Practical guide · Standard work, SOPs and training
How to estimate cycle time for a new product, with a worked example
Short answer
To estimate cycle time for a product that does not exist yet, list the work elements from the drawing, take a time for each from a similar part, your element library or a predetermined time system, add allowances, and report a range with its assumptions.
You cannot time what has not been built, so you build the time from pieces. Break the assembly into elements. Give each one a low, likely and high time from the best basis you have: the same element on an existing product, your library of standard elements, a predetermined time system such as MTM or MOST, or a quick mock-up. Add them up, add your plant's allowance, and divide by takt to get operators. In the worked example the answer is 482 seconds of work, somewhere between 430 and 562, which means five operators.
Last reviewed:
What you are estimating: work content first, cycle time second
From a drawing to an estimate: the whole method on one line
Example numbers- List the elements
8 groups
From the drawing and the assembly sequence, with the designer.
- Time each one, add up
430 s
384 to 502 s
Normal time. History, element library or predetermined times.
- Add the allowance
482 s
430 to 562 s
Standard time = normal x 1.12.
- Divide by takt
4.0
3.6 to 4.7 operators
Takt 120 s: 27,000 s / 225 a day.
- Report
5 operators
About 482 s of work, between 430 and 562, with the assumptions listed.
A five-step flow. One: list the elements, 8 groups. Two: time each one and add up, 430 seconds of normal time, range 384 to 502. Three: add the 12 percent allowance, 482 seconds, range 430 to 562. Four: divide by the 120 second takt, 4.0 operators, range 3.6 to 4.7. Five: plan 5 operators.
People ask for the cycle time of a new product, but that is the second number. The first is work content: the total hands-on time in one unit, added up over every station. Cycle time is what one station takes, and you only know it once you have decided how many stations share the work.
- Work content: all the manual time in one unit. This is what you estimate.
- Takt time: available time divided by demand. The customer sets it, not you.
- Operators: work content divided by takt, rounded up.
- Station cycle time: work content divided by the number of operators, if the line balances well. It has to come in under takt.
- Machine time: a press stroke, a cure, a test. It comes from the equipment specification, not from an estimate of hand work, and it is listed apart.
So the question behind the question is usually one of three: what will the labour cost, how many stations do we need, or can we make the rate. All three start from work content. For how cycle time relates to the other time measures, see cycle time vs lead time.
How to estimate cycle time in 8 steps
- 1
Get the design pack
The drawing or model, the bill of materials, the assembly sequence if there is one, the test specification and the volume. Use the checklist at the end of this page.
- 2
Write the element list
Walk through the build in order and list every element: get, place, fasten, press, connect, check, pack. Group them into 8 to 15 lines. Include the ones that are easy to forget: unpacking, orienting, cable routing, labels, checks.
- 3
Pick the basis for each element
Same element on an existing product: use its standard. Similar element: scale the old time. New but simple: your element library. New and unlike anything you make: a predetermined time system or a mock-up.
- 4
Give each element three times
Low, likely and high, in normal time before allowances. The spread should match how well you know the element. A carried-over element gets a narrow range. A brand-new one gets a wide one.
- 5
List machine and process time apart
Test cycles, cure times and automatic strokes are not hand work. Note whether the operator waits or works on something else while they run.
- 6
Add up and add allowances
Add the low, likely and high columns. Multiply each by one plus your plant's allowance for personal needs, fatigue and delay. The result is a low, likely and high standard time.
- 7
Turn it into operators and stations
Divide each of the three figures by takt. If the range crosses a whole number of operators, plan to the higher one or say plainly what would have to be true for the lower.
- 8
Report a range with its assumptions
State the likely figure, the range, the basis of each element and everything you assumed: volume, shifts, tooling, fixtures, what was not on the drawing. Then say when the estimate will be checked.
Five ways to get a time for work nobody has done yet
Use them in this order. Each one down the list costs more effort or carries more doubt than the one above it.
