before

360 a day, 5 operators

Station times at 360 a day5 stations against a planned cycle time of 69 seconds and a takt of 75 seconds. Station 1: O-2, O-3, O-4, 60 seconds. Station 2: I-1, O-7, O-8, 59 seconds. Station 3: O-1, O-5, O-6, 56 seconds. Station 4: O-9, O-10, 58 seconds. Station 5: I-2, O-11, O-12, 53 seconds.020406080O-2O-3O-4160I-1O-7O-8259O-1O-5O-6356O-9O-10458I-2O-11O-12553Station, with its total in secondsSeconds per unit
  • Planned cycle time 69 s
  • Takt 75 s
Operators, calculated
4.14
Balance efficiency
82.9%
Units per operator hour
9.6
Testers (one passes 443 a day)
1
Roster for one crew
6

Paid per unit 375 s: work 286, spare 59, stoppages 30

After

540 a day, 7 operators

Station times at 540 a day7 stations against a planned cycle time of 46 seconds and a takt of 50 seconds. Station 1: O-2, O-3, 40 seconds. Station 2: O-7, O-1, 40 seconds. Station 3: O-4, O-8, 41 seconds. Station 4: I-1, O-5, 36 seconds. Station 5: O-6, O-9, 46 seconds. Station 6: O-10, I-2, 46 seconds. Station 7: O-11, O-12, 37 seconds.020406080O-2O-3140O-7O-1240O-4O-8341I-1O-5436O-6O-9546O-10I-2646O-11O-12737Station, with its total in secondsSeconds per unit
  • Planned cycle time 46 s
  • Takt 50 s
Operators, calculated
6.22
Balance efficiency
88.8%
Units per operator hour
10.3
Testers (one passes 443 a day)
2
Roster for one crew
8

Paid per unit 350 s: work 286, spare 36, stoppages 28

Each bar is one station and each block one step from the routing. Every bar has to stay under the yellow line, the planned cycle time. At 540 a day two stations sit exactly on it, and all seven are new groupings of the same steps. The strip under each chart is paid labour per unit on one scale: 375 seconds before, 350 after.

Demand went up by half and operators by two fifths, from 5 to 7, because the rounding wasted less. Labour per unit fell from 375 to 350 seconds. That is common: a line is cheapest per unit just below the point where it needs one more person.

Three things in the table would have been missed by a plan that only scaled headcount. The tester: at 46 seconds a unit, one tester tied up for 56 seconds can't keep up, so a second has to be ordered. The margin: two of the seven stations sit at exactly 46 seconds, so any element that runs long will show at once. And the stations themselves: all seven are new groupings, which means new work instructions, new training and a new layout for parts. A demand change is a small relaunch.

Absence, utilisation and the other allowances: count each once

Most staffing plans that come out wrong added the same loss twice or left one out. Each loss has one place in the chain.

Where each loss goes in the staffing sum
LossWhere it goesWhy there
Personal needs and fatigueIn the element times, as the allowance in the standard time. Or out of available time, if the whole line stops for breaksIt is part of doing the work at a pace a person can hold all day
Line stoppages: breakdowns, shortages, quality holdsOff takt, as the stoppage factor, to give the planned cycle timeThe line still owes the same units, so it has to run faster while it is up
Changeovers, where the line runs more than one productOut of available timeThe line makes nothing during a changeover
Scrap and reworkOn demand: units to start = good units needed / yieldScrapped units used up the same work content
Absence: holidays, sickness, trainingOn the rosterIt changes how many people you need on the books, not how the line is balanced
Operators not yet at standardOn the work content, week by week during ramp-upThe same step takes a new operator longer

Utilisation needs a plain definition before anyone quotes it. On this page it is work content divided by paid operator time: 286 / 375 = 76% at 360 a day. A plan that shows 100% has no room for a dropped screw. A plan in the low 70s is paying for a lot of waiting and should say what that time is for.

Plan for a range of demand, not one number

The forecast for a new product is the least reliable number in the plan. So work out the staffing at several demand levels and design the line so it can move between them without a rebuild.

