How to estimate cycle time for a new product, with a worked example

Short answer

To estimate cycle time for a product that does not exist yet, list the work elements from the drawing, take a time for each from a similar part, your element library or a predetermined time system, add allowances, and report a range with its assumptions.

You cannot time what has not been built, so you build the time from pieces. Break the assembly into elements. Give each one a low, likely and high time from the best basis you have: the same element on an existing product, your library of standard elements, a predetermined time system such as MTM or MOST, or a quick mock-up. Add them up, add your plant's allowance, and divide by takt to get operators. In the worked example the answer is 482 seconds of work, somewhere between 430 and 562, which means five operators.

Last reviewed:

What you are estimating: work content first, cycle time second

From a drawing to an estimate: the whole method on one line

Example numbers
  1. List the elements

    8 groups

    From the drawing and the assembly sequence, with the designer.

  2. Time each one, add up

    430 s

    384 to 502 s

    Normal time. History, element library or predetermined times.

  3. Add the allowance

    482 s

    430 to 562 s

    Standard time = normal x 1.12.

  4. Divide by takt

    4.0

    3.6 to 4.7 operators

    Takt 120 s: 27,000 s / 225 a day.

  5. Report

    5 operators

    About 482 s of work, between 430 and 562, with the assumptions listed.

A five-step flow. One: list the elements, 8 groups. Two: time each one and add up, 430 seconds of normal time, range 384 to 502. Three: add the 12 percent allowance, 482 seconds, range 430 to 562. Four: divide by the 120 second takt, 4.0 operators, range 3.6 to 4.7. Five: plan 5 operators.

Three numbers travel through every step, not one. The low and high figures are what tell you that four operators would only work if everything went right.

People ask for the cycle time of a new product, but that is the second number. The first is work content: the total hands-on time in one unit, added up over every station. Cycle time is what one station takes, and you only know it once you have decided how many stations share the work.

  • Work content: all the manual time in one unit. This is what you estimate.
  • Takt time: available time divided by demand. The customer sets it, not you.
  • Operators: work content divided by takt, rounded up.
  • Station cycle time: work content divided by the number of operators, if the line balances well. It has to come in under takt.
  • Machine time: a press stroke, a cure, a test. It comes from the equipment specification, not from an estimate of hand work, and it is listed apart.

So the question behind the question is usually one of three: what will the labour cost, how many stations do we need, or can we make the rate. All three start from work content. For how cycle time relates to the other time measures, see cycle time vs lead time.

How to estimate cycle time in 8 steps

  1. 1

    Get the design pack

    The drawing or model, the bill of materials, the assembly sequence if there is one, the test specification and the volume. Use the checklist at the end of this page.

  2. 2

    Write the element list

    Walk through the build in order and list every element: get, place, fasten, press, connect, check, pack. Group them into 8 to 15 lines. Include the ones that are easy to forget: unpacking, orienting, cable routing, labels, checks.

  3. 3

    Pick the basis for each element

    Same element on an existing product: use its standard. Similar element: scale the old time. New but simple: your element library. New and unlike anything you make: a predetermined time system or a mock-up.

  4. 4

    Give each element three times

    Low, likely and high, in normal time before allowances. The spread should match how well you know the element. A carried-over element gets a narrow range. A brand-new one gets a wide one.

  5. 5

    List machine and process time apart

    Test cycles, cure times and automatic strokes are not hand work. Note whether the operator waits or works on something else while they run.

  6. 6

    Add up and add allowances

    Add the low, likely and high columns. Multiply each by one plus your plant's allowance for personal needs, fatigue and delay. The result is a low, likely and high standard time.

  7. 7

    Turn it into operators and stations

    Divide each of the three figures by takt. If the range crosses a whole number of operators, plan to the higher one or say plainly what would have to be true for the lower.

  8. 8

    Report a range with its assumptions

    State the likely figure, the range, the basis of each element and everything you assumed: volume, shifts, tooling, fixtures, what was not on the drawing. Then say when the estimate will be checked.

Five ways to get a time for work nobody has done yet

Use them in this order. Each one down the list costs more effort or carries more doubt than the one above it.

1. Similar-part history

If the new product has a predecessor, most of its elements already have a standard. Pressing the same bearing with the same press takes the same time. Take the old standard time element by element, not as a total, and sort the elements into three piles: carried over unchanged, carried over but scaled (three gears where there were two), and new. Only the last pile needs real estimating.

The trap is using an old standard that nobody has checked in years. Before you rely on it, look at when it was last studied and whether the method still matches. A recent time study of the predecessor is the best input an estimate can have.