1. Similar-part history
If the new product has a predecessor, most of its elements already have a standard. Pressing the same bearing with the same press takes the same time. Take the old standard time element by element, not as a total, and sort the elements into three piles: carried over unchanged, carried over but scaled (three gears where there were two), and new. Only the last pile needs real estimating.
The trap is using an old standard that nobody has checked in years. Before you rely on it, look at when it was last studied and whether the method still matches. A recent time study of the predecessor is the best input an estimate can have.
2. An element library
Textbooks call it standard data. It is a table of times for elements that turn up on many products: drive one screw of a given size with a given tool, apply one label, scan one barcode, close and tape one carton. Each time comes from your own past studies. Once you have it, a new job that is made of known elements can be timed at a desk by counting.
A library is only as good as the studies behind it, and each entry belongs to a method and a tool. A time for a screw driven with a torque-controlled driver on a balancer is not the time for the same screw driven with a hand tool.
3. A predetermined time system
When no history exists, a predetermined time system gives a time for each basic human motion: reach, grasp, move, position, release. An analyst writes out the motions the job will need and reads the times from the system's tables. It works from a drawing and a method description, which is exactly what you have before launch. The next section names the main systems.
4. Mock-up timing
Build the station out of cardboard, tubing and a table, use 3D-printed or sample parts, and have someone go through the motions while you time them. Mock-up times are rough, because the person is not practised and the parts are not real. They are still the fastest way to find the element you forgot, compare two layouts, and check reaches and postures. See designing a future workstation.
5. Parts-count and fastener-count rules
The idea comes from design for assembly: assembly time grows with the number of parts and with how awkward each one is to handle and insert. In the Boothroyd and Dewhurst method each part gets a handling time and an insertion time from tables keyed to its size, symmetry and how it is secured. The times are added up and compared with an ideal of about 3 seconds per part for the fewest parts the design could have.
You can use the same idea without the tables. Count the parts and the fasteners on the new design. Do the same for two or three products you already build, divide each one's work content by its count, and you have your own seconds per part and seconds per fastener for that product family. It is crude, and it is honest about being crude. Use it for a first look, or as a cross-check on an estimate built element by element. We are not giving you a constant, because one that fits your products has to come from your products.
| The element is | Use | How wide a range to expect |
|---|---|---|
| The same as on an existing product, same tool | The existing standard | Narrow |
| Like an existing one, but more or fewer of something | The existing time, scaled | Narrow to medium |
| New here, but made of common motions (screws, labels, scans) | Your element library | Medium |
| New, and nothing like it in the plant | A predetermined time system from the drawing | Medium to wide |
| New, and the method itself is unclear | A mock-up, then a predetermined time system | Wide |
Choosing the basis for one element: stop at the first yes
Is the element done today on another product, with the same tool?
YesUse its standard
Press two bearings: 44 s
Narrow rangeIs it like one you do, with more or fewer of something?
YesScale the existing time
3 gears where there were 2: 57 s
Medium rangeIs it made of motions you already have times for?
YesBuild it from the element library
Cover and 8 screws: 22 + 8 x 7 = 78 s
Medium rangeIs the method clear from the drawing?
YesPredetermined time system
New shaft seal: 36 s
Wide rangeNone of the four: the method itself is unclear
ThenMock it up, then analyse the method you settle on
Coupling and connector: 52 s, from 40 to 72
Widest range
A decision ladder of four questions. If the element is done today with the same tool, use its standard. If it is like one you do, scale the existing time. If it is made of known motions, use the element library. If the method is clear from the drawing, use a predetermined time system. If none applies, build a mock-up first. The range gets wider with each step down.
