Practical guide · Lean manufacturing fundamentals
Labor losses in manufacturing: 13 losses a time study should expose
Short answer
A labor loss is paid time that does not turn into good product. A time study should expose 13 of them: walking, searching, reaching and bending, double handling, starving, blocking, machine watching, over-processing, rework, imbalance, changeover, micro-stops and learning.
Labor losses come in two layers. The first is time lost against the standard: idle time, working slower than standard and time spent on bad units. Labor reports and overall labor effectiveness (OLE = availability x performance x quality) measure this layer. The second is waste built into the standard itself: walking, reaching, double handling and machine watching that were there when the job was timed, so the report counts them as earned hours. Only a time study that classifies every element finds the second layer, and it is often the larger one.
Last reviewed:
What is a labor loss?
Where 45 paid hours went: two readings of one shift
Example numbersWhat the labor report sees
What a time study sees in the same hours
- Lost against the standard: 10.8 h
- Waste built into the standard: 11.4 h
- Necessary work: 8.55 h
- Value added: 14.25 h (31.7% of paid hours)
One bar of 45 paid hours read twice. The labor report sees 10.8 hours lost against the standard and 34.2 hours earned, an overall labor effectiveness of 76.0%. The time study splits the earned hours into 11.4 hours of waste built into the standard, 8.55 hours of necessary work and 14.25 hours of value-added work, 31.7% of the paid hours.
A labor loss is any paid labor time that does not end up as good product made by the best known method. An operator waiting for parts is a loss. So is an operator walking six steps to a rack every cycle, even when the cycle is on standard and the labor report shows 100 percent.
That second case is the reason to study the work and not just read the report. A labor report compares actual hours with standard hours. It can only see losses against the standard. If the walk was there on the day the job was timed, the walk is inside the standard, and every report since has counted it as hours earned.
Almost none of these losses are about effort. Starving, blocking, imbalance, long reaches and double handling are designed into the line, the layout and the schedule. The people doing the job did not choose them and cannot remove them alone. Keep that in view when the numbers come out.
The labor loss tree
A loss tree breaks one big number into parts until each part has a cause someone can fix. For labor, the first split is the one that matters most: is the loss measured against the standard, or hidden inside it?
The labor loss tree
Paid labor hours that did not become good product
Lost against the standard
The labor report sees it
Not workingOLE availability
- Starving
- Blocking
- Changeover
Working below standardOLE performance
- Searching
- Micro-stops
- Learning
Working on bad productOLE quality
- Rework
Built into the standard
Only a time study sees it
Movement
- Walking
- Reaching and bending
- Double handling
Built-in waiting
- Machine watching
- Imbalance
Extra work
- Over-processing
Paid labor hours that did not become good product split into two layers. Lost against the standard, which the labor report sees: not working (starving, blocking, changeover), working below standard (searching, micro-stops, learning) and working on bad product (rework). Built into the standard, which only a time study sees: movement (walking, reaching and bending, double handling), built-in waiting (machine watching, imbalance) and extra work (over-processing).
- Against the standard, not working: the crew is paid and present, and no work is being done. Starved for parts, blocked by the next station, waiting out a changeover.
- Against the standard, working below it: the job is running, slower than standard. Micro-stops, searching, people still learning the job.
- Against the standard, working on bad product: hours that went into units that were scrapped or had to be made again. Rework.
- Inside the standard, movement: walking, reaching and bending, double handling.
- Inside the standard, built-in waiting: machine watching and the idle time that line imbalance gives every station but the slowest.
- Inside the standard, extra work: over-processing.
The first three branches line up with the three factors of overall labor effectiveness: availability, performance and quality. The last three do not show in any ratio that uses the standard as its yardstick. A loss can also move between branches. Rework with its own routing and its own standard time becomes earned hours, and drops out of sight.
Plants that run World Class Manufacturing will know the same losses by their cost deployment names. NVAA, non value added activity, covers the movement and extra work inside the cycle. Unbalancing is imbalance. And an operator left waiting by a breakdown is booked as a resultant loss of that breakdown, so the cost lands on the cause and not on the station where the waiting shows.