Illustrative: staffing the work light line across five levels of demand
Demand a dayTaktPlanned cycle timeOperators, calculatedOperatorsBalance efficiencyTestersRoster
240112.5 s103.5 s2.76392.1%14
30090 s82.8 s3.45486.4%15
36075 s69 s4.14582.9%16
45060 s55.2 s5.18686.4%27
54050 s46 s6.22788.8%28

Each row was checked for a station split that fits. One tester passes 443 units a day, so 450 a day already needs the second.

Headcount moves in steps, demand does not

Example numbers
Operators needed across a range of demandOperators against daily demand. The calculated number rises in a straight line, one operator for every 86.9 units a day. The number on the line is the next whole number above it: 3 at 240 a day, 4 at 300 a day, 5 at 360 a day, 6 at 450 a day, 7 at 540 a day. A second tester is needed above 443 a day.02468240300360450540Demand, units a dayOperators2nd tester above 44332.7643.4554.1465.1876.22
  • Operators on the line
  • Calculated: demand / 86.9
  • Paid waiting from rounding
The dashed line is the calculated number of operators and the staircase is what you staff. The shaded gap is paid waiting from rounding. It is smallest just before each step, which is where a line is cheapest per unit, and widest just after one. The yellow dots are the two cases worked on this page.

Four design choices make moving between these rows cheap.

  • Lay the line out so people can cover more than one station: a U shape or stations close enough to step between, with no fixed seats and nothing that traps an operator in place.
  • Write a balance for each staffing level before launch, as a set of work instructions per level, so going from 5 to 6 operators is a planned switch.
  • Train wider than the line needs. A skills matrix with every operator on at least two stations is what lets the roster number work.
  • Buy or reserve space for the machine that runs out first. On this line that is the tester, and the table says at what demand.

Once the line runs, rebalancing from real times is quicker than from estimates. LeanSuite's Line Balancing builds the yamazumi from a video of the line and compares it with takt.

Ramp-up staffing: the weeks before standard

The 286 seconds is the time for trained operators at standard pace. In the first weeks the same work takes longer, so the sum has one more term: divide the work content by the efficiency you expect that week. At 55% efficiency the light needs 286 / 0.55 = 520 seconds of operator time, not 286.

That leaves two ways to plan the launch. Ramp the volume and hold the crew, or hold the volume and add people.

Illustrative: operators needed by week under two launch plans
WeekExpected efficiencyWork content at that pacePlan A: daily volumePlan A: operators neededPlan B: operators needed for 360 a day
155%520 s1202.517.54, so 8
270%409 s2003.295.92, so 6
385%336 s2803.794.88, so 5
495%301 s3604.364.36, so 5
5100%286 s3604.144.14, so 5

The efficiency column is an assumption for the example. Set yours from the pilot run and from how your last launch actually went.

Two ways to staff the first five weeks

Example numbers
Operators needed by week under two launch plansOperators needed in each of the first five weeks under two plans. Plan A, where volume ramps: week 1 2.51, week 2 3.29, week 3 3.79, week 4 4.36, week 5 4.14. Plan B, 360 a day from the first day: week 1 7.54, week 2 5.92, week 3 4.88, week 4 4.36, week 5 4.14. The planned crew is 5.024682.58Wk 155%3.36Wk 270%3.85Wk 385%4.45Wk 495%4.15Wk 5100%Operators neededExpected efficiency against standard
  • Plan A: volume ramps 120, 200, 280, 360, 360 a day
  • Plan B: 360 a day throughout, rounded up
  • Plan B needs more than the planned crew
  • Planned crew of 5
Plan A ramps the daily volume, so the crew of 5 always has more time than the schedule needs, and the difference goes on training and fixing problems. Plan B asks for 360 a day from the first morning, which takes 8 people in week 1 and 6 in week 2. The yellow bars are the temporary people.

Plan A keeps the full crew of 5 on the line from the first day while the schedule climbs from 120 to 360. In week 1 the schedule needs only 2.51 operators' worth of time, and the rest is where training, problem solving and the daily launch meeting fit. Plan B asks for 360 from day one, which takes 8 people in week 1 and 6 in week 2. Three of those are temporary. They learn the job and are gone within a fortnight.

