Value-added analysis worksheet: value added, necessary or waste, element by element

A value-added analysis takes the elements of one job, gives each a time, and sorts each into one of three classes: value added (the customer is paying for it, it changes the product, and it is done right the first time), necessary non value added (it fails a test, but the job cannot be done without it today) or waste. This worksheet holds up to 30 elements. You type the element, its time per cycle and its class; the sheet counts the elements and adds up the seconds in each class, shows each as a share of the cycle, works out the value-added ratio of the job, and draws a bar chart of the three classes. A second box works out process cycle efficiency, value-added time over lead time, if you want the process-level figure. The three tests and a short how-to are printed on the sheet, and a second tab has a 14-element example filled in.

See the sheet before you downloadPDF, 2 pages. Also Excel

Free to use: print it, copy it and edit it for your team. Enter your name and work email once to download.

Page 1 of the value-added analysis worksheetRows for element, time and class, a summary by class and the three tests.
30 elementsThree classesTotals by classValue-added ratioProcess cycle efficiencyBar chartThe three testsFilled example

Page 1 of the real file. PDF, 2 pages. Also Excel.

When to use it

When to use a value-added analysis worksheet

  • Straight after a time study, while you still remember what each element was.
  • When a station meets its standard time and still looks busy with walking, waiting and handling.
  • Before a kaizen event or a workstation redesign, to decide which seconds to go after first.
  • To show a team where a cycle goes, in three colors, without arguing about effort.
  • Before and after a change, to prove the cycle got shorter because waste left it, not because the standard was squeezed.

How to fill it in

  1. 1

    List the elements and their times

    One row per element, in order, with its time per cycle in seconds. Split an element wherever the class changes inside it: a walk hidden inside an assembly step gets its own row.
  2. 2

    Add the work that does not happen every cycle

    Rework, tote changes and jams go in as their own rows, spread over the cycle: a 50 second rework on 1 unit in 10 is 5 seconds a cycle.
  3. 3

    Class each element

    Value added passes all three tests printed on the sheet. Necessary fails a test, but the job cannot be done without it today. Waste fails, and the job can be done without it. Write your rules for the hard cases, such as inspection and handling, before you start.
  4. 4

    Say what would remove it

    For every necessary or waste element, write what would have to change for it to go. A necessary element with no such note is usually waste nobody wanted to argue about.
  5. 5

    Read the summary and the chart

    Seconds and share by class, and the value-added ratio: value-added seconds divided by cycle time. Start with the largest waste element, not the largest class.
  6. 6

    Add the process figure if you need it

    Type the value-added minutes across every operation and the lead time from start to finish. Process cycle efficiency is one divided by the other. Write which bottom line each ratio uses.

What is in the download

Every page and every sheet of the Value-added analysis worksheet

2 PDF pages and 2 Excel sheets, as they come. The worked examples use made-up numbers.

PDF, 2 pages

Excel, 2 sheets

The pictures show the top of each sheet with the formulas worked out; the file keeps every row.

A filled-in example

Illustrative, not a benchmark

Illustrative example, not a customer: a pump housing assembly and leak test station with one operator.

  • A video time study gives 14 elements and a 90 second cycle. Four are value added: seat the gasket, position the cover, start four bolts and tighten them to torque, 29 seconds in all.
  • Six are necessary today, 25 seconds: clamp the housing, pick up the driver, carry to the tester, load it, unload into the tote and write the serial number.
  • Four are waste, 36 seconds: a walk to the rack, a wait for the tester, 15 seconds of standing and watching the test, and rework spread over the cycle.
  • Across the whole process, 10 minutes of value-added work sit inside a lead time of 4 days, or 5,760 minutes.

The value-added ratio of the job is 29 / 90 = 32.2%, with waste the largest class at 40.0%. Process cycle efficiency is 10 / 5,760 = 0.17%. The station and its times are made up; they are the worked example of our value-added guide.

Common mistakes

  • Elements that are too big

    One row called assemble cover gets one class and hides a walk, two reaches and a rework inside it. Split at every change of class.

  • Calling everything necessary

    The middle class becomes the place where every awkward step is parked. For each one, write what would have to change for it to go.

  • Leaving out occasional work

    Rework and jams are not in the cycles that were timed, so the ratio looks too good. Time them when they happen and spread them over the cycle.

  • Comparing ratios with different bottom lines

    A 32% station ratio set beside a 0.2% process figure makes one of them look broken. One divides by cycle time and the other by lead time. Write the bottom line next to each.

  • Chasing the percentage

    The ratio rises when necessary work is relabeled as value added, with nothing changed on the floor. Track the seconds removed; the ratio is the summary.

Download the template

Free to use: print it, copy it and edit it for your team. Enter your name and work email once to download.

Run this template in LeanSuite

LeanSuite's Vision AI does the time study from one phone video of the process: it times every element, splits each operator's time into value-added, semi-value-added and non-value-added, and links each figure to its video frame for you to review and certify.

See it in a 45-minute demo

FAQ

Value-added analysis worksheet: common questions

  1. Work the customer is not paying for and that does not change the product: walking, waiting, searching, handling a part twice, watching a machine run, rework. Some of it is necessary today, such as clamping a part or a test the contract requires, and the rest is plain waste. This worksheet keeps the two apart, because you shrink the first and remove the second.

  2. Value added is work that changes the product in a way the customer is paying for, done right the first time. Seating a gasket, tightening a bolt to torque, welding and painting are value added. Carrying the part to the bench is not, even though the job cannot be done without it.

  3. Add up the time of the value-added elements and divide by the total. For one job the total is the cycle time: 29 seconds of value-added work in a 90 second cycle is 32.2%. For a whole process the total is the lead time, which gives process cycle efficiency: 10 minutes in a 5,760 minute lead time is 0.17%.

  4. There is no universal target. The figure depends on how strict your rules are for hard cases such as inspection and handling, and on whether you divide by cycle time or lead time. Compare a job with itself before and after a change, or with another job classed under the same written rules.

  5. Under the three tests, no: an inspection changes nothing about the product. Class it as necessary while a contract, a regulation or the process's own failure rate requires it, and as waste when it repeats an earlier check. Some plants class a customer-specified test as value added. Either way, write the rule down and use it on every job.

More free templates

All templates
Browse all 312 templates

Can't find the template you need?

Tell us what you're looking for. We'll make it and send it to your inbox, free.

A shift handover sheet, a red tag log, a changeover checklist for one machine: if your team uses it on the floor, ask.

By sending this form you agree to our Terms of Service and Privacy Policy.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.