2. An element library

Textbooks call it standard data. It is a table of times for elements that turn up on many products: drive one screw of a given size with a given tool, apply one label, scan one barcode, close and tape one carton. Each time comes from your own past studies. Once you have it, a new job that is made of known elements can be timed at a desk by counting.

A library is only as good as the studies behind it, and each entry belongs to a method and a tool. A time for a screw driven with a torque-controlled driver on a balancer is not the time for the same screw driven with a hand tool.

3. A predetermined time system

When no history exists, a predetermined time system gives a time for each basic human motion: reach, grasp, move, position, release. An analyst writes out the motions the job will need and reads the times from the system's tables. It works from a drawing and a method description, which is exactly what you have before launch. The next section names the main systems.

4. Mock-up timing

Build the station out of cardboard, tubing and a table, use 3D-printed or sample parts, and have someone go through the motions while you time them. Mock-up times are rough, because the person is not practised and the parts are not real. They are still the fastest way to find the element you forgot, compare two layouts, and check reaches and postures. See designing a future workstation.

5. Parts-count and fastener-count rules

The idea comes from design for assembly: assembly time grows with the number of parts and with how awkward each one is to handle and insert. In the Boothroyd and Dewhurst method each part gets a handling time and an insertion time from tables keyed to its size, symmetry and how it is secured. The times are added up and compared with an ideal of about 3 seconds per part for the fewest parts the design could have.

You can use the same idea without the tables. Count the parts and the fasteners on the new design. Do the same for two or three products you already build, divide each one's work content by its count, and you have your own seconds per part and seconds per fastener for that product family. It is crude, and it is honest about being crude. Use it for a first look, or as a cross-check on an estimate built element by element. We are not giving you a constant, because one that fits your products has to come from your products.

Which basis for which element
The element isUseHow wide a range to expect
The same as on an existing product, same toolThe existing standardNarrow
Like an existing one, but more or fewer of somethingThe existing time, scaledNarrow to medium
New here, but made of common motions (screws, labels, scans)Your element libraryMedium
New, and nothing like it in the plantA predetermined time system from the drawingMedium to wide
New, and the method itself is unclearA mock-up, then a predetermined time systemWide

Choosing the basis for one element: stop at the first yes

  1. Is the element done today on another product, with the same tool?

    Yes

    Use its standard

    Press two bearings: 44 s

    Narrow range
  2. Is it like one you do, with more or fewer of something?

    Yes

    Scale the existing time

    3 gears where there were 2: 57 s

    Medium range
  3. Is it made of motions you already have times for?

    Yes

    Build it from the element library

    Cover and 8 screws: 22 + 8 x 7 = 78 s

    Medium range
  4. Is the method clear from the drawing?

    Yes

    Predetermined time system

    New shaft seal: 36 s

    Wide range
  5. None of the four: the method itself is unclear

    Then

    Mock it up, then analyse the method you settle on

    Coupling and connector: 52 s, from 40 to 72

    Widest range

A decision ladder of four questions. If the element is done today with the same tool, use its standard. If it is like one you do, scale the existing time. If it is made of known motions, use the element library. If the method is clear from the drawing, use a predetermined time system. If none applies, build a mock-up first. The range gets wider with each step down.

The further down the ladder an element lands, the wider its range should be. The examples are the pump elements from the worked estimate below.

Predetermined time systems: MTM, MOST and MODAPTS in one line each

All of these work the same way. Decades ago someone filmed and measured thousands of basic motions and published the times. You describe your job as a sequence of those motions and add up the table values. Most count in TMU, the time measurement unit: 1 TMU is 0.00001 hour, which is 0.036 seconds.

The main predetermined time systems
SystemWhat it isFits
MTM-1The original Methods-Time Measurement, published in 1948 by Maynard, Stegemerten and Schwab. Times for basic motions such as reach, move, grasp, position and release, in TMUShort, highly repetitive cycles where the detail pays for itself
MTM-2, MTM-UAS and other condensed versionsLater MTM systems that combine basic motions into larger blocks, so an analysis is quicker and less detailedLonger cycles and batch work
MOSTThe Maynard Operation Sequence Technique, developed by Kjell Zandin. Work is described as a few fixed sequence models (general move, controlled move, tool use). Each step gets an index value, and the total times 10 is the TMUMost assembly work, from under a minute up to several minutes a cycle
MODAPTSDeveloped by G. C. Heyde in Australia in the 1960s. Motions are coded by the body part that moves, in units called MODs of 0.129 secondsQuick analysis of manual work

Each system has its own rules, and a result is only as good as the analyst's training. The times are licensed data: use the publisher's current tables, not a copy from the internet. Deeper guides to each system are planned.