Plan A is nearly always the better launch, and it needs sales to agree a launch curve. If the customer needs full volume on day one, build stock ahead on Plan A before the start date. Use Plan B's numbers to show what the alternative costs.

Where the efficiency numbers come from, and how to turn a learning rate into a weekly plan, is in ramp-up plan and the learning curve. The first real evidence comes from the pilot run.

Where the sums stop working

  • Machine-paced lines. If a machine sets the rate and people tend it, staff from the tending tasks and how many machines one person can cover, not from work content over takt.
  • Mixed models. Use the weighted average work content across the mix to size the crew, then check the heaviest model against the planned cycle time, because that one unit still has to fit.
  • Long-cycle and project work. When one unit takes hours, staff from total hours per week against hours available, and expect the learning curve to dominate.
  • Work that can't be split. If one operation is longer than the planned cycle time, no rounding fixes it. Split the operation, run two stations in parallel or change the method.
  • Very low demand. Under about two operators the line is one person doing everything, and the question becomes skills and cover, not balance.

And the sums say nothing about who. A line of 5 new hires and a line of 5 people who built the last product are different lines for the first two months. Operators also tend to distrust headcount worked out from a spreadsheet. Show them the chain, tell them which numbers are estimates, and tell them the times will be studied on the real job with them in the room, as in how to conduct a time study. A crew that has seen the sum is far more likely to tell you where it is wrong.

Common mistakes

  • Dividing by takt with no stoppage factor. The line then has to be perfect to make the number.
  • Counting a loss twice: breaks out of available time and again as an allowance.
  • Rounding the operators and stopping there. The split into stations is the real test.
  • Sizing people and forgetting machines. The tester, the oven or the press runs out before the crew does.
  • One demand number. The forecast will move, so the plan should already say what happens when it does.
  • Staffing launch week at standard efficiency.
  • Leaving out the people who are not at a station: material handling, the team leader, rework.

Templates and tools for staffing a new line

FAQ

Questions about planning operators and stations for a new line

  1. Divide the work content of one unit by the time available per unit, then round up. Time per unit is takt time, less an allowance for stoppages. For example, 286 seconds of work with a 75 second takt and 8 percent stoppages gives 286 / 69 = 4.14, so 5 operators. Then check that the work splits into 5 stations that each fit.

  2. The theoretical minimum is total work content divided by the cycle time the line is balanced to, rounded up. On a manual line that equals the number of operators. It is a minimum, not a promise: operations come in lumps and must follow the build order, so test the split with a precedence diagram or a yamazumi chart before fixing the number.

  3. Capacity is the time available divided by the time the slowest resource needs per unit. For a balanced manual line, take available time, remove expected stoppages and divide by the longest station time. With 27,000 seconds a shift, 8 percent stoppages and a longest station of 60 seconds, capacity is 24,840 / 60 = 414 units a shift.

  4. Divide the time the machine is available by the time it is tied up per unit, including loading and unloading. A tester that takes 16 seconds to load and unload and runs for 40 seconds is tied up 56 seconds a unit. With 27,000 seconds a shift less 8 percent stoppages, it passes 24,840 / 56 = 443 units.

  5. There are three that go together. Takt time = available time / demand. Operators = work content / planned cycle time, rounded up. Output = available time x (1 minus stoppage share) / longest station time. Takt says how fast you must go, the operator sum says who you need, and the output sum says what the line as built can really make.

  6. Up, unless you can remove enough work to get under the lower whole number. Rounding down leaves the line short every day, and the gap comes out as overtime or missed checks. If the sum is just over a whole number, look for the few seconds of waste that would let you run with one fewer, or give the spare time real work.

  7. Divide the operators the line needs by one minus your absence rate and round up. Five operators at a 10 percent absence rate is 5 / 0.90 = 5.56, so six trained people for each crew. Use your own attendance records for the rate, and make sure the extra people are trained on several stations, not one.

  8. Divide the work content by the efficiency you expect each week before dividing by the time per unit. At 55 percent efficiency, 286 seconds of work takes 520. Then choose: keep the planned crew and raise the daily volume week by week, or hold full volume and add temporary people. Ramping the volume is usually cheaper and trains the crew that stays.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.