Precedence diagram template, with the precedence matrix and positional weights

A precedence diagram is the map of what must be done before what: one node per work element, one arrow from each immediate predecessor. Every line balancing method reads from it. This template takes up to 15 elements. You list them in an order the job could be done in, give each a time, and type the letters of its immediate predecessors. The sheet builds the precedence matrix (a 1 where the row element comes immediately before the column element), checks that every letter you typed is an element listed above, works out each element's positional weight (its own time plus the time of every element that follows it, directly or through a chain) and ranks them. It also places each element in its diagram column and lays them out on a grid you print and add arrows to. Type a takt time and it shows the total work and the fewest stations the line could have. The example is a 12-element cordless drill line.

See the sheet before you downloadPDF, 2 pages. Also Excel

Free to use: print it, copy it and edit it for your team. Enter your name and work email once to download.

Page 1 of the precedence diagram templateAn element table with times, predecessors, weights and ranks beside a dot grid.
15 elementsImmediate predecessorsPrecedence matrixPredecessor checkPositional weightsRanksDiagram grid12-element example

Page 1 of the real file. PDF, 2 pages. Also Excel.

When to use it

When to use a precedence diagram

  • Before any line balance, by hand or in software: the diagram is the input.
  • When a new product is being planned and nobody has written down which steps depend on which.
  • When a balance on paper keeps failing on the floor, to find the arrow that was invented and the one that was missed.
  • When demand changes and elements have to move between stations: the diagram shows which ones are free to move.
  • When you want to apply ranked positional weight and need the weights worked out without counting followers by hand.

How to fill it in

  1. 1

    List the elements and their times

    Take the element list from a time study. Put it in an order the job could be done in, so every element sits below everything it must come after.
  2. 2

    Type the immediate predecessors

    For each element, the letters of the last things that must be done before it, with commas. Immediate means only the last ones: if A leads to B and B leads to D, D's predecessor is B, not A.
  3. 3

    Check the matrix

    The matrix shows a 1 for every arrow. The check column turns red when a letter is missing or is listed below the element that needs it. Fix the order or the letter.
  4. 4

    Read the weights and ranks

    Positional weight is the element's own time plus the time of everything that follows it. Rank 1 is the largest. Ties go to the longer element, which is the sheet's own rule: the sources leave ties open.
  5. 5

    Print the grid and draw the arrows

    Each element appears in its diagram column with its time and its predecessors. Draw one arrow from each immediate predecessor and no arrow that is already implied.
  6. 6

    Walk it with the people who do the job

    An operator and the process engineer will find the dependency you assumed. Then use the ranks to fill the stations.

What is in the download

Every page and every sheet of the Precedence diagram template

2 PDF pages and 4 Excel sheets, as they come. The worked examples use made-up numbers.

Excel, 4 sheets

The pictures show the top of each sheet with the formulas worked out; the file keeps every row.

A filled-in example

Illustrative, not a benchmark

Illustrative example, not a customer: a line that assembles a cordless drill, with a 50 second takt.

  • The line has 12 elements, A to L, from placing the left housing half in the fixture (6 s) to label and pack (13 s). Total work is 213 seconds.
  • A has no predecessor. B, C, E and H need only A. D needs B and C, F needs C and E, G needs B. I needs D, F and H; then J, K (which also needs G) and L follow in a chain.
  • The matrix has a 1 for each of the 16 arrows. The diagram has seven columns: A; B, C, E and H; D, F and G; then I, J, K and L one by one.
  • A's positional weight is 213, the whole job. D's is 32 + 6 + 34 + 22 + 13 = 107 and E's is also 107; D is longer, so D ranks fourth and E fifth. G ranks tenth with a weight of 49.

At a 50 second takt the line needs at least 5 stations: 213 / 50 = 4.26, rounded up. The line and its times are made up; they are the worked example of our line balancing guide, where the ranks fill five stations.

Common mistakes

  • Typing every upstream element as a predecessor

    Only the immediate ones belong in the list. Extra letters draw arrows that are already implied and clutter the diagram.

  • Listing elements out of order

    The sheet reads predecessors from the rows above. An element listed above something it depends on is flagged in the check column and left out of the weights until the order is fixed.

  • Inventing dependencies

    This is how we do it is not the same as this must come first. Each false arrow takes away freedom the balance needs. Ask what physically stops the other order.

  • Leaving the rules that are not arrows off the page

    Elements that must share a station, or must not, and elements tied to a fixed machine are not precedence. Write them beside the list so the balance respects them.

Download the template

Free to use: print it, copy it and edit it for your team. Enter your name and work email once to download.

Run this template in LeanSuite

If you want the element times from video instead of a stopwatch, LeanSuite's line balancing page covers that: drop in a video of your line and get a Yamazumi chart, a takt comparison and rebalancing recommendations.

See it in a 45-minute demo

FAQ

Precedence diagram template: common questions

  1. A precedence diagram shows the order in which the elements of a job can be done. Each element is a node, and an arrow runs from each element to the ones that cannot start until it is finished. Elements with no arrow between them, directly or through a chain, can be done in either order. Line balancing uses it to decide which elements may share a station.

  2. An immediate predecessor is an element that must be finished just before another can start, with nothing required in between. If the housing must be in the fixture before the motor is fitted, and the motor before its leads are connected, the immediate predecessor of connecting the leads is fitting the motor. The fixture step is upstream, but it is not immediate.

  3. A precedence matrix holds the same information as the diagram in rows and columns. The elements are listed down the side and across the top, and a 1 marks each cell where the row element is an immediate predecessor of the column element. It is easier to check and to compute from than a drawing, which matters once a line has more than a dozen elements.

  4. An element's positional weight is its own time plus the times of all the elements that follow it in the precedence diagram, directly or through a chain. On the example line, D takes 32 seconds and is followed by I, J, K and L, so its weight is 32 + 6 + 34 + 22 + 13 = 107 seconds. In ranked positional weight, elements are assigned to stations in order of weight, largest first.

  5. No. It places each element in its column on a grid, with its time and the letters it comes after, and you draw the arrows on the printout. A spreadsheet cannot route arrows well, and drawing them is where you notice the one that should not be there. The PDF example shows the finished drawing.

More free templates

All templates
Browse all 312 templates

Can't find the template you need?

Tell us what you're looking for. We'll make it and send it to your inbox, free.

A shift handover sheet, a red tag log, a changeover checklist for one machine: if your team uses it on the floor, ask.

By sending this form you agree to our Terms of Service and Privacy Policy.

Pass it on

We want LeanSuite to be the best place on the internet for lean help. If this was useful, send it to someone on your team or in your network who needs it.