How a predetermined time is built: one move in BasicMOST

Example numbers

The move: pick up a shaft seal from a bin within reach and place it on the shaft, adjusting it to seat.

Get

  • A1Action distanceseal is within reach
  • B0Body motionnone
  • G1Gain controllight object, one hand

Put

  • A1Action distanceshaft is within reach
  • B0Body motionnone
  • P3Placementneeds adjusting to seat

Return

  • A0Action distanceno return move

Time = sum of the index values x 10 TMU

1 TMU = 0.00001 hour = 0.036 seconds

  1. Index total =1 + 0 + 1 + 1 + 0 + 3 + 0= 6
  2. TMU =6 x 10= 60
  3. Seconds =60 x 0.036= 2.16
Normal time for this move, before allowances2.16 s

A worked example of a BasicMOST general move: pick up a shaft seal from a bin within reach and place it on the shaft with some adjustment. The sequence is A1 B0 G1, A1 B0 P3, A0. The index values add to 6, times 10 is 60 TMU, times 0.036 is 2.16 seconds.

Nobody held a stopwatch. The analyst described the move, read an index for each letter from the system's table and added them up. A whole job is a few dozen lines like this one. The index meanings shown are abbreviated: a trained analyst works from the publisher's data card.

Three things to know before you rely on one. First, the times are for a defined normal pace, so you do not rate them, but you do still add allowances. Second, they cover manual motion only. Machine and process time come from somewhere else. Third, the analysis describes a method, and if the real method turns out different, the time is for a job nobody is doing.

Adding allowances, and what to leave out

Everything so far is normal time: what the work takes at a normal pace with no interruptions. Nobody works a shift like that. An allowance covers personal needs, fatigue and small unavoidable delays, and turns normal time into standard time.

Use the allowance your plant already applies to similar work, and use the same convention. The ILO form is standard time = normal time x (1 + allowance). Some plants divide by one minus the allowance instead, which gives a slightly larger number. Either is fine as long as the estimate and the later time study use the same one.

  • Leave learning out. The estimate is for a trained operator. The slow first weeks belong in the ramp plan, as a separate number.
  • Leave scrap and rework out of the time. Carry them as a yield assumption next to it.
  • Leave balance loss out of the work content, but remember it when you count operators. Five stations never share the work perfectly.
  • Do not add a private safety margin on top of the allowance. If you are unsure, widen the range and say why.

Uncertainty: why the estimate is a range

A single number hides the one thing the reader most needs to know, which is how far to trust it. An estimate of 482 seconds built from last month's time study of a near-identical part is a different object from 482 seconds built from a sketch. A range shows the difference.

Give every element a low, a likely and a high. The low is the time if everything about the design turns out easy. The high is the time if the awkward things you can already see turn out as awkward as they look. Neither is a disaster case.

Adding all the lows and all the highs gives the widest range, because it assumes every element lands at the same end together. A common alternative is the three-point convention from project planning (PERT): the expected value of each element is (low + 4 x likely + high) / 6 and its standard deviation is (high minus low) / 6, and the deviations combine as the square root of the sum of their squares. That gives a much tighter band, but it assumes the errors are independent. They rarely are. One estimator, one set of beliefs about the fixtures, one drawing: when one element is optimistic the rest tend to be. The truth often sits between the two bands, so use the wide one for decisions that are expensive to reverse.

  • State the likely figure and the range together, always. Never let the likely figure travel alone.
  • List the assumptions: volume and takt, shifts, the tooling and fixtures you assumed, the level of automation, the allowance.
  • Name the two or three elements that carry most of the range. That tells the design team where an answer would help most.
  • Say what is not included: learning, scrap, material handling to the line, changeovers.
  • Give the date of the next check, which is the first prototype build.

A range covers uncertainty in the elements you listed. It cannot cover an element you did not list. That is why the element walk-through with the design engineer matters more than the arithmetic.

Worked example: estimating a pump before it exists

A plant builds a small coolant pump, the CP-30, and is asked to quote its successor, the CP-40. The new pump has a third gear, a new lip seal on the shaft, eight cover screws and, for the first time, an electrical connector. Nothing has been built. Demand is 225 a day on one 450 minute shift, so takt is 27,000 / 225 = 120 seconds. The plant's allowance is 12 percent.

The engineer walks the assembly sequence with the designer and writes eight element groups. Four are carried over from the CP-30, whose standard was re-studied last year. One is scaled. One comes from the element library. Two are new and are analysed with a predetermined time system from the drawing.