To build the tree for your own area in hours or dollars, the loss tree worksheet lists each item under its parent and works out its share. For machine time, as opposed to people's time, the matching breakdown is the six big losses worksheet.
Movement losses: walking, searching, reaching and double handling
Movement losses are the easiest to see on video and the cheapest to remove. They sit inside the cycle, so they repeat with every unit.
Four movement losses at one bench, seen from above
Walking. The rack is three steps from the bench, so every cycle starts with a walk there and back.
Searching. Tools lie loose on the bench with no fixed place. The hand hovers before it picks.
Reaching and bending. A high-use bin sits outside the shaded zone of easy reach, so each pick is a stretch.
Double handling. The part goes from tote to bench, then from bench to fixture: two touches where one would do.
A top view of a workstation. The operator stands at a bench with a shaded zone of easy reach. A rack stands away from the bench with a dashed walking path to it. Loose tools lie on the bench. One bin sits outside the reach zone. A part moves from a tote to the bench and then to the fixture.
Movement losses: what to look for, how to measure and how to remove
1. Walking
- What it looks like on video
- The operator's feet leave the work position: to a rack, a bin, a printer, another machine. Hands are empty or carrying, and nothing happens to the product.
- How to measure it
- Seconds per cycle with the feet moving, and steps or meters per cycle. Trace the route on a spaghetti diagram.
- How to remove it
- Bring parts and tools to the point of use. Shorten the route with a U-shaped layout. Have material delivered on a set route.
2. Searching
- What it looks like on video
- The head turns and the hands pause over a bench or a bin. A tool is picked up and put back. Someone leaves the frame to ask.
- How to measure it
- Count how often it happens and time each one. It is irregular, so film long enough to catch several.
- How to remove it
- A fixed, marked place for every tool and part, which is what 5S is for. Kit parts in assembly order.
3. Reaching and bending
- What it looks like on video
- Arms at full stretch, a hand above the shoulder or below the knee, the trunk bent or twisted to get a part.
- How to measure it
- Seconds per reach and reaches per cycle outside easy arm's length. Note the posture for an ergonomic check.
- How to remove it
- Put the high-use parts inside easy reach, between hip and shoulder height. Tilt the bins. Raise the pallet.
4. Double handling
- What it looks like on video
- The same part is picked up twice: tote to bench, bench to fixture. Parts are unwrapped, restacked, turned over or moved from one container to another.
- How to measure it
- Count the touches per part and the seconds per touch. One pick and one place is the minimum.
- How to remove it
- Present the part in the position it is used in. Take out the containers in between. Combine the pick with the load.
Reaching and bending are a labor loss and a strain on the body at once. When the study flags them, look at the posture as well as the seconds.
Waiting losses: starving, blocking and machine watching
Waiting is the loss people stop seeing first, because a person who is waiting looks calm and the line looks under control. There are three kinds, and they have different causes. A stopwatch study often misses the first two, because the observer pauses the watch when the work stops.
Three kinds of waiting, and where the cause sits
Starved
B is ready. The slots before it are empty, because A is slow or stopped.
Blocked
B has finished a part. The slots after it are full, because C is slow or stopped.
Machine watching
The machine is running on its own. The operator stands and waits for the cycle to end.
Three drawings. Starved: station B is ready and the buffer slots before it are empty. Blocked: station B has finished and the buffer slots after it are full. Machine watching: the operator stands in front of a machine that is running on its own.
Waiting losses: what to look for, how to measure and how to remove
5. Starving
- What it looks like on video
- The operator is ready, hands empty, looking upstream. The infeed is empty: no part has arrived from the station before, or the material has run out.
- How to measure it
- Seconds per cycle and minutes per shift with no part to work on. Note what was missing each time.
- How to remove it
- Fix the cause upstream, which is usually the slow station or a late delivery. Rebalance the work. Hold a small, sized buffer where it is needed.
6. Blocking
- What it looks like on video
- The operator has finished a part and is holding it or standing next to it. The outfeed is full: the next station has not taken the last one.
- How to measure it
- Seconds per cycle and minutes per shift with a finished part and nowhere to put it.
- How to remove it
- Fix the slow station downstream. Rebalance. Do not add buffer to hide it unless the stop is short and rare.