Predetermined time systems: MTM, MOST and MODAPTS in one line each
All of these work the same way. Decades ago someone filmed and measured thousands of basic motions and published the times. You describe your job as a sequence of those motions and add up the table values. Most count in TMU, the time measurement unit: 1 TMU is 0.00001 hour, which is 0.036 seconds.
| System | What it is | Fits |
|---|---|---|
| MTM-1 | The original Methods-Time Measurement, published in 1948 by Maynard, Stegemerten and Schwab. Times for basic motions such as reach, move, grasp, position and release, in TMU | Short, highly repetitive cycles where the detail pays for itself |
| MTM-2, MTM-UAS and other condensed versions | Later MTM systems that combine basic motions into larger blocks, so an analysis is quicker and less detailed | Longer cycles and batch work |
| MOST | The Maynard Operation Sequence Technique, developed by Kjell Zandin. Work is described as a few fixed sequence models (general move, controlled move, tool use). Each step gets an index value, and the total times 10 is the TMU | Most assembly work, from under a minute up to several minutes a cycle |
| MODAPTS | Developed by G. C. Heyde in Australia in the 1960s. Motions are coded by the body part that moves, in units called MODs of 0.129 seconds | Quick analysis of manual work |
Each system has its own rules, and a result is only as good as the analyst's training. The times are licensed data: use the publisher's current tables, not a copy from the internet. Deeper guides to each system are planned.
How a predetermined time is built: one move in BasicMOST
Example numbersThe move: pick up a shaft seal from a bin within reach and place it on the shaft, adjusting it to seat.
Get
- A1Action distanceseal is within reach
- B0Body motionnone
- G1Gain controllight object, one hand
Put
- A1Action distanceshaft is within reach
- B0Body motionnone
- P3Placementneeds adjusting to seat
Return
- A0Action distanceno return move
Time = sum of the index values x 10 TMU
1 TMU = 0.00001 hour = 0.036 seconds
- Index total =1 + 0 + 1 + 1 + 0 + 3 + 0= 6
- TMU =6 x 10= 60
- Seconds =60 x 0.036= 2.16
A worked example of a BasicMOST general move: pick up a shaft seal from a bin within reach and place it on the shaft with some adjustment. The sequence is A1 B0 G1, A1 B0 P3, A0. The index values add to 6, times 10 is 60 TMU, times 0.036 is 2.16 seconds.
Three things to know before you rely on one. First, the times are for a defined normal pace, so you do not rate them, but you do still add allowances. Second, they cover manual motion only. Machine and process time come from somewhere else. Third, the analysis describes a method, and if the real method turns out different, the time is for a job nobody is doing.
Adding allowances, and what to leave out
Everything so far is normal time: what the work takes at a normal pace with no interruptions. Nobody works a shift like that. An allowance covers personal needs, fatigue and small unavoidable delays, and turns normal time into standard time.
Use the allowance your plant already applies to similar work, and use the same convention. The ILO form is standard time = normal time x (1 + allowance). Some plants divide by one minus the allowance instead, which gives a slightly larger number. Either is fine as long as the estimate and the later time study use the same one.
- Leave learning out. The estimate is for a trained operator. The slow first weeks belong in the ramp plan, as a separate number.
- Leave scrap and rework out of the time. Carry them as a yield assumption next to it.
- Leave balance loss out of the work content, but remember it when you count operators. Five stations never share the work perfectly.
- Do not add a private safety margin on top of the allowance. If you are unsure, widen the range and say why.
Uncertainty: why the estimate is a range
A single number hides the one thing the reader most needs to know, which is how far to trust it. An estimate of 482 seconds built from last month's time study of a near-identical part is a different object from 482 seconds built from a sketch. A range shows the difference.
Give every element a low, a likely and a high. The low is the time if everything about the design turns out easy. The high is the time if the awkward things you can already see turn out as awkward as they look. Neither is a disaster case.