Illustrative: the CP-40 estimate, in seconds of normal time
Element groupBasisLowLikelyHigh
Housing: unpack, check, load to fixtureCP-30 standard, same element303438
Press two bearingsCP-30 standard, same press404450
Gear set and shaft (3 gears)CP-30: 38 s for 2 gears, scaled to 3 = 57 s525766
Shaft seal press (new lip seal)Predetermined times from the drawing303646
Gasket, cover and 8 screwsElement library: 22 s + 8 x 7 s = 78 s727888
Coupling and connector (new)Predetermined times, no part to hold yet405272
Leak and run test: load, connect, unloadCP-30 standard, same tester364046
Label, final check, packCP-30 standard, same pack848996
Total normal time384430502

The test itself runs for 45 seconds on the machine. That is machine time, listed apart: the operator packs the previous pump while it runs.

Where the uncertainty sits: low, likely and high for each element group

Example numbers
  • Housing to fixture30 · 34 · 38 s
  • Two bearings40 · 44 · 50 s
  • Gears and shaft52 · 57 · 66 s
  • Shaft seal30 · 36 · 46 s
  • Cover, 8 screws72 · 78 · 88 s
  • Coupling, connector40 · 52 · 72 s
  • Test handling36 · 40 · 46 s
  • Label and pack84 · 89 · 96 s
  • CP-30 history
  • Element library
  • Predetermined times
  • Likely
Total normal time384 · 430 · 502 s

Range bars for the eight element groups, in seconds of normal time. Housing to fixture: 30 to 38, likely 34, from history. Two bearings: 40 to 50, likely 44, from history. Gears and shaft: 52 to 66, likely 57, from history. Shaft seal: 30 to 46, likely 36, from predetermined. Cover, 8 screws: 72 to 88, likely 78, from library. Coupling, connector: 40 to 72, likely 52, from predetermined. Test handling: 36 to 46, likely 40, from history. Label and pack: 84 to 96, likely 89, from history. Totals: 384, 430 and 502.

Bar length is doubt, not work. Coupling, connector is 12% of the likely time and 27% of the total range, because nobody has held the part. The elements carried over from the CP-30 have short bars.

Now the allowance and the takt.

Illustrative: from normal time to operators
LowLikelyHigh
Normal time384 s430 s502 s
Standard time = normal x 1.12430 s482 s562 s
Operators = standard / 120 s takt3.64.04.7
Operators, rounded up455

482 / 120 is 4.01, which rounds up to 5. Four operators would be 100.3 percent loaded before any balance loss.

The estimate reads: about 482 seconds of work content, between 430 and 562. Five operators on five stations, with an average station cycle near 96 seconds against a 120 second takt. Four operators would only work at the very bottom of the range.

Look at where the range comes from. The coupling and connector group is 12 percent of the likely work (52 of 430 seconds) and 27 percent of the range (32 of the 118 seconds between low and high). It is the one element nobody has held in their hands. If the design team can produce a sample connector, that single answer narrows the estimate more than anything else.

The three-point convention gives an expected 434 seconds of normal time, which is 486 standard, with a standard deviation of 8.6 seconds. Two deviations either side is 469 to 504. That band would be right if the eight errors were independent. The plant quoted on the wide range.

How the estimate held up

The playbook follows this pump to the end. The first prototype builds came in at 566 seconds, just outside the range, because the connector cable had to be routed through a clip that was not on the drawing at quote. After two design changes it was 539. Ninety days into production the standard was locked at 528 seconds: inside the range, 46 seconds above the likely figure, and still five operators. The tight band of 469 to 504 would have missed it.

How the estimate held up against what was measured later

Example numbers
The quoted range against what later studies measuredA number line from 420 to 620 seconds. The quoted range runs from 430 to 562 with the likely figure at 482. The tighter band that assumes independent errors runs from 469 to 504. Later results: Standard locked at day 90 528, After the design change 539, First prototype 566. Four operators can absorb 480 seconds and five can absorb 600.4 operators: 480 s5 operators: 600 sQuoted range: 430 to 562 s469 to 504 if independent440480520560600Locked: 528 sAfter change: 539 sPrototype: 566 s

A number line from 420 to 620 seconds. The quoted range runs from 430 to 562 with the likely figure at 482. The tighter band that assumes independent errors runs from 469 to 504. Later results: Standard locked at day 90 528, After the design change 539, First prototype 566. Four operators can absorb 480 seconds and five can absorb 600.

The locked standard, 528 s, landed inside the quoted range and outside the tight band. The first prototype, 566 s, landed just outside both, because of an element that was not on the drawing. All three later figures sit between the four-operator and five-operator lines, which is the decision the range was for.

What to ask engineering for

Most bad estimates come from a thin design pack, not from bad arithmetic. Ask for these before you start, and write down which ones you did not get. Each missing item is an assumption.