7. Machine watching
- What it looks like on video
- The machine is running and the operator stands in front of it, arms folded or a hand on the guard, until the cycle ends.
- How to measure it
- Seconds per cycle of machine time with no manual work. A standard work combination table shows it as a gap in the operator's line.
- How to remove it
- Let the machine stop itself on a fault. Give the operator work during the cycle: load the next machine, or prepare the next part.
Starving and blocking are symptoms. The cause sits at another station, so the fix is rarely at the station where the waiting shows. Machine watching is different: it is designed into the job and repeats every cycle, which is why it usually sits inside the standard.
Extra work: over-processing and rework
These two are real work, done with care. That is what makes them hard to challenge.
Extra work losses: what to look for, how to measure and how to remove
8. Over-processing
- What it looks like on video
- More than the drawing asks for: an extra wipe, a third check, a bolt tightened past the click, tape where a clip would hold, a form filled in twice.
- How to measure it
- List each element against the specification. Time the ones the specification does not call for.
- How to remove it
- Agree the standard with quality and engineering, write it down and train to it. Remove checks that repeat an earlier check.
9. Rework
- What it looks like on video
- A part comes back to the bench. A fastener is backed out and redone. A unit is pulled aside, fixed and put back in the flow.
- How to measure it
- Time each rework as its own element and count how often it happens. Seconds per rework x reworks per 100 units.
- How to remove it
- Find the cause of the defect and fix it at the source. Error-proof the step. Do not give rework its own standard time, or it disappears from the report.
System losses: imbalance, changeover, micro-stops and learning
The last four come from how the line is set up and scheduled. No single station owns them.
Imbalance: each operator's work against the 36 second line cycle
Example numbers- Work per filter, seconds
- Idle, waiting for the line: 14 s in all
Six columns, one per operator, against a line cycle of 36 seconds. Work per filter: 36, 34, 31, 36, 33, 32 seconds. Idle per filter: 0, 2, 5, 0, 3, 4 seconds, 14 seconds in all.
System losses: what to look for, how to measure and how to remove
10. Imbalance
- What it looks like on video
- One operator never stops and the next one waits a few seconds every cycle. Film two stations side by side and the pattern is plain.
- How to measure it
- Each operator's work time against the line's cycle. Idle seconds per cycle = line cycle time minus the operator's work time. Stack it on a Yamazumi chart.
- How to remove it
- Move elements from the full station to the idle one. See line balancing.
11. Changeover
- What it looks like on video
- The line stops making parts. People fetch tools, wait for a die cart, adjust, run trial pieces and wait for a first-off approval.
- How to measure it
- Labor minutes from the last good part of one run to the first good part of the next, for everyone involved, split into work that needed the line stopped and work that did not.
- How to remove it
- Prepare before the line stops and standardize what is left, which is the SMED method.
12. Micro-stops
- What it looks like on video
- A jam cleared by hand, a part reseated, a sensor wiped, a label that did not feed. Each one is a few seconds and nobody writes it down.
- How to measure it
- Count them and time them from video or from a machine signal. Group them by cause. A log kept by hand will undercount.
- How to remove it
- Fix the top cause first: the feed, the sensor or the part variation behind it.
13. Learning
- What it looks like on video
- A new operator stops to look at the instruction, moves in a different order each cycle and is helped by a neighbor.
- How to measure it
- A new operator's cycle time against the standard, tracked by day until it levels out.
- How to remove it
- Train with a clear method, element by element, before the person joins the line. Plan the ramp into the schedule so it is not found as a surprise.
Learning is the one loss on this list that should not be driven to zero by pressure. Nobody starts a job at standard, and a planned ramp is a cost of bringing someone in. The loss to remove is the unplanned part: no training method, no instruction and no time set aside.
How to measure labor losses with a time study
The method is an ordinary time study with two changes: nothing is left out, and every element gets a class and a loss type.
From video to a ranked list of losses
- 1
Film the whole job, including the gaps
- 2
Break the job into elements
- 3
Classify every element
- 4
Tag each waste element with one of the 13 losses
- 5
Record how often the irregular ones happen
- 6
Convert seconds per unit into hours per week
- 7
Rank the losses and pick the first one
- 1
Film the whole job, including the gaps
Keep the camera running between cycles. Waiting, searching and micro-stops happen in the gaps, and a study that only times clean cycles will not find them. Film more than one operator and more than one time of day.