Adding all the lows and all the highs gives the widest range, because it assumes every element lands at the same end together. A common alternative is the three-point convention from project planning (PERT): the expected value of each element is (low + 4 x likely + high) / 6 and its standard deviation is (high minus low) / 6, and the deviations combine as the square root of the sum of their squares. That gives a much tighter band, but it assumes the errors are independent. They rarely are. One estimator, one set of beliefs about the fixtures, one drawing: when one element is optimistic the rest tend to be. The truth often sits between the two bands, so use the wide one for decisions that are expensive to reverse.
- State the likely figure and the range together, always. Never let the likely figure travel alone.
- List the assumptions: volume and takt, shifts, the tooling and fixtures you assumed, the level of automation, the allowance.
- Name the two or three elements that carry most of the range. That tells the design team where an answer would help most.
- Say what is not included: learning, scrap, material handling to the line, changeovers.
- Give the date of the next check, which is the first prototype build.
A range covers uncertainty in the elements you listed. It cannot cover an element you did not list. That is why the element walk-through with the design engineer matters more than the arithmetic.
Worked example: estimating a pump before it exists
A plant builds a small coolant pump, the CP-30, and is asked to quote its successor, the CP-40. The new pump has a third gear, a new lip seal on the shaft, eight cover screws and, for the first time, an electrical connector. Nothing has been built. Demand is 225 a day on one 450 minute shift, so takt is 27,000 / 225 = 120 seconds. The plant's allowance is 12 percent.
The engineer walks the assembly sequence with the designer and writes eight element groups. Four are carried over from the CP-30, whose standard was re-studied last year. One is scaled. One comes from the element library. Two are new and are analysed with a predetermined time system from the drawing.
| Element group | Basis | Low | Likely | High |
|---|---|---|---|---|
| Housing: unpack, check, load to fixture | CP-30 standard, same element | 30 | 34 | 38 |
| Press two bearings | CP-30 standard, same press | 40 | 44 | 50 |
| Gear set and shaft (3 gears) | CP-30: 38 s for 2 gears, scaled to 3 = 57 s | 52 | 57 | 66 |
| Shaft seal press (new lip seal) | Predetermined times from the drawing | 30 | 36 | 46 |
| Gasket, cover and 8 screws | Element library: 22 s + 8 x 7 s = 78 s | 72 | 78 | 88 |
| Coupling and connector (new) | Predetermined times, no part to hold yet | 40 | 52 | 72 |
| Leak and run test: load, connect, unload | CP-30 standard, same tester | 36 | 40 | 46 |
| Label, final check, pack | CP-30 standard, same pack | 84 | 89 | 96 |
| Total normal time | 384 | 430 | 502 |
The test itself runs for 45 seconds on the machine. That is machine time, listed apart: the operator packs the previous pump while it runs.
Where the uncertainty sits: low, likely and high for each element group
Example numbers- Housing to fixture30 · 34 · 38 s
- Two bearings40 · 44 · 50 s
- Gears and shaft52 · 57 · 66 s
- Shaft seal30 · 36 · 46 s
- Cover, 8 screws72 · 78 · 88 s
- Coupling, connector40 · 52 · 72 s
- Test handling36 · 40 · 46 s
- Label and pack84 · 89 · 96 s
- CP-30 history
- Element library
- Predetermined times
- Likely
Range bars for the eight element groups, in seconds of normal time. Housing to fixture: 30 to 38, likely 34, from history. Two bearings: 40 to 50, likely 44, from history. Gears and shaft: 52 to 66, likely 57, from history. Shaft seal: 30 to 46, likely 36, from predetermined. Cover, 8 screws: 72 to 88, likely 78, from library. Coupling, connector: 40 to 72, likely 52, from predetermined. Test handling: 36 to 46, likely 40, from history. Label and pack: 84 to 96, likely 89, from history. Totals: 384, 430 and 502.