The design pack for a cycle time estimate
Ask forWhy you need it
Drawing or 3D model, and the bill of materialsPart count, fastener count and types
Which parts and operations carry over, and from which productTells you which existing standards you can use
The intended assembly sequence, or an exploded viewThe element list and its order
Fits and tolerances on mating partsA press fit and a slip fit are different elements
Fastener sizes, torque values and tightening sequenceTool choice and time per fastener
Adhesives, sealants, cure and settle timesProcess time that no one can shorten
Test specification and test durationMachine time, and what the operator does meanwhile
Part weights and sizesHandling time, two-person lifts, lift assists
Cables, hoses and anything flexibleRouting is slow and is often missing from the drawing
Special characteristics and required inspectionsEvery check is an element
Labelling, traceability and packaging specificationA fifth of the work in the worked example, and usually decided last
Volume, mix and variants by yearTakt, and how much of the work differs by variant
Fixture, tooling and automation conceptThe method your times assume
Open design items likely to changeWhere to put the widest ranges

Limits and common mistakes

An estimate is the wrong tool once you can observe the work. The day a prototype exists, time it. The day the line runs, film it. The estimate's job is to get you to a sensible quote and a sensible first line plan, then be replaced.

Six mistakes in estimating a new product
MistakeWhat happensDo this instead
Scaling the old product's total by a percentageThe new elements are buried in an averageEstimate element by element
Forgetting the unglamorous elementsUnpacking, routing, labels and checks turn up at prototypeWalk the sequence with the designer
Treating machine time as work contentOperators are counted for time the machine is runningList machine time apart and decide what the operator does
Mixing learning into the estimateThe standard is inflated and the ramp is still not plannedEstimate for a trained operator and plan the ramp separately
Reporting one numberThe quote is read as a promiseReport the range and the assumptions
Never checking it against the real standardThe same error goes into every quoteRecord estimate against locked standard for each launch

One more limit: an estimate describes a method, and methods belong to people. When the line starts, the operators will find a better sequence than the one you assumed. Plan to update the numbers with them, not to hold them to yours.

Tools and related guides

Your next estimate is only as good as your record of the last product. In LeanSuite's time and motion study you film a station on a phone, the AI times every element and you review and certify it, so the predecessor's element times are measured and kept under its process when the next quote arrives.

FAQ

Questions about how to estimate cycle time for a new product

  1. List the work elements from the drawing and the assembly sequence. Take a time for each from the same element on an existing product, your element library, a predetermined time system such as MTM or MOST, or a mock-up. Add them, add your plant's allowance, and report a low, likely and high figure with the assumptions. Divide by takt to get operators.

  2. For a running process, cycle time = net production time / units produced. A station that makes 225 good units in 27,000 seconds of running time has a cycle time of 120 seconds. For one operator, time several cycles from the same point in each and average them. For a product that does not exist yet, you estimate the work content first.

  3. Total cycle time, also called work content, is the sum of the cycle times of every step needed to make one unit: step 1 + step 2 + and so on to the last step. Divide it by takt time to get the number of operators the work needs. For example, 482 seconds of work at a 120 second takt needs 4.01 operators, so plan five.

  4. Cycle time is how long one step, or one station, takes to complete one unit. Lead time is how long a unit takes to travel from order or first operation to delivery, including every wait in between. A pump can have 8 minutes of cycle time across its stations and a lead time of several days, because most of the lead time is waiting.

  5. There is no universal ideal. For a manual station the target is a cycle time a little under takt time, so the line keeps up with demand without overproducing. In an OEE calculation, ideal cycle time means something narrower: the fastest time the equipment is designed to make one part, used to work out the performance factor.

  6. A TMU is a time measurement unit, the unit used by predetermined time systems such as MTM and MOST. One TMU is 0.00001 hour, which is 0.0006 minutes or 0.036 seconds, so 1,000 TMU is 36 seconds. It is small because the basic motions it measures, such as a reach or a grasp, take fractions of a second.

  7. It depends on how much of the work is carried over from a product you already time. Elements with a recent standard can be close. New elements estimated from a drawing can be far out, and an element missing from the drawing is not in the estimate at all. Report a range, then compare it with the standard you finally set so you learn your own error.

  8. Yes. Predetermined times are set at a defined normal pace, so you do not apply a performance rating, but they contain no time for personal needs, fatigue or unavoidable delays. Add the same allowance your plant uses for a stopwatch study of similar work, with the same formula, so the estimate and the later standard are comparable.

Or browse the topics, the full library and the lean glossary.

Rather see it on your own problem?

Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.