- 2
Break the job into elements
Split wherever the kind of activity changes, so a walk is not buried inside an assembly element. The guide to breaking a job into elements covers the break points.
- 3
Classify every element
Value added, necessary or waste, using written rules. The guide to value added vs non value added has the tests and the hard cases.
- 4
Tag each waste element with one of the 13 losses
A class says the time is waste. The loss type says what kind, and so who can fix it: layout for walking, the upstream station for starving, quality for rework.
- 5
Record how often the irregular ones happen
Rework, searching, micro-stops and changeovers do not come every cycle. Time each one, count how often it occurs and spread it over the units made.
- 6
Convert seconds per unit into hours per week
Hours per week = seconds per unit x units per week / 3,600. Ten seconds of walking per unit looks small. At 3,000 units a week it is 8.3 labor hours.
- 7
Rank the losses and pick the first one
Sort by hours per week. Start with the largest loss that the team in the room can fix. Study the job again after the change, because removing one loss often exposes the next.
The formulas: utilization, efficiency, line efficiency and OLE
Four ratios describe the losses against the standard. They are built from the same four numbers: hours paid, hours worked, standard hours produced and good units. Names vary between plants and textbooks, so write your own definitions down before comparing anything.
| Ratio | Formula | What it shows | What it misses |
|---|---|---|---|
| Labor utilization | Hours worked / hours available | How much of the paid time the crew had work to do | How well the working time was used |
| Labor efficiency | Standard hours produced / hours worked | Output against the standard while working | Idle time, and anything wrong with the standard |
| Line efficiency | Standard minutes produced / minutes attended | Utilization and efficiency in one number | Which of the two is the problem, and quality |
| Overall labor effectiveness (OLE) | Availability x performance x quality | Paid hours that became good units at standard | Waste built into the standard |
| Labor efficiency variance | (Actual hours minus standard hours allowed) x standard rate | The same gap as efficiency, in money | Everything efficiency misses |
Utilization and efficiency follow the common capacity-planning definitions. Line efficiency in this form is the sewing industry's, where standard minutes are SAM. OLE has no single standard: this is the version on the [OLE calculator](/tools/ole-calculator). In line balancing, line efficiency means something else: work content / (stations x cycle time).
How the labor ratios nest
Example numbersHours paid45.0 h
6 operators x 7.5 h
Hours worked40.5 h
40.5 / 45.0 = 90.0% availability, or labor utilization
Standard hours produced36.0 h
36.0 / 40.5 = 88.9% performance, or labor efficiency. 36.0 / 45.0 = 80.0% line efficiency
Standard hours of good units34.2 h
34.2 / 36.0 = 95.0% quality. 34.2 / 45.0 = 76.0% OLE
Four bars on one scale. Hours paid 45.0. Hours worked 40.5, which is 90.0% utilization. Standard hours produced 36.0, which is 88.9% efficiency and 80.0% line efficiency. Standard hours of good units 34.2, which is 95.0% quality and 76.0% overall labor effectiveness.
The three factors of OLE
- Availability = hours worked / hours paid, where hours worked is paid hours minus idle hours. Planned breaks are taken off the paid hours first. This is labor utilization under another name.
- Performance = standard hours produced / hours worked, where standard hours produced = standard time per unit x all units made. This is labor efficiency under another name.
- Quality = good units / all units made.
- OLE = availability x performance x quality. The short way to the same answer: standard hours of good units / hours paid.
Because OLE multiplies, three factors that each look acceptable give a result that does not: 90 percent x 89 percent x 95 percent is 76 percent. The OLE calculator runs the sum on your own hours and counts. For the machine version of the same idea, see how to calculate OEE.
A worked example: where 45 paid hours went
Illustrative example. Six operators run a filter assembly line for one shift. Each is paid for 7.5 hours of work after breaks. The standard time is 3.6 labor minutes per filter. The line makes 600 filters, of which 570 are good first time. The supervisor's log shows 4.5 labor hours of idle time, mostly waiting for housings.