Now the allowance and the takt.
| Low | Likely | High | |
|---|---|---|---|
| Normal time | 384 s | 430 s | 502 s |
| Standard time = normal x 1.12 | 430 s | 482 s | 562 s |
| Operators = standard / 120 s takt | 3.6 | 4.0 | 4.7 |
| Operators, rounded up | 4 | 5 | 5 |
482 / 120 is 4.01, which rounds up to 5. Four operators would be 100.3 percent loaded before any balance loss.
The estimate reads: about 482 seconds of work content, between 430 and 562. Five operators on five stations, with an average station cycle near 96 seconds against a 120 second takt. Four operators would only work at the very bottom of the range.
Look at where the range comes from. The coupling and connector group is 12 percent of the likely work (52 of 430 seconds) and 27 percent of the range (32 of the 118 seconds between low and high). It is the one element nobody has held in their hands. If the design team can produce a sample connector, that single answer narrows the estimate more than anything else.
The three-point convention gives an expected 434 seconds of normal time, which is 486 standard, with a standard deviation of 8.6 seconds. Two deviations either side is 469 to 504. That band would be right if the eight errors were independent. The plant quoted on the wide range.
How the estimate held up
The playbook follows this pump to the end. The first prototype builds came in at 566 seconds, just outside the range, because the connector cable had to be routed through a clip that was not on the drawing at quote. After two design changes it was 539. Ninety days into production the standard was locked at 528 seconds: inside the range, 46 seconds above the likely figure, and still five operators. The tight band of 469 to 504 would have missed it.
How the estimate held up against what was measured later
Example numbersA number line from 420 to 620 seconds. The quoted range runs from 430 to 562 with the likely figure at 482. The tighter band that assumes independent errors runs from 469 to 504. Later results: Standard locked at day 90 528, After the design change 539, First prototype 566. Four operators can absorb 480 seconds and five can absorb 600.
What to ask engineering for
Most bad estimates come from a thin design pack, not from bad arithmetic. Ask for these before you start, and write down which ones you did not get. Each missing item is an assumption.
| Ask for | Why you need it |
|---|---|
| Drawing or 3D model, and the bill of materials | Part count, fastener count and types |
| Which parts and operations carry over, and from which product | Tells you which existing standards you can use |
| The intended assembly sequence, or an exploded view | The element list and its order |
| Fits and tolerances on mating parts | A press fit and a slip fit are different elements |
| Fastener sizes, torque values and tightening sequence | Tool choice and time per fastener |
| Adhesives, sealants, cure and settle times | Process time that no one can shorten |
| Test specification and test duration | Machine time, and what the operator does meanwhile |
| Part weights and sizes | Handling time, two-person lifts, lift assists |
| Cables, hoses and anything flexible | Routing is slow and is often missing from the drawing |
| Special characteristics and required inspections | Every check is an element |
| Labelling, traceability and packaging specification | A fifth of the work in the worked example, and usually decided last |
| Volume, mix and variants by year | Takt, and how much of the work differs by variant |
| Fixture, tooling and automation concept | The method your times assume |
| Open design items likely to change | Where to put the widest ranges |
Limits and common mistakes
An estimate is the wrong tool once you can observe the work. The day a prototype exists, time it. The day the line runs, film it. The estimate's job is to get you to a sensible quote and a sensible first line plan, then be replaced.
| Mistake | What happens | Do this instead |
|---|---|---|
| Scaling the old product's total by a percentage | The new elements are buried in an average | Estimate element by element |
| Forgetting the unglamorous elements | Unpacking, routing, labels and checks turn up at prototype | Walk the sequence with the designer |
| Treating machine time as work content | Operators are counted for time the machine is running | List machine time apart and decide what the operator does |
| Mixing learning into the estimate | The standard is inflated and the ramp is still not planned | Estimate for a trained operator and plan the ramp separately |
| Reporting one number | The quote is read as a promise | Report the range and the assumptions |
| Never checking it against the real standard | The same error goes into every quote | Record estimate against locked standard for each launch |
One more limit: an estimate describes a method, and methods belong to people. When the line starts, the operators will find a better sequence than the one you assumed. Plan to update the numbers with them, not to hold them to yours.
