Assembly time estimate worksheet: a low, likely and high time before the product exists

An assembly time estimate is a forecast of the operator time to build a product from its drawing and bill of materials, made before any part has been assembled. This worksheet builds it from your own times for a short list of basic motions, such as handling a small part, inserting with a loose fit, or driving a fastener with a power tool. Each line of the bill gets a quantity and up to two motions, plus any fixed add-on seconds, and the sheet works out a low, a likely and a high time for the line, adds them up as normal time, adds the allowance to give standard time, and divides by takt time to give the operators. It also shows each line's share of the low to high range, so you can see which line carries the uncertainty. The motion times on the example are placeholders to show the sums, not times to use.

See the sheet before you downloadPDF, 2 pages. Also Excel

Free to use: print it, copy it and edit it for your team. Enter your name and work email once to download.

Page 1 of the assembly time estimate worksheetA time basis of eleven basic motions, a result box, and a bill table with low, likely and high columns.
11 basic motionsLow, likely and high13 bill linesFixed add-on secondsRange share by lineAllowance, two conventionsTakt timeOperators needed

Page 1 of the real file. PDF, 2 pages. Also Excel. See every page

When to use it

When to use the assembly time estimate worksheet

  • When you are quoting a product that has a drawing and a bill of materials but no prototype yet.
  • When a sales or engineering team asks for a labor number and you can only give it as a range.
  • When two designs are being compared and you want to see which one costs fewer seconds to assemble.
  • When you need a first idea of how many operators a new line will need before the line is planned.
  • When the estimate is being reviewed and you want to show what it is made of, line by line.

How to fill it in

  1. 1

    Enter the header and the demand

    Write the product and revision, the drawing reference, and the demand and the available time a day. The sheet works out the takt time from them.
  2. 2

    Fill in your own time for each basic motion

    The eleven motions are the list to use as a start. For each, write a low, a likely and a high time in seconds from your own plant records, video of similar work or an earlier study, and write where it came from. Never copy a published table of times into the cells without saying so.
  3. 3

    List the parts and operations of the bill

    One line for each part or operation: the name, the quantity and the number of the basic motion for it. A second motion is for the line that needs two, such as orient and then insert. Use the add-on columns for fixed seconds that are not per part, such as a test run or a label.
  4. 4

    Choose the allowance and how it is applied

    Write the allowance as a percent of normal time and pick how your plant applies it: added to normal time, or taken as a share of the shift. The two give slightly different numbers, so use the one your other standards use.
  5. 5

    Read the result as a range

    The standard time and the operators come out as a low, a likely and a high. If the range spans two numbers of operators, the estimate alone cannot settle the staffing. Look at the range share column to see which line to firm up first.
  6. 6

    Replace the estimate with measurements as they arrive

    When the prototype is built, time it and write the result into the new product time study plan. Keep the estimate: the gap between it and the measurement is how your next estimate improves.

What is in the download

Assembly time estimate worksheet: every page of the PDF

All 2 pages, pictured from the file you download. The download also comes as Excel.

  1. Page 1 of 2 of the Assembly time estimate worksheet PDF: Assembly time estimate worksheet
    PDF page 1 of 2Assembly time estimate worksheet
  2. Page 2 of 2 of the Assembly time estimate worksheet PDF: Assembly time estimate worksheet: example
    PDF page 2 of 2Assembly time estimate worksheet: example
Back to the download buttons

A filled-in example

Illustrative, not a benchmark

An illustrative example, not a customer: a small valve actuator that nobody has built yet, 240 a day on one 450 minute shift. The motion times are placeholders.

  • Thirteen lines give a normal time of 104.4 seconds at the low end, 149.7 as the likely figure and 224.9 at the high end.
  • At a 12 percent allowance added to normal time, the standard time is 116.9, 167.7 and 251.9 seconds.
  • Takt is 27,000 seconds divided by 240, or 112.5 seconds, so the operators are 1.04, 1.49 and 2.24: two, two and three after rounding up.
  • The eight cover screws carry 36 of the 120.5 seconds between low and high, 30 percent of the range, because the fastener and the tool are not chosen yet.

The estimate says two operators, with a real chance of three, and says fixing the fastener and the tool would narrow it more than anything else. The product, times and result are made up to show how the sheet works.

Common mistakes

  • Giving one number

    A single figure hides how little is known. A low, likely and high show which lines are firm and which are guesses, and the staffing may change across the range.

  • Using times from a table without checking them

    A table of times belongs to the conditions it was measured in. Put your own times in the cells and name their source, even if the source is another product's study.

  • Counting machine time as operator time

    A test that runs 45 seconds on a machine is not 45 seconds of operator time. List the operator's part of it, loading and unloading, and keep the machine run apart.

  • Using the allowance twice

    If the times you started with already include allowances, adding another overstates the standard. Check what your motion times contain before choosing the allowance.

  • Not saying which line carries the range

    An estimate with a wide range is useful when you know why it is wide. The range share column points to the one or two lines worth firming up first.

Download the template

Free to use: print it, copy it and edit it for your team. Enter your name and work email once to download.

Run this template in LeanSuite

LeanSuite's Vision AI does the time study from one phone video of the process: it times every element, splits each operator's time into value-added, semi-value-added and non-value-added, and links each figure to its video frame for you to review and certify.

See it in a 45-minute demo

FAQ

Assembly time estimate worksheet: common questions

  1. List every part and operation from the drawing and the bill of materials, give each a count of basic motions such as handling, orienting, inserting and fastening, and multiply by your own time for each motion. Do it three times, low, likely and high, add the lines up, and apply the allowance. The result is a range, not a single figure.

  2. From your own plant: earlier time studies of similar work, video of comparable assemblies, or a quick study of a mock-up. Published tables of predetermined times exist, but many are licensed and tied to a method. The worksheet has a column to name the source of each time so the estimate can be audited.

  3. Normal time is the time a trained operator needs at a normal pace with no interruptions. Standard time is normal time plus an allowance for rest, personal needs and unavoidable delay. The sheet shows both. Two forms of the allowance are common: adding a percent to normal time, or taking a share of the shift.

  4. Divide the standard time by the takt time. In the example, 167.7 seconds against a takt of 112.5 seconds is 1.49 operators, which rounds up to two. The sheet does this for the low, likely and high times, so you can see whether the range crosses a whole number.

  5. It is as good as the motion times and the bill behind it, and it gets better each time you compare it with a measured result. That is why it gives a range and a range share by line. Treat it as a guide for quoting and for planning the line, and replace it with the measured standard at day 90.

More free templates

All templates
Browse all 312 templates

Can't find the template you need?

Tell us what you're looking for. We'll make it and send it to your inbox, free.

A shift handover sheet, a red tag log, a changeover checklist for one machine: if your team uses it on the floor, ask.