Illustrative: overall labor effectiveness for the filter line
Example numbersOLE = availability × performance × quality
Check the short way: 34.2 / 45.0 = 76.0%. Line efficiency is availability x performance: 0.900 x 0.889 = 80.0%.
- Hours paid =6 operators x 7.5 h= 45.0 h
- Hours worked =45.0 minus 4.5 idle= 40.5 h
- Availability (labor utilization) =40.5 / 45.0= 90.0%
- Standard hours produced =600 units x 3.6 min / 60= 36.0 h
- Performance (labor efficiency) =36.0 / 40.5= 88.9%
- Quality =570 / 600= 95.0%
- Line efficiency =36.0 / 45.0= 80.0%
- Standard hours of good units =570 x 3.6 min / 60= 34.2 h
- OLE =0.900 x 0.889 x 0.950= 76.0%
So 10.8 of the 45 paid hours were lost against the standard: 4.5 hours idle, 4.5 hours working slower than standard, and 1.8 hours on the 30 filters that were not good. Most plants stop here. The labor report has nothing more to say.
What the time study adds
A video time study of the same line classifies the 3.6 standard minutes, 216 labor seconds, element by element.
| Class | Seconds per filter | Share of the standard | Hours in the shift's 570 good filters |
|---|---|---|---|
| Value added | 90 | 41.7% | 14.25 h |
| Necessary non value added | 54 | 25.0% | 8.55 h |
| Waste built into the standard | 72 | 33.3% | 11.40 h |
| Total | 216 | 100% | 34.20 h |
Waste inside the standard, seconds per filter: walking 22, machine watching 18, waiting from imbalance 14, double handling 12, over-processing 6. Hours = seconds x 570 / 3,600.
All eight losses on the filter line, in hours per shift
Example numbers- Idle, waiting for housings4.50 h
- Working slower than standard4.50 h
- Walking3.48 h
- Machine watching2.85 h
- Waiting from imbalance2.22 h
- Double handling1.90 h
- Hours on the 30 bad filters1.80 h
- Over-processing0.95 h
- Lost against the standard: 10.8 h
- Built into the standard: 11.4 h
Losses ranked by hours per shift: Idle, waiting for housings 4.50 hours; Working slower than standard 4.50 hours; Walking 3.48 hours; Machine watching 2.85 hours; Waiting from imbalance 2.22 hours; Double handling 1.90 hours; Hours on the 30 bad filters 1.80 hours; Over-processing 0.95 hours. Three are lost against the standard and total 10.8 hours. Five are built into the standard and total 11.4 hours.
The hidden layer, 11.4 hours, is larger than everything the report could see, 10.8 hours. Of 45 paid hours, 14.25 were spent changing the product, which is 31.7 percent. A line at 76 percent OLE sounds like it has 24 points to gain. Count the waste inside the standard and it has about twice that, and the bigger half is in the method.
That also sets the order of work. Chasing the 4.5 idle hours means fixing the housing supply. Chasing the 11.4 hours means moving racks, giving the operator work during the machine cycle and rebalancing, then timing the job again and setting a new standard time. The second is usually cheaper and lasts, because it changes the job and not the day.
What the ratios miss, and the people side
- A ratio is only as good as its standard. A loose standard gives a high efficiency and an OLE over 100 percent. A standard with waste built in gives a good score to a wasteful job.
- Efficiency rewards output, wanted or not. A line can lift its number by making parts nobody ordered. Read the labor ratios next to schedule attainment.
- Idle time is under-reported when it is logged by hand. Short waits are never written down.
- One shift is one shift. Losses differ by product mix, crew and time of day, so measure more than once before deciding.
- No published benchmark says what a good OLE is, and plants count idle time differently. Compare a line with its own past.
People fear a labor loss study for a fair reason: they expect the result to be a headcount cut or a faster line. Say before filming what the study is for and what will happen to time that is freed, and keep to it. Show results as losses by type with the cause beside each, not as a ranking of operators. Almost every loss on this page is fixed by changing layout, supply, balance or method, and the operators are the people who know which fix will work.