Tools and related guides
Your next estimate is only as good as your record of the last product. In LeanSuite's time and motion study you film a station on a phone, the AI times every element and you review and certify it, so the predecessor's element times are measured and kept under its process when the next quote arrives.
- The new product time study playbook: the six studies that follow this estimate.
- Process planning for a new product: from the element list to a routing.
- Planning operators and stations for a new line: from work content to a station plan.
- Standard time calculator: normal time, rating and allowance.
- Takt time calculator and line balancing calculator.
- Operator staffing calculator: operators from work content and takt.
- How many operators do I need?: the staffing arithmetic in full.
Go deeper
This page is the short version. These guides cover each part in full.
- Takt Time in JIT: Matching Production to DemandWhere the takt in the estimate comes from and what changes it.
- The Three Elements of Standard Work: Takt Time, Work Sequence, Standard WIPWhat the estimated sequence turns into once the line runs.
- Standard Work Tools: Combination Sheet, Standardized Work Chart, Job BreakdownSplitting manual, machine and walking time, which the estimate lists apart.
- Cell Design for JIT Flow: Step-by-Step Layout PlanningTurning the operator count into a cell layout.
All our articles on this subject are in the standard work, sops and training topic.
Free templates and tools
- Operator staffing calculatorTakt, work content, the operators a line needs, a check of your station plan and the roster with absence cover, from your own demand and element times.
- Time study sheetTime each element over 10 cycles and work out the average, lowest repeatable and standard time. Excel does the sums.
- Process flow diagram templateA squared sheet to draw the flow with a symbol key, and a step table that counts operations, moves, checks, waits and storage.
- Learning curve and ramp-up workbookBoth learning curve models side by side, a fit from your own observed hours, batch hours, the unit that reaches standard and a weekly ramp plan.
- Standard time calculatorObserved times, a rating and an allowance in; normal time, standard time, units per hour, pieces per shift and labour cost per unit out, with the working.
- Takt time calculatorThe pace a line must hit to meet customer demand, from shift time, breaks and daily demand.
- Cycle time calculatorCycle time against takt, units per hour, capacity per shift and the gap to daily demand.
- Line balancing calculatorLine efficiency, balance delay and the minimum number of stations from station times and takt.
Doing this in LeanSuite
Time and Motion Study
Film a similar job or a prototype build on a phone and LeanSuite times every element, so your next estimate starts from measured times.
See Time and Motion StudyAI Video Analysis
Upload one process video and get time and motion, line balancing and ergonomic studies to review and certify.
See AI Video Analysis
See it on your own lines
Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.
FAQ
Questions about how to estimate cycle time for a new product
List the work elements from the drawing and the assembly sequence. Take a time for each from the same element on an existing product, your element library, a predetermined time system such as MTM or MOST, or a mock-up. Add them, add your plant's allowance, and report a low, likely and high figure with the assumptions. Divide by takt to get operators.
For a running process, cycle time = net production time / units produced. A station that makes 225 good units in 27,000 seconds of running time has a cycle time of 120 seconds. For one operator, time several cycles from the same point in each and average them. For a product that does not exist yet, you estimate the work content first.
Total cycle time, also called work content, is the sum of the cycle times of every step needed to make one unit: step 1 + step 2 + and so on to the last step. Divide it by takt time to get the number of operators the work needs. For example, 482 seconds of work at a 120 second takt needs 4.01 operators, so plan five.
Cycle time is how long one step, or one station, takes to complete one unit. Lead time is how long a unit takes to travel from order or first operation to delivery, including every wait in between. A pump can have 8 minutes of cycle time across its stations and a lead time of several days, because most of the lead time is waiting.
There is no universal ideal. For a manual station the target is a cycle time a little under takt time, so the line keeps up with demand without overproducing. In an OEE calculation, ideal cycle time means something narrower: the fastest time the equipment is designed to make one part, used to work out the performance factor.