This is general practice, not legal or labor relations advice. Where a union agreement or works council covers work measurement, follow it.
Templates and tools
- OLE calculator: availability, performance, quality and OLE from your own hours and counts.
- Loss tree worksheet: break total lost hours down by area, line, loss type and cause.
- Six big losses worksheet: the matching breakdown for machine time.
- Time study sheet: the element list the loss study starts from.
- Spaghetti diagram template: trace and measure the walking.
- Line balancing calculator: balance efficiency and idle time per station.
LeanSuite's time and motion study works from video of the station: every element is timed on a timeline that links to the footage and split into value-added, necessary and waste, with a breakdown of the waste. Its balance view shows each operator's cycle time, idle time and utilization. An engineer reviews and certifies the study.
Go deeper
This page is the short version. These guides cover each part in full.
- How to Improve Shop Floor ProductivityWhat to change on the floor once a study has put hours on each loss.
- The 8 Wastes of Lean ManufacturingThe eight wastes by name, of which the labor losses here are the ones a person's time shows.
- The Six Big Losses in Lean ManufacturingThe same kind of breakdown for machine time, and how it feeds OEE.
- Loss Prioritization FrameworkChoosing which loss to work on first when there are more losses than people.
All our articles on this subject are in the lean manufacturing fundamentals topic.
Free templates and tools
- Loss tree worksheetBreak one big loss number into area, line, machine, loss type and cause, and stop at the cause a team can fix.
- Six big losses worksheetWhere a machine's planned time goes: the six big losses in minutes, ranked, with A, P, Q and OEE worked out.
- Time study sheetTime each element over 10 cycles and work out the average, lowest repeatable and standard time. Excel does the sums.
- Spaghetti diagram templateSquared paper to trace every trip, a trip log that turns grid squares into feet, meters and walking time, and a before and after comparison.
- Waste walk checklist (TIMWOODS)32 things to look for across the eight wastes, with where and how much, and a findings log with dot votes, owners and dates.
- SMED changeover worksheetChangeover steps with times, internal or external, what can move, ideas and before/after totals.
- Overall labor effectiveness (OLE) calculatorHow well paid labor hours turn into good output: availability, performance and quality of the crew.
- Line balancing calculatorLine efficiency, balance delay and the minimum number of stations from station times and takt.
- Cycle time calculatorCycle time against takt, units per hour, capacity per shift and the gap to daily demand.
- SMED changeover calculatorTime saved by moving changeover steps from internal to external, capacity freed per week and the smaller batch it allows.
Doing this in LeanSuite
Time and Motion Study
Film the station and the AI times every element on a timeline that links to the video, split into value-added, necessary and waste.
See Time and Motion StudyLine Balancing
Drop in a video of your line and get a Yamazumi chart, a takt comparison and rebalancing recommendations.
See Line Balancing
See it on your own lines
Bring the problem you are working on to a 45-minute demo. Or look around with sample data first, or pilot LeanSuite on your own lines for 90 days, with the setup done by our team.
FAQ
Questions about labor losses in manufacturing
Labor losses are paid labor hours that do not become good product made by the best known method. Some are lost against the standard: idle time, working slower than standard and time on bad units. Others are built into the standard: walking, reaching, double handling and machine watching that were present when the job was timed. Labor reports see only the first kind. A time study that classifies each element finds both.
OLE = availability x performance x quality. Availability is hours worked divided by hours paid. Performance is standard hours produced divided by hours worked. Quality is good units divided by all units made. A crew paid for 45 hours that works 40.5, produces 36 standard hours and gets 570 good units from 600 has an OLE of 0.90 x 0.889 x 0.95, which is 76 percent. OLE has no single standard, so write down how you count idle time.
Labor efficiency = standard hours produced / hours actually worked, as a percentage. Standard hours produced is the standard time per unit multiplied by the units made. A crew that works 40.5 hours and makes 600 units with a standard of 3.6 minutes each has produced 36 standard hours, so efficiency is 36 / 40.5, or 88.9 percent. Idle time is left out of this ratio; utilization covers it.
Utilization asks whether people had work to do: hours worked divided by hours available. Efficiency asks how the working time compared with the standard: standard hours produced divided by hours worked. A crew can be fully utilized and inefficient, or efficient for the few hours it had parts. Multiply the two and you get line efficiency, the standard hours produced per hour paid.
Line efficiency = standard minutes produced / minutes attended x 100. Standard minutes produced is units made x the standard minutes per unit. Minutes attended is operators x minutes each was at work. A six-person line at work for 450 minutes each that makes 600 units at 3.6 standard minutes has a line efficiency of 2,160 / 2,700, or 80 percent. In line balancing the same name is used for work content divided by stations x cycle time.
OEE measures a machine: the share of planned production time that became good parts at the ideal cycle time. OLE applies the same three factors, availability, performance and quality, to a crew's paid hours. A line can have a high OEE and a low OLE if the machine runs well with more people around it than the work needs. OEE has a widely used definition; OLE does not, so definitions must be written down.
A starved station is ready to work and has nothing to work on, because no part has arrived from upstream. A blocked station has finished a part and cannot pass it on, because the next station or the buffer after it is full. Both are waiting, and both are symptoms: the cause is at another station, usually the slowest one or the one that just stopped.
A labor report compares actual hours with standard hours, so it only sees time lost against the standard. Any walking, reaching, double handling or machine watching that was present when the standard was set is inside the standard and is counted as earned. A time study looks at the work itself, element by element, and classifies each one, so it finds the waste the standard includes.
Related guides and tools
- Value added vs non value added: the tests and the rules for classifying each element
- How to conduct a time study: the method step by step
- Line balancing: removing the idle time that imbalance creates
- SMED: cutting changeover time
- How to calculate OEE: the machine counterpart of OLE
- OLE calculator: work out overall labor effectiveness from your own numbers
More method guides
- The 6 Ms of production
- Poka-yoke
- Model area 90-day plans
- Moving from Excel to one system
- Reducing machine downtime: a worked month
- Andon
- Cycle time vs lead time, worked through
- Root cause analysis
- How many operators a line needs
- Reducing scrap and rework: a worked month
- Unsafe acts and unsafe conditions
- Just culture
- Stop-work authority
- Material review board (MRB)
- Nonconformance and NCRs
- Problem solving methods
- Quad chart
- OEE calculation
- Quality assurance vs quality control
- SOP meaning and format
- Job hazard analysis
- Near miss reporting
- Fishbone diagram
- Pareto chart
- Histogram
- Control chart
- What is a gemba walk
- What is lead time
- What is operational excellence
- How to improve product quality
- Preventive vs predictive maintenance
- Kanban
- FMEA
- PDSA cycle
- Safety moments
- Just-in-time manufacturing
- Kaizen
- 5S
- Total quality management (TQM)
- CAPA (corrective and preventive action)
- Layered process audit (LPA)
- Lean tools
- Lockout tagout (LOTO)
- A3 problem solving
- Preventive maintenance
- APQP
- High reliability organization (HRO)
- Manufacturing KPIs
- Quality metrics
- Practical problem solving
- CMMS
- Risk assessment
- Production efficiency
- Total productive maintenance (TPM)
- Reliability-centered maintenance (RCM)
- Hierarchy of controls
- Personal protective equipment (PPE)
- Emergency action plan
- Safety signs
- Warehouse safety
- ISO 9001
- SIPOC diagram
- Rolling action item list (RAIL)
- Pugh matrix
- Flowchart
- Project charter
- ISO 9001:2026
- Fleet maintenance
- IATF 16949
- AS9100
- ISO 14001
- ISO 45001
- One point lesson
- Standard work
- Meeting cadence
- OSHA penalties and the top 10 cited standards
- OSHA 300A summary
- SMART goals examples for manufacturing
- Year-end review for manufacturing plants
- 2027 goals for a manufacturing plant
- Lean manufacturing principles
- Toyota Production System
- 5W1H
- 5 Whys
- Continuous improvement
- Takt time
- DMAIC
- PDCA
- 8D problem solving
- Prioritization matrix
- Gemba walk questions
- 5W1H questions
- Layered process audit questions
- 5S audit questions
- Difficult conversations at work
- How to talk to an employee about poor performance
- How to resolve conflict between employees