A TMU is a time measurement unit, the unit used by predetermined time systems such as MTM and MOST. One TMU is 0.00001 hour, which is 0.0006 minutes or 0.036 seconds, so 1,000 TMU is 36 seconds. It is small because the basic motions it measures, such as a reach or a grasp, take fractions of a second.
It depends on how much of the work is carried over from a product you already time. Elements with a recent standard can be close. New elements estimated from a drawing can be far out, and an element missing from the drawing is not in the estimate at all. Report a range, then compare it with the standard you finally set so you learn your own error.
Yes. Predetermined times are set at a defined normal pace, so you do not apply a performance rating, but they contain no time for personal needs, fatigue or unavoidable delays. Add the same allowance your plant uses for a stopwatch study of similar work, with the same formula, so the estimate and the later standard are comparable.
Related guides and tools
- The new product time study playbook: the six studies after the estimate
- New product introduction: where the estimate sits in the launch gates
- Standard time: normal time, rating and allowances
- Takt time: the number the estimate is divided by
- How many operators do I need? The staffing arithmetic
- Cycle time vs lead time: which time measure is which
- Designing a future workstation: mock-ups and reach checks
- Line balancing: sharing the work content across stations
More method guides
- The 6 Ms of production
- Poka-yoke
- Model area 90-day plans
- Moving from Excel to one system
- Reducing machine downtime: a worked month
- Andon
- Cycle time vs lead time, worked through
- Root cause analysis
- How many operators a line needs
- Reducing scrap and rework: a worked month
- Unsafe acts and unsafe conditions
- Just culture
- Stop-work authority
- Material review board (MRB)
- Nonconformance and NCRs
- Problem solving methods
- Quad chart
- OEE calculation
- Quality assurance vs quality control
- SOP meaning and format
- Job hazard analysis
- Near miss reporting
- Fishbone diagram
- Pareto chart
- Histogram
- Control chart
- What is a gemba walk
- What is lead time
- What is operational excellence
- How to improve product quality
- Preventive vs predictive maintenance
- Kanban
- FMEA
- PDSA cycle
- Safety moments
- Just-in-time manufacturing
- Kaizen
- 5S
- Total quality management (TQM)
- CAPA (corrective and preventive action)
- Layered process audit (LPA)
- Lean tools
- Lockout tagout (LOTO)
- A3 problem solving
- Preventive maintenance
- APQP
- High reliability organization (HRO)
- Manufacturing KPIs
- Quality metrics
- Practical problem solving
- CMMS
- Risk assessment
- Production efficiency
- Total productive maintenance (TPM)
- Reliability-centered maintenance (RCM)
- Hierarchy of controls
- Personal protective equipment (PPE)
- Emergency action plan
- Safety signs
- Warehouse safety
- ISO 9001
- SIPOC diagram
- Rolling action item list (RAIL)
- Pugh matrix
- Flowchart
- Project charter
- ISO 9001:2026
- Fleet maintenance
- IATF 16949
- AS9100
- ISO 14001
- ISO 45001
- One point lesson
- Standard work
- Meeting cadence
- OSHA penalties and the top 10 cited standards
- OSHA 300A summary
- SMART goals examples for manufacturing
- Year-end review for manufacturing plants
- 2027 goals for a manufacturing plant
- Lean manufacturing principles
- Toyota Production System
- 5W1H
- 5 Whys
- Continuous improvement
- Takt time
- DMAIC
- PDCA
- 8D problem solving
- Prioritization matrix
- Gemba walk questions
- 5W1H questions
- Layered process audit questions
- 5S audit questions
- Difficult conversations at work
- How to talk to an employee about poor performance
- How to resolve conflict between employees
- High performer, bad attitude
- How to get employees to follow procedures
- Resistance to change on the shop floor
- Influence without authority for CI, quality and safety people
- Quality vs production: the hold against the ship date
- Hard savings vs soft savings
- How to handle a customer quality complaint call
- 30 60 90 day plan for a manufacturing manager
- First 90 days in a new manufacturing role
- New supervisor training: the first 90 days
- Night shift supervisor
- Engineer to manager in manufacturing
- What to do after a serious workplace accident
- Disagree and commit: disagreeing with your boss in a plant
- How to deliver bad news to your boss
- How to present audit findings to management
- How to get leadership buy-in for continuous improvement
- How to ask for more headcount or resources
- How to ask for a promotion in manufacturing
- PPE compliance
- Language barriers on the shop floor
- Train the trainer in manufacturing
- Contractor safety management
- Return to work after an injury
- Attendance conversation with an employee
- Managing former peers after a promotion
- Managing older or more experienced employees
- Inheriting a team
- How to delegate as a supervisor
- Holding supervisors accountable
- How to tell employees about layoffs or a shift change
- How to deny a raise request or a promotion
- Time and motion study
- How to conduct a time study
- Standard time
- Work sampling
- SMED
- Line balancing
- Yamazumi chart
- Ergonomic assessment in manufacturing
- Spaghetti diagram
- Time study vs motion study vs method study
- Why do a time study
- How to plan a time study
- How to break a job into elements
- How many cycles to time
- Stopwatch time study
- Time study mistakes
- Time study vs work sampling
- Value added vs non value added
- Labor losses in manufacturing
- New product time study playbook
- New product introduction for industrial engineers
- Process planning for a new product
- Planning operators and stations for a new line
- Pilot run and line trial
- Ramp-up plan and the learning curve
- Workstation design
- Designing a future workstation
- Time study and ergonomic study in one pass
- Predetermined motion time systems (PMTS)
- MTM (Methods-Time Measurement)
- MOST and MODAPTS
- Therbligs and motion economy
- RULA assessment
- REBA assessment
- RULA vs REBA
- NIOSH lifting equation
- Production capacity calculation
- Precedence diagram
- Labor efficiency and labor variance
- Labor cost and quoting with time standards
- SMV and SAM in garment manufacturing
- From time study to standard work
- Standard work combination table
- Standard work vs SOP vs work instruction
- Standard WIP
- Updating standard work after an improvement
- Time study from video
- Time study app or software
- Man-machine chart
- Timing long-cycle and team work
- Time study in a union plant
- History of time and motion study
- Golden zone (power zone)
- Workstation assessment
- Reach envelope and work area study
- Standing, seated and sit-stand workstations
- Line-side material presentation
- Time study in automotive assembly
- Time study in electronics assembly
- Time study in CNC machining
- Time study in metal fabrication and welding
- Time study in plastics injection molding
- Time study in warehouse operations
- Time study in garment manufacturing
- Time study in maintenance work
- Time study in aerospace assembly and MRO
- Time study in food and beverage manufacturing
- Time study examples
- Historical and machine data as time standards
- Line balancing examples
- How to measure cycle time
- Manpower planning from standard time
- Bottleneck analysis from a time study
- Standard work examples
- U-cells and one-piece flow
- Flow process chart and operation process chart
- Two-handed process chart
- 3P production preparation process
- Plant layout basics
- Design for assembly
- Time study, PFMEA, control plan and work instructions
- Explaining a time study to a worried operator
- The observer effect in time studies
- Time standards and incentive pay
- Seven wastes vs eight wastes
- Job safety analysis (JSA)
- JSRA (job safety risk assessment)
- JSA vs JHA vs JSRA
- Job safety analysis from video
- HIRA (hazard identification and risk assessment)
- Management of change (MOC)
- Safe work method statement (SWMS)
- Permit to work (PTW)
- Pre-task plan (PTP)
- Field level risk assessment (FLRA)
- Safety observation
- Safety walk