- High performer, bad attitude
- How to get employees to follow procedures
- Resistance to change on the shop floor
- Influence without authority for CI, quality and safety people
- Quality vs production: the hold against the ship date
- Hard savings vs soft savings
- How to handle a customer quality complaint call
- 30 60 90 day plan for a manufacturing manager
- First 90 days in a new manufacturing role
- New supervisor training: the first 90 days
- Night shift supervisor
- Engineer to manager in manufacturing
- What to do after a serious workplace accident
- Disagree and commit: disagreeing with your boss in a plant
- How to deliver bad news to your boss
- How to present audit findings to management
- How to get leadership buy-in for continuous improvement
- How to ask for more headcount or resources
- How to ask for a promotion in manufacturing
- PPE compliance
- Language barriers on the shop floor
- Train the trainer in manufacturing
- Contractor safety management
- Return to work after an injury
- Attendance conversation with an employee
- Managing former peers after a promotion
- Managing older or more experienced employees
- Inheriting a team
- How to delegate as a supervisor
- Holding supervisors accountable
- How to tell employees about layoffs or a shift change
- How to deny a raise request or a promotion
- Time and motion study
- How to conduct a time study
- Standard time
- Work sampling
- SMED
- Line balancing
- Yamazumi chart
- Ergonomic assessment in manufacturing
- Spaghetti diagram
- Time study vs motion study vs method study
- Why do a time study
- How to plan a time study
- How to break a job into elements
- How many cycles to time
- Stopwatch time study
- Time study mistakes
- Time study vs work sampling
- Value added vs non value added
- New product time study playbook
- How to estimate cycle time for a new product
- New product introduction for industrial engineers
- Process planning for a new product
- Planning operators and stations for a new line
- Pilot run and line trial
- Ramp-up plan and the learning curve
- Workstation design
- Designing a future workstation
- Time study and ergonomic study in one pass
- Predetermined motion time systems (PMTS)
- MTM (Methods-Time Measurement)
- MOST and MODAPTS
- Therbligs and motion economy
- RULA assessment
- REBA assessment
- RULA vs REBA
- NIOSH lifting equation
- Production capacity calculation
- Precedence diagram
- Labor efficiency and labor variance
- Labor cost and quoting with time standards
- SMV and SAM in garment manufacturing
- From time study to standard work
- Standard work combination table
- Standard work vs SOP vs work instruction
- Standard WIP
- Updating standard work after an improvement
- Time study from video
- Time study app or software
- Man-machine chart
- Timing long-cycle and team work
- Time study in a union plant
- History of time and motion study
- Golden zone (power zone)
- Workstation assessment
- Reach envelope and work area study
- Standing, seated and sit-stand workstations
- Line-side material presentation
- Time study in automotive assembly
- Time study in electronics assembly
- Time study in CNC machining
- Time study in metal fabrication and welding
- Time study in plastics injection molding
- Time study in warehouse operations
- Time study in garment manufacturing
- Time study in maintenance work
- Time study in aerospace assembly and MRO
- Time study in food and beverage manufacturing
- Time study examples
- Historical and machine data as time standards
- Line balancing examples
- How to measure cycle time
- Manpower planning from standard time
- Bottleneck analysis from a time study
- Standard work examples
- U-cells and one-piece flow
- Flow process chart and operation process chart
- Two-handed process chart
- 3P production preparation process
- Plant layout basics
- Design for assembly
- Time study, PFMEA, control plan and work instructions
- Explaining a time study to a worried operator
- The observer effect in time studies
- Time standards and incentive pay
- Seven wastes vs eight wastes
- Job safety analysis (JSA)
- JSRA (job safety risk assessment)
- JSA vs JHA vs JSRA
- Job safety analysis from video
- HIRA (hazard identification and risk assessment)
- Management of change (MOC)
- Safe work method statement (SWMS)
- Permit to work (PTW)
- Pre-task plan (PTP)
- Field level risk assessment (FLRA)
- Safety observation
- Safety walk
Or browse the topics, the full library and the lean glossary.
Rather see it on your own problem?
Bring the problem you are stuck on, and we will show you on a call how LeanSuite handles it.